Feedback of The CT QC

Name: Nubab Habibulah School & College ID: 4677271692-sub Date: 2021-7-13

Sub-C
NO Subject JV QC JV QC Comment Schedio Comment
Desk

1 Is Project Name & ID correctly provided in the Drawings?


2 Is ID presented in all pages and if it is correct? No title box found
3 Is North direction presented and is corect?
4 Are at least two levels of dimension lines provided for plan?
5 Check the column orientation and if have brick column, mark it with its identification like BC1, BC2
6 Column types should be according to rebar number not just dimention.
7 Is separation joint identified in plan and compatible with its picture. Identified but no picture
8 Is scales correctly provided for all drawings? No title box
9 Are lintel rebar arrangements provided?
10 Are all columns and beams named in layout plan?
11 Check Grid distance and compare with Arch Plan grid

12 Are gridlines and column orientation compatible in all Str plans ad also are they compatible with Arch plan?

13 Stair section with details with detailing of landing beam.


14 Are all column, beam and slab details are based on Ferro results
15 over all compatibility with Arch Plan
Section of Columns
16 Are all columns long sections and cross sections given in column schedule?
17 Are longitudinal rebars (size, number, and spacing) matches with Ferro Scan and exposure Results No data found in rebar exposure
18 Ties (size, number and spacing) with reference to Ferro in middle portion
19 Ties (size, number and spacing) with reference to Ferro in Bottom portion and exposure results No data found in rebar exposure
20 Is concrete cover matches with ferro and exposure? No data found in rebar exposure
Is long section of column consistent with each column section and footing. (dimension and longitudinal rebar
21
and ties)?
22 Are orientation of columns OK? (according o field sketches)
23 Is there any soil investigation report ?
24 Are dimensions of all columns given in column schedule properly ?
Section of footing
25 Dimension of footing present on drawing (level, grade beam, thickness, depth, etc.)
26 Check footing measurement with checklist
27 Are the dimensions of the footing same in all drawings (plan, elevation, section)
Section of slab
28 Are stair slab details provided and match with Ferro?
29 Is long section of slab presenting rebar in both direction?
30 Is long section of slab matches with Ferro and exposure? problem in expo
31 Is section of slab and stair slab presented in all sections and compatible with their own section?
32 Is the beam section correctly presented in the Slab section?
Section of Beams
33 Are the grade Beam details presented?
34 Are all beams long sections and cross sections given in beam schedule and compatible with layout?
35 Is beam naming and dimensions in all drawings match?
36 Are beam rebar details match the ferro scan result and exposure? No scanning found in expo location.
37 Is long section of beam consistent with each beam section (dimension and rebar long and stirrups)
2.Feed Back in Site Plan
38 Is Site Plan matches with google earth photo?
39 Six photos (included two insides, two out sides , front side,and google earth) are provided?
40 Is the shape of building in site plan and Arch drawing matches?
41 Is distance between all buildings are presented in site plan?
42 Is tin shed shown in roof top layout plan? (if exist) N/A
43 Is the boundary wall include in site plan with height, length and materials section?
44 Is project details information tabel provided in site plan? and if it is correct?
45 Are Sewarage system located in site plan with proper direction?
46 Are two section for each building included with site plan marking with section cut lines?
47 Is the north direction presented in site plan?
3-Feedback for the Documentations
48 Are Project Name & ID correct in the report?
49 Are ID in all checklists and test results correct?
50 Are all columns and beams named in layout plan?
51 Is different construction phases mentioned ?
52 Are PDF files same as DWG files?
53 Are all texts in PDF format legible?
54 Are all checklists provided (Str and Arch layout should be signed by supervisrs)?
55 Naming should be based on template provided
4-Feedback for the Floor Plan
56 Is North direction presented in the plan and all North symbols match together?
57 Are all columns and beams named in layout plan?
58 Are all location maps for all tests presented?
59 Are IDs of tests match with report (Ferro)?
60 Are thickness of all walls presented?
61 Are floor finishing details compatible with pictures?
62 Are floor finishing details compatible with exposure pictures?
63 Are gridlines and column orientation compatible in all Arch plans?
Are the level of storey presented in title of plan match with other dimentions? (in elevation, section, foundation
64
data, etc)
65 Is separation joint and slab connection presented in the plan with notes?
66 Is dimension plans for all floors 1/100 scale presented?
67 Is detailed information table provided? (Floor Finishing Schedule table)
68 Is Details information about window (with sill height and size) presented for all windows?
69 Is details information about door with sill height and size presented?
70 Is detailed information about wall, floor and ceiling in each room presented?
71 Is the level changes in every floor presented?
72 Are the wall sections in plan and section hatched? Skipped as per suggestion by POC
5-Feedback for the Section
73 Are the wall sections in section hatched and sections are provided?
74 Are all room number and code and use presented in the sction? Skipped as per suggestion by POC
75 Is the number of stairs presented correctly on plan and section?
76 Are thickness of Walls match the plan?
77 Are landing beam details are presented in stair case?
Feedback of The CT QC
Name: Nubab Habibulah School & College ID: 4677271692-sub Date: 2021-7-13

