GUIDE IN QUANTITY TAKE-OFF AND ESTIMATING

1.0 EXAMPLE OF QUANTITY TAKE-OFF SHEET (LUMBER):

2.0 ESTIMATE GUIDE:

 2.1.1 CLEARING & GRUBBING WORKS - MANUAL OR BY MACHINE (BULLDOZER OR GRADER).


 2.1.1.1 MANUAL CLEARING & GRUBBING - LABOR COST & CLEARING TOOLS
• CAPABILITY OF LABOR:
• CLEARING UNDERGROWTH & TREES (12” Ø)
• - 0.05 M H / SQ.M.
• CLEARING UNDERGROWTH & SHRUBS
• - 0.03 M H / SQ.M.
 2.1.1.2 MACHINE CLEARING & GRUBBING - EQUIPMENT OPERATOR, LABOR, & EQUIPMENT RENTAL
COSTS; FUEL COST.
• EQUIPMENT:
• BULLDOZER: CLEARING - 500 SQ.M. / HOUR
• STRIPPING - 200 SQ.M. / HOUR
• PUSHING - 3 SQ.M. / HOUR
• GRADER: GRADING - 300 SQ.M. / HOUR
• SPREADING – 40 CU.M. / HOUR
LABOR: COMMON LABORERS & EQUIPMENT OPERATORS
MATERIALS: OIL AND FUEL