You are on page 1of 49

S.No.

Item Description Unit Quantity Rate Amount Remarks


I 220/132/11 kV GIS BARHABISE Substation
Part - C : Civil Works
1 Excavation in all types of soil and rock including backfiling disposal etc. for Cu.M 11,785.23 500.00 5,892,615.00
al leads and lifts
2 Providing and laying of plain cement Concrete (PCC) (1:4:8) Cu.M 1,805.82 14,000.00 25,281,480.00
3 Providing and laying of plain cement Concrete (PCC) (1:2:4) Cu.M 906.13 16,000.00 14,498,080.00

4 Providing and laying of Reinforced cement Concrete Design Mix M25 Cu.M 2,810.73 19,000.00 53,403,870.00
including per cast, shuttering reinforcement M25
5 Providing and laying plain Cement Concrete 1:5:10 (1 Cement: 5 sand: 10 Cu.M 600.00 12,000.00 7,200,000.00
Stone aggregate ( 1:5:10)
6 Steel Reinfircement (Fe 500) MT 186.96 132,000.00 24,678,720.00

7 Stone filling (40 mm size) over grating of tranformer/reactor foundation Cu.M 20.00 3,500.00 70,000.00
Misc. Structural steel including rails embedments, edgs protection angles,
8 gratings etc but excluding the reinforcement steel and steel for lattice and MT 37.00 200,000.00 7,400,000.00
pipe structures.
9 Sq.M. 8,000.00 1,500.00 12,000,000.00
Stone spreading including antiweed treatment in switchyard excluding
All Civil works for following building as per technical Specification and soil excavation, concrete, and steel
10 bars of the foundation of the GIS room
approved drawing but are separately measured not included in
i) Auxilliary building (excluding finish) (11 kV indoor panel) Sq.M. 125.00 11,000.00 1,375,000.00 this . The outdoor ladder belongs to the
Sq.M. 98.00 11,000.00 1,078,000.00 scope of the steel structure supplier
ii) Fire fighting pump house building ( excluding Finish) and is not within the scope of this
iii) water tank ( excluding finish) LS 1.00 1,000,000.00 1,000,000.00 bidding; 2. Bulk water (if any) is
included in this quotation; 3. Outdoor
v)Township (Quarters (excluding finish)) drainage Ditch is separately measured in
a) B type Sq.M. 300.00 11,000.00 3,300,000.00 BOQ item 20. Except that the main steel
Sq.M. 360.00 9,500.00 3,420,000.00 structure frame is supplied and
b) C type installed by Party A, other civil
c) D type Sq.M. 126.00 14,000.00 1,764,000.00 masonry and masonry decoration and
Sq.M. 252.00 13,500.00 3,402,000.00 ground decoration need to be quoted. For
vi) Transit Camp TC details, please refer to the PEB
vii) Parking Shed (for 10 Car) LS 3.00 925,000.00 2,775,000.00 construction drawings.
11 internal & External Finish as per Specification for following buildings
i) Auxilliary building ( 11kV indoor panel) Sq.M. 125.00 10,000.00 1,250,000.00
ii) Fire fighting pump house building Sq.M. 98.00 15,000.00 1,470,000.00
iii) water tank LS 1.00 300,000.00 300,000.00
v) township(Quarters)

Page 1 of 49
construction drawings.

S.No. Item Description Unit Quantity Rate Amount Remarks


a) B type B Sq.M. 500.00 13,800.00 6,900,000.00
b) C type C Sq.M. 600.00 13,100.00 7,860,000.00
c) D type D Sq.M. 210.00 23,500.00 4,935,000.00
Vi) Transit Camp TC Sq.M. 420.00 15,900.00 6,678,000.00
vii) Parking Shed for 10 Car LS 3.00 1,050,000.00 3,150,000.00
13 Concrete road as per drawing except reinforcement & concrete
(a) Road 3.75m wide Sq.M. 2,850.00 1,500.00 4,275,000.00

Construction of rail cum road as per drawing including all items such as
14 excavation, compaction, rolling, watering, WBM ect but excluding
concrete, reinforcement and structural steel.
(a) Section having four rails . Sq.M. 230.00 2,000.00 460,000.00

15 Chain link fencing as per technical sepcification and approved drawing RM 300.00 3,500.00 1,050,000.00
excluding concrete .
16 Switchyard Gate excluding Concrete. Nos. 2.00 250,000.00 500,000.00
Septic tank and soak pit (for 50 users) complete as per technical
17 specification and approved drawing excluding concrete & reinforcement LS 3.00 470,000.00 1,410,000.00
which shall be measured and paid seperately under respective items of BPS

18 Supplying & laying hume pipe of grad (NP-3) excluding concrete and
reinforcement
a) 250mm dia 250mm RM 150.00 4,600.00 690,000.00
b)300mm dia 300mm RM 120.00 5,000.00 600,000.00
c) 450mm dia 450mm RM 80.00 7,000.00 560,000.00
d) 600mm dia 600mm RM 40.00 12,000.00 480,000.00
e) 900mm dia 900mm RM 10.00 18,000.00 180,000.00
19 Supplying and erecting dewatering pumps.
a) Electrict Pump 5 HP Nos. 2.00 230,000.00 460,000.00
b) Electrict Pump 0.5 HP Nos. 2.00 25,000.00 50,000.00
20 Drains Excluding Concrete .
a) Section A-A (300 mm wide X depth up to 600 mm) RM 200.00 7,800.00 1,560,000.00
b) Section B-B (450 mm wideX depth from 600 mm to 900 mm) RM 100.00 13,500.00 1,350,000.00
c) Section C-C (600 mm wide X depth from 900 mm to 1200 mm) RM 80.00 21,000.00 1,680,000.00
d) Section D-D (750 mm wide X depth from 1200 mm to 1500 mm ) RM 20.00 31,000.00 620,000.00

Page 2 of 49
S.No. Item Description Unit Quantity Rate Amount Remarks
21 external water supply form borewell/ main water supply point to fire water
tank, control room building, township building
(i) 80 mm Dia GI pipe RM 100.00 1,600.00 160,000.00
(ii) 50 mm Dia Gi pipe RM 80.00 1,100.00 88,000.00
(iii) 40 mm Dia Gi pipe RM 60.00 800.00 48,000.00
iv) 25mm Dia GI pipe RM 40.00 500.00 20,000.00

22 External sewerage system including all item such as excavation, piping,


pipe fitting, manholes, gali
i) 250 mm dia RM 50.00 1,500.00 75,000.00
ii) 150 mm dia RM 50.00 1,000.00 50,000.00

23 All civil works for Bounday wall including excavation, concrete, RM 340.00 41,000.00 13,940,000.00
reinforcement steel, structural steel, plaster, painting, barbed wire and
concertina coil etc all complete as per technical specification (2.5 m high
brick masonary wall and 0.5 m high angle support on top ).
24 Main boundary wall Gate ( Steel ) including all works complete as per LS 1.00 250,000.00 250,000.00
technical specification.
25 Site Levelling

i Earthwork in excavation and filling in all types of soils including soft/ Cu.M 350.00 -
disintegrated rock with all leads and lifts within sub station boundary
ii Earthworks filling with Borrowed earth with all leads and lifts including Cu.M 500.00 -
royalty, taxes etc.

