WORKOUTTHERATEOFSTANDARDUNITFOR
BRICK WORKIN CM1: 5
Materials
500 Nos Bricks @ Rs. 3500 / 1000 Nos
43 kg Cement @ Rs. 350 / bag
0.24 Cum Dry Sand @ Rs. 2500 / Cum
Labour
0.7 Brick Mason @Rs. 750 / each / day
0.35 Man @ Rs. 600 / each/day
1.20 Woman @ Rs. 500 / each / day
iii) Conveyance
Item Lead Unit Rate Unit of Rate Cost (Rs)
Cement 15 km 50 km 750
Sand 27 km 15 km 405
Brick 20 km 20 km 400
Total 1555.00
SOLUTION
Item Quantity Unit Rate Unit of Rate Cost
40mm aggregate 0.92 m3 700 m3 644.00
Cement 0.115 m3 8000 ton 1324.8
Sand 0.46 Cum 1000 m3 460
Mason 0.20 Each 850 Each/day 170
Man 1.80 Each 750 Each/day 1350
Woman 1.40 Each 700 Each/ day 980
Material Quantity Unit Lead in km Conveyance charges Per Cost
40mm aggregate 0.92 m3 12 12 km 132.48
Sand 0.46 m3 14 15 km 96.60
Total = Rs5157.88
Add contractor’s profit 10% = 515.788
Total = 5673.668, say Rs5674