You are on page 1of 14

THE UNITED NATION DEVELOPMENT PROGRAMME (UNDP)

The Sulawesi Programme for Earthquake and Tsunami Infrastructure Reconstruction Assistance (PETRA)
Construction Supervision For 2 (Two) Publik Market Omu - Sigi District and Sibado - Donggala District

RECAPITULATION
Location : Omu, Sigi District and Period : 29 November - 31 December 2021
: Sibado, Donggala District
Contractor : PT. Insan Cita Karya

Contract Actual Progress


Previous This Week Up To This Week
Contain
No. Work Description Contain Contain Contain Remarks
Cumulative
Contain (%) Cumulative Contain (%) Cumulative Contain (%) Cumulative
(%)
(%) (%) (%)

1 OMU MARKET 46.16 94.89 43.81 1.19 0.55 96.08 44.36

2 SIBADO MARKET 53.84 91.20 49.10 3.93 2.12 95.13 51.22

TOTAL 100.00 92.90 2.67 95.57

Acknowledged by Certified by Prepare by


UNDP Petra Supervisor Engineer PT. Insan Cita Karya

WHISNU Y. ANGGONO M. ANDRIANSYAH, ST JASMANSYAH ST, MT


Community Mobilization Officer Team Leader Project Manager
THE UNITED NATION DEVELOPMENT PROGRAMME (UNDP)
The Sulawesi Programme for Earthquake and Tsunami Infrastructure Reconstruction Assistance (PETRA)
Construction Supervision For 2 (Two) Publik Market Omu - Sigi District and Sibado - Donggala District

Main Item Works : Progress Work Period : 29 November - 31 December 2021


Location : Omu, Sigi District
Contractor : PT. Insan Cita Karya

Actual Progress
Contract Up To This
No. Work Description Previous This Week Remarks
Week
Contain (%) Contain (%) Contain (%) Contain (%)
1 MARKET -1 (DRY AREA)
A PREPARATION WORK 4.59 4.33 0.13 4.46
B ARCHITECTURAL WORKS 45.48 45.16 - 45.16
C STRUCTURAL WORK 26.91 26.91 - 26.91
D ELECTRICAL WORKS 1.15 0.31 0.21 0.51
Sub Total 1 78.13 76.72 0.33 77.05
2 TOILET
A PREPARATION WORK 0.11 0.11 - 0.11
B ARCHITECTURAL WORKS 3.32 2.89 0.05 2.94
C STRUCTURAL WORK 1.62 1.62 - 1.62
D MECHANICAL AND ELECTRICAL WORKS 1.33 0.38 0.25 0.64
Sub Total 2 6.38 5.01 0.30 5.31
3 SEPTICKTANK Sub Total 3 3.49 3.49 - 3.49
4 SITE PLAN
A SITEPLAN PLUMBING WORKS 0.85 0.85 - 0.85
B SITE PLAN ELECTRICAL WORKS 2.58 0.92 - 0.92
C SITE WORK, PAVING AND FENCE WORKS 6.07 5.51 0.56 6.07
D GARBAGE BOX AND SLAB 0.83 0.72 - 0.72
E DRAINAGE 1.68 1.68 - 1.68
Sub Total 4 12.01 9.68 0.56 10.24
TOTAL 100.00 94.89 1.19 96.08

Acknowledged by Certified by Prepare by


UNDP Petra Supervisor Engineer PT. Insan Cita Karya

WHISNU Y. ANGGONO M. ANDRIANSYAH, ST JASMANSYAH ST, MT


Community Mobilization Officer Team Leader Project Manager
THE UNITED NATION DEVELOPMENT PROGRAMME (UNDP)
The Sulawesi Programme for Earthquake and Tsunami Infrastructure Reconstruction Assistance (PETRA)
Construction Supervision For 2 (Two) Publik Market Omu - Sigi District and Sibado - Donggala District

Main Item W orks : Market-1 (Dry Area) Period : 29 November - 31 December 2021
Location : Omu, Sigi District
Contractor : PT. Insan Cita Karya

Contract Actual Progress


No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
A PREPARATION WORK
1
Site Measurement and Bowplank Intallation m' 178.00 0.327 109.85 0.202 68.15 0.125 178.00 0.327 100.00%
2
Project Safety Fencing m' 100.00 1.301 100.00 1.301 0.00 0.000 100.00 1.301 100.00%
3
Project Signage unit 2.00 0.018 2.00 0.018 0.00 0.000 2.00 0.018 100.00%
4
Temporary Office Construction; Plaster Floor unit 2.00 1.313 2.00 1.313 0.00 0.000 2.00 1.313 100.00%
5
Storage Construction & Bordinghouse m2 20.00 0.597 20.00 0.597 0.00 0.000 20.00 0.597 100.00%
6
Mobilization, Demobilization of Personnel and Tools ls 2.00 0.367 1.30 0.239 0.00 0.000 1.30 0.239 65.00%
7
HSE (Safety Net, Hat, Helmet,etc.) ls 2.00 0.275 2.00 0.275 0.00 0.000 2.00 0.275 100.00%
8
Cleaning of field and leveling m2 744.00 0.389 744.00 0.389 0.00 0.000 744.00 0.389 100.00%
SUB TOTAL (A) 4.588 4.334 0.125 4.459
B ARCHITECTURAL WORKS
B.1 1ST LEVEL
I. Floor Installation Work
1 40x40 cm of ceramic tile m2 659.63 3.744 659.63 3.744 0.00 0.000 659.63 3.744 100.00%

