Professional Documents
Culture Documents
Barabise Substation With Analysis 23aug2021
Barabise Substation With Analysis 23aug2021
4 Providing and laying of Reinforced cement Concrete Design Mix M25 Cu.M 2,810.73 19,000.00 53,403,870.00
including per cast, shuttering reinforcement M25
5 Providing and laying plain Cement Concrete 1:5:10 (1 Cement: 5 sand: 10 Cu.M 600.00 12,000.00 7,200,000.00
Stone aggregate ( 1:5:10)
6 Steel Reinfircement (Fe 500) MT 186.96 132,000.00 24,678,720.00
7 Stone filling (40 mm size) over grating of tranformer/reactor foundation Cu.M 20.00 3,500.00 70,000.00
Misc. Structural steel including rails embedments, edgs protection angles,
8 gratings etc but excluding the reinforcement steel and steel for lattice and MT 37.00 200,000.00 7,400,000.00
pipe structures.
9 Sq.M. 8,000.00 1,500.00 12,000,000.00
Stone spreading including antiweed treatment in switchyard excluding
All Civil works for following building as per technical Specification and soil excavation, concrete, and steel
10 bars of the foundation of the GIS room
approved drawing but are separately measured not included in
i) Auxilliary building (excluding finish) (11 kV indoor panel) Sq.M. 125.00 11,000.00 1,375,000.00 this . The outdoor ladder belongs to the
Sq.M. 98.00 11,000.00 1,078,000.00 scope of the steel structure supplier
ii) Fire fighting pump house building ( excluding Finish) and is not within the scope of this
iii) water tank ( excluding finish) LS 1.00 1,000,000.00 1,000,000.00 bidding; 2. Bulk water (if any) is
included in this quotation; 3. Outdoor
v)Township (Quarters (excluding finish)) drainage Ditch is separately measured in
a) B type Sq.M. 300.00 11,000.00 3,300,000.00 BOQ item 20. Except that the main steel
Sq.M. 360.00 9,500.00 3,420,000.00 structure frame is supplied and
b) C type installed by Party A, other civil
c) D type Sq.M. 126.00 14,000.00 1,764,000.00 masonry and masonry decoration and
Sq.M. 252.00 13,500.00 3,402,000.00 ground decoration need to be quoted. For
vi) Transit Camp TC details, please refer to the PEB
vii) Parking Shed (for 10 Car) LS 3.00 925,000.00 2,775,000.00 construction drawings.
11 internal & External Finish as per Specification for following buildings
i) Auxilliary building ( 11kV indoor panel) Sq.M. 125.00 10,000.00 1,250,000.00
ii) Fire fighting pump house building Sq.M. 98.00 15,000.00 1,470,000.00
iii) water tank LS 1.00 300,000.00 300,000.00
v) township(Quarters)
Page 1 of 49
construction drawings.
Construction of rail cum road as per drawing including all items such as
14 excavation, compaction, rolling, watering, WBM ect but excluding
concrete, reinforcement and structural steel.
(a) Section having four rails . Sq.M. 230.00 2,000.00 460,000.00
15 Chain link fencing as per technical sepcification and approved drawing RM 300.00 3,500.00 1,050,000.00
excluding concrete .
16 Switchyard Gate excluding Concrete. Nos. 2.00 250,000.00 500,000.00
Septic tank and soak pit (for 50 users) complete as per technical
17 specification and approved drawing excluding concrete & reinforcement LS 3.00 470,000.00 1,410,000.00