26 All civil works for security room as per TS including septic tank and soak pit. Sq.M. 9.00 45,000.00 405,000.00
Internal and External finish, sanitary amd plumbing works, plinth
protection etc. to complete the building are included in the item.

Construction of retaining wall with random rubble masonary in cement


motar (1:6) including levelling up with cement concrete (1:6:12), providing
27 weep holes of PVC pipes (150 mm dia) with necessary filter material at the Cu.M 1,000.00 12,000.00 12,000,000.00
mouth of weep holes, 50 mm thick cement concrete (1:2:4) copping on the
top of wall, 100 mm thick PCC (1:4:8) below RR masonary works,excavation
of foundation for all lifts up to 3m above lower level, Item of excavation,
PCC (1:2:4 & 1:4:8) shall be measured and paid seperately under respective
items of BPS

Page 3 of 49
S.No. Item Description Unit Quantity Rate Amount Remarks

Aproach Road-Strengthening of existing approach road as per TS (2.5 cm


thick pre-mix carpet, 100 mm thick WBM, filling the pot holes with WBM)
28 including cross drainage works but excluding concrete, RCC hume pipes Sq.M. 24,000.00 1,000.00 24,000,000.00
and reinforcement steel which shall be meausered and paid under
respective items of BPS

SUB TOTAL-I 268,042,765.00

Page 4 of 49
S.No. Item Description Unit Quantity Rate Amount Remarks
II EXTENSION OF 220 KV KHIMTI S/S
Part-C : Civil Works
1 Excavation in All type of Soil and Rock including backfilling disposal etc, for Cu.M 950.00 500.00 475,000.00
all and lifts
2 Providing and laying of Plain Cement Concrete (PCC) (1:4:8) Cu.M 125.00 14,000.00 1,750,000.00
3 Providing and laying of Plain Cement Concrete (PCC) (1:2:4) Cu.M 60.00 16,000.00 960,000.00
Providing and laying of Reinforcement Cement Concrete Design mix M25
4 including pre cast, shuttering, Grouting of pocket & underpinning but Cu.M 230.00 19,000.00 4,370,000.00
excluding steel

5 Providing and laying of Plain Cement Concrete 1:5:10 ( 1 cement : 5 Sand Cu.M 75.00 12,000.00 900,000.00
10 Stone aggregate)
6 Steel Reinforcement (Fe 500) MT 11.00 132,000.00 1,452,000.00
Misc. Structure Steel including rails, embedments, edge protction angles,
7 grating etc, but excluding the reinforcement steel and steel for lattice and MT 5.00 200,000.00 1,000,000.00
pipe structures.

8 Stone Spreading including antiweed treatment in switchyard excluding PCC Sq.M. 1,000.00 1,500.00 1,500,000.00

9 Concrete Road as per drawing expect reinforcement and concrete


(a) Road 3.75m wide Sq.M. 375.00 1,500.00 562,500.00
Chain Link fencing as per technical specification and approved drawing
10 RM 50.00 3,500.00 175,000.00
excluding concrete
11 Dismantling & reerection of chain Link fencing excluding concrete RM 50.00 1,000.00 50,000.00
Supplying & laying Hume pipe of grade (NP-3) excluding concrete and
12
reinforcement
a) 250mm dia RM 50.00 4,600.00 230,000.00
b) 300mm dia RM 30.00 5,000.00 150,000.00
c) 450mm dia RM 25.00 7,000.00 175,000.00
d) 600mm dia RM 25.00 12,000.00 300,000.00
13 Drains Excluding Concrete
a) Section A-A (300 mm wide X depth up to 600 mm) RM 60.00 7,800.00 468,000.00
b) Section B-B (450 mm wide X depth from 600 mm to 900 mm) RM 20.00 13,500.00 270,000.00
c) Section C-C (600 mm wide X depth from 900 mm to 1200 mm) RM 20.00 21,000.00 420,000.00
d) Section D-D (750 mm wide X depth from 1200 mm to 1500 mm) RM 20.00 31,000.00 620,000.00
14 Site Levelling

Earthwork in excavation and filling all types soil includig soft /disintegrated
I Cu.M 10,000.00 350.00 3,500,000.00
rock with all leads and lifts within sub station boundary

Page 5 of 49
S.No. Item Description Unit Quantity Rate Amount Remarks
Earthworks in filling with borrowed earth with all leads and lifts including
ii Cu.M 2,000.00 500.00 1,000,000.00
royalty, taxes etc

Page 6 of 49
S.No. Item Description Unit Quantity Rate Amount Remarks

Construction of retaining wall with random rubble masonary in cement


sand motors (1:6) including levelling up with cement concrete (1:6:12),
providing weep holes of PVC pipes (150 mm dia) with necessary filter
material at the mouth of weep hole, 50 mm thick cement concrete (1:2:4)
15 Cu.M 1,000.00 12,000.00 12,000,000.00
copping on the top of wall, 100 mm thick PCC (1:2:4) below RR masonary
works, excavation of foundation for alll lifts up to 3m above lower level.
Item of excavation PCC (1:2:4) & 1:4:8) shall be measured and paid
seperately under respective items of BPS

Sub total -II 32,327,500.00

III ADDITIONAL
12 PRE ENGINEERED BUILDINGS soil excavation, concrete, and steel
bars of the foundation of the GIS room
are separately measured not included in
i) CONTROL ROOM BULIDING this . The outdoor ladder belongs to the
scope of the steel structure supplier
and is not within the scope of this
All Civil works including finishing, internal cable trench, etc. bidding; 2. Bulk water (if any) is
Sq. M. 750 22,000.00 16,500,000.00 included in this quotation; 3. Outdoor
complete as per
drainage Ditch is separately measured in
BOQ item 20. Except that the main steel
ii) 220 KV GIS HALL structure frame is supplied and
installed by Party A, other civil
masonry and masonry decoration and
ground decoration need to be quoted. For
All Civil works including finishing, internal cable trench, etc. complete as per Sq. M. 600 21,000.00 12,600,000.00 details, please refer to the PEB
construction drawings.

iii) 132 KV GIS HALL

All Civil works including finishing, internal cable trench, etc.


Sq. M. 500 20,000.00 10,000,000.00
complete as per
21 External water supply from borewell/main water supply point to Fire water Since BOQ is inconsistent with the pipe
Tank material requirements in the drawing,
please quote separately for galvanized pipes
and CPVC pipes.

( i ) 80 mm Dia GI pipe RM 100 1,600.00 160,000.00 IF CPVC PIPE RS. 800/RM


( ii ) 50 mm Dia GI pipe RM 80 1,100.00 88,000.00 IF CPVC PIPE RS. 550/RM
(iii) 40mm Dia GI pipe RM 60 800.00 48,000.00 IF CPVC PIPE RS. 400/RM
(iii) 25mm Dia GI pipe RM 40 500.00 20,000.00 IF CPVC PIPE RS. 250/RM
22 Providing, laying, spreading of Gravel mixed soil/sand with compaction for cum 3,000.00 for rates only
sites encountered with loose materials

Page 7 of 49
S.No. Item Description Unit Quantity Rate Amount Remarks
Sub total -Iii 39,416,000.00

Total Amount (I+II+III) without VAT 339,786,265.00


VAT 13 % 44,172,214.45
Grand Total(with VAT) 383,958,479.45

Submitted By :- Pradhan Builders Pvt. Ltd.