II. Painting Works


1 W all painting ; Exterior m2 478.56 0.380 478.56 0.380 0.00 0.000 478.56 0.380 100.00%
2 Listplank painting m2 76.11 0.263 76.11 0.263 0.00 0.000 76.11 0.263 100.00%
3 Steel Painting (Frame, etc.) m2 971.66 0.997 971.66 0.997 0.00 0.000 971.66 0.997 100.00%

III. Other Works


Disability Ramp Work
1 Disability Handrail Ramp work m 11.40 0.314 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
2 Lean concrete ramp fc'= 7.4 MPa (K 100) m3 0.80 0.022 0.80 0.022 0.00 0.000 0.80 0.022 100.00%
3 Ram difabel W ork m3 1.60 0.044 1.60 0.044 0.00 0.000 1.60 0.044 100.00%

B.2 ROOF WORKS


I. Roof Covering Works
1
Truss WF 150 x 75 x 5 x 7, complete kg 5,924.80 7.789 5924.80 7.789 0.00 0.000 5924.80 7.789 100.00%
2
Roof battens CNP 100.50.20.2,3 kg 6,602.64 9.335 6602.64 9.335 0.00 0.000 6602.64 9.335 100.00%
3
Sagrod dia 12 mm kg 181.94 0.239 181.94 0.239 0.00 0.000 181.94 0.239 100.00%
4
W ind tie rod dia. 14 mm, inc clam kg 449.14 0.590 449.14 0.590 0.00 0.000 449.14 0.590 100.00%
5
Span screw Tie rod ea 48.00 0.042 48.00 0.042 0.00 0.000 48.00 0.042 100.00%
6
Hollow steel truss for second skin kg 1,447.26 2.126 1447.26 2.126 0.00 0.000 1447.26 2.126 100.00%
7
W elding steel truss, all inc. rafter, battens and accessories cm 25,263.20 6.957 25263.20 6.957 0.00 0.000 25263.20 6.957 100.00%
8
Anchor bolt trus ɸ 3/4 " - 20 cm ea 128.00 0.587 128.00 0.587 0.00 0.000 128.00 0.587 100.00%
9
Zincalume spandex thk. 0,4 mm Installation m2 1,202.04 4.456 1202.04 4.456 0.00 0.000 1202.04 4.456 100.00%
10
Polycarbonat Roof installation m2 206.06 1.813 206.06 1.813 0.00 0.000 206.06 1.813 100.00%
11
Second skin, perforated plat 2.0 mm thk., d12 mm hole m2 138.40 4.192 138.40 4.192 0.00 0.000 138.40 4.192 100.00%
12
Zincalume spandex ridge m' 63.00 0.238 63.00 0.238 0.00 0.000 63.00 0.238 100.00%
13
Polycarbonat roof ridges m' 10.80 0.038 10.80 0.038 0.00 0.000 10.80 0.038 100.00%
14
Kalsiplank, finish Paint m' 380.56 1.313 380.56 1.313 0.00 0.000 380.56 1.313 100.00%
SUB TOTAL (B) 45.479 45.165 0.000 45.165
C. STRUCTURAL WORK
C.1. FOUNDATION WORK
1 Concrete foundation
- Foundation cutting m3 62.00 1.462 62.00 1.462 0.00 0.000 62.00 1.462 100.00%
- Sand layer t=10cm m3 4.00 0.023 4.00 0.023 0.00 0.000 4.00 0.023 100.00%
- Base concrete t=5 cm K-100 m3 2.00 0.055 2.00 0.055 0.00 0.000 2.00 0.055 100.00%
- Concrete K-250 m3 16.39 0.555 16.39 0.555 0.00 0.000 16.39 0.555 100.00%
- Reinforcement kg 2,342.10 1.243 2342.10 1.243 0.00 0.000 2342.10 1.243 100.00%
- Formwork m2 54.12 0.547 54.12 0.547 0.00 0.000 54.12 0.547 100.00%

2 Soil backfill m3 20.67 0.035 20.67 0.035 0.00 0.000 20.67 0.035 100.00%

C.2. 1ST LEVEL


1 K1 25/35 column
- Concrete K-250 m3 18.78 0.636 18.78 0.636 0.00 0.000 18.78 0.636 100.00%
- Reinforcement kg 5,200.51 2.760 5200.51 2.760 0.00 0.000 5200.51 2.760 100.00%
- Formwork column m2 125.20 1.173 125.20 1.173 0.00 0.000 125.20 1.173 100.00%

2 Sloof / Tie Beam 20/30


- Concrete K-250 m3 20.67 0.699 20.67 0.699 0.00 0.000 20.67 0.699 100.00%
- Reinforcement kg 4,117.94 2.186 4117.94 2.186 0.00 0.000 4117.94 2.186 100.00%
- Formwork sloof m2 112.20 0.708 112.20 0.708 0.00 0.000 112.20 0.708 100.00%

3 Beam 25/35
- Concrete K-250 m3 19.54 0.661 19.54 0.661 0.00 0.000 19.54 0.661 100.00%
- Reinforcement kg 3,881.16 2.060 3881.16 2.060 0.00 0.000 3881.16 2.060 100.00%
- Formwork sloof m2 106.02 1.028 106.02 1.028 0.00 0.000 106.02 1.028 100.00%

