PROJECT:

150MIGD IWP SWRO DESALINATION PLANT

UMM AL QUWAIN
Contractor: Owner:

Request for Inspection and Testing


Request for Inspection UAQ-C2-W0-CGG-0000-MQ-WZZ-018-4.1
Discipline Mechanical
(RFI) No.: (PS)- WFZ(STREAM-02)-001
From: CGGC To: NAQAA

Date of Request: 09-06-2021 Date of Inspection: 10-06-2021

Time of Request: 02:00 PM Time of Inspection: 10:00 AM

Inspection for feed Penstock (W2WFX01-AB401 W2WFX02-AB401, W2WFX03-AB401,


Inspection Request For: W2WFX04-AB401) & Backwsah Penstock (W2WFX01-AB402, W2WFX02-AB402,
W2WFX03-AB402, W2WFX04-AB402)
Plot 1; WFZ – DMGF- TANK 01,02,03,04
Inspection Location:
(SUB SYSTEM: W2WFX01,W2WFX02,W2WF X03,W2WFX04)
Description of Inspection Check fixing of template on wall opening, marking of anchor holes for g ate frame and shaft
Item: guide support anchors, Foot wall bracket Drilling of anchors and fixing of penstock gate frame
REF. DWG. Title /NO.: UAQ-C1-W0-SID-0000-MS-WFZ-102 REV.: A

ITP No.: UAQ-C2-W0-CGG-0000-MQ-WZZ-018 REV.: C

Inspection Item No. 4.1 ATTACHMENTS Drawings, Inspection Report

Previous inspection record s available YES□ NO□


Sub contractor CGCC SIDEM OWNER
Action code from the ITP
IS W2 W2 S/R

Result of Inspection and Testing

Other Remark If Any:

ISSUED BY Sub contractor Construction QA/QC SIDEM NAQAA

Signature :

Name : VINAY YADAV CHENG ABHIJITH NTS

Title : QC ENGG MECH SUPV. QA/QC ENGG QC ENGG

Date : 09-06-2021 10-06-2021 10-06-2021 10-06-2021