Edinburgh Tram System - Case Study
Edinburgh Tram System - Case Study
System Scenario
CASE STUDY
Date: 12.08.21
Author: Nikhil Dhand
Edinburgh Tram System Scenario PAGE 2
INSTRUCTIONS
I. Network Analysis for Tram Planning Office
II. Linked Bar Chart for Baseline Schedule
III. L2 Schedule for sign off with Client
IV. Constraints Projection and re- planning
V. Final Crashing on issues during running project
Edinburgh Tram System Scenario PAGE 3
Legend:
Postulations:
Legend:
Requirement:
The tasks ‘Install Drainage’ and ‘Install Piled Foundations’ both require the use of 2 Excavators
Constraint:
Only 2 Excavator is available, thus, ‘Install Drainage’ and ‘Install Piled Foundations’ which were
earlier parallel activities has now become "Finish to Start", linked as such, Activity 4 shall
commence only after completion of Activity 3. (Reason: Unavailability of additional 2 excavator)
Impact on Timeline:
Kindly refer attachment “Edinburgh Tram Planning Office - Revised Schedule with Constraint (IV)”
Edinburgh Tram System Scenario PAGE 5
L2 Schedule
Legend:
Technical Issues:
Crashing:
To meet original timeline, i.e. completion date of 25.02.10, normal days (Optimistic days) has been
considered for the following activity as per Appendix 2: