You are on page 1of 2

ANNEXURE A

STANDARD TERMS AND CONDITIONS FOR PRECAST QUOTATIONS


COVERING SUPPLY, DELIVERY AND ERECTION OF PRECAST CONCRETE ELEMENTS
A. GENERAL
Contract amount is re-measurable and therefore, 4. Removal of any obstructions that may affect SMEET
the total amount payable is computed based on the continuous erection flow.
actual quantity of precast elements produced 5. Supply of water and electricity to SMEET at site free
and/or erected for the project in accordance with of charge.
the approved and/or final design and the 6. Scaffolding and mobile platform for SMEET jointing
accepted/contracted unit rate. and sealant works if it is required.
Works shall commence only upon acceptance by 7. Site safety protections provisions other than PPE
SMEET of a written order from Client, either in the ARE which are supplied by SMEET.
form of a confirmation letter and/or LPO, together
with the agreed down payment. D. OTHER TERMS AND CONDITIONS
SMEET scope of works may cover design, 1. Design
manufacture, delivery and erection of precast SMEET Design Engineering includes structural
concrete elements or any of the foregoing subject analysis and calculations, preparation of
to agreement. construction drawings, fabrication/shop drawings,
construction details, as-built drawings and warranty.
B. CONDITIONS ON PRICING
SMEET reserves the right to claim for additional cost Based on client’s-supplied drawings, SMEET will
resulting from any change in the original prepare design calculations and shop drawings
Design/Plans/Layout, Design Details as first quoted. which are submitted to Client/Consultant for
SMEET will prepare fabrications drawings which will approval and once approved, will serve as the basis
be submitted to the Client for approval and once for production. Any cost that is to be incurred due
approved they become the basis for fabrication to revision after issuance of approval, will be
(production). Likewise, SMEET reserves the right to charged to the Client’s account.
claim for additional cost resulting from any change/
alteration in the fabrication and shop drawings after 2. Production
approval. Production is done in accordance with SMEET
Price is based on SMEET Precast Standard Standard Production and QA/QC Procedures and in
Operational Procedures and Processes relative to accordance with the approved fabrication drawings.
manufacturing, delivery, erection, quality control, Production tolerances are in compliance with
health and safety and site works. tolerances set in the British Standard, PCI and
Quoted/Contract price is subject to escalation in SMEET Design Requirements.
case of rise in costs of raw materials, labor or fuel.
Cement and other concrete components (sand,
C. CLIENT/CONTRACTOR SUPPLIED PROVISIONS aggregates, etc.) being organic materials, SMEET
1. Free and unobstructed access road for SMEET cannot guarantee uniformity in concrete color and
Precast delivery trailers. Access road must be flat such will not serve as basis for rejection of the
and hard to allow easy maneuvering. precast element.
2. Parking space for trailers.
3. Gate passes, road permit and other special permits Cut-outs, holes and other openings are executed by
to use public roads, neighbouring facilities and SMEET as shown in the fabrication drawings.
the like.

QMS-SM-002-REV:00,DATED:01/03/2013
All concrete-related testing activities are done in accessories) and handling purposes shall be
SMEET Central Laboratory. If testing is required and made of ordinary mild steel when these items
is to be made by an outside Independent
are embedded in concrete and shall be
Laboratory, the cost of said independent testing is
borne by the Client. galvanized when they are exposed to the
elements. Unless otherwise stated, stainless
3. Delivery and Erection steel provisions have not been considered
Construction schedule will be in accordance with and/or allotted in the price.
Construction Schedule agreed and signed by both
parties. 5. Liability
SMEET reserves its entitlement for time extension SMEET shall not be liable in damages or be
due to any delay incurred for faults or reasons not furnishing to the other Party grounds to a right to
attributable to SMEET i.e., readiness of in-situ terminate the contract by reason of delay or default
foundation, bad weather condition (strong wind, caused by conditions beyond the control of SMEET
rain, sandstorm) etc. including, but not limited to Acts of God,
Likewise, SMEET reserves its entitlement for time government restrictions, wars, insurrections and the
extension for any delay due to raw materials likes.
shortage (cement, steel, sand and aggregates, etc.). SMEET shall not be liable for any third party claims
Delivery/Erection is commenced upon receipt of a
arising in connection with the works, except as
written confirmation from client with respect to the
readiness of the foundation/site to proceed with the solely and directly arising from the wilful default of
delivery/erection of precast units. In case the SMEET. SMEETs cumulative liability for damages, if
production of the precast elements is completed in any, for all claims of any kind arising in connection
accordance with the Construction Programme and with the work in limited to 10% of the contract
the site is not ready to receive the cast units, the value. Notwithstanding the foregoing SMEET shall
Client has to provide stocking area at site to allow
not be liable for any special, punitive, indirect,
delivery and stocking at site. Delivered and stocked
incidental or consequential damages, lost revenues
slabs at site shall be considered as “Materials Off-
site” and shall be invoiced accordingly at 85% of or lost profits, however caused, arising from or in
their contract value. connection with the work done by SMEET.”

If the Client is unable to provide stocking area at site 6. Disputes


and the cast units are to be stocked at SMEET All disputes and similar matter arising out of or
factory premises, the cost of stocking is to be borne relating to contract or the interpretation thereof, is
by the client at a reasonable amount to be agreed to be settled at the first place amicably by both
by both parties. SMEET and Client.
The cost of double handling shall be to Client’s
account. In the event of failure for amicable settlement, said
In case of night delivery/erection, permit if required dispute (and similar matter) has to be referred to
and supply of lighting provisions are to be provided any competent court in Qatar and therefore said
by the Client. The Client and or authorized court shall have exclusive jurisdiction over any suit
representative thereof shall ensure that all SMEET or legal proceeding relating to the contract. Both
Delivery Tickets are properly acknowledged and parties shall submit to the exclusive jurisdiction of
signed. SMEET will abide by existing Safety the said court as the proper legal venue for the
Regulations at site. dispute that cannot be settled amicably by both
parties.
4. Fixing/Connection Materials and
Accessories --------END--------
All items for fixing (and related

QMS-SM-002-REV:00,DATED:01/03/2013

You might also like