You are on page 1of 1

IWN No.

: MEG-IWN-0785
INSPECTION WITNESS NOTICE Date : 19-Aug-2021
To : eWay From : Samsung C&T
Agency : TPL Engineering & Construction Group.
Plant Procurement Team / SQS Unit
Project Name 718MW CCPP MEGHNAGHAT, BANGLADESH
PO No. 5000581492
Inspection Item Expansion Joint
SQS Engineer Kwantae Kim Contact Number +82-2-2145-7937
SQS Engineer Email ktf1967.kim@samsung.com
Supplier Name PCTL
Supplier Contact Person Md Akheruzzaman Contact Number 033 40133435
Manufacturer Name PAHARPUR
Inspection Location 14 Diamnod Harbour Road, South 24 Pargana Kolkata 700008
Location Contact Person Syamantak Chandra Contact Number 91 9874240260
Inspection Country India
Inspection Date 23-Aug-2021
Assigned Inspector Sudipto Datta
■ Reference Document
Approved Vendor Drawings/Documents Approved Shop Inspection & Test Plan/Procedure
Datasheet / Item List Others
■ Inspection Description
100% Inspection Random Inspection Material Inspection
Review of NDE Report Visual Inspection Dimensional Inspection
Routine Test Performance Test Insulation Resistance
High Voltage Test Pneumatic Test Hydrostatic Test
Factory Acceptance Test PQR/WQT Witness Painting Inspection
Packing Review of Test Records IRN Issue
■ Special Instruction
A. Inspection Activity Reports (incl. Daily Flash Report)
A-1. Daily Flash Report shall be submitted by the close of business.
A-2. Inspection Activity Report (IAR) shall be issued within two days after the date of inspection completion.
A-3. Document Number of IAR : MEG-5000581492-M28-IAR-043
A-4. All reviewed QC dossiers including test report, records, approved dimensional drawings and certificates shall
be stamped and signed.
A-5. Next expected inspection date shall be checked and reported on IAR.
A-6. Photographic records with description shall be included on IAR.
A-7. Check List for Dimensional Witness Inspection shall be signed by inspector & supplier and submitted in
scanned copy after Dimensional inspection.
A-8. The related drawings shall be received from supplier at shop and confirm/record the latest related
drawing's revision No. on IAR.
A-9. Packing Inspection Check List shall be handwritten and submitted in scanned copy.
A-10. If the inspection result is not easy to define whether it’s acceptable or not, inspector should contact
SQS Engineer in Samsung C&T directly on the day of inspection.
B. Inspection Release Notice
B-1. Inspection Relase Notice (IRN), with both PDF and Word format, shall be issued to Samsung C&T right after
packing inspection if there is no outstanding issue.
 (If Samsung C&T is agreed, Samsung C&T's representative can issue Inspection Release Notice (IRN) to
Supplier right after packing inspection if there is no outstanding issue.)
* Fumigation or Heat treatment certificate for wooden packing materials shall be attached.
B-2. Document Number of IRN : MEG-5000581492-M28-IRN-027
B-3. Packing List shall be submitted in both excel and PDF format.
■ Attachments
Application for Shop Inspection & Test Approved Shop Inspection and Test Plan&Procedure
Approved Vendor Drawings/Documents Formats for Inspector
Approved Procedures (NDE, PMI, Painting, …) Others