JOB SAFETY ANALYSIS SHEET

JSA Team: Approved by: Date: SPECIFIC ACTIVITY BEING ASSESSED:


-M.Inam Ali 09.01.2009 Lifting of MS Sheets 20’x4’x5mm (275 kg)
M.Faraz Qureshi
M.Usman
PPE: Helmet, safety shoes, gloves, goggle, Leather gloves, high visibility jackets Job Location: Site Store

ACTIVITY POTENTIA LIKELY CAUSES CONSEQUENCE CONTROL MEASURE


L HAZARD S
(What I am (What can go (What can cause it to (What will happen (What can be done to prevent it from going
going to do?) wrong?) go wrong?) if the Hazard is wrong?)
released?)

Inspection of Falling of load Sinking of ground Serious personnel injury - Proper compaction of ground that could withstand with
ground Crane collapse Damage to property the Max weight of load.
Inspection of Falling Failure of Crane Serious injuries / Fatality - Crane should have passed the load Test.
Crane, Lifting load/Falling Failure of lifting gears Property damage - 3rd Party certification of Fitness should be
gears object ensured for Crane and all other lifting tackle e.g.
slings, shackles etc.

Trained Rigging Collapse of crane Untrained Crane collapse Trained and Valid crane operation License holder
Crew Unsuitable to the task Fatality operator shall be deployed
Inappropriate lifting Property damage Trained rigger with heavy & critical lifting experienced
crew shall be assigned
Rigger assigned shall wear jacket and authorize for
signaling and should be physically fit.

Slinging of MS Falling object Under rated lifting gears Personnel injury / - Only Trained & authorized personnel shall work
Sheet Yielding of lifting Uncertified lifting gears Fatality  - Certified / inspected lifting gears shall be used.
tackles Inappropriate sling fixing Property damage  Packing must be used to avoid cutting of slings.

Lifting by a Falling of load / - Failure of Crane Serious injuries / Fatality - Pre lift check list must be filled and duly signed
crane & loading Unbalancing of - Failure of lifting lug Property damage by area supervisor before start of the activity.
JOB SAFETY ANALYSIS SHEET
of sheets on crane. - Improper lifting - Safety Talk shall be conducted to explain JSA
truck . Fouling of booms technique/geometry with all participants before lifting
- Inadequate Placing - Designated signalman, Rigger, wearing high
of Crane visibility jacket to be allowed to give signals to
- High wind velocity both crane operators.
- Crane outriggers shall be extended fully.
- Ground shall have hard surface & Outrigger pads
to be used.
- Area around the work place shall be barricaded to
stop unauthorized entry.
- No body should stay under suspended load or
move through the operating radius of boom.
- Using of two tag lines.
- The weight of the load shall be taken smoothly
without allowing it to jerk.
- At least one rigger must be present on the truck
to receive the load.
- The entire activity shall be performed under the
supervision of a qualified Supervisor & Safety
officer.

WARNING..

IF THERE IS ANY ABNORMAL SITUATION OBSERVED WITH RESPECT TO LIFTING OPERATION TESTING RESULT OR PHYSICAL CONDITION ACTIVITY WOULD IMMEDIATELY BE
STOPPED