Sub-C
NO Subject JV QC JV QC Comment Schedio Comment
Desk

78 Are Stair Slab details are presented?


79 Are the location of cut lines displayed in all plans?
Having 2 sections in different directions with stair case( if required additional sections such as stairs cases,
80
1/50 scele) .
Section X-X
81 Is name of section being correct (X-X)?
82 Are drop walls correctly presented?
83 Is the beam dimension and slab dimensions presented correctly and match with frame layout?
84 Is the section containing foundation and grade beam witth details information?
85 Is the foundation section and grade beam matched with their section?
86 Are parapet dimensions correctly presented?
87 Are window openings in plan and elevation and section match?
88 Are door openings in plan and elevation and section match? N/A
89 Are parapet wall and water tank and roof access presented correctly?
90 Are elevation levels (height) in section match with plan?
91 Roof Details information provided?
Section Y-Y
92 Is name of section being correct (Y-Y)?
93 Are drop walls correctly presented?
94 Is the beam dimension and slab dimensions presented correctly and match with frame layout?
95 Is the section containing foundation and grade beam witth details information?
96 Is the foundation section and grade beam matched with their section?
97 Are parapet dimensions correctly presented?
98 Are window openings in plan and elevation and section match? N/A
99 Are door openings in plan and elevation and section match?
100 Are parapet wall and water tank and roof access presented correctly?
101 Are elevation levels (height) in section match with plan?
102 Roof Details information provided?
6-Feedback for the Elevation
103 Is different construction phases presented in plan and elevation? Skipped as per suggestion by POC
104 Are at least two levels of dimension lines provided in at least two sides for plan and elevation?
105 Are exposed pipes presented in Elevation? Skipped as per suggestion by POC
106 Are elevation symbols presented in all plans?
107 Are window and door openings in plan and elevation match?
108 Are levels (heights) in elevation match with plan?
109 Are naming of elevations correct? (North, South…)
110 Are parapet wall and water tank and roof access presented correctly?
111 Are elevations match with pictures? Skipped as per suggestion by POC
112 Are stair slab elevations mentioned correctly in both plan and section?
113 Is Ground level Shown in elevation?
7-Feedback for the Lintel Section/False Slab/ Counter slab
114 Are Lintel Id Name Lintel Type presented?
115 Is the size of sun shade presented?
116 Is Sill height of counter slab with thickness
117 Is Sill height of false slab with thickness presented?
8-Feedback for the NDT and DT Test
118 Are Locations and IDs of NDTs and Destructive tests correct?
119 Check the image scan point in layout with Image ID.

