Professional Documents
Culture Documents
TABLE OF CONTENTS.................................................................................................................................ii
LIST OF TABLE.............................................................................................................................................iii
LIST OF FIGURE...........................................................................................................................................iv
CHAPTER 1.....................................................................................................................................................1
BAB 1...............................................................................................................................................................1
PREFACE.........................................................................................................................................................1
PENDAHULUAN............................................................................................................................................1
1.1 GENERAL..............................................................................................................................................1
1.1. UMUM..................................................................................................................................................1
1.2 BACKGROUND....................................................................................................................................2
1.2 LATAR BELAKANG............................................................................................................................2
1.3 PURPOSE...............................................................................................................................................2
1.3 TUJUAN.................................................................................................................................................2
1.4 REFERENCE..........................................................................................................................................2
1.4 REFERENSI...........................................................................................................................................2
1.5 ACTIVITY DATA..................................................................................................................................3
1.5 DATA KEGIATAN................................................................................................................................3
1.6 SCOPE OF WORK.................................................................................................................................4
1.6 RUANG LINGKUP PEKERJAAN........................................................................................................4
CHAPTER 2.....................................................................................................................................................4
BAB 2...............................................................................................................................................................4
TREE CUTTING..............................................................................................................................................4
PENEBANGAN POHON.................................................................................................................................4
2.1 TREE CUTTING....................................................................................................................................4
2.1 PENEBANGAN POHON.......................................................................................................................4
2.2 Work Schedule of Tree Cutting by PT Adhi Karya (Persero) Tbk.........................................................7
2.2 Rencana pekerjaan penebangan pohon oleh PT Adhi Karya (Persero) Tbk...........................................7
CHAPTER 3.....................................................................................................................................................8
BAB 3...............................................................................................................................................................8
ADDITION OF NEW WORK ITEM TREE CUTTING................................................................................8
PENAMBAHAN ITEM PEKERJAAN BARU PEMOTONGAN POHON....................................................8
3.1 Adjustment of Payment Item...............................................................................................................8
3.1 Penyesuaian Item Pembayaran............................................................................................................8
CHAPTER 4.....................................................................................................................................................9
BAB 4...............................................................................................................................................................9
CONSLUSION.................................................................................................................................................9
KESIMPULAN.................................................................................................................................................9
ii
LIST OF TABLE
iii
LIST OF FIGURE
iv
CHAPTER 1 BAB 1
PREFACE PENDAHULUAN
1.1 GENERAL
1.1. UMUM
Emission Reduction in Cities (ERiC)
Emission Reduction in Cities (ERiC)
Project in Jombang Regency located about
Project in Jombang Regency terletak kira-
3.0 km to the west of the city center of
kira 3.0 km ke arah barat dari pusat kota
Jombang, as shown in figure 1.1. This area
Jombang, seperti yang ditunjukkan pada
were spread around 26 ha with the height
Gambar 1.1. Area ini tersebar sekitar 26
of 36 masl in the northernmost part until
ha dengan ketinggian 36 mdpl di bagian
52 masl in the southern part of the area.
paling Utara hingga 52 mdpl di bagian
Selatan daerah tersebut
The area of work project is divided into the Area pekerjaan proyek dibagi menjadi bagian
following section: berikut:
1
1.2 BACKGROUND 1.2 LATAR BELAKANG
At the beginning of this project started, almost Pada awal proyek ini mulai, hampir seluruh
all the project locations covered by trees, both area lokasi pekerjaan tertutup oleh pohon, baik
teak trees or other trees. The tree located in the pohon jati maupun jenis pohon yang lain.
project location belongs to The Environment Pohon yang berada di lokasi proyek adalah
Agency (DLH) of Jombang Regency, so cutting milik Dinas Lingkungan Hidup (DLH)
is the responsibility of DLH of Jombang Kabupaten Jombang, sehingga penebangan
Regency because trees which cut are a highly menjadi tanggung jawab DLH Kab. Jombang
economical asset especially for the teak tree. karena pohon yang ditebang adalah asset yang
Tree cutting start on August 2020 with the mempunyai nilai ekonomis tinggi terutama
completion target in the end of December 2020. untuk pohon jati.
