[Type here]

TEMPORARY CONSTRUCTION FACILITY


TCF-1
Date: 01/09 /2021
Sr. TOPICS PHOTO/ DETAILS Direct Manpower: 37
No Indirect Manpower: 34
1 TOOL BOX TALK

(a) Life Saving rule,


Electrical safety,
Excavation Safety
PPEs &
Housekeeping.

2 WORK PERMIT
Total No of Permit. 11 S Work Equipment’s/Tools Hot Work Permit Manpo Company
r. Permit wer
(a) Hot Work Permit N No.
= 09 o
(b) Cold work permit 1 1928 Boom truck & Hand tools Steel beam installation for fire station building. 07 X-smart
=02
2 1930 Generator and welding machine Gathering tent fabric tying and internal insulation 09 Al-kadi
work.
3 1931 Mani fold and Pump Fuel station gasoline and diesel 02 Advanced Elements

4 1932 Screw gun and Hand tools Telecommunication (EMT conduit) installation 03 Hexagon
work.
5 1933 JCB & Water tanker Backfilling and compaction work for 25 m light 02 Advanced Elements
pole foundation.
[Type here]

6 1934 JCB & Hand tools Excavation and cable pulling for 25 m light pole 02 Hexagon
foundation.
7 1935 JCB Excavation for (FOC) fiber optical cable line 03 Naizak
trench.
8 1936 JCB & Hand tools Excavation Pipe laying and Backfilling for 05 Hexagon
irrigation system.
9 1937 JCB & Hand tools Gate valve excavation and valve installation for 03 Hexagon
irrigation system.
COLD WORK

10 0746 Cleaning for light pole foundation Hand tools 05 Advanced Elements
bolt.
11 0747 Shuttering and DE shuttering for light Hand tools 03 Advanced Elements
pole foundation.

3 Daily Activities
Steel beam installation for fire station building. Excavation for (FOC) fiber optical cable line trench.

Gathering tent fabric tying and internal insulation work. Excavation Pipe laying and Backfilling for irrigation system.

Fuel station gasoline and diesel Gate valve excavation and valve installation for irrigation system.

Telecommunication (EMT conduit) installation work. Cleaning for light pole foundation bolt.

Backfilling and compaction work for 25 m light pole foundation. Shuttering and DE shuttering for light pole foundation.

Excavation and cable pulling for 25 m light pole foundation.

4 HEIGH RISK
ACTIVITIES
5 ACHIVEMENT ZERO INCIDENT/ ACCIDENT

6 LOOK AHEAD Hand Rail Installation for the Kitchen &Clinic, Excavation for the 15 m Gate foundation near to the helipad, Swimming Pool Tiles Installation,
ACTIVITEIS Interlock and curbstone work, Gathering Tend foundation backfilling, Backfilling and leveling for Around stp Area, Backfilling and leveling roads
and sport area, Backfilling for inside the roundabout, Sludge tank leak rectification, Excavation & layer by layer backfilling and compaction for the
street poles, Foundation preparation for the control panel water well pump, RO {LIGHTING , POWER SOCKETS & FIRE ALARM}, Grounding
connection for the AC, INSTALLATION OF STREET LIGHTING POLES {OFFICE}, INSTALLATION OF STREET LIGHT POLES IN
PLAYGROUND 25 MTR, CLOSING OF EIL COMMENTS AND OPEN RFI'S, Irrigation water tank commissioning, Spindle Surface cover
installation transmission & force main line, Kitchen commissioning(Air balancing for Duct& Exhaust fans), A/C Rectification and inspection,
Diesel Tank flushing with Diesel, Potable water supply installation for STP, Fire networking commissioning with overall network, Air valve
installation for fire network, Inspection Chamber Extension for STP, Water well existing pump remove and install the new pump.
[Type here]

7 MAJOR INCIDENT/
NEAR MISS
[Type here]

8
CONCERN & ISSUES CONSTRUCTION

9 Safety
1. Sabre Alam

10 TCF- 1 Project/ Sign:


Construction Manager