Professional Documents
Culture Documents
1
Out Side Plant (OSP)
2
Out Side Plant (OSP)
Man Holes
Station - Station -
A B
3
Items Used
4
HDPE Duct
5
HDPE Duct Accessories
• Push-fit Couplers: Used to couple two duct. They are simple, easy
to install and provide air/water tight joint between two ducts
• End Plug: Used for sealing of ends of the empty duct prior to
installation of OF cable to prevent entry of dirt, water, moisture etc.
6
HDPE Duct Accessories/Cutting tools
• Cable Sealing Plug / Simplex Plug: Used to seal the end of the duct
perfectly, after cable is installed. It is required, where cable has come
out of duct either by joint or entry into the building as required
• End Cap: Made of hard rubber/suitable plastic material, fitted onto both
end of duct coil after manufacturing the duct
• Duct Cutter: To cut duct ends squarely without any burr or notch
7
Machines/Tools
• Trenching Tools
• Decoiler
• DIT equipments
• Blowing Machines
• Splicing Machines
• Testing tools- OTDR, PMLS
• Cable locator
8
ITP
Requisition/
Issue of Obtaining
Execution material (Duct, Approval for RoW
Complete/Billing coupler, end issue of
plug, OFC) permission
material
Submission of
Retention Bill HOTO documents To
payment/Con Certificate whomsoever
tract Closure concern
9/23/2013
RoW process
Obtaining RoW
permission & Submission of
submission to CPDH payment to authority Approval & payment
(Photocopy of the & receipt submission release
same to vendor for to CPDH for record
execution)
BG/SD clearance
Execution of work from Authority &
Work finish
after intimation to all submission to CPDH
information to all the
the utility owner & for approval to
authorities & get NOC
local authority release retention
payment
11
Installation Process
12
End-
End-to-
to-End Installation
13
End-
End-to-
to-End Installation
Installation of
– Chamber
– Route Markers
– Earthing
Optical work
– DIT & Cable blowing
– Fibre splicing
– Fibre termination /tapping
ITP Preparation after each activity completion,
As Built Drawing using IFC drawing
14
Trenching
• The process of continuous digging following a single line in a specific
condition called trenching.
• The depth of the trench may vary as per soil strata &
specification.
Soil
15
Trenching Methods
Methods
Excavator Trencher
16
Prerequisite for Trenching
• Ensure safety .
• Trench should be in ROW Limits.
• Make cross pits for finding underground utilities to ensure
no damage manually.
• If damaged then inform and attend them to restore the
damages.
• A day plan trenching to be carried out
• Mark the trench line for straight trenching with lime
powder.
• Trench bed should be plain to avoid Kinks & Bends etc.
• No sharp turns and undulations to maintain the bending
radius.
• CDR to be raised if specs not met.
• Avoid electric/utility poles/trees in line of trench
18
Making of Cross Pit at every
200 mtr( or as needed)
450 mm
650 mm
Warning Tape
1650 mm
Depth
300 mm
21
Rocky Area
450 mm
1250 mm
Depth
Warning Tape
200 mm
300 mm 50mm
Bedding
22
Duct Sequence
27
Open Trenches & Ducting
Vertical GOOD Horizontal GOOD
Undulations TRENCH Undulations TRENCH
31
Traffic Jam due to bad planning
Prerequisite for Ducting
34
Prerequisite for Ducting
35
Damaged Bundle of Duct
36
Damaged Bundle of Duct
37
Damaged Bundle of Duct
38
Proper way of Ducting
Use of Decoiler
Use of Decoiler
Duct Cutter
39
Coupler Fitting
40
The Correct Method of Coupler Fitting
● Use ONLY a Duct Cutter to cut the Ducts. Do not use hacksaw /
Knife.
• Duct should be cut with about 20-30 mm overlap with duct cutter at 90
degree. Mark the “Cut Mark” using a Measuring Tape and a Marker.
• Coupler should not be rotated while fitting otherwise its teeth will get
damaged and it will not have proper grip to stand firm against pressure during
DIT /blowing.
• Rotating the coupler also damages the “O-Ring” and therefore air leakage
can happen also do not use hammer on Coupler while installing
O-
Ring
Teeth
Ring
Teeth
Ring
Reliance Industries Limited 42
The Correct Method of Coupler Fitting.......
• The Chamfering tool must be used to sharpen the face of duct so
that the duct is inserted into the push fit coupler easily without
damaging the rubber (O-Ring) in side coupler.
Chamfering To Marker
ol
Reliance Industries Limited 43
Purpose of using the Chamfering Tool
Chamfering tool
reduces the outer dia
of the duct to less
than inner dia of the
rubber “O-Ring”
As the duct is
The duct now pushed
enters the further, the O-
Rubber O-Ring Ring slips over
without any the
effort, and unchamfered
without any portion of the
damage to the Duct, and
O-Ring provides leak-
proof seal.
Reliance Industries Limited 44
The Correct Method of Coupler Fitting.......
• Clean both the duct-ends with water and waste cloth. There should be no
dirt on the two duct-ends. Then cut the duct by duct cutter with about 20-30
mm overlap.
• Mark both duct-ends with 60mm “Insertion Mark”, with a permanent marker
pen after Chamfering the duct-ends.
• Apply “a drop of a Shampoo”, as a soap-based lubricant, on the inner side
of O-Ring inside the coupler, without opening the coupler.
60
60
mm
mm
• First insert one duct-end into the coupler. With a gentle push, the duct-end
should slip inside the rubber O-Ring, with a “tik” sound and come to the
centre of the coupler. This will be visible from other side of the coupler.