which shall be measured and paid seperately under respective items of BPS
18 Supplying & laying hume pipe of grad (NP-3) excluding concrete and
reinforcement
a) 250mm dia 250mm RM 150.00 4,600.00 690,000.00
b)300mm dia 300mm RM 120.00 5,000.00 600,000.00
c) 450mm dia 450mm RM 80.00 7,000.00 560,000.00
d) 600mm dia 600mm RM 40.00 12,000.00 480,000.00
e) 900mm dia 900mm RM 10.00 18,000.00 180,000.00
19 Supplying and erecting dewatering pumps.
a) Electrict Pump 5 HP Nos. 2.00 230,000.00 460,000.00
b) Electrict Pump 0.5 HP Nos. 2.00 25,000.00 50,000.00
20 Drains Excluding Concrete .
a) Section A-A (300 mm wide X depth up to 600 mm) RM 200.00 7,800.00 1,560,000.00
b) Section B-B (450 mm wideX depth from 600 mm to 900 mm) RM 100.00 13,500.00 1,350,000.00
c) Section C-C (600 mm wide X depth from 900 mm to 1200 mm) RM 80.00 21,000.00 1,680,000.00
d) Section D-D (750 mm wide X depth from 1200 mm to 1500 mm ) RM 20.00 31,000.00 620,000.00
Page 2 of 49
S.No. Item Description Unit Quantity Rate Amount Remarks
21 external water supply form borewell/ main water supply point to fire water
tank, control room building, township building
(i) 80 mm Dia GI pipe RM 100.00 1,600.00 160,000.00
(ii) 50 mm Dia Gi pipe RM 80.00 1,100.00 88,000.00
(iii) 40 mm Dia Gi pipe RM 60.00 800.00 48,000.00
iv) 25mm Dia GI pipe RM 40.00 500.00 20,000.00
23 All civil works for Bounday wall including excavation, concrete, RM 340.00 41,000.00 13,940,000.00
reinforcement steel, structural steel, plaster, painting, barbed wire and
concertina coil etc all complete as per technical specification (2.5 m high
brick masonary wall and 0.5 m high angle support on top ).
24 Main boundary wall Gate ( Steel ) including all works complete as per LS 1.00 250,000.00 250,000.00
technical specification.
25 Site Levelling
i Earthwork in excavation and filling in all types of soils including soft/ Cu.M 350.00 -
disintegrated rock with all leads and lifts within sub station boundary
ii Earthworks filling with Borrowed earth with all leads and lifts including Cu.M 500.00 -
royalty, taxes etc.
26 All civil works for security room as per TS including septic tank and soak pit. Sq.M. 9.00 45,000.00 405,000.00
Internal and External finish, sanitary amd plumbing works, plinth
protection etc. to complete the building are included in the item.
Page 3 of 49
S.No. Item Description Unit Quantity Rate Amount Remarks
Page 4 of 49
S.No. Item Description Unit Quantity Rate Amount Remarks
II EXTENSION OF 220 KV KHIMTI S/S
Part-C : Civil Works
1 Excavation in All type of Soil and Rock including backfilling disposal etc, for Cu.M 950.00 500.00 475,000.00
all and lifts
2 Providing and laying of Plain Cement Concrete (PCC) (1:4:8) Cu.M 125.00 14,000.00 1,750,000.00
3 Providing and laying of Plain Cement Concrete (PCC) (1:2:4) Cu.M 60.00 16,000.00 960,000.00
Providing and laying of Reinforcement Cement Concrete Design mix M25
4 including pre cast, shuttering, Grouting of pocket & underpinning but Cu.M 230.00 19,000.00 4,370,000.00
excluding steel
5 Providing and laying of Plain Cement Concrete 1:5:10 ( 1 cement : 5 Sand Cu.M 75.00 12,000.00 900,000.00
10 Stone aggregate)
6 Steel Reinforcement (Fe 500) MT 11.00 132,000.00 1,452,000.00
Misc. Structure Steel including rails, embedments, edge protction angles,
7 grating etc, but excluding the reinforcement steel and steel for lattice and MT 5.00 200,000.00 1,000,000.00
pipe structures.
8 Stone Spreading including antiweed treatment in switchyard excluding PCC Sq.M. 1,000.00 1,500.00 1,500,000.00
Earthwork in excavation and filling all types soil includig soft /disintegrated
I Cu.M 10,000.00 350.00 3,500,000.00
rock with all leads and lifts within sub station boundary
Page 5 of 49
S.No. Item Description Unit Quantity Rate Amount Remarks
Earthworks in filling with borrowed earth with all leads and lifts including
ii Cu.M 2,000.00 500.00 1,000,000.00
royalty, taxes etc
Page 6 of 49
S.No. Item Description Unit Quantity Rate Amount Remarks
III ADDITIONAL
12 PRE ENGINEERED BUILDINGS soil excavation, concrete, and steel
bars of the foundation of the GIS room
are separately measured not included in
i) CONTROL ROOM BULIDING this . The outdoor ladder belongs to the
scope of the steel structure supplier
and is not within the scope of this
All Civil works including finishing, internal cable trench, etc. bidding; 2. Bulk water (if any) is
Sq. M. 750 22,000.00 16,500,000.00 included in this quotation; 3. Outdoor
complete as per
drainage Ditch is separately measured in
BOQ item 20. Except that the main steel
ii) 220 KV GIS HALL structure frame is supplied and
installed by Party A, other civil
masonry and masonry decoration and
ground decoration need to be quoted. For
All Civil works including finishing, internal cable trench, etc. complete as per Sq. M. 600 21,000.00 12,600,000.00 details, please refer to the PEB
construction drawings.