In fact, till the end of December 2020 the target Penebangan pohon dimulai pada bulan Agustus
is not achieved so that Sorting, Composting, 2020 dengan target penyelesaian pada akhir
LTP, Reservoir, still have the trees which not Desember 2020. Pada kenyataannya, sampai
yet cut, as a result the main work such as LTP, dengan akhir Desember 2020 target tersbut
Sorting and Composting and access road can tidak tercapai sehingga di lokasi Sorting
not be finished. Composting, LTP, Reservoir, masih ada pohon
yang belum ditebang, sehingga berakibat pada
pekerjaan utama seperti LTP, Sorting and
Composting dan jalan akses belum bisa
1.3 PURPOSE dikerjakan.
Accelerate the work progress of LTP, Sorting
and Composting (Sorcom) as well as access road 1.3 TUJUAN
because LTP work supposed to be started in the Mempercepat progress pekerjaan LTP, Sorting
beginning of December 2020 and Sorcom work dan Composting (Sorcom) serta jalan akses
supposed to be started in the beginning of karena pekerjaan LTP seharusnya dimulai awal
January 2021. Desember 2020 dan pekerjaan Sorcom dimulai
awal Januari 2021.
1.4 REFERENCE
1. Letter from Leader of Working Unit of
Settlement Infrastructure Implementation 1.4 REFERENSI
Region I East Java Province number : 1. Surat dari Kepala Satuan Kerja
CK.0601-Cb16/Satker1/1073 dated 9 Pelaksanaan Prasarana Permukiman
November 2020 about the information Wilayah I Provinsi Jawa Timur nomor :
of license status for North-River in TPA CK.0601-Cb16/Satker1/1073 tanggal 9
2
Banjardowo location and tree cutting November 2020, mengenai informasi
process. status perijinan Sungai Utara lokasi
2. Request from DLH, the remaining teak TPA Banjardowo dan proses
trees which not yet cut of 593 pieces, in penebangan pohon.
order to be implemented by Eric Project 2. Permintaan DLH, sisa pohon jati yang
Jombang (Attached (Minutes of Meeting belum ditebang sebanyak 593 batang agar
BAB 2
2.1 TREE CUTTING
PENEBANGAN POHON
In the beginning of the work, the number of
trees was recorder on building location
according to the layout (figure 1.3). 2.1 PENEBANGAN POHON
Pada awal mulai pekerjaan, dilakukan
pendataan jumlah pohon di lokasi
bangunan-bangunan sesuai dengan lay out
(gambar 1.3).
4
Figure 1. 1 Layout of Work Location
6
2.2 Work Schedule of Tree Cutting by PT 2.2 Rencana pekerjaan penebangan pohon
Adhi Karya (Persero) Tbk oleh PT Adhi Karya (Persero) Tbk
Based on the result of mutual meeting between Berdasarkan hasil rapat bersama antara PPK
PPK, Consultant, Contractor, and DLH konsultan, kontraktor, dan DLH Kab.
Jombang Regency, was mutually agreed that Jombang, disepakati bersama bahwa diusulkan
proposed the teak cutting will performed by PT pemotongan pohon jati akan dilakukan oleh
Adhi Karya (Persero) Tbk. according to the PT Adhi Karya (Persero) Tbk sesuai dengan
Minutes of Meeting No. 25 on December 16 th, notulen rapat no. 25 tanggal 16 Desember
2020 with the remaining teak tree which not yet 2020 dengan sisa jumlah pohon jati yang
cut of 593 pieces (for diameter > 30 cm). in belum ditebang sebanyak 593 batang (untuk
connection with the unlogged tree located in diameter > 30 cm). Berhubung pohon yang
GWT 2, Sorting Composting, access road, belum ditebang berada di lokasi GWT 2,
reservoir, LSP, LTP thus, tree cutting should be Sorting Composting, jalan akses, reservoir,
finished /completed in order to the work do not LSP, LTP, maka penebangan harus segera
delay. DLH request the cutting performed with diselesaikan agar proyek tidak mengalami
the cutting tools because of have the high keterlambatan pekerjaan. DLH menghendaki
economical value and perform the pemotongan dilakukan dengan alat potong
stacking/build up on location which has been karena mempunyai nilai ekonomis yang tinggi
mutually agreed before. Besides the teak tree, dan dilakukan penumpukan di lokasi yang
there is some type of the other trees on work telah disepakati bersama. Selain pohon jati,
location which the cutting can be performed by ada beberapa jenis pohon lain di lokasi
heavy equipment. Before the cutting of the pekerjaannya yang pemotongannya dapat
remaining tree, already perform the mutual dilakukan dengan menggunakan alat berat.