4 Floor Slab
- Soil fill for floor elevation m3 144.91 1.102 144.91 1.102 0.00 0.000 144.91 1.102 100.00%
- Sand layer t=10cm m3 82.81 0.478 82.81 0.478 0.00 0.000 82.81 0.478 100.00%
- Base concrete t=5 cm K-100 m3 46.11 1.260 46.11 1.260 0.00 0.000 46.11 1.260 100.00%
- Concrete K-250 m3 66.20 2.241 66.20 2.241 0.00 0.000 66.20 2.241 100.00%
- Reinforcement kg 1,833.91 0.973 1833.91 0.973 0.00 0.000 1833.91 0.973 100.00%
- Formwork m2 13.30 0.134 13.30 0.134 0.00 0.000 13.30 0.134 100.00%
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
5 Drainage and steel grating
- Foundation cutting m3 19.62 0.463 19.62 0.463 0.00 0.000 19.62 0.463 100.00%
- Brick W all 1:5 H=0,3 m m2 78.48 1.220 78.48 1.220 0.00 0.000 78.48 1.220 100.00%
- Mortar plaster work m2 130.80 0.292 130.80 0.292 0.00 0.000 130.80 0.292 100.00%
- Mortar Neat Plaster W ork m2 130.80 0.158 130.80 0.158 0.00 0.000 130.80 0.158 100.00%
- Concrete t=5 cm K-100 m3 13.08 0.357 13.08 0.357 0.00 0.000 13.08 0.357 100.00%
- Steel Grating m' 130.80 2.401 130.80 2.401 0.00 0.000 130.80 2.401 100.00%
SUB TOTAL (C) 26.910 26.910 0.000 26.910
D. ELECTRICAL WORKS
D.1. LOW VOLTAGE PANEL WORKS
Procurement and installation of a complete panel
1 MCB-Box of Los Type-A Market unit 2.00 0.020 0.00 0.000 0.00 0.000 0.00 0.000 0.00%

D.2. LIGHTING WORKS


Procurement, installation of lighting and sockets
1 TL Led 19 W Type unit 16.00 0.068 8.00 0.034 0.00 0.000 8.00 0.034 50.00%
2 Single Electrical Switch unit 2.00 0.005 1.00 0.002 1.00 0.002 2.00 0.005 100.00%
3 Double Electrical Switch unit 8.00 0.022 4.00 0.011 4.00 0.011 8.00 0.022 100.00%
4 100 W W all Electric Socket unit 4.00 0.034 2.00 0.017 2.00 0.017 4.00 0.034 100.00%
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pi point 16.00 0.216 8.00 0.108 8.00 0.108 16.00 0.216 100.00%
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of c point 14.00 0.136 7.00 0.068 7.00 0.068 14.00 0.136 100.00%

D.3. Lightning Rod Installation


Procurement, installation of a complete lightning rod
1 Ø 3/4 30cm Air Terminal , Completed W ith Ø 3/4 70cm GIP set 2.00 0.514 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
2 BC 25 mm² Cable Installation m 60.00 0.033 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
3 600mm² x 600mm² c/w Junction Box with Grounding Syste set 2.00 0.066 2.00 0.066 0.00 0.000 2.00 0.066 100.00%
4 Auxiliary Materials lot 2.00 0.037 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
SUB TOTAL (D) 1.150 0.306 0.206 0.512
TOTAL 78.126 76.715 0.331 77.047

Main Item W orks : Toilet Period : 29 November - 31 December 2021


Location : Omu, Sigi District
Contractor : PT. Insan Cita Karya

Contract Actual Progress


No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
A PREPARATION WORK
1 Site Measurement and Bowplank Installation m' 49.00 0.090 49.00 0.090 0.00 0.000 49.00 0.090 100.00%
2 Cleaning of field and leveling m2 33.00 0.017 33.00 0.017 0.00 0.000 33.00 0.017 100.00%
SUB TOTAL (A) 0.107 0.107 0.000 0.107
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I. Wallwork
1 Brick W all 1:3 m2 34.94 0.202 34.94 0.202 0.00 0.000 34.94 0.202 100.00%
2 Brick W all 1:5 m2 48.63 0.271 48.63 0.271 0.00 0.000 48.63 0.271 100.00%
3 Mortar Plaster W ork m2 189.66 0.423 189.66 0.423 0.00 0.000 189.66 0.423 100.00%
4 Mortar Neat Plaster W ork m2 145.76 0.176 145.76 0.176 0.00 0.000 145.76 0.176 100.00%
5 20x20 Tile work m2 43.94 0.146 43.94 0.146 0.00 0.000 43.94 0.146 100.00%
6 Glass wall / Boven Light roster m2 0.96 0.011 0.96 0.011 0.00 0.000 0.96 0.011 100.00%
7 Roster m2 3.84 0.061 3.84 0.061 0.00 0.000 3.84 0.061 100.00%

II. Floor Installation Work


1 40x40 cm of Ceramic Tile m2 11.29 0.064 11.29 0.064 0.00 0.000 11.29 0.064 100.00%
2 20x20 cm of Ceramic Tile m2 17.28 0.057 17.28 0.057 0.00 0.000 17.28 0.057 100.00%
3 W aterproofing Coating + mortar m2 17.28 0.059 17.28 0.059 0.00 0.000 17.28 0.059 100.00%

III. Painting Works


1 W all ; Interior m2 45.26 0.036 22.63 0.018 22.63 0.018 45.26 0.036 100.00%
2 W all Painting; Exterior m2 100.50 0.080 100.50 0.080 0.00 0.000 100.50 0.080 100.00%
3 Ceiling Painting m2 43.81 0.035 21.91 0.017 21.91 0.017 43.81 0.035 100.00%
3 Lisplank Painting m2 8.15 0.028 4.08 0.014 4.08 0.014 8.15 0.028 100.00%

