1.6 Building Services Proposal 2 weeks
1.7 Landscape Deisgn Proposal 1 week
1.8 Preliminary estimated cost per square ft 1 week
1.9 Client's approval 1 week
T 1.10 Development Order Submission 2 months
h 2.0 Design Development Phase
2.1 Detailed architectural drawings to prepare for Building Plans 2 months
2.2 Detailed structural drawings to be completed 2 months
2.3 Detailed M&E drawingsto be completed 2 months
BP
2.4 Detailed landscaping drawings to be completed 1 month
2.5 Pre-tender cost 2 weeks
2.6 Building Plans Submissions
2.7 Other authorities Submissions 1 month
2.7.1 Passive fire compliance drawings to be submitted to BOMBA 1 month
2.7.2 Active fire compliance drawings to be submitted to BOMBA 2 months
2.7.3 Electrical drawings to be submitted to TNB 2 months
2.7.4 Plumbing and Sewerage drawings to be submitted to JBA & JBS 2 months
2.7.5 Landscape department 2 months
BP APPROVAL
2.7.6 Street lightings 2 months
2.7.7 Transport department for Car Park 2 months
2.7.8 Kuala Lumpur Engineering Department 2 months
3.0title
Sample phase Contract
block Documentation Phase
3.1 Complete architectural tender documentation drawings 1 month
3.2 Complete structural tender documentation drawings 1 month
3.3 Complete M&E tender documentation drawings 1 month
3.4 Tender estimates and preperation of BQ 1 month
LETTER OF APPROVAL
3.5 Call for tender 1 week
3.6 Tender Period 2 weeks
3.7 Tender Close
3.8 Review and evaluation of tender offers 2 weeks
3.9 Tender report and recommendation 1 week
3.10 Letter of award to appointer contractor 1 week
4.0title
Sample phase Contract
block Implementation Phase
4.1 Preliminaries
4.1.1 Site handling over and site possesions 1 week
4.1.2 Site mobilization 1 week
4.1.3 Putting up hoardings and signages 1 week
4.1.4 Site clearing and site leveling (earthworks) 1 week
4.1.5 Setting out 2 weeks
4.2 Foundation
4.2.1 Excavation 2 months
4.2.2 Piling 2 months
4.2.3 Constructing pile caps 1 month
4.2.4 Pile caps installation 1 month
4.3 Basement works
4.3.1 RC retaining wall to be errected 1 month
4.3.2 RC floor slabs to be installed 3 weeks
4.3.3 RC ramps to be installed 2 weeks
4.3.4 Lift pit 2 weeks
4.4 Superstructure
4.4.1 Basement B1 RC Columns 2 weeks
4.4.2 Basement B1 RC Beams 2 weeks
4.4.3 Basement B1 RC Floors 2 weeks
4.4.4 GF RC Columns 2 weeks
4.4.5 GF RC Beams 2 weeks
4.4.6 GF RC Floors 2 weeks
4.4.7 1F RC Columns 2 weeks
4.4.8 1F RC Beams 2 weeks
4.4.9 1F RC Floors 2 weeks
4.4.10 2F RC Columns 2 weeks
4.4.11 2F RC Beams 2 weeks
4.4.12 2F RC Floors 2 weeks
4.5 Walls
4.5.1 Pre cast concrete walls for services cores 1 month
4.5.2 Pre cast concrete load bearing wall 1 month
4.5.3 In-situ concrete walls 1 month
4.5.4 Brickwalls 1 month
4.5.5 Curtain walls 1 month
4.5.6 Perforated steel sheet walls 1 month
4.6 Roof
4.6.1 Metal Roofing 1 month
4.6.2 Stormwater drainage system installation 1 week
4.7 Façade Construction
4.7.1 Installation of steel frame 2 months
4.7.2 Installation of perforated steel sheets 2 months
4.8 M&E
4.8.1 Cabling and wiring works 1 month
4.8.2 Lift installation 1 month
4.8.3 Extra-Low Voltage wiring works 1 month
4.8.4 Air-conditioning and Mechanical ventilation installation 2 weeks
4.8.5 Fire protection system 1 week
4.8.6 Water supply and plumbing works 1 week
4.8.7 Sewerage works 1 week
4.8.8 RWDP installation 1 week
4.8.9 Flat water tank installation 1 week
4.8.10 Security surveillence system 1 week
4.8.11 Fire water storage installation 1 week
4.8.12 Water sprinklers installation 1 week
4.8.13 Smoke detectors installation 1 week
4.8.14 Stormwater reticulation system 1 week
4.8.15 External lighting works 2 weeks
4.8.16 Internal lighting works 2 months
4.8.17 Civil works 2 months
4.9 Architectural Finishes
4.9.1 Celing finishes 1 month
4.9.2 Internal wall plastering 2 weeks
4.9.3 External wall plastering 2 weeks
4.9.4 Internal wall paintings 2 weeks
4.9.5 External wall paintings 2 weeks
4.9.6 Floor finishes 1 month
4.9.7 Sanitary fixtures 2 weeks
4.9.8 Staircase finishes 2 weeks
4.9.9 Staircase railings 2 weeks
4.9.10 Ramps railings 2 weeks
4.9.11 Balcony railings 2 weeks
4.9.12 Door frames 2 weeks
4.9.13 Door ironmongery 2 weeks
4.9.14 Door installation 2 weeks
4.9.15 Window frame 2 weeks
4.9.16 Window ironmongery 2 weeks
4.9.17 Window installation 2 weeks
4.9.18 Building and commercial space signages 2 weeks
4.10 Landscaping
4.10.1 Street pavement into building 2 weeks
4.10.2 Trees to be planted at green spine 1 week
4.10.3 Trees to be planted at hanging gardens 1 week
4.10.4 Plantings on green wall 1 week
5.0 Final Completion Phase
5.1 Testing and commisioning 1 month
5.2 Cleaning up 2 weeks
5.3 Inspection by consultants 2 weeks
5.4 Pre CCC inspection by authorities (clearance letter) 2 weeks
CPC
FINAL ACCOUNTS
5.5 Collect as built drawings, warrenties and garauntees from contractors 2 months
CCC
CMGD
5.6 Granting of CPC to contractor (contractual) 1 week
5.7 Granting of CCC 2 weeks
5.8 Defect liability Period 96 weeks
5.9 CMGD-Certificate of Making Good Defects is issued 96 weeks
5.10 Final Accounts Cetificate 96 weeks