120 Check the rebar exposure point (at least three points) and image scan point and cross check the rebar dia with
exposer report
121 Check the 20% ferro scan point in column, beam in all floors
9-Feedback for the MEP
Water Distribution Plan
122 Exposed water piping route, and size shall be shown.
Water supply pipe material will be GI at east side. Others material
123 Material & specification (uPVC,PVC,PPR,CPVC,GI) of piping shall be clarified. specifications are OKAY.
Skipped as per suggestion by POC

124 Inlet (From WASA) of water piping of building shall be identified and clearly depicted in the drawings.
125 Exposed pipe route should be shown in elevation. Skipped as per suggestion by POC
126 Elevation (heigjht) of piping shall be clarified. Skipped as per suggestion by POC
All material and specification is okay as per picture only one material
127 Material & specification of all piping shall be clarified. clarification at east side is not okay. Water supply pipe material will be GI. Skipped as per suggestion by POC
Material of water inlet from WASA is PPR not PVC

128
Water piping inlet and outlet of wet are like toilets shall be clearly presented in the drawings with picture
129 If mechanical room exists, a plan of the mechanical room shall be provided with pictures. N/A

130 Show the location of reservoir tank (if exists) with picture. Show the inlet point with picture at reservoir tank
(if possible)
As there is reservoir tank there must be a centrifugal pump to lift water to
131 Show the pump with specifications and pictures. If there is a submersible pump show the location with picture. over head tank.
Skipped as per suggestion by POC

Show the route of piping to over head tank from reservoir with pictures and elevation. Show the route of piping
132 Skipped as per suggestion by POC
in elevation drawing

133 Only pump picture missing


Show the distribution line (if exposed) to every wet areas of each floor (washrooms, basins) with pictures.
Show each point of inlet at wet areas with height (basin point, bib-cock, push shower etc) from floor level with
134 Skipped as per suggestion by POC
pictures.
Sewage Plan
135 A sewage plan shall be provided in autocad format in elevation. (both vertical and horizontal piping) Skipped as per suggestion by POC
136 Show the sewage line which enters at septic tank with pictures.
137 Show the septic tank location with pictures.
138 Elevation (heigjht) of piping shall be clarified. Skipped as per suggestion by POC

139 Show the point of each sewage line and waste water evacuation line with pictures at every washroom. Skipped as per suggestion by POC

140 A sewage plan shall be provided in autocad format with pictures. Skipped as per suggestion by POC
141 Exposed sewage pipes and size shall be shown with pictures.
142 Outlet of sewage of building shall be identified and clearly depicted in the drawings
143 Material & specification (size) of all swage pipes shall be clarified Skipped as per suggestion by POC
144 Sewage inlet and outlet of wet are like toilets shall be clearly presented in the drawings
145 Location of specification of sewage pump shall be shown with picture (if exists) N/A
Feedback of The CT QC
Name: Nubab Habibulah School & College ID: 4677271692-sub Date: 2021-7-13

Sub-C
NO Subject JV QC JV QC Comment Schedio Comment
Desk

Down Pipes and rain piping systems (Drainage Plan)