discussion about the continuity of tree cutting Sebelum dilakukan penebangan sisa pohon,
implementation which attended by telah dilakukan diskusi bersama terkait
representative of PT Adhi Karya (Persero) Tbk, kelanjutan pelaksanaan penebangan pohon
representative of Fitchner GmbH & Co. KG, yang dihadiri oleh perwakilan dari PT Adhi
and representative of TPA Banjardowo Karya (Persero) Tbk, konsultan Fitchner
Jombang and issued Official Report of GmbH & Co. KG, dan perwakilan dari TPA
Implementation of Tree Cutting No. Banjardowo Jombang dan diterbitkan Berita
7994A20/ME/BA-050-020 dated December Acara Pelaksanaan Penebangan Pohon No.
17th, 2020. 7994A20/ME/BA-050-020 tanggal 17
Desember 2020.
7
5
Table 1. 3 The Remaining Tree which not yet cut diameter > 30 cm
REMAINING TREE WHICH NOT YET CUT UNTILL DECEMBER 16 TH, 2020
TOTAL IN EACH
LOCATION TREE TYPE TOTAL
LOCATION
GWT 2 TEAK 7 7
TEAK 105
MAONI 8
TREMBESI 20
SORCOM +NEW ROAD (STA 0+217R2 - 0+425R3) 105
MANGO 11
RANDU 4
GEMBLINA 4
MANGO 35
RESERVOIR MAONI 1 147
TEAK 147
TEAK 334
10. LSP JAMBU MONYET 1
11. ANAEROBIC (STEP 1) TREMBESI 11
12. AEROBIC (STEP 2) ASEM 4 334
13. WETLAND (STEP 3) MANGO 31
14. LTP BUILDING MAHONI 5
RANDU 2
TOTAL ALL TREE IN ALL LOCATION 593
CHAPTER 3 BAB 3
ADDITION OF NEW WORK ITEM PENAMBAHAN ITEM
TREE CUTTING PEKERJAAN BARU
PEMOTONGAN POHON
8
CHAPTER 4 BAB 4
CONSLUSION KESIMPULAN
The teak cutting activity performed in Emission Kegiatan penebangan pohon jati yang
Reduction in Cities Project – Solid Waste dilakukan di Proyek Emission Reduction in
Management (ERiC-I), Jombang Regency, Cities – Solid Waste Management (ERiC-I),
Indonesia Jombang Regency, Indonesia dapat diambil
1. Initial activity of tree cutting performed by kesimpulan sebagai berikut :
DLH Jombang Regency since august 2020 1. Kegiatan awal penebangan pohon dilakukan
because of teak tree have highly oleh DLH Kab. Jombang sejak bulan
economical value. Agustus 2020 karena pohon jati mempunyai
2. Until the end of December 2020, in fact nilai ekonomis yang tinggi.
DLH Jombang Regency unable to complete 2. Sampai dengan akhir Desember 2020,
the work of teak cutting and remains 593 ternyata DLH Kab. Jombang belum bisa
pieces (for diameter > 30 cm). menyelesaikan pekerjaan penebangan
3. Cutting tree work proposed will be pohon jati dan masih menyisakan 593
performed by PT Adhi Karya (Persero) batang (untuk diameter > 30 cm).
Tbk. in order to the project perform further 3. Pekerjaan penebangan pohon diusulkan
work without any obstacle to unlogged tree. akan dikerjakan oleh PT Adhi Karya
(Persero) Tbk agar proyek dapat
melaksanakan pekerjaan lanjutan tanpa
terkendala dengan pohon yang belum
ditebang.
9
8