IV. Sanitary Work and Installation


Sanitary work includes procurement & installation
1 Squatting Closet Unit 4.00 0.062 4.00 0.062 0.00 0.000 4.00 0.062 100.00%
2 Sitting Toilet Unit 2.00 0.141 2.00 0.141 0.00 0.000 2.00 0.141 100.00%
3 Shower spray Unit 2.00 0.009 2.00 0.009 0.00 0.000 2.00 0.009 100.00%
4 Handrail Stainless; Diffable Unit 2.00 0.055 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
5 Faucet Unit 6.00 0.028 6.00 0.028 0.00 0.000 6.00 0.028 100.00%
6 Floor Drain Unit 6.00 0.047 6.00 0.047 0.00 0.000 6.00 0.047 100.00%
7 Fibre Basin 0,30 m3 Unit 6.00 0.107 6.00 0.107 0.00 0.000 6.00 0.107 100.00%

V. Door and Window Installation Work (complete w. wooden frame)


1 Door Installation W ork (type P1) Unit 4.00 0.055 4.00 0.055 0.00 0.000 4.00 0.055 100.00%
2 Door Installation W ork (type P2) Unit 2.00 0.027 2.00 0.027 0.00 0.000 2.00 0.027 100.00%

VI. Ceiling Installation Work


1 6 mm of Calcium Board; hollow frame m2 43.81 0.086 43.81 0.086 0.00 0.000 43.81 0.086 100.00%

VII. Other Works


Disability Ramp Work
1 Disability Handrail Ramp work m 11.72 0.323 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
2 Ram difabel W ork m3 1.04 0.028 1.04 0.028 0.00 0.000 1.04 0.028 100.00%
3 Lean concrete ramp fc'= 9.8 MPa (K 125) m3 1.04 0.030 1.04 0.030 0.00 0.000 1.04 0.030 100.00%

B.2 ROOF WORKS


I. Roof Covering Works
1 Zincalume spandex thk. 0,40 mm installation m2 48.64 0.180 48.64 0.180 0.00 0.000 48.64 0.180 100.00%
2 Light steel frame; including rafter and accessoris m2 48.64 0.349 48.64 0.349 0.00 0.000 48.64 0.349 100.00%
3 Calsiplank list m 40.80 0.141 40.80 0.141 0.00 0.000 40.80 0.141 100.00%
SUB TOTAL (B) 3.320 2.893 0.049 2.942
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
C STRUCTURAL WORK
I. FOUNDATION WORK
1 Foundation 1
- Foundation Cutting m3 27.22 0.642 27.22 0.642 0.00 0.000 27.22 0.642 100.00%
- Sand layer t=10cm m3 3.02 0.017 3.02 0.017 0.00 0.000 3.02 0.017 100.00%
- Anstamping Stone H=15cm m3 4.54 0.050 4.54 0.050 0.00 0.000 4.54 0.050 100.00%
- Masonry 1:4 m3 11.21 0.063 11.21 0.063 0.00 0.000 11.21 0.063 100.00%
- Backfill m3 9.07 0.015 9.07 0.015 0.00 0.000 9.07 0.015 100.00%

2 Foundation 2 (terrace)
- Foundation Cutting m3 0.32 0.008 0.32 0.008 0.00 0.000 0.32 0.008 100.00%
- Concrete K-175 m3 0.87 0.027 0.87 0.027 0.00 0.000 0.87 0.027 100.00%

3 Sloof 13/20
- Concrete K-250 m3 0.94 0.032 0.94 0.032 0.00 0.000 0.94 0.032 100.00%
- Reinforcement kg 421.35 0.224 421.35 0.224 0.00 0.000 421.35 0.224 100.00%
- Foundation formwork m2 3.20 0.020 3.20 0.020 0.00 0.000 3.20 0.020 100.00%

II. 1ST LEVEL


1 130x130 Column K1
- K-250 Concrete m3 0.76 0.026 0.76 0.026 0.00 0.000 0.76 0.026 100.00%
- Reinforcement kg 268.93 0.143 268.93 0.143 0.00 0.000 268.93 0.143 100.00%
- Column Formwork m2 11.75 0.110 11.75 0.110 0.00 0.000 11.75 0.110 100.00%

2 13/20 Beam B1
- Concrete K-250 m3 0.94 0.032 0.94 0.032 0.00 0.000 0.94 0.032 100.00%
- Reinforcement kg 230.28 0.122 230.28 0.122 0.00 0.000 230.28 0.122 100.00%
- Beam Formwork m2 9.54 0.093 9.54 0.093 0.00 0.000 9.54 0.093 100.00%
SUB TOTAL (C) 1.623 1.623 0.000 1.623
D MECHANICAL AND ELECTRICAL WORKS
I. TOILET PLUMBING WORKS

1.1 CLEAN WATER SYSTEM


Procurement and installation of PPR-PN 10 Pipes
a. Toilet 1 Clean Water Piping and Its Completeness
1 PPR PN-10 Ø 25 mm m 23.50 0.017 23.50 0.017 0.00 0.000 23.50 0.017 100.00%
2 Fitting ls 2.00 0.004 2.00 0.004 0.00 0.000 2.00 0.004 100.00%
3 Gate Valve Ø 32mm unit 2.00 0.001 2.00 0.001 0.00 0.000 2.00 0.001 100.00%