146 Location of all floors drain & rain drain shall be shown with pictures. Skipped as per suggestion by POC
147 Location & material and specification of all rain drain piping shall be clarified N/A. Only slope and hole towards slope at outer wall. Skipped as per suggestion by POC
148 A complete plan of drainage system at the site for both rain and sewage system shall be provided.
149 Location of clean outs shall be shown with photos
Cooling, Heating and Fire Fighting N/A
150 If exists, the plans for cooling and heating systems shall be provided including HVAC
151 Location of indoor and outdoor AC units, condensers, splits etc… shall be shown (if exist)
152 Location and size of all ceiling fans shall be clarified
153 Exhaust system of toilets shall be clarified
154 Location & size of fire box shall be shown in each floor
Verify if Firefighting systems exist including the sprinkler systems, booster pumps, water storage/tank etc. and
155
if exist complete plan shall be provided
EL Drawings
156 Cable routes (In exposed condition) shall be demonstrated in the autocad drawings with pictures. Skipped as per suggestion by POC
157 Technical specifications of cables such as the size and watt shall be presented (Cable Picture) Skipped as per suggestion by POC
158 Outlet and inlet of cables of building and MDB SDB shall be presented in the drawings with pictures
159 Outlet and inlet of cables of wet area like toilet shall be presented in the drawings with cable size Skipped as per suggestion by POC
160 Socket outlet plan shall be presented in the drawings with pictures.
161 If any more hazerd materials exist mention with picture & location. N/A
162 Fire detection/alarm plan shall be presented through autocad drawings. (if exist) N/A
163 All the MDB, SDB picture mention in drawing by locating in layout.
164 Have sound system and CC camera with picture & location.
165 All electro-mechanical equipments have to show with picture in details
10-Feedback for the NSE
166 NSEs should be provided in excel format and number of the items should be presented
167 Compatibility between the Number of the NSEs and the photos
168 All the photos should be stored in floor-wise aproach
photos should be taken at the locations of anchorage if the elements are not anchored, photos of the gap
169
between nonstructural element and the wall/floor should be taken
170 NSE Checklist have to fill up with proper guidline
The number of items of each NSE component found in each story should be noted down in the checklist under
171
the columns of 1st Floor, 2nd Floor, 3rd Floor and so on.
The dimensions of each component should be measured and incorporated in the checklist in the appropriate
172 box. For example, length,width and height of a table, bench could be measured for dimensions

173 The weight of each item should be estimated based on visual observation.
Height of the NSEs should be measured either from the ceiling or from the floor and incorporated into the
174
checklist in appropriate box.

11-Feedback for the Photos


175 Photograph taken from each side of the structure
176 Photograph taken from foundation with measurement
177 Photograph taken from All test with grid number and separation joint (if any) with measurement
178 Photos of Damaged members and other critical places of the structure
Photograph taken from NSEs in each room from six position with mentioning the particular room number in
179
each floor

180 For column give all doc : like all scan image, picture of data takeing, gride no in a separet folder
181 For beam give all doc : like all scan image, picture of data, gride no in a separet folder
182 For slab give all doc : like all scan image, picture of data, gride no in a separet folder
183 In structural drawing marks scaning position and give note 20% or type base
184 Ferro scan checklist is signed by JV and PIU

185 Scan Image data of Rebar exposure position , checklist and picture in a folder.
186 All picture must be clear for measurment observation.
187 Incorporate the exposure area in structure drawing

188 All picture of foundation must be clear with measurment in a folder


189 If excavation is not possible than attach the existing drawing in a folder and give note in footing drawing N/A
190 Check checklist information with section of footing
Explanation of QC

Name: NUBAB HABIBULAH SCHOOL&COLLEGE ID: 4677271692- Sub Date: 2021-7-13

1-Feedback for the ARCH. Drawing


status (Red:
NO Subject Not OK) Location Reference Schedio Comment

1 Is Site Plan matches with google earth photo? Corrected

Six photos (included two insides, two out sides , front side,and google NOT VISUAL RAFERANCE
2 Corrected
earth) are provided? PICTURES

3 Is the shape of building in site plan and Arch drawing matches? Corrected

PROVIDE EVERY NEAREST


4 Is distance between all buildings are presented in site plan? EXISING BUILDING DISTANCE Corrected
PROPERLY.

Is North direction presented in the plan and all North symbols match
5 DRAWING SUBMITE CAREFULLY Corrected
together?

6 Are all location maps for all tests presented?

ADDRESS ALL TESTING POINS IN


ELIMENATED POINT
ALL FLOORS.