Page 7 of 49
S.No. Item Description Unit Quantity Rate Amount Remarks
Sub total -Iii 39,416,000.00
Page 8 of 49
BILL OF QUANTITY
SUMMARY
BILL NO. DESCRIPTION
I 220/132/11 kV GIS BARHABISE Substation
II EXTENSION OF 220 KV KHIMTI S/S
III ADDITIONAL
Total Amount (I+II+III) without VAT
VAT 13 %
Grand Total(with VAT)
• The Advance Payment shall be 20 (Twenty)% of the contract price excluding VAT upon submission of Bank Guarantee iss
Nepal & Deductions from Payment Certificates shall commence in the first certificate in which the value of works executed
Contract Price. Deduction will be at the rate of 15% of the respective Interim Payment Certificate (IPC) until such time as th
been repaid as per rules of Government of Nepal.
• The Main Contractor shall be responsible and bear the entire cost for the quality assurance plan i.e. Lab Test & Field Test
• Payment shall be made atmost 1(one) week after the submission & verification of each IPC.
• Roofing material available in Nepali (local) market shall be used in GIS Hall if material stated in specification isn't readily a
• All the doors & windows has been analized with aluminium.
224.25 18582.15
Door & Windows for two floor
D1 m2 3.00 1.50 2.40 1.00 10.80
D2 m2 1.00 1.20 2.40 1.00 2.88
D3 m2 4.00 1.20 2.40 1.00 11.52
D4 m2 2.00 1.00 2.40 1.00 4.80
D5 m2 2.00 0.90 2.40 1.00 4.32
D6 m2 3.00 0.75 2.10 1.00 4.73
D7 m2 1.00 1.00 2.00 1.00 2.00
ED m2 3.00 2.00 2.40 1.00 14.40
W1 m2 17.00 2.00 2.40 1.00 81.60
W2 m2 0.00 1.20 2.40 1.00 0.00
V m2 1.00 2.40 1.45 1.00 3.48
G1 3.00 4.71 3.50 1.00 49.46
G2 3.00 2.00 2.40 1.00 14.40
G3 1.00 2.00 2.40 1.00 4.80
209.18 10000.00
GF
GF
FF
FF
4,167,047.14
2,091,800.00
GF
GF
FF
FF
12,363,085.14
957,451.00
900,000.00
871,787.00
3,375,000.00
1,854,462.77 15% of total works
14,217,547.91 37,913.46 per sqm two storey
18,956.73 per sqm
21,800.24
22,000.00 per sqm
mas exca filling geotextile wipehole soling
quantity 7.5 12 4.5 1 4.75 0.54
amount 67500 6000 2250 100 2850 810 79510
10601.333
S.No. Description Unit No. Length(m) Breadth(m) Height(m) Quantity
1 50mm thick puff sandwiched panels sqm.