New Baneshwor, Kathmandu
Email:- pbpl2050@gmail.com

Page 8 of 49
BILL OF QUANTITY
SUMMARY
BILL NO. DESCRIPTION
I 220/132/11 kV GIS BARHABISE Substation
II EXTENSION OF 220 KV KHIMTI S/S
III ADDITIONAL
Total Amount (I+II+III) without VAT
VAT 13 %
Grand Total(with VAT)

Terms & Conditions:


• The Contract shall be subjected to Price Adjustment.

• The Advance Payment shall be 20 (Twenty)% of the contract price excluding VAT upon submission of Bank Guarantee iss
Nepal & Deductions from Payment Certificates shall commence in the first certificate in which the value of works executed
Contract Price. Deduction will be at the rate of 15% of the respective Interim Payment Certificate (IPC) until such time as th
been repaid as per rules of Government of Nepal.
• The Main Contractor shall be responsible and bear the entire cost for the quality assurance plan i.e. Lab Test & Field Test
• Payment shall be made atmost 1(one) week after the submission & verification of each IPC.
• Roofing material available in Nepali (local) market shall be used in GIS Hall if material stated in specification isn't readily a
• All the doors & windows has been analized with aluminium.

Submitted By :- Pradhan Builders Pvt. Ltd.


New Baneshwor, Kathmandu
Email:- pbpl2050@gmail.com
TOTAL AMOUNT (NPR.) REMARKS
268,042,765.00
32,327,500.00
39,416,000.00
339,786,265.00
44,172,214.45
383,958,479.45

ubmission of Bank Guarantee issued by A-Class Bank of


hich the value of works executed exceeds 30% of the
tificate (IPC) until such time as the advance payment has

nce plan i.e. Lab Test & Field Test.

ted in specification isn't readily available.


Pradhan Builders Pvt. Ltd
Baneshwor, Kathmandu
CRB analysis sheet

SN Description Unit No. Length Breadth Height Quantity Rate


1 Control Room Building
Brick work
LS m3 2.00 25.00 0.23 3.50 40.25
SS m3 2.00 15.00 0.23 3.50 24.15
LS m3 2.00 25.00 0.23 4.00 46.00
SS m3 2.00 15.00 0.23 4.00 27.60
PW m3 2.00 15.00 0.23 7.50 51.75
PW m3 2.00 10.00 0.23 7.50 34.50

224.25 18582.15
Door & Windows for two floor
D1 m2 3.00 1.50 2.40 1.00 10.80
D2 m2 1.00 1.20 2.40 1.00 2.88
D3 m2 4.00 1.20 2.40 1.00 11.52
D4 m2 2.00 1.00 2.40 1.00 4.80
D5 m2 2.00 0.90 2.40 1.00 4.32
D6 m2 3.00 0.75 2.10 1.00 4.73
D7 m2 1.00 1.00 2.00 1.00 2.00
ED m2 3.00 2.00 2.40 1.00 14.40
W1 m2 17.00 2.00 2.40 1.00 81.60
W2 m2 0.00 1.20 2.40 1.00 0.00
V m2 1.00 2.40 1.45 1.00 3.48
G1 3.00 4.71 3.50 1.00 49.46
G2 3.00 2.00 2.40 1.00 14.40
G3 1.00 2.00 2.40 1.00 4.80
209.18 10000.00

Plastering Work for two face


LS m2 2.00 25.00 2.00 3.50 350.00
SS m2 2.00 15.00 2.00 3.50 210.00
LS m2 2.00 25.00 2.00 4.00 400.00
SS m2 2.00 15.00 2.00 4.00 240.00
PW m2 2.00 15.00 2.00 7.50 450.00
PW m2 2.00 10.00 2.00 7.50 300.00
1950.00

Deduction for Door & Windows for two floor


D1 m2 3.00 1.50 2.40 1.00 10.80
D2 m2 1.00 1.20 2.40 1.00 2.88
D3 m2 4.00 1.20 2.40 1.00 11.52
D4 m2 2.00 1.00 2.40 1.00 4.80
D5 m2 2.00 0.90 2.40 1.00 4.32
D6 m2 3.00 0.75 2.10 1.00 4.73
D7 m2 1.00 1.00 2.00 1.00 2.00
ED m2 3.00 2.00 2.40 1.00 14.40
W1 m2 17.00 2.00 2.40 1.00 81.60
W2 m2 0.00 1.20 2.40 1.00 0.00
V m2 1.00 2.40 1.45 1.00 3.48
G1 3.00 4.71 3.50 1.00 49.46
G2 3.00 2.00 2.40 1.00 14.40
G3 1.00 2.00 2.40 1.00 4.80
209.18
Plastering Quantity 1,740.82 550.00
False ceiling Quantity 750.00 1,200.00
Painting Quantity 2,490.82 350.00
Tile Quantity 750.00 4,500.00
Sanitary & Electrical Works LS
Total
Amount Remarks

GF
GF
FF
FF

4,167,047.14

2,091,800.00

GF
GF
FF
FF
12,363,085.14
957,451.00
900,000.00
871,787.00
3,375,000.00
1,854,462.77 15% of total works
14,217,547.91 37,913.46 per sqm two storey
18,956.73 per sqm
21,800.24
22,000.00 per sqm
mas exca filling geotextile wipehole soling
quantity 7.5 12 4.5 1 4.75 0.54
amount 67500 6000 2250 100 2850 810 79510
10601.333
S.No. Description Unit No. Length(m) Breadth(m) Height(m) Quantity
1 50mm thick puff sandwiched panels sqm.
a) roof 1 42.50 16.00 680.00
b) wall 1 109.00 7.50 817.50

2 0.23m thick brick masonry sqm.


a) wall 1 109.00 0.20 5.35 116.63

3 Plastering works sqm.


a) wall 2 109.00 5.35 1166.30
4 Color works sqm.
a) wall 2 109.00 12.85 2801.30
Remarks S.No. Description Unit Rate Quantity
1 50mm thick puff sandwiched panels sqm. 5382 1497.50
2 0.23m thick brick masonry cum 18000 116.63
3 Plastering works sqm. 550 1166.30
4 Color works sqm. 350.00 2801.30
Total
Rate per sqm.
Amount
8,059,545.00
2,099,340.00
641,465.00
980,455.00
11,780,805.00 per sqm.(assuming 40.5m*14m)
20,777.43
20,777.43
21,000.00 per sqm
S.No. Description Unit No. Length(m) Breadth(m) Height(m) Quantity
1 50mm thick puff sandwiched panels sqm.
a) roof 1 42.50 14.50 616.25
b) wall 1 106.00 5.75 609.50

2 0.23m thick brick masonry sqm.


a) wall 1 106.00 0.23 5.35 130.43

3 Plastering works sqm.


a) wall 2 106.00 5.35 1134.20
4 Color works sqm.
a) wall 2 106.00 11.10 2353.20
Remarks S.No. Description Unit Rate Quantity
1 50mm thick puff sandwiched panels sqm. 5382 1225.75
2 0.23m thick brick masonry sqm. 18000 130.43
3 Plastering works sqm. 550 1134.20
4 Color works sqm. 350 2353.20
Total
Rate per sqm.
Amount
6,596,986.50
2,347,794.00
623,810.00
823,620.00
10,392,210.50 per sqm.(assuming 40.5m*12.5m)
20,527.82
20,527.82
20,000.00 per sqm
Pradhan Builders Pvt. Ltd
Baneshwor, Kathmandu
Plaster and color analysis sheet