1.2 VENT AND GREY WATER SYSTEM


Procurement and installation of PVC Pipes
Grey Water Piping and Its completeness in toilet to Sepictank
1 PVC-AW Ø 100 mm; SW (Sewage W ater) m 27.50 0.102 27.50 0.102 0.00 0.000 27.50 0.102 100.00%
2 PVC-AW Ø 80 mm; WW (W aste W ater) m 26.00 0.060 26.00 0.060 0.00 0.000 26.00 0.060 100.00%
3 PVC-D Ø 40 mm; VT (Vent) m 4.00 0.002 4.00 0.002 0.00 0.000 4.00 0.002 100.00%
4 Floor Clean Out Ø 80 mm, WW (W aste W ater) unit 6.00 0.014 6.00 0.014 0.00 0.000 6.00 0.014 100.00%
5 Floor Clean Out Ø 100 mm, SW (Sewage W ater) unit 6.00 0.022 6.00 0.022 0.00 0.000 6.00 0.022 100.00%
6 Fitting ls 2.00 0.008 2.00 0.008 0.00 0.000 2.00 0.008 100.00%

1.3 DRAINAGE PIPE SYSTEM TO INFILTRATION WELL


Procurement and installation of PVC Pipes
a. PVC-AW Ø 80 mm; PAH m 8.00 0.082 8.00 0.082 0.00 0.000 8.00 0.082 100.00%

b. Junction Box
Size : dia. of 600 mm x depth adjusted to inlet level of the unit 2.00 0.073 2.00 0.073 0.00 0.000 2.00 0.073 100.00%

2 TOILET ELECTRICAL WORKS


2.1 PANEL WORKS
Procurement & Installation
NYM 3x2,5 mm² Lamp Installation in 20 mmi conduit pipe m 50.00 0.674 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
of MCB-BOX from Market MCB-BOX to Toilet

2.2 LIGHTING WORKS


Procurement, installation of lighting
1 Roset Led 5 W Type Bulb (Toilet) unit 8.00 0.034 0.00 0.000 4.00 0.017 4.00 0.017 50.00%
2 Double Electrical Switch unit 2.00 0.006 0.00 0.000 2.00 0.006 2.00 0.006 100.00%
3 Single Electrical Switch unit 6.00 0.015 0.00 0.000 6.00 0.015 6.00 0.015 100.00%
4 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pi point 16.00 0.216 0.00 0.000 16.00 0.216 16.00 0.216 100.00%
SUB TOTAL (D) 1.329 0.385 0.253 0.638
TOTAL 6.379 5.008 0.302 5.311

Main Item W orks : Septicktank Period : 29 November - 31 December 2021


Location : Omu, Sigi District
Contractor : PT. Insan Cita Karya

Contract Actual Progress


No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)

1 Ground W ork
- STP Foundation Cutting m3 19.15 0.452 19.15 0.452 0.00 0.000 19.15 0.452 100.00%
- Backfill m3 6.38 0.011 6.38 0.011 0.00 0.000 6.38 0.011 100.00%

2 W all SPT
- Sand layer t=10cm m3 1.14 0.007 1.14 0.007 0.00 0.000 1.14 0.007 100.00%
- Brick wall 1:5 m3 39.32 0.219 39.32 0.219 0.00 0.000 39.32 0.219 100.00%
- Mortar Plaster W ork m2 39.32 0.088 39.32 0.088 0.00 0.000 39.32 0.088 100.00%
- Mortar Neat Plaster W ork m2 39.32 0.047 39.32 0.047 0.00 0.000 39.32 0.047 100.00%
- K-100 Concrete LC m3 1.44 0.039 1.44 0.039 0.00 0.000 1.44 0.039 100.00%
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
3 Concrete Column
- K-250 Concrete m3 1.79 0.061 1.79 0.061 0.00 0.000 1.79 0.061 100.00%
- Reinforcement kg 76.03 0.040 76.03 0.040 0.00 0.000 76.03 0.040 100.00%
- Column Formwork m2 19.80 0.185 19.80 0.185 0.00 0.000 19.80 0.185 100.00%

4 Concrete Slab
- K-250 Concrete m3 1.13 0.038 1.13 0.038 0.00 0.000 1.13 0.038 100.00%
- Reinforcement kg 93.58 0.050 93.58 0.050 0.00 0.000 93.58 0.050 100.00%
- Sloof Formwork m2 11.38 0.110 11.38 0.110 0.00 0.000 11.38 0.110 100.00%

5 Install PVC 2" Pipe m 4.00 0.061 4.00 0.061 0.00 0.000 4.00 0.061 100.00%
Install PVC 3" Pipe m 18.00 0.299 18.00 0.299 0.00 0.000 18.00 0.299 100.00%
Install Tee 3" unit 12.00 0.140 12.00 0.140 0.00 0.000 12.00 0.140 100.00%

6 Install Manhole (Inc. handel)


- K-250 Concrete m3 0.53 0.018 0.53 0.018 0.00 0.000 0.53 0.018 100.00%
- Reinforcement kg 63.50 0.034 63.50 0.034 0.00 0.000 63.50 0.034 100.00%
- Formwork m2 3.84 0.037 3.84 0.037 0.00 0.000 3.84 0.037 100.00%