a) roof 1 42.50 16.00 680.00
b) wall 1 109.00 7.50 817.50
3 Building Type D
Plastering work
LS m2 2.00 15.00 2.00 4.00 240.00
SS m2 2.00 14.00 2.00 4.00 224.00
PW m2 2.00 14.00 2.00 4.00 224.00
PW m2 1.00 14.00 2.00 4.00 112.00
PW m2 2.00 15.00 2.00 4.00 240.00
ceiling m2 2.00 15.00 14.00 420.00
1460.00
Deduction
Door & Windows for single floor
D1 m2 3.00 1.00 2.10 1.00 6.30
D2 m2 1.00 0.90 2.10 1.00 1.89
D3 m2 7.00 0.80 2.10 1.00 11.76
D4 m2 2.00 1.00 2.10 1.00 4.20
MD m2 1.00 1.60 2.10 1.00 3.36
W1 m2 8.00 1.50 1.20 1.00 14.40
W2 m2 1.00 1.00 1.20 1.00 1.20
V m2 3.00 0.50 0.50 1.00 0.75
43.86
Plastering Quantity 1416.14 550.00 778877.00
Painting Quantity 1,416.14 320.00 453,164.80
Tile Work m2 2.00 15.00 14.00 420.00 4,500.00 1,890,000.00
Sanitation & Electrification works 1,461,760.45
Total 4,583,802.25
4 Transit Camp TC
Plastering work
LS m2 2.00 15.00 2.00 4.50 270.00
SS m2 2.00 14.00 2.00 4.50 252.00
LS m2 2.00 15.00 2.00 4.00 240.00
SS m2 2.00 14.00 2.00 4.00 224.00
PW m2 2.00 14.00 2.00 8.50 476.00
PW m2 2.00 15.00 2.00 8.50 510.00
ceiling m2 2.00 15.00 14.00 420.00
2392.00
Deduction
Door & Windows for two floor
D1 m2 3.00 1.00 2.10 2.00 12.60
D2 m2 1.00 0.90 2.10 2.00 3.78
D3 m2 6.00 0.80 2.10 2.00 20.16
MD m2 1.00 1.60 2.10 1.00 3.36
W1 m2 8.00 1.50 1.20 2.00 28.80
W2 m2 1.00 1.00 1.20 2.00 2.40
V m2 4.00 0.50 0.50 2.00 2.00
73.10
Plastering Quantity 2318.90 550.00 1275395.00
Painting Quantity 2,318.90 320.00 742,048.00
Tile Work m2 2.00 15.00 14.00 420.00 4,500.00 1,890,000.00
Sanitation & Electrification works 2,303,485.75
Total 6,210,928.75
6 Auxiliary building
Plaster work
LS m2 2.00 12.00 4.00 192.00
SS m2 2.00 8.00 4.00 128.00
ceiling m2 1.00 12.00 8.00 96.00
416.00
Deduction
Door & Windows
D1 m2 1.00 1.60 2.10 3.36
D m2 1.00 1.00 2.10 2.10
W m2 2.00 0.90 1.20 2.16
7.62
Plastering Quantity 408.38 550.00 224609.00
Painting Quantity 408.38 320.00 130,681.60
Sanitation & Electrification works 291,872.65
Total 647,163.25
Remarks
1,061,438.88
1,050,000.00
2 Building Type C
Brick work
LS m3 2.00 25.00 0.35 3.50 61.25
SS m3 2.00 12.00 0.35 3.50 29.40
LS m3 2.00 25.00 0.23 3.00 34.50
SS m3 2.00 12.00 0.23 3.00 16.56
PW m3 2.00 12.00 0.23 6.50 35.88
PW m3 2.00 12.00 0.12 6.50 17.94
PW m3 1.00 25.00 0.12 6.50 18.69
214.22 20,000.00 4,284,350.00
Door & Windows for two floor
D1 m2 6.00 1.00 2.10 2.00 25.20
D2 m2 2.00 0.90 2.10 2.00 7.56
D3 m2 10.00 0.80 2.10 2.00 33.60
MD m2 1.00 2.00 2.50 1.00 5.00
W1 m2 6.00 1.50 1.20 2.00 21.60
W2 m2 2.00 1.00 1.20 2.00 4.80
V m2 4.00 0.50 0.50 2.00 2.00
G m2 1.00 2.00 1.20 1.00 2.40
102.16 10,000.00 1,021,600.00
Total 5,305,950.00
3 Building Type D
Brick work
LS m3 2.00 15.00 0.35 4.00 42.00
SS m3 2.00 14.00 0.35 4.00 39.20
PW m3 2.00 14.00 0.12 4.00 12.88
PW m3 1.00 14.00 0.12 4.00 6.44
PW m3 2.00 15.00 0.12 4.00 13.80
114.32 20,000.00 2,286,400.00
Door & Windows for single floor
D1 m2 3.00 1.00 2.10 1.00 6.30
D2 m2 1.00 0.90 2.10 1.00 1.89
D3 m2 7.00 0.80 2.10 1.00 11.76
D4 m2 2.00 1.00 2.10 1.00 4.20
MD m2 1.00 1.60 2.10 1.00 3.36
W1 m2 8.00 1.50 1.20 1.00 14.40
W2 m2 1.00 1.00 1.20 1.00 1.20
V m2 3.00 0.50 0.50 1.00 0.75
43.86 10,000.00 438,600.00
Total 2,725,000.00
4 Transit Camp TC
Brick work
LS m3 2.00 15.00 0.35 4.50 47.25
SS m3 2.00 14.00 0.35 4.50 44.10
LS m3 2.00 15.00 0.23 4.00 27.60