SN Description Unit No. Length Side Height Quantity Rate Amount


1.00 Building Type B
Plastering work
LS m2 2.00 25.00 2.00 3.50 350.00
SS m2 2.00 10.00 2.00 3.50 140.00
LS m2 2.00 25.00 2.00 3.00 300.00
SS m2 2.00 10.00 2.00 3.00 120.00
PW m2 2.00 10.00 2.00 6.50 260.00
PW m2 2.00 10.00 2.00 6.50 260.00
PW m2 1.00 25.00 2.00 6.50 325.00
ceiling m2 2.00 25.00 10.00 500.00
2,255.00
Deduction
Door & Windows for two floor
D1 m2 6.00 1.00 2.10 2.00 25.20
D2 m2 2.00 0.90 2.10 1.00 3.78
D3 m2 12.00 0.80 2.10 2.00 40.32
MD m2 1.00 2.00 2.50 1.00 5.00
W1 m2 6.00 1.50 1.35 2.00 24.30
W2 m2 2.00 0.50 0.50 2.00 1.00
V m2 2.00 2.00 1.35 2.00 10.80
110.40
Plastering Quantity 2,144.60 550.00 1,179,530.00
Painting Quantity 2,144.60 320.00 686,272.00
Tile Work m2 2.00 25.00 10.00 500.00 4,500.00 2,250,000.00
Sanitation & Electrification works 2,292,888.00
Total 6,408,690.00

2.00 Building Type C


Plastering work
LS m2 2.00 25.00 2.00 3.50 350.00
SS m2 2.00 12.00 2.00 3.50 168.00
LS m2 2.00 25.00 2.00 3.00 300.00
SS m2 2.00 12.00 2.00 3.00 144.00
PW m2 2.00 12.00 2.00 6.50 312.00
PW m2 2.00 12.00 2.00 6.50 312.00
PW m2 1.00 25.00 2.00 6.50 325.00
ceiling m2 2.00 25.00 12.00 600.00
2,511.00
Deduction
Door & Windows for two floor
D1 m2 6.00 1.00 2.10 2.00 25.20
D2 m2 2.00 0.90 2.10 2.00 7.56
D3 m2 10.00 0.80 2.10 2.00 33.60
MD m2 1.00 2.00 2.50 1.00 5.00
W1 m2 6.00 1.50 1.20 2.00 21.60
W2 m2 2.00 1.00 1.20 2.00 4.80
V m2 4.00 0.50 0.50 2.00 2.00
G m2 1.00 2.00 1.20 1.00 2.40
102.16
Plastering Quantity 2,408.84 550.00 1,324,862.00
Painting Quantity 2,408.84 320.00 770,828.80
Tile Work m2 2.00 25.00 12.00 600.00 4,500.00 2,700,000.00
Sanitation & Electrification works 2,525,410.20
Total 7,321,101.00

3 Building Type D
Plastering work
LS m2 2.00 15.00 2.00 4.00 240.00
SS m2 2.00 14.00 2.00 4.00 224.00
PW m2 2.00 14.00 2.00 4.00 224.00
PW m2 1.00 14.00 2.00 4.00 112.00
PW m2 2.00 15.00 2.00 4.00 240.00
ceiling m2 2.00 15.00 14.00 420.00
1460.00
Deduction
Door & Windows for single floor
D1 m2 3.00 1.00 2.10 1.00 6.30
D2 m2 1.00 0.90 2.10 1.00 1.89
D3 m2 7.00 0.80 2.10 1.00 11.76
D4 m2 2.00 1.00 2.10 1.00 4.20
MD m2 1.00 1.60 2.10 1.00 3.36
W1 m2 8.00 1.50 1.20 1.00 14.40
W2 m2 1.00 1.00 1.20 1.00 1.20
V m2 3.00 0.50 0.50 1.00 0.75
43.86
Plastering Quantity 1416.14 550.00 778877.00
Painting Quantity 1,416.14 320.00 453,164.80
Tile Work m2 2.00 15.00 14.00 420.00 4,500.00 1,890,000.00
Sanitation & Electrification works 1,461,760.45
Total 4,583,802.25

4 Transit Camp TC
Plastering work
LS m2 2.00 15.00 2.00 4.50 270.00
SS m2 2.00 14.00 2.00 4.50 252.00
LS m2 2.00 15.00 2.00 4.00 240.00
SS m2 2.00 14.00 2.00 4.00 224.00
PW m2 2.00 14.00 2.00 8.50 476.00
PW m2 2.00 15.00 2.00 8.50 510.00
ceiling m2 2.00 15.00 14.00 420.00
2392.00
Deduction
Door & Windows for two floor
D1 m2 3.00 1.00 2.10 2.00 12.60
D2 m2 1.00 0.90 2.10 2.00 3.78
D3 m2 6.00 0.80 2.10 2.00 20.16
MD m2 1.00 1.60 2.10 1.00 3.36
W1 m2 8.00 1.50 1.20 2.00 28.80
W2 m2 1.00 1.00 1.20 2.00 2.40
V m2 4.00 0.50 0.50 2.00 2.00
73.10
Plastering Quantity 2318.90 550.00 1275395.00
Painting Quantity 2,318.90 320.00 742,048.00
Tile Work m2 2.00 15.00 14.00 420.00 4,500.00 1,890,000.00
Sanitation & Electrification works 2,303,485.75
Total 6,210,928.75

5 Parking Shed (for 10 Car)


Plaster work
LS m2 1.00 32.90 2.00 4.00 263.20
SS m2 2.00 7.00 2.00 4.00 112.00
ceiling m2 1.00 32.90 7.00 230.30
Plastering Quantity 605.50 550.00 333025.00
Painting Quantity 605.50 320.00 193,760.00
Flooring works(80mm flexi pa m2 1.00 32.90 7.00 230.30 2,000.00 460,600.00
Total 987,385.00

6 Auxiliary building
Plaster work
LS m2 2.00 12.00 4.00 192.00
SS m2 2.00 8.00 4.00 128.00
ceiling m2 1.00 12.00 8.00 96.00
416.00
Deduction
Door & Windows
D1 m2 1.00 1.60 2.10 3.36
D m2 1.00 1.00 2.10 2.10
W m2 2.00 0.90 1.20 2.16
7.62
Plastering Quantity 408.38 550.00 224609.00
Painting Quantity 408.38 320.00 130,681.60
Sanitation & Electrification works 291,872.65
Total 647,163.25
Remarks

25,634.76 per sqm two storey


12,817.38 per sqm
13,778.68
13,800.00 per sqm
24,403.67 per sqm two storey
12,201.84 per sqm
13,116.97
13,100.00 per sqm

21,827.63 per sqm single storey


23,464.70
23,500.00 per sqm
29,575.85 per sqm two storey
14,787.93 per sqm
15,897.02
15,900.00 per sqm

1,061,438.88
1,050,000.00

6,741.28 per sqm single storey


7,246.88
10,000.00 per sqm
Pradhan Builders Pvt. Ltd
Baneshwor, Kathmandu
Different Building analysis sheet

