Bill No.3: Earth Works
3.1 Rehabilitation of existing road formation
3.1.1 Shaping of road formation including watering and compaction Sm 1 400 400
(AWD)
3.2.2 Excavation in side, mitre, catch water and other specified drains m 1 1,500 1,500
(AWD)
Page 2
Bill No.4: Drainage Works.
4.1 Provide and install scour checks:
(AWD)
4.6
Provide material and build cement bound masonry work in:
(MAP/AWD
)
4.9
Provide and fix steel reinforcement:
(MAP/AWD
)
Page 3
4.11
Provide, cast and cure concrete in class:
(MAP/AWD
)
4.14
Provide select material and backfill structures m3
(MAP/AWD 1 75,000 75,000
)
4.15
Excavate water diversions and/or construct barriers(Provisional) m3
(MAP/AWD 1 50,000 50,000
)
Page 4
Bill No.5: Gravelling and Completion of Works.
Rate Amount
Description of Works Unit Qty.
Item (Ush) (Ush)
5.1 Preparation of quarry site consisting of clearing vegetation and m2 1,000
(AWD) removing topsoil. 1 1,000
5.2 Excavate gravel, remove boulders, stockpile, load, haul, offload, m3 5,000
(AWD) spread, water and compact in place. 1 5,000
SUBTOTAL 1 12,624,550
Contingencies (5%) 631,228
SUBTOTAL 2 13,255,778
ADD 18% VAT 2,386,040
GRAND TOTAL (Carried to Grand Summary) 15,641,817
Page 5