People of Punjab
Amount
Sub
GENERAL ABSTRACT OF COST (Rs.)
Head
in million
SUPPLY CONSTRUCTION, INSTALLATION OF WATER
1 FILTRATION PLANTS & DIRECT SUPPLY IN RAWALPINDI 306.63
DIVISION
SUPPLY CONSTRUCTION, INSTALLATION OF WATER
2 FILTRATION PLANTS & DIRECT SUPPLY IN LAHORE 370.81
DIVISION
SUPPLY CONSTRUCTION, INSTALLATION OF WATER
3 FILTRATION PLANTS & DIRECT SUPPLY IN FAISALABAD 493.84
DIVISION
SUPPLY CONSTRUCTION, INSTALLATION OF WATER
4 FILTRATION PLANTS & DIRECT SUPPLY IN DG KHAN 361.79
DIVISION
SUPPLY CONSTRUCTION, INSTALLATION OF WATER
5 FILTRATION PLANTS & DIRECT SUPPLY IN SAHIWAL 399.02
DIVISION
SUPPLY CONSTRUCTION, INSTALLATION OF WATER
6 FILTRATION PLANTS IN MULTAN DIVISION
253.73
5,966,779,114
5,966.78
SAY Million
PHYSICAL PHASING OF THE PROJECT
Sr. Description Year Wise Physical Activities
INSTALLATION OF CONVENTIONAL
13 TREATMENT PLAN IN CHAK JUMRAH 50 50
TEHSIL FAISALABAD
2019- 2021-
2020-21 2022-23
20 22
INSTALLATION OF CONVENTIONAL
13 TREATMENT PLAN IN CHAK JUMRAH - 100 39.62 -
TEHSIL FAISALABAD
4,153.9