SN Description Unit No. Length Breadth Height Quantity Rate Amount


1 Building Type B
Brick work
LS m3 2.00 25.00 0.35 3.50 61.25
SS m3 2.00 10.00 0.35 3.50 24.50
LS m3 2.00 25.00 0.23 3.00 34.50
SS m3 2.00 10.00 0.23 3.00 13.80
PW m3 2.00 10.00 0.23 6.50 29.90
PW m3 2.00 10.00 0.12 6.50 14.95
PW m3 1.00 25.00 0.12 6.50 18.69
197.59 20,000.00 3,951,750.00
Door & Windows for two floor
D1 m2 6.00 1.00 2.10 2.00 25.20
D2 m2 2.00 0.90 2.10 1.00 3.78
D3 m2 12.00 0.80 2.10 2.00 40.32
MD m2 1.00 2.00 2.50 1.00 5.00
W1 m2 6.00 1.50 1.35 2.00 24.30
W2 m2 2.00 0.50 0.50 2.00 1.00
V m2 2.00 2.00 1.35 2.00 10.80
110.40 10,000.00 1,104,000.00
Total 5,055,750.00

2 Building Type C
Brick work
LS m3 2.00 25.00 0.35 3.50 61.25
SS m3 2.00 12.00 0.35 3.50 29.40
LS m3 2.00 25.00 0.23 3.00 34.50
SS m3 2.00 12.00 0.23 3.00 16.56
PW m3 2.00 12.00 0.23 6.50 35.88
PW m3 2.00 12.00 0.12 6.50 17.94
PW m3 1.00 25.00 0.12 6.50 18.69
214.22 20,000.00 4,284,350.00
Door & Windows for two floor
D1 m2 6.00 1.00 2.10 2.00 25.20
D2 m2 2.00 0.90 2.10 2.00 7.56
D3 m2 10.00 0.80 2.10 2.00 33.60
MD m2 1.00 2.00 2.50 1.00 5.00
W1 m2 6.00 1.50 1.20 2.00 21.60
W2 m2 2.00 1.00 1.20 2.00 4.80
V m2 4.00 0.50 0.50 2.00 2.00
G m2 1.00 2.00 1.20 1.00 2.40
102.16 10,000.00 1,021,600.00
Total 5,305,950.00
3 Building Type D
Brick work
LS m3 2.00 15.00 0.35 4.00 42.00
SS m3 2.00 14.00 0.35 4.00 39.20
PW m3 2.00 14.00 0.12 4.00 12.88
PW m3 1.00 14.00 0.12 4.00 6.44
PW m3 2.00 15.00 0.12 4.00 13.80
114.32 20,000.00 2,286,400.00
Door & Windows for single floor
D1 m2 3.00 1.00 2.10 1.00 6.30
D2 m2 1.00 0.90 2.10 1.00 1.89
D3 m2 7.00 0.80 2.10 1.00 11.76
D4 m2 2.00 1.00 2.10 1.00 4.20
MD m2 1.00 1.60 2.10 1.00 3.36
W1 m2 8.00 1.50 1.20 1.00 14.40
W2 m2 1.00 1.00 1.20 1.00 1.20
V m2 3.00 0.50 0.50 1.00 0.75
43.86 10,000.00 438,600.00
Total 2,725,000.00

4 Transit Camp TC
Brick work
LS m3 2.00 15.00 0.35 4.50 47.25
SS m3 2.00 14.00 0.35 4.50 44.10
LS m3 2.00 15.00 0.23 4.00 27.60
SS m3 2.00 14.00 0.23 4.00 25.76
PW m3 2.00 14.00 0.23 8.50 54.74
PW m3 2.00 15.00 0.12 8.50 29.33
228.78 20,000.00 4,575,500.00
Door & Windows for two floor
D1 m2 3.00 1.00 2.10 2.00 12.60
D2 m2 1.00 0.90 2.10 2.00 3.78
D3 m2 6.00 0.80 2.10 2.00 20.16
MD m2 1.00 1.60 2.10 1.00 3.36
W1 m2 8.00 1.50 1.20 2.00 28.80
W2 m2 1.00 1.00 1.20 2.00 2.40
V m2 4.00 0.50 0.50 2.00 2.00
73.10 10,000.00 731,000.00
Total 5,306,500.00

5 Parking Shed (for 10 Car)


Brick work
LS m3 1.00 32.90 0.23 4.00 30.27
SS m3 2.00 7.00 0.23 4.00 12.88
43.15 20,000.00 862,960.00

6 Auxiliary building
Brick work
LS m3 2.00 12.00 0.23 4.00 22.08
SS m3 2.00 8.00 0.23 4.00 14.72
36.80 20,000.00 736,000.00
Door & Windows
D1 m2 1.00 1.60 2.10 3.36
D m2 1.00 1.00 2.10 2.10
W m2 2.00 0.90 1.20 2.16
7.62 10,000.00 76,200.00
Total 812,200.00
Remarks

GF
GF
FF
FF

20,223.00 per sqm two storey


10,111.50 per sqm
10,869.86
11,000.00 per sqm

17,686.50 per sqm two storey


8,843.25 per sqm
9,506.49
9,500.00 per sqm

12,976.19 per sqm single storey


13,949.40
14,000.00 per sqm

25,269.05 per sqm two storey


12,634.52 per sqm
13,582.11
13,500.00 per sqm

927,682.00
925,000.00
8,460.42 per sqm single storey
9,094.95
9,000.00 per sqm
Pradhan Builders Pvt. Ltd
Baneshwor, Kathmandu
Septic Tank analysis sheet

SN Description Unit No. Length Breadth Height Quantity Rate


1.00 Brick work
LS m2 2.00 4.85 0.45 0.65 2.84
LS m2 2.00 4.85 0.35 0.65 2.21
LS m2 2.00 4.85 0.23 0.90 2.01
SS m2 2.00 2.50 0.45 0.65 1.46
SS m2 2.00 2.50 0.35 0.65 1.14
SS m2 2.00 2.50 0.23 0.90 1.04
10.69 20,000.00
2.00 Concrete
Baffle wall m3 1.00 1.60 0.15 1.45 0.35
Top concrete m3 1.00 2.50 4.85 0.10 1.21
Base concrete m3 1.00 2.90 6.50 0.15 2.83
Screed Concrete m3 2.00 2.45 1.60 0.13 1.02
PCC m3 1.00 2.90 6.50 0.10 1.89
7.29 20,000.00
3.00 Rebar Kg 8% of concrete volume 583.38 132.00
Total
Amount Remarks

213,738.00

145,844.00
77,005.63
436,587.63
469,331.70
470,000.00
S.No. Description Unit No. Length(m) Breadth(m) Height(m) Quantity
1 Drain(brick masonry) cum
a) 0.30m*0.60m 2 1.00 0.30 0.60 0.360

b) 0.45m*(0.60 to 0.90m) 2 1.00 0.30 0.60 0.360


2 1.00 0.45 0.30 0.270

c) 0.60m*(0.90 to 1.20m) 2 1.00 0.30 0.60 0.360


2 1.00 0.45 0.30 0.270
2 1.00 0.60 0.30 0.360

d) 0.75m*(1.20 to 1.50m) 2 1.00 0.30 0.60 0.360


2 1.00 0.45 0.30 0.270
2 1.00 0.60 0.30 0.360
2 1.00 0.75 0.30 0.450
Rate Amount Remarks