7 Junction Box (0.5x0.5x0.5 m) with manhole cover Lot 2.00 0.073 2.00 0.073 0.00 0.000 2.00 0.073 100.00%

8 Infiltration
- Cutting (2 m depth) m3 6.28 0.148 6.28 0.148 0.00 0.000 6.28 0.148 100.00%
- Install concrete pipa (buis beton) dia. 1 m m' 8.00 0.188 8.00 0.188 0.00 0.000 8.00 0.188 100.00%
- Install pipe PVC 3" (inc. accesories) m 4.00 0.058 4.00 0.058 0.00 0.000 4.00 0.058 100.00%
- Install Manhole cover (inc. handel) m3 0.31 0.011 0.31 0.011 0.00 0.000 0.31 0.011 100.00%
- Reinforecement Manhole (sumur resapan) kg 43.98 1.038 43.98 1.038 0.00 0.000 43.98 1.038 100.00%
- Formwork m2 1.00 0.010 1.00 0.010 0.00 0.000 1.00 0.010 100.00%
- Gravel and sand filter m3 0.79 0.007 0.79 0.007 0.00 0.000 0.79 0.007 100.00%
- Sarang tawon / Bio Media Filter m3 2.40 0.020 2.40 0.020 0.00 0.000 2.40 0.020 100.00%

TOTAL 3.489 3.489 0.000 3.489

Main Item W orks : Site Plan Period : 29 November - 31 December 2021


Location : Omu, Sigi District
Contractor : PT. Insan Cita Karya

Contract Actual Progress


No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)

A. SITEPLAN PLUMBING WORKS


1.1 MAIN EQUIPMENTS OF CLEAN WATER SYSTEM
Pipeline procurement and installation include excavation, accessories, and auxiliary equipment
a. Piping and accessories
1 12 m water shalow well Ls 1.00 0.275 1.00 0.275 0.00 0.000 1.00 0.275 100.00%

b. Clean Water Oump


1 Type : Jet Pump, shallow water pump Ls 1.00 0.073 1.00 0.073 0.00 0.000 1.00 0.073 100.00%
Capacity : 20 Lpm
Suction Head : 10 m
Discharge Head : 31 m
Output Power : 0.125 Kw
Installed complete with W LC (water level control), holder, support etc. according to specifications and drawing

c. Piping from Jet Pump to water tank


1 PPR PN-10 Ø 40 mm m 18.80 0.013 18.80 0.013 0.00 0.000 18.80 0.013 100.00%
2 Gate Valve Ø 40mm unit 1.00 0.002 1.00 0.002 0.00 0.000 1.00 0.002 100.00%
3 Check Valve Ø 40mm unit 1.00 0.002 1.00 0.002 0.00 0.000 1.00 0.002 100.00%
4 Fitting ls 1.00 0.002 1.00 0.002 0.00 0.000 1.00 0.002 100.00%

d. Tower Tank
1 Type : Fibreglass Capacity : 1 m3 unit 2.00 0.129 2.00 0.129 0.00 0.000 2.00 0.129 100.00%
2 Rooftank work c/w W ater Tower 4 meters high unit 1.00 0.275 1.00 0.275 0.00 0.000 1.00 0.275 100.00%
(incl. foundation)

1.2 CLEAN WATER SYSTEM


Procurement and installation of PPR-PN 10 Pipes including excavation, accessories, and auxiliary equipment
a. Piping and accessories from the Tank to toilet - 1
1 PPR PN-10 Ø 40 mm m 10.00 0.007 10.00 0.007 0.00 0.000 10.00 0.007 100.00%
2 Fitting ls 1.00 0.002 1.00 0.002 0.00 0.000 1.00 0.002 100.00%
3 Gate Valve Ø 32mm unit 1.00 0.001 1.00 0.001 0.00 0.000 1.00 0.001 100.00%

b. Piping and accessories from the Tank to toilet - 2


1 PPR PN-10 Ø 40 mm m 45.00 0.032 45.00 0.032 0.00 0.000 45.00 0.032 100.00%
2 Fitting ls 1.00 0.002 1.00 0.002 0.00 0.000 1.00 0.002 100.00%
3 Gate Valve Ø 32mm unit 1.00 0.001 1.00 0.001 0.00 0.000 1.00 0.001 100.00%

1.3 VENT AND GREY WATER SYSTEM


Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary tool
a. Grey Water Piping and accessories to Sepictank.1
1 PVC-AW Ø 100 mm; SW (Sewage W ater) m 5.00 0.011 5.00 0.011 0.00 0.000 5.00 0.011 100.00%
2 PVC-AW Ø 80 mm; WW (W aste W ater) m 5.00 0.018 5.00 0.018 0.00 0.000 5.00 0.018 100.00%
3 Fitting ls 1.00 0.004 1.00 0.004 0.00 0.000 1.00 0.004 100.00%
SUB TOTAL (A) 0.850 0.850 0.000 0.850
B. SITE PLAN ELECTRICAL WORKS
B.1 LOW VOLTAGE PANEL WORK
Procurement and installation of Panel unit 1.00 0.129 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
Market Main Panel

