PROJECT TITLE : Administration building and toilet block for proposed Thikkam
distillery complex palmyra development board at thikkam point pedro
LOCATION : Thikkam
WORK DONE : Both buildings are almost completed buildings. Sub structure
and super structure is completed. Block work, plastering work,
roofing work and Finishing work is completed.
WORK TO BE DONE : There are only remaining works are glass fittings, bathroom
fittings, light and fan fittings installation and down pipes fixing.
They also have to complete pipe work for manholes from toilets
and administration building.
RISK TO THIRD PARTY : Third-party risk is minimum in this project due to construction.
Workers are not wear the safety clothing such as safety helmets, safety jackets, boots etc.
Temporary electrical installation is not not properly implemented. Therefore, it is
recommended to implement proper temporarily electrical installation.
They installed a glass door as front access to the administrative building. It can be damaged
due to accidental loss.
According to the conferred person, some of the labors are occupy at the site.
Akila Wickramanayake
Risk Management Department
23rd July 2021