7 Are IDs of tests match with report (Ferro)?

ADD TOILET ZONE IN FLOOR


8 Are floor finishing details compatible with pictures? Corrected
FINISHING DETAIL TABLES

ADD TOILET ZONE IN FLOOR


9 Are floor finishing details compatible with exposure pictures? Corrected
FINISHING DETAIL TABLES

PROVIDE EVERY
ARCHITECCTURAL
10 Is dimension plans for all floors 1/100 scale presented? ELEMENTS(wall, column etc.) already Skip
DIMENSSIONS AS LIKE WORKING
DRAWING.
Explanation of QC

Name: NUBAB HABIBULAH SCHOOL&COLLEGE ID: 4677271692- Sub Date: 2021-7-13

1-Feedback for the ARCH. Drawing


status (Red:
NO Subject Not OK) Location Reference Schedio Comment

Is detailed information about wall, floor and ceiling in each room PROVIDE ALL ROOMS FLOOR,
11 Corrected
presented? CEILING & WALL DETAILES

PROVIDE HATCHES IN ALL


12 Are the wall sections in plan and section hatched? ELIMENATED POINT
ARCHITECTURAL ELEMANTS

PROVIDE HATCHES IN ALL


13 Are the wall sections in section hatched and sections are provided? ARCHITECTURAL PLAN, ELV & Corrected
SECTIONS

PROVIDE EVERY ROOM NUMBER


14 Are all room number and code and use presented in the sction? ELIMENATED POINT
CODE IN SECTION

PRESENT CORRECTLY STAIR


15 Is the number of stairs presented correctly on plan and section? Corrected
SECTION DRAWING

PRESENT STAIRCASE LANDING


BEAM & OMITE UN-NESSESARY
16 Are landing beam details are presented in stair case? Corrected
DRAWINGS TO SUBMITED FINAL
DRAWINGS.

PRESENT CORRECTLY STAIR


17 Are Stair Slab details are presented? Corrected
SECTION DRAWING

PROVIDE PERAPATE WALL


18 Are parapet dimensions correctly presented? Corrected
CORRECTLY.
Explanation of QC

Name: NUBAB HABIBULAH SCHOOL&COLLEGE ID: 4677271692- Sub Date: 2021-7-13

1-Feedback for the ARCH. Drawing


status (Red:
NO Subject Not OK) Location Reference Schedio Comment

PROPERLY PROVIDE O.H.W.T. &


19 Are parapet wall and water tank and roof access presented correctly? PARAPET WALL INSECTION Corrected
DRAWINGS.

PROVIDE Y-Y SECTION AGAIN.


20 Are drop walls correctly presented? Corrected
FOLLOW DIRECTION LINES.

PROVIDE PERAPATE WALL


21 Are parapet dimensions correctly presented? DIMENSSION pERFECTLY & USE Corrected
PROFESSIONAL HATCHES.

PROVIDE SECTION DRAWING


22 Are door openings in plan and elevation and section match? PERFECTLY WITH EVERY DOOR & Corrected
DOOR OPENING DIRECTIONS.

23 Are parapet wall and water tank and roof access presented correctly?

Parapet wall and water tank and roof


access presented correctly with roof Corrected
detailes.

24 Roof Details information provided?

CORRECT TYPE WINDOW PROVIDE


25 Are window and door openings in plan and elevation match? Corrected
IN ELV DRAWINGS.

PROVIDE O.H.W.T. HIGHT


26 Are parapet wall and water tank and roof access presented correctly? SEPARATELY IN ALL ELV Corrected
DRAWINGS.

PERFECTLY PROVIDE ELV


27 Are elevations match with pictures? DRAWING. FOLLOW PERSPECTIVE Corrected
VIEW RULE.
Explanation of QC

Name: NUBAB HABIBULAH SCHOOL&COLLEGE ID: 4677271692- Sub Date: 2021-7-13

1-Feedback for the ARCH. Drawing


status (Red:
NO Subject Not OK) Location Reference Schedio Comment

PERFECTLY PROVIDE LINTEL ID


28 Are Lintel Id Name Lintel Type presented? Corrected
NAME RAWINGS.

29 Is the size of sun shade presented?

RECHECK EXISTING BUILDINGS


ALL LINTEL & PROVIDE ACTUAL Corrected
SIZE & THICKNESS.

