You are on page 1of 5

NATIONAL ANIMAL GENETIC RESOURCES CENTER AND DATA BANK

ROAD OPENING AND FIREBREAK AND MAINTENANCE SERVICES


Bill of Quantities
Bill No.1: Site Preparatory Works
Rate Amount
Description of Works Unit Qty.
Item (Ush) (Ush)
Allow a sum to cover preliminary costs Km 1 1,000,000 1,000,000
1.1
Construction of access roads to quarry sites including their
km 1 1,000,000 1,000,000
(MBC) maintenance throughout the working period
Total Bill No. 1 (Carried to Summary) 2,000,000

Bill No.2: Setting out and Site Clearing Works


2.1 (Re) Establishment of road alignment and setting out of road
m 1 300 300
(AWD) works
Clear site of all trees including stumps, grass, bushes and
2.2 boulders and Grub all roots of trees, grass and bushes including Sm 1 500 500
(AWD) excavation of top soil from road formation
2.2.1 Extra over item 2.2 for boulders over 1.5m maximum girth. No. 1 50,000 50,000
(AWD)

Cut and remove from site trees (up to 1m girth), including


No. 1 3,000 3,000
2.3 removal of stumps and roots
2.3.1 Extra over item 2.3 for trees over 1m girth No. 1 50,000 50,000
Total Bill No.2 (Carried to Summary) 103,800

Page 1
Bill No.3: Earth Works
3.1 Rehabilitation of existing road formation
3.1.1 Shaping of road formation including watering and compaction Sm 1 400 400
(AWD)

3.2 Construction of road formation


3.2.1
(MBC/AWD Excavation to level m3 1 1,700 1,700
)

3.2.2 Excavation in side, mitre, catch water and other specified drains m 1 1,500 1,500
(AWD)

3.2.3 Form, water and compact road bed m 1 600 600


(AWD)

3.3 Provision of Fill Materials


3.3.1 Preparation of borrow pit Site consisting of clearing vegetation
m2 1 1,000 1,000
(AWD) and removing topsoil
Excavation, hauling, placing, watering and compaction of
3.3.2 approved fill material in embank-ments & lowspots to create a m3 1 5,000 5,000
(AWD) level road bench.
Ditto but final wearing course 150mm thick m2 1 1,050 1,050
3.4 Excavation of Rock m3 1 100,000 100,000
(AWD)

Total Bill No.3 (Carried to Summary) 111,250

Page 2
Bill No.4: Drainage Works.
4.1 Provide and install scour checks:
(AWD)

4.1.1 Using stones No. 1 17,000 17,000


4.1.2 Using sticks No. 1 20,000 20,000
4.2 Excavation of foundations for structures:
(AWD)

4.2.1 In soil not more than 1m deep m3 1 30,000 30,000


4.2.2 In soil more than 1m deep m3 1 35,000 35,000
4.3 Supply and install concrete pipe culvert rings:
(AWD)

4.3.1 600mm diameter m 1 250,000 250,000


4.3.2 900mm diameter m 1 400,000 400,000
4.3.3 1200mm diameter m 1 600,000 600,000
4.3.4 1500mm diameter m 1 850,000 850,000
4.4 Supply and install steel pipe culvert rings:
(AWD)

4.4.3 1200mm diameter m 1 2,000,000 2,000,000


4.4.4 1500mm diameter m 1 2,500,000 2,500,000
4.5 Demolish existing masonary structures and cart away debris: m3 1 40,000 40,000
(MBC)

4.6
Provide material and build cement bound masonry work in:
(MAP/AWD
)

4.6.2 C25 Reinforced concrete m3 1 500,000 500,000


4.8
Provide, erect & remove formwork for concrete m2
(MAP/AWD 1 15,000 15,000
)

4.9
Provide and fix steel reinforcement:
(MAP/AWD
)

4.9.1 A142 BRC m2 1 8,000 8,000


4.10
Provide, place and compact hardcore / Rockfill foundation layer m3
(MAP/AWD for structures 1 80,000 80,000
)

Page 3
4.11
Provide, cast and cure concrete in class:
(MAP/AWD
)

4.11.1 Class 10 (1:4:8) m3 1 300,000 300,000


4.11.2 Class 15 (1:3:6) m3 1 400,000 400,000
4.11.3 Class 20 (1:2:4) m3 1 450,000 450,000
4.11.4 Class 25 (1:1.5:2) m3 1 500,000 500,000
4.12 m3
(AWD)
Provide gabion baskets and stones, place and fill baskets 1 1,200,000 1,200,000
4.13
Provide materials and build grouted stone pitching, 200mm m2
(MAP/AWD thickness 1 65,000 65,000
)

4.14
Provide select material and backfill structures m3
(MAP/AWD 1 75,000 75,000
)

4.15
Excavate water diversions and/or construct barriers(Provisional) m3
(MAP/AWD 1 50,000 50,000
)

Sub Total (4.1 - 4.17)


4.18(a) Water profing to structures:- Provide two coats of bituminous
m2 1 18,000 18,000
.3.2 paint

Sub Total (DRAINAGE) 10,403,000

Page 4
Bill No.5: Gravelling and Completion of Works.
Rate Amount
Description of Works Unit Qty.
Item (Ush) (Ush)
5.1 Preparation of quarry site consisting of clearing vegetation and m2 1,000
(AWD) removing topsoil. 1 1,000

5.2 Excavate gravel, remove boulders, stockpile, load, haul, offload, m3 5,000
(AWD) spread, water and compact in place. 1 5,000

5.3 Restoration of site(s), quarries and borrow pits. m2 500


(AWD)
1 500

Total Bill No.5 (Carried to Summary) 6,500

SUMMARY OF BILLS (Including Bridges & Box Culverts)


Bill Description Amount (Ush)
1 Site Preparatory Works 2,000,000
2 Setting Out and Site Clearing Works 103,800
3 Earth Works 111,250
4 Drainage Works 10,403,000
5 Gravelling and Completion Works 6,500

SUBTOTAL 1 12,624,550
Contingencies (5%) 631,228
SUBTOTAL 2 13,255,778
ADD 18% VAT 2,386,040
GRAND TOTAL (Carried to Grand Summary) 15,641,817

Page 5