20,000.00 7,200.00
7,200.00 per rm 7,740.000 7,800.00 per rm
20,000.00 7,200.00
20,000.00 5,400.00
12,600.00 per rm 13,545.000 13,500.00 per rm
20,000.00 7,200.00
20,000.00 5,400.00
20,000.00 7,200.00
19,800.00 per rm 21,285.000 21,000.00 per rm
20,000.00 7,200.00
20,000.00 5,400.00
20,000.00 7,200.00
20,000.00 9,000.00
28,800.00 per rm 30,960.000 31,000.00 per rm
S.No. Description Unit No. Length(m) Breadth(m) Height(m) Quantity
1 Boundary Wall(brick masonry)
i) Excavation cum 19 5.30 1.50 151.121

ii) Concrete cum


a) M7.5(1:4:8) 19 1.15 1.35 0.08 2.212
b) M25(1:1:2) 19 1.00 1.20 0.30 6.840
19 0.30 0.35 1.20 2.394
19 0.30 0.35 2.50 4.988
1 45.00 0.35 0.45 7.088
c) M15(1:2:4) 1 45.00 0.40 0.08 1.350

iii) Rebar kg
a) footing 266 0.90 147.778
228 1.10 154.815
b) column 152 4.30 580.978
399 1.10 173.393
399 0.40 63.052
c) beam 6 46.80 249.600
226 1.40 124.998

iv) Formworks sqm


a) footing 19 5.00 0.08 7.125
19 4.40 0.30 25.080
b) column 19 1.30 3.70 91.390
c) beam 1 45.00 1.60 72.000

v) Stone masonry(1:6) cum 1 45.00 0.35 2.50 39.375

vi) Cement Plaster(1:6) sqm 2 45.00 2.50 225.000


Rate Amount Remarks
for 45m long
500.00 75,560.63

11,000.00 24,335.44 @2.5m c/c


19,000.00 129,960.00 footing
19,000.00 45,486.00 column below GL
19,000.00 94,762.50 column above GL
19,000.00 134,662.50 beam
14,000.00 18,900.00 capping layer(top of masonry)

132.00 19,506.67 6.50


132.00 20,435.56 5.50
132.00 76,689.07 main bar
132.00 22,887.82 stirrups
132.00 8,322.84 stirrups 21.53
132.00 32,947.20 main bar
132.00 16,499.67 stirrups 226.00

1,000.00 7,125.00
1,000.00 25,080.00
1,000.00 91,390.00
1,000.00 72,000.00

12000.00 472,500.00

500.00 112,500.00
1,501,550.89
33,367.80 for 45m long, excluding painting, barbed wire, concertina coil & structural steel
38,367.80 all complete 5000 for painting, barbed wire, concertina coil & structural steel
41,245.38
41,000.00 per rm
tructural steel
SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
1 SITE CLEARANCE
Felling of trees including cutting branches, sawing and carrying up to 15m away
from the site. For Each
1.01 1,1,ka Girth of tree 12 - 30cm Each 93.60
1.02 1,1,kha Girth of tree 31 - 60cm Each 280.80
1.03 1,1,ga Girth of tree 61 - 90cm Each 705.60
1.04 1,1,gha Girth of tree 91 - 120cm Each 0.00
1.05 1,1,ng Girth of tree 121 - 180cm Each 0.00
1.06 1,1,cha Girth of tree 181 - 240cm Each 0.00
1.07 1,1,chha Girth of tree 241 - 300cm Each 0.00
1.08 1,1,ja Girth of tree over 301cm Each 0.00
Tree root digging, lifting it and carrying up to 15m away from the site. For Each
1.09 1,2,ka Girth of tree 12 - 30cm Each 288.00
1.10 1,2,kha Girth of tree 31 - 60cm Each 381.60
1.11 1,2,ga Girth of tree 61 - 90cm Each 1814.40
1.12 1,2,gha Girth of tree 91 - 120cm Each 0.00
1.13 1,2,ng Girth of tree 121 - 180cm Each 0.00
1.14 1,2,cha Girth of tree 181 - 240cm Each 0.00
1.15 1,2,chha Girth of tree 241 - 300cm Each 0.00
1.16 1,6 Bamboo cutting,root digging,removel of bamboo from site (Dug-pit
dimension to be measured).For 1m3 cum 2016.00
1.17 1,7 Surface dressing work,cutting and filling earthwork,including levelling
ground surface(service road etc.). For 1m2 sqm 7.20
1.18 1 ,8 Excavation 15-20 cm of the top soil including disposal
out side of the construction site. For 1 m2 sqm 115.20
2 EARTHWORK
Earthwork in excavation including a lead of 10m and a lift of 1.5m in:
2.01 2,1 Soft Clay : For 1 cum cum 519.12
2.02 2,2 Hard clay mixed boulder less than 30cm size :.For 1cum cum 593.28
2.03 2 ,10 Soft Rock : For 1 cum cum 1854.00
2.04 2 ,4 Medium Rock without blasting : For 1 cum cum 2224.80
2.05 2 ,6ka Hard Rock without chiselling : For 1 cum cum 3708.00
Earthwork in filling including watering & ramming every 20cm th. Layers For 1cum :
2.06 2 ,25ka With Ordinary Soil cum 370.80
Earthwork in filling including ramming every 15cm th. Layers (without watering )For 1cum :
2.07 2 ,25kha With Ordinary Soil cum 185.40
Turfing work Including cutting, hauling for 10m and watering For 1sqm :
2.08 2 , 40 Turfing work cum 37.08
3 STONE WORK
Stone (rubble) masonry work up to 5 m ht. Of wall including collection of stones,
preparation of mortar and a lead of 10 m. For 1 cum :
3.01 6,1,ka,2 In 1:4 Cement Sand Mortar cum 11730.00
3.02 6,1ka,3 In 1:6 Cement Sand Mortar cum 10686.84

Prepared By: Total Consultancy Pvt Ltd


SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
3.03 6 ,2.1 Dry Stone Masonry cum 4400.82
3.04 6 ,2.2 Mud Mortar Stone Masonry cum 4729.03

Stone (rubble) masonry work 5 to 10 m ht. Of wall including collection of stones,


preparation of mortar and a lead of 10 m.For 1 cum :
3.05 6,1,ka,2 In 1:4 Cement Sand Mortar cum 12572.40
3.06 6,1,ka,3 In 1:6 Cement Sand Mortar cum 11529.24
3.07 6 ,2.2 Mud Mortar Stone Masonry cum 5571.43
Stone (rubble) masonry work in arch or in sloping plane including collection of stones,
preparation of mortar and a lead of 30 m. For 1cum:
3.08 6,3,2 In 1:4 Cement Sand Mortar cum 12528.00
3.09 6,3,3 In 1:6 Cement Sand Mortar cum 11484.84
3.10 6,3,4 Stone (rubble) masonry work in (1:2) lime sand mortar For 1cum: cum 11677.04
Stone (One side dressed) masonry work including collection of stones, preparation of
mortar and a lead of 30m. For 1cum:
3.11 6,3,5 In 1:6 Cement Sand Mortar cum 14537.31
Stone (Three side dressed) masonry work including collection of stones, preparation
of mortar and a lead of 30m. For 1cum:
3.12 6,3,5 In 1:6 Cement Sand Mortar cum 21723.72
Stone (Five side dressed) masonry work including collection of stones, preparation of
mortar and a lead of 30m. For 1cum:
3.13 6,3,5 In 1:6 Cement Sand Mortar cum 31758.36
4 BRICK WORK
Brick work including collection of brick, preparation of mortar and transportation of
materials upto 30 m lead. For 1 cum :
Machine made brick ( size 224*108*57 mm) in :
4.01 5,1,ka,2 Cement mortar 1:4 cum 18582.15
4.02 5,1,ka,4 Cement mortar 1:6 cum 18047.71
Chimney made brick( size 224*108*57 mm) in:
4.03 5,1,kha,2 Cement mortar 1:4 cum 17112.04
4.04 5,1,kha,3 Cement mortar 1:6 cum 16547.61
4.05 5,1,kha,6 Mud mortar cum 13469.01
Extra work for scaffolding for 1cum
4.06 5,2,ka For ground floor cum 148.32
4.07 5,2,kha For above one floor cum 519.12
5 CEMENT CONCRETE WORK
Cement Ccncrete work in foundation,wall includingcollection of materials and a lead
of 30 m. For 1 cum
5.01 7 ,2 Ga With P.C.C ( 1:3:6 ) cum 12558.33
5.02 7 ,2 Gha With P.C.C. ( 1:2:4 ) cum 14444.76
5.03 With P.C.C. ( 1:1.5:3 ) cum 16079.88

