2020 2021 2022 2023 2024 2026 2026 2027 2028


T Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Dec Dec Dec Jan
hi Phases Task/Deliverables Duration 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 2 3 3 1
C
el
C 1.0 Schematic Design Phase
el
R 1.1 Project briefing by client and site visit with client 1 week
o 1.2 Site Analysis 1 week
1.3 Sapatial Planning and Tabulation 1 week
1.4 Preliminary Design Proposal 2 weeks
1.5 Building Structure Proposal 2 weeks

DO APPROVAL
1.6 Building Services Proposal 2 weeks
1.7 Landscape Deisgn Proposal 1 week
1.8 Preliminary estimated cost per square ft 1 week
1.9 Client's approval 1 week
T 1.10 Development Order Submission 2 months
h 2.0 Design Development Phase
2.1 Detailed architectural drawings to prepare for Building Plans 2 months
2.2 Detailed structural drawings to be completed 2 months
2.3 Detailed M&E drawingsto be completed 2 months

BP
2.4 Detailed landscaping drawings to be completed 1 month
2.5 Pre-tender cost 2 weeks
2.6 Building Plans Submissions
2.7 Other authorities Submissions 1 month
2.7.1 Passive fire compliance drawings to be submitted to BOMBA 1 month
2.7.2 Active fire compliance drawings to be submitted to BOMBA 2 months
2.7.3 Electrical drawings to be submitted to TNB 2 months
2.7.4 Plumbing and Sewerage drawings to be submitted to JBA & JBS 2 months
2.7.5 Landscape department 2 months

BP APPROVAL
2.7.6 Street lightings 2 months
2.7.7 Transport department for Car Park 2 months
2.7.8 Kuala Lumpur Engineering Department 2 months
3.0title
Sample phase Contract
block Documentation Phase
3.1 Complete architectural tender documentation drawings 1 month
3.2 Complete structural tender documentation drawings 1 month
3.3 Complete M&E tender documentation drawings 1 month
3.4 Tender estimates and preperation of BQ 1 month

LETTER OF APPROVAL
3.5 Call for tender 1 week
3.6 Tender Period 2 weeks
3.7 Tender Close
3.8 Review and evaluation of tender offers 2 weeks
3.9 Tender report and recommendation 1 week
3.10 Letter of award to appointer contractor 1 week
4.0title
Sample phase Contract
block Implementation Phase
4.1 Preliminaries
4.1.1 Site handling over and site possesions 1 week
4.1.2 Site mobilization 1 week
4.1.3 Putting up hoardings and signages 1 week
4.1.4 Site clearing and site leveling (earthworks) 1 week
4.1.5 Setting out 2 weeks
4.2 Foundation
4.2.1 Excavation 2 months
4.2.2 Piling 2 months
4.2.3 Constructing pile caps 1 month
4.2.4 Pile caps installation 1 month
4.3 Basement works
4.3.1 RC retaining wall to be errected 1 month
4.3.2 RC floor slabs to be installed 3 weeks
4.3.3 RC ramps to be installed 2 weeks
4.3.4 Lift pit 2 weeks
4.4 Superstructure
4.4.1 Basement B1 RC Columns 2 weeks
4.4.2 Basement B1 RC Beams 2 weeks
4.4.3 Basement B1 RC Floors 2 weeks
4.4.4 GF RC Columns 2 weeks
4.4.5 GF RC Beams 2 weeks
4.4.6 GF RC Floors 2 weeks
4.4.7 1F RC Columns 2 weeks
4.4.8 1F RC Beams 2 weeks
4.4.9 1F RC Floors 2 weeks
4.4.10 2F RC Columns 2 weeks
4.4.11 2F RC Beams 2 weeks
4.4.12 2F RC Floors 2 weeks
4.5 Walls
4.5.1 Pre cast concrete walls for services cores 1 month
4.5.2 Pre cast concrete load bearing wall 1 month
4.5.3 In-situ concrete walls 1 month
4.5.4 Brickwalls 1 month
4.5.5 Curtain walls 1 month
4.5.6 Perforated steel sheet walls 1 month
4.6 Roof
4.6.1 Metal Roofing 1 month
4.6.2 Stormwater drainage system installation 1 week
4.7 Façade Construction
4.7.1 Installation of steel frame 2 months
4.7.2 Installation of perforated steel sheets 2 months
4.8 M&E
4.8.1 Cabling and wiring works 1 month
4.8.2 Lift installation 1 month
4.8.3 Extra-Low Voltage wiring works 1 month
4.8.4 Air-conditioning and Mechanical ventilation installation 2 weeks
4.8.5 Fire protection system 1 week
4.8.6 Water supply and plumbing works 1 week
4.8.7 Sewerage works 1 week
4.8.8 RWDP installation 1 week
4.8.9 Flat water tank installation 1 week
4.8.10 Security surveillence system 1 week
4.8.11 Fire water storage installation 1 week
4.8.12 Water sprinklers installation 1 week
4.8.13 Smoke detectors installation 1 week
4.8.14 Stormwater reticulation system 1 week
4.8.15 External lighting works 2 weeks
4.8.16 Internal lighting works 2 months
4.8.17 Civil works 2 months
4.9 Architectural Finishes
4.9.1 Celing finishes 1 month
4.9.2 Internal wall plastering 2 weeks
4.9.3 External wall plastering 2 weeks
4.9.4 Internal wall paintings 2 weeks
4.9.5 External wall paintings 2 weeks
4.9.6 Floor finishes 1 month
4.9.7 Sanitary fixtures 2 weeks
4.9.8 Staircase finishes 2 weeks
4.9.9 Staircase railings 2 weeks
4.9.10 Ramps railings 2 weeks
4.9.11 Balcony railings 2 weeks
4.9.12 Door frames 2 weeks
4.9.13 Door ironmongery 2 weeks
4.9.14 Door installation 2 weeks
4.9.15 Window frame 2 weeks
4.9.16 Window ironmongery 2 weeks
4.9.17 Window installation 2 weeks
4.9.18 Building and commercial space signages 2 weeks
4.10 Landscaping
4.10.1 Street pavement into building 2 weeks
4.10.2 Trees to be planted at green spine 1 week
4.10.3 Trees to be planted at hanging gardens 1 week
4.10.4 Plantings on green wall 1 week
5.0 Final Completion Phase
5.1 Testing and commisioning 1 month
5.2 Cleaning up 2 weeks
5.3 Inspection by consultants 2 weeks
5.4 Pre CCC inspection by authorities (clearance letter) 2 weeks

CPC

FINAL ACCOUNTS
5.5 Collect as built drawings, warrenties and garauntees from contractors 2 months

CCC

CMGD
5.6 Granting of CPC to contractor (contractual) 1 week
5.7 Granting of CCC 2 weeks
5.8 Defect liability Period 96 weeks
5.9 CMGD-Certificate of Making Good Defects is issued 96 weeks
5.10 Final Accounts Cetificate 96 weeks