New Installation of PLN


Connecting Fee VA 1.00 0.367 1.00 0.367 0.00 0.000 1.00 0.367 100.00%
Deposit Money VA 1.00 0.092 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
SLO (Certificate of Eligibility for Operation) (adjusted for rat VA 1.00 0.092 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
B.2 CONNECTOR CABLE PROVISION AND INSTALLATION
The work of procurement, installation and testing Low Voltage Cable ;
From Main Panel to MCB-BOX.1, NYY 3 x 6 mm² + BC 6m m 10.00 0.096 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
From Main Panel to MCB-BOX.2, NYY 3 x 4 mm² + BC 6m m 8.00 0.077 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
From Main Panel to MCB-BOX.3, NYY 3 x 4 mm² + BC 6m m 20.00 0.193 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
From Main Panel to MCB-BOX.4, NYY 3 x 4 mm² + BC 6m m 10.00 0.096 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
From Main Panel to MCB-BOX.5, NYY 3 x 4 mm² + BC 6m m 20.00 0.193 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
From MCB-BOX.1 to Jet Pump, NYY 3 x 4 mm² + BC 6mm m 5.00 0.048 0.00 0.000 0.00 0.000 0.00 0.000 0.00%

B.3 LIGHTING POLE


Ligthing pole (solar cell) complete with founfation ea 4.00 1.102 2.00 0.551 0.00 0.000 2.00 0.551 50.00%

B.4 TESTING & COMMISSIONING


A Testing and setting the installation until it functions properly Lot 1.00 0.092 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
SUB TOTAL (B) 2.575 0.918 0.000 0.918
C. SITE WORK, PAVING AND FENCE WORKS
1 Cleaning of field and leveling, Inc. tree removal m2 1,723.00 0.902 1723.00 0.902 0.00 0.000 1723.00 0.902 100.00%
2 Paving block m2 1,204.56 4.399 1054.71 3.851 149.85 0.547 1204.56 4.399 100.00%
3 Trotoar Canstein, Inc. Painting m' 129.61 0.103 113.04 0.090 16.57 0.013 129.61 0.103 100.00%
4 Fence:
- Foundation Cutting m3 8.70 0.205 8.70 0.205 0.00 0.000 8.70 0.205 100.00%
- Sand layer t=10cm m3 1.74 0.010 1.74 0.010 0.00 0.000 1.74 0.010 100.00%
- Anstamping Stone H=15cm m3 2.61 0.029 2.61 0.029 0.00 0.000 2.61 0.029 100.00%
- Masonry 1:4 m3 7.61 0.043 7.61 0.043 0.00 0.000 7.61 0.043 100.00%
- Backfill m3 2.90 0.005 2.90 0.005 0.00 0.000 2.90 0.005 100.00%
- Mortar Plaster W ork m2 58.00 0.115 58.00 0.115 0.00 0.000 58.00 0.115 100.00%
- Mortar Neat Plaster W ork m2 58.00 0.070 58.00 0.070 0.00 0.000 58.00 0.070 100.00%
- K-250 Concrete m3 0.65 0.022 0.65 0.022 0.00 0.000 0.65 0.022 100.00%
- Reinforcement kg 116.09 0.062 116.09 0.062 0.00 0.000 116.09 0.062 100.00%
- Column Formwork m2 3.30 0.031 3.30 0.031 0.00 0.000 3.30 0.031 100.00%
- Roster m2 5.00 0.080 5.00 0.080 0.00 0.000 5.00 0.080 100.00%
SUB TOTAL (C) 6.074 5.514 0.560 6.074
D. GARBAGE BOX AND SLAB
1 Concrete slab for garbage truck
- Sand layer t=10cm m3 1.75 0.010 1.75 0.084 0.00 0.000 1.75 0.010 100.00%
- Base concrete t=8 cm K-100 m3 0.88 0.024 0.88 0.024 0.00 0.000 0.88 0.024 100.00%
- K-250 Concrete m3 2.10 0.071 2.10 0.071 0.00 0.000 2.10 0.071 100.00%
- Reinforcement kg 142.10 0.075 142.10 0.075 0.00 0.000 142.10 0.075 100.00%
- Formwork m2 1.02 0.006 1.02 0.006 0.00 0.000 1.02 0.006 100.00%

2 Garbage Box / Trush Bin


- Foundation Cutting m3 2.69 0.063 2.69 0.063 0.00 0.000 2.69 0.063 100.00%
- Sand layer t=10cm m3 0.90 0.005 0.90 0.005 0.00 0.000 0.90 0.005 100.00%
- Anstamping Stone H=15cm m3 1.34 0.015 1.34 0.015 0.00 0.000 1.34 0.015 100.00%
- Masonry 1:4 m3 2.08 0.012 2.08 0.012 0.00 0.000 2.08 0.012 100.00%
- Backfill m3 0.90 0.002 0.90 0.002 0.00 0.000 0.90 0.002 100.00%
- Soil fill for floor elevation m3 2.00 0.015 2.00 0.015 0.00 0.000 2.00 0.015 100.00%
- Brick wall 1:5 m2 15.40 0.086 15.40 0.086 0.00 0.000 15.40 0.086 100.00%
- Mortar Plaster W ork m2 30.80 0.069 30.80 0.069 0.00 0.000 30.80 0.069 100.00%
- Mortar Neat Plaster W ork m2 30.80 0.037 30.80 0.037 0.00 0.000 30.80 0.037 100.00%
- K-175 Concrete m3 1.24 0.039 1.24 0.039 0.00 0.000 1.24 0.039 100.00%
- Reinforcement kg 128.55 0.068 128.55 0.068 0.00 0.000 128.55 0.068 100.00%
- Column Formwork m2 4.80 0.045 4.80 0.045 0.00 0.000 4.80 0.045 100.00%
- Cover Ls 1.00 0.184 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
SUB TOTAL (D) 0.826 0.716 0.000 0.642
E. DRAINAGE
- DraInage Cutting m3 38.16 0.900 38.16 0.900 0.00 0.000 38.16 0.900 100.00%
- Sand layer t=10cm m3 6.36 0.037 6.36 0.037 0.00 0.000 6.36 0.037 100.00%
- Concrete drainage (K-100) t=15 cm m3 21.47 0.587 21.47 0.587 0.00 0.000 21.47 0.587 100.00%
- Formwork m3 26.50 0.157 26.50 0.157 0.00 0.000 26.50 0.157 100.00%
SUB TOTAL (E) 1.680 1.680 0.000 1.680
TOTAL 12.005 9.678 0.560 10.164
THE UNITED NATION DEVELOPMENT PROGRAMME (UNDP)
The Sulawesi Programme for Earthquake and Tsunami Infrastructure Reconstruction Assistance (PETRA)
Construction Supervision For 2 (Two) Publik Market Omu - Sigi District and Sibado - Donggala District