Prepared By: Total Consultancy Pvt Ltd


SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
Cement Concrete work in supper structure, deck slab,beams including collection of
materials and a lead of 30 m. For 1 cum
5.04 7,4,ka With P.C.C. ( 1:2:4 ) cum 16400.76
5.05 7,4,kha With P.C.C. ( 1:1.5:3 ) cum 18035.88
5.06 7,4,ga With P.C.C. ( 1:1:2 ) cum 22376.82
6 IRON WORK
6.01 7 ,5 Reinforcement bar cutting, binding, placing in position according to drawing & binding
for RCCwork including a lead of 30m. For 1kg. kg 125.17
6.02 M/S angle including making hole, cutting in required
length and shape. Per 1 kg kg 149.47
7 FORM WORK
7.01 8 ,2 Ka Preparation of formwork including selection,collection of materials cutting, nailing, fixing in
position, removel & disposal etc. as per drawing and a lead of 30 m.
For floor & slab. For 1 SQM : Sqm 776.94
7,02 Formwork for Ferrocement :For 1 SQM Sqm 369.39
Formwork for Column including nailing, fixing in position,removing and a lead of
30 m. For 1sqm :
7.03 8,3,ka Perimeter of column 0 - 2 m Sqm 1203.54
Form work for structural beam including selection, fixing,nailing,oiling,removel and
disposal with a lead of 30 m.For 1sqm :
7.04 8,4,ka Height of beam upto 0.30 m Sqm 1256.46
8 FLOORING
8.01 Preparation of Concrete-floor in 1:2:4, complete with cement punning. For 1.0 Sqm
11, ka a. 25 mm (1") Thick Sqm 512.51
11, kha b. 38 mm (1 / 2") Thick
1
Sqm 704.05
11, ga c. 50 mm (2") Thick Sqm 868.30
11, gha d. 75 mm (3") Thick Sqm 1190.60
8.02 11 ,20 3 mm th.cement Punning in For 1 SQM Sqm 284.73
8.03 11 ,16 Stone Soling with sand For 1cum cum 7610.42
8.04 11 ,16 Dry stone soling For 1 cum cum 5480.82
8.05 11,15,ka Brick soling with sand - On Flat For 1sqm Sqm 1043.74
8.06 Brick soling without sand - On Flat For 1sqm Sqm 953.76
8.07 11,15,kha Brick soling with sand - On Edge For 1 sqm Sqm 2032.46
8.08 Brick soling without sand - On Edge For 1 sqm Sqm 1819.50
8.09 11,8,ka Paving of 50 mm thick flagstone in (1:4) C/M : For 1sqm Sqm 1953.01
8.10 11, 9 Paving of 37.5 mm thick flagstone in (1:4) C/M : For 1sqm Sqm 1826.61
8.11 11, 10 Paving of 25 mm thick flagstone in (1:4) C/M : For 1sqm sqm 1704.23
8.12 11, 12 Paving brick, flat on cement sand mortar, complete with
1:2 cement sand pointing. For 1.0 Sqm Sqm 1545.08
8.13 11, 13 Paving brick, on - edge on 1:6 C / M, complete with
1:2 cement sand pointing. For 1.0 Sqm Sqm 2106.43
8.14 11, 21 Planking work of 25mm th. Local salwood planks on 600*600mm
frame of 50mm*75mm Local salwood. For 1.0 sqm Sqm 6982.30

Prepared By: Total Consultancy Pvt Ltd


SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
8.15 11, 21 Planking work of 25mm th. Local soft wood planks on 600*600mm
frame of 50mm*75mm Local salwood. For 1.0 sqm Sqm 2577.47

8.16 11,3 Laying of 25mm th. Mosaic flooring, 20mm th. C/ P in 1:2 and on th top of that 6mm th. White cement
and marble ( in 1:1) coat, complete with polishing. For 1.00 sqm Sqm 3753.47
8.17 11, 5 Paving 25mm th. Oiled terrazo tiles on 1:2 Surkhi mortar complete
with 1:1 cement sand pointing. For 1.0 Sqm Sqm 2111.37
8.18 11, 7 Laying of procelain glaxed tiles on 1:4 cement sand
mortar. For 1.0 sqm sqm 2902.79
8.19 11, 6 Laying of 25mm th. 450*450mm Marble on 20mmth. 1:4 surkhi mortar,
complete with polishing. For 1.00 sqm Sqm 4990.44
Filling work including watering and compaction.For 1cum:
8.20 11,19,ka With sand cum 3962.38
8.21 11,19,kha With 15 -150 mm broken bricks cum 3381.70
9 CEMENT PLASTERING
12.5 mm thick Cement Sand plaster For 1 sqm
9.01 12 , 1 ka In 1:2 cement sand mortar Sqm 461.52
9.02 12 ,1 Kha In 1:3 cement sand morter Sqm 406.08
9.03 12 ,1 Ga In 1:4 cement sand mortar Sqm 393.37
9.04 12,1,gha In 1:6 cement sand mortar Sqm 364.20
20 mm thick cement sand plaster For 1 sqm
9.05 12 ,4 ka In 1:3 cement sand morter Sqm 537.90
9.06 12 ,4 Kha In 1:4 cement sand mortar Sqm 514.18
9.07 12,4,ga In 1:6 cement sand mortar Sqm 468.73
9.08 12,5 25mm th. Mud plaster.For 1 sqm: Sqm 405.22
9.09 12, 6 12.5mm th. Mud plaster.For 1 sqm: Sqm 312.26
9.10 Flush pointing work on bricks masonry wall.
14,1, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 265.87
14,1, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 245.91
14,1, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 235.36
9.11 Flush ruled pointing work on bricks masonry wall.
14,1, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 309.07
14,1, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 289.11
14,1, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 278.56
9.12 Flush ruled pointing work on boulder stone masonry wall.
14,2, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 343.08
14,2, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 304.82
14,2, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 285.39
9.13 14,3 Flush ruled pointing work with 1:3 c/ m on ashler
stone masonry wall. For 1.0 sqm Sqm 182.50
10 PAINTING WORK
10.01 13 ,11 Three coats chapra resin polishing.For 1sqm Sqm 177.80