Confirm that “Insert Mark” line is just outside the coupler.
60
mm
60
mm
• Next, push the other Duct-end into the coupler and use the pressure of
the duct itself to push the duct into the coupler. The duct-end should slip
inside the rubber O-Ring, with a “tik” sound and come to the centre of
the coupler. This can ONLY be confirmed by the “Insert Mark” line if it is
just outside the coupler.
● In the same pit, separate the Push-fit couplers preferably with 200 mm
of gap in between any two.
● All coupler locations shall be covered with red stone (25 mm thick X
300 wide X 1000 mm length) after 200 mm sieved soil.
Reasons of Leakage:
Use of incorrect tools, specially “Hacksaw Blade”. An unclean cut
damages the O-Ring.
Duct cut exactly at 90 degree (Square-Cut) can damage the O-Ring.
Not Chamfering and using heavy force to push the duct can damage the
O-Ring.
Penetration of dust while coupler fitting/handling. The duct should be
properly cleaned before starting the coupling process.
Don’t install the couplers in ducts which are being pulled in HDD if cut
short.
The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the file again. If the red x still appears, y ou may hav e to delete the image and then insert it again.
Don’t practice the pulling of duct directly from roll or without D-Coiling.
If required to open the installed coupler, then it should ONLY be opened
with the proper C-Spanner else it will get damaged.
Reliance Industries Limited 48
Continued….
● Gap in ducts- due to this the duct-ends will not cross the “O” Ring and
(b) Shrinkage- Avoid the coupling immediately just after pulling the duct by HDD,
(c) Do not use the “Chinese Figure” applied portion in the duct coupling.
Coupler shall not be installed along the bent portion of duct/trench in both
sharp enough for grip and same way while closing precaution to be
52
Proper way of ducting
53
Decoiler Not Used
56
Kink in the duct
57
Couplers Missing
58
Gap is too big to fit the couplers
59
Slope Gradient Not Maintained during laying
60
Prerequisite for Back Filling
• Ensure coupling.
• Back filling should be done just after verifying the ducting and
use fine sieved soil for 200 mm and then backfill fully with
500mm layer dry compaction.
• Do not let the trench remain opened for a long period, that
cause traffic jams and life risk either human or animals.
61
Prerequisite for Back Filling
62
Back Filling
63
Warning Tape
In Normal Soil -
650 mm below
from NGL (Inter-
city)
500mm (Intra-
City)
65
Route Markers
67
Route Markers
• Shall be erected straight, facing the road side and placed
0.5 m from the trench and away from the road centre.
68
Route Marker
69
Route Marker
71
Manual Boring “Moling”
72
Horizontal Direction Drilling
73
HDD Installation
74
77
HDD
Reliance Industries
Confidential
Limited
Guidelines for Railway Crossing
83
Installation at utility crossings
84
Highway Road Crossing
85
Prerequisite for Clamping
89
Typical Installation
90
Typical Installation
91
Typical Installation
92
Bridges
Bridges
Clamping on Bridges and Nodes
95
Clamping on Bridges
96
Bad Practice
97
Manhole & Handhole
101
Manhole & Handhole
104
Typical Hand Hole
Cylindrical Chamber
Conical Chamber
Checklist
108
Reliance Industries
Confidential
Limited
MH & HH
Duct Integrity Test
Purpose:
Purpose of Integrity Test is to ascertain and ensure the suitability of duct for optical
fiber cable installation through jetting.
What is DIT?
DIT is a series of tests performed on the underground duct. It is the intermediate step
between duct laying and cable jetting.
114
Pressure Testing Equipment
2 1
4
3
118
Ducting
& DIT
Blowing of OFC
• Ensure the duct Integrity test (DIT) completed.
• ITP to be filled.
122
Blowing
126
Salient Points During Cable Blowing :
127
Super Jet Machine
Speedometer
Hydraulic Hoses
128
Super Jet Machine
129
Push Mechanism in Super Jet Machine
Air Compressor
(12 Bar, 400 CFM) Power Pack
Pumps Hydraulic
Oil into the Motor
Cable
Air Pressure
Drum
Chambers
Hydraulic
Motor Caterpillars
Jack
130
Proper cable blowing
Making Figure 8
Fiber Blowing
136
Fiber optic cable fusion splicing
137
Fiber optic cable splicing process - fusion splicing
Fiber optic cable splicing process - fusion splicing
Splice Machine - Dos
143
Splice Machine – Don’ts
• Do not clean or touch the bare fiber after it has been cleaved, and
do not let it come in contact with any surfaces.
• Never touch the electrodes when the fusion splicer is powered on.
Doing so may cause electrical shock.
144
Termination
• All fibers will be terminated on fiber distribution panel(FDP) at
aggregation nodes(AG1, AG2,AG3 and so on) or masts or
eNodeB, ILA with ROADMs(Reconfigurable optical add drop mux.)
145
Termination
• End to end testing can be carried out from the FDP to FDP
• OFC entry into FDP shall be done through holes provided for this
purpose as per instruction of FDP supplier.
146
Schematic of Earthing
Earthing (Typical)
151
Link Budgeting
• Power loss in link dB/Km for 1550 nm, the average power loss of the
link = No. of connector X 0.5+No of splices X 0.1+distance in Km X
IOR of the cable=losses in dB/Km
• Power loss in link dB/Km for 1310nm the average power loss of the
link = No of connector * 0.5+No of splices * 0.1+distance in Km X
IOR of the cable =losses in dB/Km.
Note: The above 0.22 dB/km for 1550nm and 0.35 dB/km for 1310nm depends
on cable specs. It may vary.
153