Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
3
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
The project includes building a High tension panel room(HT Panel Room), Utility
block, Rain water harvesting system, sump room, dining area and altering an
existing structure.
A total of 4 contractors were working on this project
KCPL
FABTON
PPPL
UTILITY CONTRACTORS
Where FABTON are subcontractors of KCPL
Weekly meetings from TTID would take place where they used to set targets
4
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
5
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
WEEK-1
6
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
7
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
8
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
9
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
• Wearing helmets is a must when on site. Because there can be chances
when any objects can fall from height that can cause serious injuries.
• Safety jackets and shoes are provided to everyone. Safety jackets will be
helpful when the work is going on during the night. It provides a good
visibility when light flashes on it.
• Personal Protective Equipment (PPE) given were
● Helmet
● Jacket
● Safety shoes
● Gloves
● Glasses
● Safety belt
• Wearing of mask all the time is mandatory
10
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
TTID
11
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
SUMP AND PUMP ROOM
First day we were briefed about the project and the various works that were going on.
12
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
13
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
Once the lintel beam was cured and The safety officer doing checks whether
masonry was done up to the slab level. the safety precautions are taken or not.
14
Department of civil engineering
QUANTITY ESTIMATION INTERNSHIP / PROFESSIONAL PRACTICE
HT panel room
16
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
For plinth beam
Total 5.52
Total 3.107
17
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
HT panel room
19
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
Bar-bending
for trench room
20
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
• Once the PCC was cured, the footing Binding wires were used to tie
mats were laid. the column to the footing mat.
• Clear cover blocks were used to
provide the necessary clear cover.
21
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
WEEK-2
24
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
After the footing is ready, the column has to be raised.
But it is not possible to shutter all 6 columns and make
sure they are aligned. So the surveyor using a total
station gives points on all 6 footings from where the
column has to start and from where the shuttering has to
be given.
25
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
After the points are given, shuttering is not directly given to the entire
column. Instead first a starter is constructed over that, the column starts.
26
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
27
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
After the column is cured, the soil is
backfilled. And excavation is done for
plinth beam. Even for plinth beam,
PCC is provided. Once the PCC is laid
for the plinth beam, reinforcements
are kept on it. And shuttering is given
for plinth beam
28
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
29
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
30
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
The shutter of the plinth beam is Again the surveyor gives points for
removed. Curing the plinth beam of the column. Starter is again laid and
the trench room is done for 3 days. shuttering of column up to the lintel
level.
31
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONTINUED….
After the plinth beam is ready, shuttering work starts. With help of formwork, the
column is erected up to the half wall level. M25 grade of concrete was used for
columns. Once the concrete is dried, shutter is removed and curing of column is done.
32
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
FIRE AND SUMP ROOM
While the work of trench room was
going on, on the other side of the site,
excavation for the fire and sump room
was going on. A Tata Hitachi was used.
33
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
HT panel room
Trench: It is the part of the HT panel room, where the cables would run.
Excavation for the trench was done using a JCB.
34
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
35
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
WEEK-3
36
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
● After curing the PCC, reinforcement work is carried out,
● U - shaped bars - #10mm dia @ 150mm c/c
● Straight bars - #8mm dia @200mm c/c
● U - shaped bars and straight bars are run perpendicular to
each other.
37
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
38
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
40
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
41
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
42
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
43
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
44
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
45
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
• For connecting the HT cables to the panel room, hume pipes were required.
The HT cables would run through the hume pipes. The hume pipes join the
transformer.
• First excavation is done.
• After excavation the hume pipes are laid.
46
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
47
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
WEEK-4
48
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
50
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
51
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
52
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
• Curing of wall.
• The curing period wall
should be at least 7 days.
53
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
54
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
55
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
56
Department of civil engineering
INTERNSHIP / PROFESSIONAL PRACTICE
CONCLUSION
• This internship gave us an opportunity to understand the concepts that we had learnt
in the college in a practical way.