RIL, Jamnagar
Cover Page…….……………………………………………………………………….. 1
Index……………………………………………………………………………………… 2
Amendment Sheet…………………………………………………………………... 4
Abbreviations…………………………………………………………………………. 6
Introduction…………………………………………………………………………… 7
Purpose…………………………………………………………………………………. 7
Objective……………………………………………………………………………….. 7
Guidelines……………………………………………………………………………… 7
RACI Matrix…………………………………………………………………………… 9
Annxure-1………………………………………………………………………………. 11
Annxure-2……………………………………………………………………………… 12
Annxure-3……………………………………………………………………………… 13
Annxure-4……………………………………………………………………………… 15
Annxure-5……………………………………………………………………………… 16
Annxure-6……………………………………………………………………………… 17
Controlled copy of the current version of this document is held at RIL, Jamnagar and
also available on RIL Jamnagar portal. Any printed/ electronic copy of this document is
uncontrolled. It is recommended that users verify that the version being used by them is
the current version by referring to the controlled version
The plant operation and maintenance personnel play vital role for the effective control
of emergency as they are the first respondents to emergency in their plant areas. This
necessitates frequent rehearsals on simulated emergency situations in the plant to gain
more confidence and proper coordination during emergency.
Purpose
To establish guidelines for conducting table top exercise and dry-drills to improve
effectiveness of mock-drills.
Objectives
• To cover all O&M personnel for rehearsals on emergency situation as per PIPA.
• To gain more confidence amongst the employees during emergency.
• To enhance the knowledge of employees for use of emergency equipment.
Guidelines
• Each process plant shall conduct 4 table top exercises per month.
• One of the table top out of 4 will be escalated to conducting dry drill.
• The emergency scenarios may be taken from plant ER manual/ PIPA document.
• Plant ERCP subcommittee member will make annual schedule for the table top
exercise & dry drill and submit the schedule to ERCP subcommittee. (As per
Annxure-1)
• Based on annual schedule, plant ERCP subcommittee member will prepare
monthly schedule for table top exercise and dry drill and publish it to all the
O&M members of plant. (As per Annxure-2)
• Production manager & ERCP Sub Committee member of the safety district will be
the observer for dry drill.
• Plant may also request to SSM/SFM/Safety Manager for observing the dry drill.
• In table top exercise, shift crew will sit together and discuss operation activities
and prioritizing mitigation measures for a particular selected scenario. SS of the
shift will chair the discussions.
S.No. Activity R A C I
1 Preparation of annual Plant ERCP Plant HOD ERCP All O&M
schedule for table top subcommittee Subcommittee members of
exercise & dry drill member Chairman plant, ERCP
and submit to ERCP subcommittee
subcommittee.
2 Monthly Scheduling Plant ERCP Production Plant HOD All O&M
of table top exercise & subcommittee Manager members of
dry drill. member plant
3 Selection of Observer Plant ERCP Production Plant HOD All O&M
for dry drill. subcommittee Manager members of
member plant
4 Conducting table top Plant SS Production Plant ERCP All O&M
exercise Manager subcommittee members of
member plant
5 Conducting Dry drill Plant SS Production Plant ERCP All O&M
Manager subcommittee members of
member plant,
Observer
6 Table top exercise Plant SS Plant HOD Shift Crew Plant ERCP
observations to be subcommittee
communicated to member,
production manager Plant HOD
7 Dry Drill Report Plant SS Production Observer, Plant ERCP
Preparation Manager Shift crew subcommittee
member,
Plant HOD
8 Review of Report Plant ERCP Plant HOD Plant SS All O&M
subcommittee members of
Plant:
PIPA Scenarios
Month
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Plant: Month:
Table Top-1 Table Top-2 Table Top-3 Table Top-4 Dry Drill
Date
Shift
PIPA
No.
Observer for Dry Drill:
Drill No.
Date
Time of Incident
All Clear Time
Duration of Drill
Plant
Equipment Involved
Type / Text of the
Scenario
Observer
Plant Members
Sequential Actions
Sr No Sequence of Actions
1
2
3
4
5
6
7
8
9
10
11
Observations
Name: Sign:
Name: Sign:
Plant: Month:
Table Top Exercise Dry Drill
No. of No. of No. of
Scope Actual Remarks Scope Actual Recomm. Recomm. Recomm.
Generated Completed Pending