NCC Limited

Nagpur Metro Rail Project - NHAI

M/s. Mageba Spherical Bearing Drawing Approval & Deliverey Status ( 4- lane)
1/8/2019
S.no Span Length No of Spans No of Bearings Drawing approval status Bearing Delivered Balance qty to be Remarks
delivered
1 25 m 16 64 Approved 64 0
2 28 m 44 176 Approved 168 8

3 31 m 16 64 Approved 0 64

Total 76 304 232 72

M/s. Sanfield Spherical Bearing Drawing Approval & Deliverey Status (6- lane & station spans)

Balance qty to be
S.no Span Length No of Spans No of Bearings Drawing approval status Bearing Delivered delivered Remarks

1 19.375 m 12 48 Approved 48 0
2 22 m 1 4 Approved 4 0
3 25 m 6 24 Approved 24 0
4 28 m 8 32 Approved 32 0
5 31 m 1 4 Approved 4 0
6 40.5 m (Nallah) 1 4 Approved 4 0
Total 29 116 116 0

M/s. Sanfield Spherical Bearing Drawing Approval & Deliverey Status (Manish nagar project)

S.no Description No of Spans No of Bearings Drawing approval status Bearing Delivered Balance qty to be Remarks
delivered
1 Spherical bearing 20 80 Approved 0 80
2 POT-PTFE bearings 1 4 Approved 0 4 RDSO drawing