Professional Documents
Culture Documents
Percentage
WHEN THE SOIL IS EXCAVATED IT WILL Increase in
INCREASE IN VOLUME – THIS IS CALLED Type of Soil Bulk After
BULKING Excavation
C) METHODS OF FILLING
I) HAND
II) MACHINE
COMPACTION
FILLING MATERIAL REQUIRES COMPACTION AFTER PLACING IN POSITION
THE VOLUME OF FILLING MATERIAL WILL BE LESS THAN ITS ORIGINAL BULK
AFTER PLACING AND COMPACTION
MEASUREMENT FOR QUANTITIES OF FILLING MATERIALS IN THE BQ IS EQUAL
TO THE VOLUME OF VOIDS TO BE FILLED
THE ACTUAL QUANTITIES OF MATERIALS REQUIRED FOR FILLING BY WORKERS
ON SITE ARE MORE THAN THE MEASURED QUANTITIES.
COMPACTION MUST BE CONSIDERED IN THE CALCULATION OF RATE FOR
FILLING
NEED TO ADD 25% TO COST OF MATERIAL (IF MATERIAL OBTAINED OFF
SITE ONLY) TO COVER FOR LOSS IN VOLUME DUE TO COMPACTION
LABOUR CONSTANT FOR FILLING TO EXCAVATION (BACKFILLING AND
RAMMING) – M3
1 UNSKILLED WORKER = 0.75HOUR/M3
Thickness of Unskilled
hardcore worker
(hour/m2)
100mm 0.15
150mm 0.20
200mm 0.30
250mm 0.35
EXAMPLE 3
FILLING TO EXCAVATION WITH MATERIALS ARISING FROM
EXCAVATION. – M3
Price/m2 RM 6.85/m2
TUTORIAL 2
1. REMOVE EXCAVATED MATERIAL (ROCK) IN 15M DISTANCE. –M3
2. REMOVE EXCAVATED MATERIAL AND DEPOSIT IN HEAPS AT CONTRACTOR’S OWN
DUMPING AREA IN 15KM DISTANCE. –M3
DATA : I) RENTAL COST OF 3 M3 DUMPER = RM 575/DAY
(NOT INCLUDING DIESEL & LUBRICANT)
II) SPEED OF DUMPER = 35KM/HR
3. FILLING TO MAKE UP LEVEL AVERAGE 200MM THICK WITH HARDCORE OBTAINED OFF
SITE. – M2
DATA : I) COST OF HARDCORE = RM 27.50/M3 (DELIVER TO SITE)
II) RENTAL COST OF COMPACTOR = RM 173/DAY
III) OUTPUT OF EXCAVATOR = 17M2/HR
DATA:
UNSKILLED WORKER = RM 40/DAY
DIESEL = RM 1.70/LITER
LUBRICANT = RM 20.00/LITER