30 Is Sill height of counter slab with thickness

31 LINTEL

PROVIDE SILL HIGHT OF FALSE


32 Is Sill height of false slab with thickness presented? SLAB WITH THICKNESS There is no false slab here
PRESENTED.

33 TRIM EXTA LINES Corrected

34 CORRECTION EXTRA SLAB SLOAP Corrected


Explanation of QC

Name: NUBAB HABIBULAH SCHOOL&COLLEGE ID: 4677271692- Sub Date: 2021-7-13

1-Feedback for the ARCH. Drawing


status (Red:
NO Subject Not OK) Location Reference Schedio Comment

35 PROVIDE ACTUAL DRAWINGS. Corrected

36 PROVIDE NEAREST ROAD NAME or NUMBER IN SITE LAYOUT Corrected

37 SHOW GROUND FLOOR WINDOW. Corrected

38 PROVIDE ACTUAL DRAWINGS FOR MORE DETAILS. Corrected

FOLLOW 2ND STYLE FOR PROVIDE DOOR & WINDOW SIZE


39 Corrected
& SILL HIGHT.
Explana

Name: Nubab Habibulah School & College ID: 4677271692-sub

Explanation of QC- Structure P


status
NO Subject (Red: Not Location/ Reference
OK)

1 Is ID presented in all pages and if it is correct?

2 Are lintel rebar arrangements provided?

Are all column, beam and slab details are based on Ferro
3
results

Is long section of column consistent with each column


4 section and footing. (dimension and longitudinal rebar
and ties)?

5 Check footing measurement with checklist

Are the dimensions of the footing same in all drawings


6
(plan, elevation, section)

Are longitudinal rebars (size, number, and spacing)


7 matches with Ferro Scan and exposure Results
Is long section of slab matches with Ferro and
8 exposure?

Are beam rebar details match the ferro scan result and
9
exposure?

Is separation joint identified in plan and compatible with


10
its picture.
Explanation of QC

ub 7/13/2021

QC- Structure Part


Location/ Reference Explanation

No any title box and Id name

No scanning found in C3 type column , so how can u determine the


rebar arrangement of that column with doing ferro scan

Check the measurement carefully with footing field sketch

Check the measurement carefully with field sketch

Please count the rebar number in C2 and C4.


Check rebar dia which is not match with rebar exposure .If exposure
and ferro scan result have difference than give a note and give more
focus on exposure as it is visiable. Check all the rebar arrangment in
beam schedule with expo and scanning

Need input picture also.


8/8/2021 8/9/2021

Schedio Comment JV Comments

Corrected

Provided OK

Corrected OK

Corrected Not Ok

Corrected Not Ok

Corrected Not Ok

Corrected Ok
Corrected Not Ok

Corrected Not Ok

Input Picture Ok
Explanation of QC

Name: Nobab Habibullah School & College ID: 4677271692-Sub 7/13/2021

Feedback for Plumbing Drawing


status
NO Subject (Red: Not Location/ Reference Explanation Schedio Comment
OK)

Material & specification (uPVC,PVC,PPR,CPVC,GI) of Water supply pipe material will be GI at


1 Corrected
piping shall be clarified. east side.

All material and specifications are okay


as per picture. Only one material
clarification at east side is not okay.
2 Material & specification of all piping shall be clarified. Corrected
Water supply pipe material will be GI.
Material of water inlet from WASA is
PPR not PVC.

As there is reservoir tank there must be a


Show the pump with specifications and pictures. If there
3 centrifugal pump to lift water to over Corrected
is a submersible pump show the location with picture.
head tank.