SS m3 2.00 14.00 0.23 4.00 25.76
PW m3 2.00 14.00 0.23 8.50 54.74
PW m3 2.00 15.00 0.12 8.50 29.33
228.78 20,000.00 4,575,500.00
Door & Windows for two floor
D1 m2 3.00 1.00 2.10 2.00 12.60
D2 m2 1.00 0.90 2.10 2.00 3.78
D3 m2 6.00 0.80 2.10 2.00 20.16
MD m2 1.00 1.60 2.10 1.00 3.36
W1 m2 8.00 1.50 1.20 2.00 28.80
W2 m2 1.00 1.00 1.20 2.00 2.40
V m2 4.00 0.50 0.50 2.00 2.00
73.10 10,000.00 731,000.00
Total 5,306,500.00
6 Auxiliary building
Brick work
LS m3 2.00 12.00 0.23 4.00 22.08
SS m3 2.00 8.00 0.23 4.00 14.72
36.80 20,000.00 736,000.00
Door & Windows
D1 m2 1.00 1.60 2.10 3.36
D m2 1.00 1.00 2.10 2.10
W m2 2.00 0.90 1.20 2.16
7.62 10,000.00 76,200.00
Total 812,200.00
Remarks
GF
GF
FF
FF
927,682.00
925,000.00
8,460.42 per sqm single storey
9,094.95
9,000.00 per sqm
Pradhan Builders Pvt. Ltd
Baneshwor, Kathmandu
Septic Tank analysis sheet
213,738.00
145,844.00
77,005.63
436,587.63
469,331.70
470,000.00
S.No. Description Unit No. Length(m) Breadth(m) Height(m) Quantity
1 Drain(brick masonry) cum
a) 0.30m*0.60m 2 1.00 0.30 0.60 0.360
20,000.00 7,200.00
7,200.00 per rm 7,740.000 7,800.00 per rm
20,000.00 7,200.00
20,000.00 5,400.00
12,600.00 per rm 13,545.000 13,500.00 per rm
20,000.00 7,200.00
20,000.00 5,400.00
20,000.00 7,200.00
19,800.00 per rm 21,285.000 21,000.00 per rm
20,000.00 7,200.00
20,000.00 5,400.00
20,000.00 7,200.00
20,000.00 9,000.00
28,800.00 per rm 30,960.000 31,000.00 per rm
S.No. Description Unit No. Length(m) Breadth(m) Height(m) Quantity
1 Boundary Wall(brick masonry)
i) Excavation cum 19 5.30 1.50 151.121
iii) Rebar kg
a) footing 266 0.90 147.778
228 1.10 154.815
b) column 152 4.30 580.978
399 1.10 173.393
399 0.40 63.052
c) beam 6 46.80 249.600
226 1.40 124.998
1,000.00 7,125.00
1,000.00 25,080.00
1,000.00 91,390.00
1,000.00 72,000.00
12000.00 472,500.00
500.00 112,500.00
1,501,550.89
33,367.80 for 45m long, excluding painting, barbed wire, concertina coil & structural steel
38,367.80 all complete 5000 for painting, barbed wire, concertina coil & structural steel
41,245.38
41,000.00 per rm
tructural steel
SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
1 SITE CLEARANCE
Felling of trees including cutting branches, sawing and carrying up to 15m away
from the site. For Each
1.01 1,1,ka Girth of tree 12 - 30cm Each 93.60
1.02 1,1,kha Girth of tree 31 - 60cm Each 280.80
1.03 1,1,ga Girth of tree 61 - 90cm Each 705.60
1.04 1,1,gha Girth of tree 91 - 120cm Each 0.00
1.05 1,1,ng Girth of tree 121 - 180cm Each 0.00
1.06 1,1,cha Girth of tree 181 - 240cm Each 0.00
1.07 1,1,chha Girth of tree 241 - 300cm Each 0.00
1.08 1,1,ja Girth of tree over 301cm Each 0.00
Tree root digging, lifting it and carrying up to 15m away from the site. For Each
1.09 1,2,ka Girth of tree 12 - 30cm Each 288.00
1.10 1,2,kha Girth of tree 31 - 60cm Each 381.60
1.11 1,2,ga Girth of tree 61 - 90cm Each 1814.40
1.12 1,2,gha Girth of tree 91 - 120cm Each 0.00
1.13 1,2,ng Girth of tree 121 - 180cm Each 0.00
1.14 1,2,cha Girth of tree 181 - 240cm Each 0.00
1.15 1,2,chha Girth of tree 241 - 300cm Each 0.00
1.16 1,6 Bamboo cutting,root digging,removel of bamboo from site (Dug-pit
dimension to be measured).For 1m3 cum 2016.00
1.17 1,7 Surface dressing work,cutting and filling earthwork,including levelling
ground surface(service road etc.). For 1m2 sqm 7.20
