方法说明
对于幕墙的安装
Method Statement
for Installation of Curtain Wall
REV-002-HWALUN-EXGA-MS-CW 1
页 Page
3.1.2. Fabrication 制造
3.1.2.2. Protection 保护
3.1.2.3. Labeling 标签
3.1.4.1. Delivery 交货
3.1.4.2. Storage 存储
3.1.6. Marking 标记
3.1.8. Installation 安装
3.1.9.1 Glazing 上釉
3.1.9.2 Sealing 封口
REV-002-HWALUN-EXGA-MS-CW 2
5.2 Key Activities 主要活动
5.4 Others 其他
REV-002-HWALUN-EXGA-MS-CW 3
1. General Objective 一般目标
REV-002-HWALUN-EXGA-MS-CW 4
3. Work Procedure 工作程序
Fabrication 制造
Fabrication
Inspection 制造检
Marking 标记
Confirm Opening
Measurements 确认开放测量
Installation 安装
Glazing and
Sealing 玻璃和封口
Protection and
Cleaning 保护和清
REV-002-HWALUN-EXGA-MS-CW 5
3.1 Detailed Procedure 详细程序
3.1.2. Fabrication 制造
3.1.2.2. Protection 保护
3.1.2.3. Labeling 标签
REV-002-HWALUN-EXGA-MS-CW 6
便于识别。 框架应分批安排运送到现场。 工厂制造应规划窗口的交付按照安
装计划,以尽量减少储存和处理现场。
3.1.4.1. Delivery 交货
All materials for delivery should be verified against the quantity and
batch number stated in the delivery order. All required accessories
should be delivered together with the main components. 应根据交货单
中规定的数量和批号验证所有交货材料。 所有需要的配件应与主要部件交付
在一起。
3.1.4.2. Storage 存储
REV-002-HWALUN-EXGA-MS-CW 7
In addition, the various components should be arranged according to
the installation sequence to facilitate ease of retrieval, i.e. to minimize
searching and unnecessary shifting of materials that may lead to
damages. 此外,各部件应按照安装顺序排列,以便于取回,即尽量减少可
能导致损坏的材料搜索和不必要的移动。
Proper dimensional control and setting out of the wall opening are
critical in ensuring the quality of curtain wall. 适当的尺寸控制和设置壁开
口的出是确保幕墙的质量是至关重要的。
3.1.6. Marking 打标
3.1.8. Installation 安装
The brackets installation will be carried out from the outside by cradle
or scaffolding. A test run for the cradle will be carried out at the
landing. 支架安装将从外部通过摇篮或脚手架进行。 对于摇篮运行测试将在
着陆进行。
Competent trained operatives will fix the brackets at set out points,
standing inside the cradle. Shims will be used if required to adjust the
brackets to the correct level. Only the required aluminum frames will
be shifted from the storage area to the point of installation. 主管训练的
操作工将固定支架在载点,摇篮里站着。 如果需要将支架调整到正确的水
平,将使用垫片。 只有所需的铝制框架才会从存储区转移到安装点。
REV-002-HWALUN-EXGA-MS-CW 8
物的边缘,用于接受组件分配到地板上。 支架内的 2-3 人将在建筑物内楼层
的 2 人的帮助下进行安装。
The operatives will check the level vertically and horizontally with the
help of plumb & spirit level, so that after installation all components are
in line with corresponding false ceiling or finish floor level. Once the
proper alignment is achieved the operative will tightened all the bolts.
操作人员将借助铅垂水平仪和水平仪进行垂直和水平水平检查,以便安装后所
有组件与相应的假天花板或饰面地板水平线一致。 一旦实现正确对齐,操作
员将拧紧所有螺栓。
3.1.9.2. Glazing 上釉
Prior to start of glazing make sure all the relevant transom screws are in
place and tightened up and seated into place. 在开始上釉之前,确保
所有相关的横梁螺钉都已就位并拧紧并固定到位。
Ensure all the gaskets are well seated not jetting out of the grooves.
Rock wool shall be installed prior to the installation of glass for spandrel
areas. PVC insulators shall be installed for all the mullions & transoms.
Glass supporting clips shall be fixed on the transom. 确保所有垫圈都安装
良好,不会从凹槽中喷出。 在拱肩区域安装玻璃之前,应先安装岩棉。 应为
所有竖框和横梁安装 PVC 绝缘子。 玻璃支撑夹应固定在横梁上。
Set the glazing blocks 300mm from the center of the block to the
center of the mullion allowing the temporary clip fixation. Clean the
glass and Aluminum surface by moist dry cloth in order to allow the
REV-002-HWALUN-EXGA-MS-CW 9
surface to fully adhere to the glass sucker pads. 将玻璃块设置为从玻璃块
中心到竖框中心 300 毫米,允许临时夹子固定。 用湿干布清洁玻璃和铝表
面,使表面完全粘附在玻璃吸盘上。
Glass which are positioned at each floor level will be guided by 2-3
operatives on the cradle and 2 - operative inside the building. The
glass will be positioned with equal gaps and set with the side blocks, so
that the unit remains firm in its position. Fix the temporary clip on all
four sides of the glass. 放置在每个楼层的玻璃将由 2-3 名操作员在摇篮上和
2 名在建筑物内操作。 玻璃将以相等的间隙放置并与侧块一起固定,以便该装
置保持固定在其位置上。 将临时夹固定在玻璃的所有四个侧面。
Screw the pressure plate with the specified screws as shown in the
approved drawing. Simultaneously the temporary clips can be
removed. Fit the cover starting vertical the horizontal. Install all the
glasses in the same procedure 使用批准的图纸中所示的指定螺钉拧紧压
板。 同时可以移除临时夹子。 从水平方向垂直安装盖子。 以相同的程序安装
所有眼镜
Remove the excess sealant and tool joint to achieve a smooth surface.
去除多余的密封剂和工具接头以获得光滑的表面。
REV-002-HWALUN-EXGA-MS-CW 10
Tape will be removed immediately after completion of the joint. 连接完
成后将立即取下胶带。
REV-002-HWALUN-EXGA-MS-CW 11
Pick up hazardous factors of each work activity and always reflect
them at safety meetings. 找出每项工作活动的危险因素,并始终在安全会
议上反映它们。
Point out them every day at the meetings in order to let individual
worker to renovate this safety consciousness 每天在会议上指出他们,让
个别工人更新这种安全意识
Security Guard should observe all passengers around the site. 保安人员
应观察现场周围的所有乘客。
REV-002-HWALUN-EXGA-MS-CW 12