Prepared By: Total Consultancy Pvt Ltd


SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
10.02 Distempering painting
13,3, ka a. Lining. For 1 sqm Sqm 54.83
13,3, kha b. First one coat. For 1 sqm Sqm 52.18 For rate to
estimate
13,3, ga c. 2nd coat and additional coats. For 1 sqm Sqm 44.69 add a, b & c
10.03 13,6 Applying 1 coat lining and 2 coats of aluminum
paint. For 1.00sqm Sqm 289.32
10.04 13,5ka-ga 1Coat primer & 2 Coat enamel paint. For 1sqm Sqm 311.95
10.05 13,5ka-ga
1Coat primer & 2 Coat weather coat(exterior)emulsion paint. For 1sqm sqm 322.94
10.06 1 Coat primer & 2 Coat emulsion paint.(Interior) For 1sqm sqm 303.05
11 7 line hori. and 2 line diago. barbed wire fencing on m/s angle
(50*50*6mm),at a spacing 2m c/c.For 1m Rm 466.64
12 ROOFING WORK
White CGI sheet roofing including collection of materials.
12.01 9 ,1 For 1 SQM (CGI sheet 24 SWG): Sqm 1058.56
12.02 9 ,1 For 1 SQM (CGI sheet 26 SWG): Sqm 871.90
12.03 9 ,1 For 1 SQM (CGI sheet 28 SWG): Sqm 747.40
Color CGI sheet roofing including collection of materials.
12.04 9 ,1 For 1 SQM (CGI sheet 24 SWG): sqm 1091.38
12.05 9 ,1 For 1 SQM (CGI sheet 26 SWG): sqm 921.71
12.06 9 ,1 For 1 SQM (CGI sheet 28 SWG): sqm 793.33
12.07 9 ,2 White GI Plain sheet ridge fixing 24 SWG. For 1 M m 852.47
12.08 9 ,2 White GI Plain sheet ridge fixing 26 SWG. For 1 M m 762.33
12.09 9 ,2 White GI Plain sheet ridge fixing 28 SWG. For 1 M m 702.40
12.10 9 ,2 Color GI Plain sheet ridge fixing 24 SWG. For 1 M m 913.64
12.11 9 ,2 Color GI Plain sheet ridge fixing 26 SWG. For 1 M m 815.15
12.12 9 ,2 Color GI Plain sheet ridge fixing 28 SWG. For 1 M m 737.15
12.13 9,5 Slate roofing . For 1Sqm Sqm 2512.19
12.14 9,9,kha Thatch roofing.For 1sqm: Sqm 4677.09
12.15 9,6 Clay tiles (Chimney made) roofing. For 1sqm : Sqm 514.00
12.16 9,7 Clay tile as ridge (Chimney made) plate fixing. For 1m: m 430.44
13 WOOD WORK
13.01 10 ,1 a.Local salwood work for frames including fixing.For 1 cum cum 202362.65
10 ,1 b.Local soft wood work for frames.For 1 cum cum 87272.30
13.02 10 ,2 38mm th. wood frame for panelled door shutter. For 1 no
(shutter size -1.07*1.982 = 2.12sqm)
a.With Local salwood Sqm 11538.15
10,2 b.With Local softwood Sqm 7392.53
13.03 10 ,3 38*75mm size wood frame using 3mm plain glass for glazed shutter. For 1no.(shutter
size - 1.892*1.22 = 2.23sqm)
a.With Local salwood Sqm 8221.99
10 ,3 b.With Local softwood Sqm 5923.00
13.04 10 ,3 38*75mm size wood frame using 4mm plain glass for glazed shutter. For 1no.(shutter

Prepared By: Total Consultancy Pvt Ltd


SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
size - 1.892*1.22 = 2.23sqm)
a.With Local salwood Sqm 8320.47
10 ,3 b.With Local softwood Sqm 6021.48
13.05 10 ,9 38mm wood frame using 26 SWG Plain GI sheet on both side. For 1 no.(shutter size -
1.092*2.058 = 2.247sqm)
a.With Local salwood sqm 6792.27
10,9 b.With Local softwood sqm 5181.18
13.06 10 ,10 38mm wood frame using 24 SWG GI wire mesh mosquito proof shutter .For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 4568.82
10 ,10 b.With Local softwood Sqm 3358.17
13.07 10,7 38mm wood frame using 3mm plywood both side for flush shutter. For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 6642.38
b.With Local softwood Sqm 5031.29
13.08 38mm wood frame using 3mm plywood one side for flush shutter .For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 5642.14
b.With Local softwood Sqm 4031.05
13.09 10,7 38mm wood frame using 6mm plywood both side for flush shutter. For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 7406.87
b.With Local softwood Sqm 5795.78
13.10 38mm wood frame using 6mm plywood one side for flush shutter .For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 6024.38
b.With Local softwood Sqm 4413.29
13.11 Fixing glass of different thichness in window frame including fixing of wooden listis.
For 1sqm with :
10,11,ka a.3 mm thick glass Sqm 797.96
b 4 mm thick glass Sqm 1000.37
13.12 10 ,17 Wood work for beam and joist including fixing .For 1cum
a.With Local salwood cum 175217.76
b.With Local softwood cum 65358.79
13.13 10,18 a.Local salwood work for truss fixing.For 1M3 cum 201669.51
b.Local soft wood work for truss fixing.For 1M3 cum 91810.54
13.14 10 ,19 a.Local salwood work for 25mm th. Eaves board including fitting.
For 1SQM Sqm 4297.76
10 ,19 b.Local hardwood work for 25mm th. Eaves board including fitting.
For 1SQM Sqm 1420.50
13.15 10,14,ka 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 3mm
plywood both side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 2859.99

Prepared By: Total Consultancy Pvt Ltd


SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
b. With Local soft wood Sqm 1831.06
13.16 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 3mm
plywood one side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 2391.82
b. With Local softwood Sqm 1362.89
13.17 10,14,ka 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 6mm
plywood both side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 3638.48
b. With Local soft wood Sqm 2609.55
13.18 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 6mm
plywood one side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 2781.06
b. With Local softwood Sqm 1752.13
13.19 10,16,ka 0.60*0.90m size wooden frame (wood size50*75mm)using 3mm plywood for different
type false ceilings( ceilings size=9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 2936.15
b. With Local soft wood Sqm 1613.24
13.20 10,16,ka 0.60*0.90m size wooden frame (wood size50*75mm)using 6mm plywood for different
type false ceilings( ceilings size=9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 3325.39
b. With Local soft wood Sqm 2002.48
14 DEMOLIITIONS AND REPAIR WORK
14.01 19-1 Demolishing mud mortar masonry and disposing the
materials to a distance of 10m. For 1cum: cum 763.20
14.02 19-2 Demolishing cement or lime surkhi mortar masonry and disposing
the materials to a distance of 10m.For 1cum : cum 1526.40
14.03 19 - 3 Demolishing RCC or RBC work and disposing
materials to a distance of 10m. For 1cum : cum 7920.00
14.04 19 - 4 Demolishing PCC or lime surkhi concrete and disposing
the materials to a distance of 10m.For 1cum : cum 2880.00
14.05 19 - 5 Demolishing cement or lime surkhi plaster and disposing
the materials to a distance of 10m.For 1cum : cum 77.76
14.06 19 -6 Demolishing tiled roof and stacking the tiles, wood etc.
properly at a distance of 10m. For 1cum : cum 113.40
END

Prepared By: Total Consultancy Pvt Ltd

You might also like