1.18 1 ,8 Excavation 15-20 cm of the top soil including disposal
out side of the construction site. For 1 m2 sqm 115.20
2 EARTHWORK
Earthwork in excavation including a lead of 10m and a lift of 1.5m in:
2.01 2,1 Soft Clay : For 1 cum cum 519.12
2.02 2,2 Hard clay mixed boulder less than 30cm size :.For 1cum cum 593.28
2.03 2 ,10 Soft Rock : For 1 cum cum 1854.00
2.04 2 ,4 Medium Rock without blasting : For 1 cum cum 2224.80
2.05 2 ,6ka Hard Rock without chiselling : For 1 cum cum 3708.00
Earthwork in filling including watering & ramming every 20cm th. Layers For 1cum :
2.06 2 ,25ka With Ordinary Soil cum 370.80
Earthwork in filling including ramming every 15cm th. Layers (without watering )For 1cum :
2.07 2 ,25kha With Ordinary Soil cum 185.40
Turfing work Including cutting, hauling for 10m and watering For 1sqm :
2.08 2 , 40 Turfing work cum 37.08
3 STONE WORK
Stone (rubble) masonry work up to 5 m ht. Of wall including collection of stones,
preparation of mortar and a lead of 10 m. For 1 cum :
3.01 6,1,ka,2 In 1:4 Cement Sand Mortar cum 11730.00
3.02 6,1ka,3 In 1:6 Cement Sand Mortar cum 10686.84
8.16 11,3 Laying of 25mm th. Mosaic flooring, 20mm th. C/ P in 1:2 and on th top of that 6mm th. White cement
and marble ( in 1:1) coat, complete with polishing. For 1.00 sqm Sqm 3753.47
8.17 11, 5 Paving 25mm th. Oiled terrazo tiles on 1:2 Surkhi mortar complete
with 1:1 cement sand pointing. For 1.0 Sqm Sqm 2111.37
8.18 11, 7 Laying of procelain glaxed tiles on 1:4 cement sand
mortar. For 1.0 sqm sqm 2902.79
8.19 11, 6 Laying of 25mm th. 450*450mm Marble on 20mmth. 1:4 surkhi mortar,
complete with polishing. For 1.00 sqm Sqm 4990.44
Filling work including watering and compaction.For 1cum:
8.20 11,19,ka With sand cum 3962.38
8.21 11,19,kha With 15 -150 mm broken bricks cum 3381.70
9 CEMENT PLASTERING
12.5 mm thick Cement Sand plaster For 1 sqm
9.01 12 , 1 ka In 1:2 cement sand mortar Sqm 461.52
9.02 12 ,1 Kha In 1:3 cement sand morter Sqm 406.08
9.03 12 ,1 Ga In 1:4 cement sand mortar Sqm 393.37
9.04 12,1,gha In 1:6 cement sand mortar Sqm 364.20
20 mm thick cement sand plaster For 1 sqm
9.05 12 ,4 ka In 1:3 cement sand morter Sqm 537.90
9.06 12 ,4 Kha In 1:4 cement sand mortar Sqm 514.18
9.07 12,4,ga In 1:6 cement sand mortar Sqm 468.73
9.08 12,5 25mm th. Mud plaster.For 1 sqm: Sqm 405.22
9.09 12, 6 12.5mm th. Mud plaster.For 1 sqm: Sqm 312.26
9.10 Flush pointing work on bricks masonry wall.
14,1, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 265.87
14,1, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 245.91
14,1, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 235.36
9.11 Flush ruled pointing work on bricks masonry wall.
14,1, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 309.07
14,1, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 289.11
14,1, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 278.56
9.12 Flush ruled pointing work on boulder stone masonry wall.
14,2, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 343.08
14,2, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 304.82
14,2, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 285.39
9.13 14,3 Flush ruled pointing work with 1:3 c/ m on ashler
stone masonry wall. For 1.0 sqm Sqm 182.50
10 PAINTING WORK
10.01 13 ,11 Three coats chapra resin polishing.For 1sqm Sqm 177.80