Main Item Works : Progress Work Period : 29 November - 31 December 2021


Location : Sibado, Donggala District
Contractor : PT. Insan Cita Karya

Actual Progress
Contract Up To This
No. Work Description Previous This Week Remarks
Week
Contain (%) Contain (%) Contain (%) Contain (%)
1 MARKET -1 (DRY AREA)
A PREPARATION WORK 3.43 3.21 - 3.21
B ARCHITECTURAL WORKS 39.25 38.34 0.87 39.21
C STRUCTURAL WORK 23.35 22.23 0.36 22.59
D ELECTRICAL WORKS 1.18 0.06 0.53 0.58
Sub Total 1 67.21 63.84 1.76 65.59
2 MARKET -2 (WET AREA)
A PREPARATION WORK 0.20 0.20 - 0.20
B ARCHITECTURAL WORKS 6.92 6.57 0.35 6.92
C STRUCTURAL WORK 4.36 3.98 - 3.98
D ELECTRICAL WORKS 0.23 - 0.23 0.23
Sub Total 2 11.70 10.74 0.57 11.32
3 TOILET
A PREPARATION WORK 0.09 0.09 - 0.09
B ARCHITECTURAL WORKS 3.31 2.78 0.48 3.26
C STRUCTURAL WORK 1.44 1.44 - 1.44
D MECHANICAL AND ELECTRICAL WORKS 1.85 0.74 - 0.74
Sub Total 3 6.69 5.05 0.48 5.53
4 SEPTICKTANK Sub Total 4 2.98 2.98 - 2.98
5 SITE PLAN
A SITEPLAN PLUMBING WORKS 1.06 1.06 - 1.06
B SITE PLAN ELECTRICAL WORKS 2.47 0.31 0.86 1.17
C SITE WORK, PAVING AND FENCE WORKS 7.19 6.67 0.26 6.93
D GARBAGE BOX AND SLAB 0.70 0.55 - 0.55
Sub Total 5 11.42 8.59 1.12 9.71
TOTAL 100.00 91.20 3.93 95.13

Acknowledged by Certified by Prepare by


UNDP Petra Supervisor Engineer PT. Insan Cita Karya

WHISNU Y. ANGGONO M. ANDRIANSYAH, ST JASMANSYAH ST, MT


Community Mobilization Officer Team Leader Project Manager
THE UNITED NATION DEVELOPMENT PROGRAMME (UNDP)
The Sulawesi Programme for Earthquake and Tsunami Infrastructure Reconstruction Assistance (PETRA)
Construction Supervision For 2 (Two) Publik Market Omu - Sigi District and Sibado - Donggala District

Main Item W orks : Market-1 (Dry Area) Period : 29 November - 31 December 2021
Location : Sibado, Donggala District
Contractor : PT. Insan Cita Karya

Contract Actual Progress


No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
A PREPARATION WORK
1
Site Measurement and Bowplank Intallation m' 178.00 0.280 115.70 0.182 0.00 0.000 115.70 0.182 65.00%
2
Project Safety Fencing m' 100.00 0.969 100.00 0.969 0.00 0.000 100.00 0.969 100.00%
3
Project Signage unit 2.00 0.016 2.00 0.016 0.00 0.000 2.00 0.016 100.00%
4
Temporary Office Construction; Plaster Floor unit 2.00 0.859 2.00 0.859 0.00 0.000 2.00 0.859 100.00%
5
Storage Construction & Bordinghouse m2 20.00 0.422 20.00 0.422 0.00 0.000 20.00 0.422 100.00%
6
Mobilization, Demobilization of Personnel and Tools ls 2.00 0.315 1.25 0.197 0.00 0.000 1.25 0.197 62.50%
7
HSE (Safety Net, Hat, Helmet,etc.) ls 2.00 0.236 2.00 0.236 0.00 0.000 2.00 0.236 100.00%
8
Cleaning of field and leveling m2 744.00 0.334 744.00 0.334 0.00 0.000 744.00 0.334 100.00%
SUB TOTAL (A) 3.431 3.215 0.000 3.215
B ARCHITECTURAL WORKS
B.1 1ST LEVEL
I. Floor Installation Work
1 40x40 cm of ceramic tile m2 659.63 3.349 594.87 3.020 64.75 0.329 659.63 3.349 100.00%

II. Painting Works


1 W all painting ; Exterior m2 478.56 0.463 0.00 0.000 435.05 0.421 435.05 0.421 90.91%
2 Listplank painting m2 76.11 0.232 76.11 0.232 0.00 0.000 76.11 0.232 100.00%
3 Steel Painting (Frame, etc.) m2 971.66 0.855 971.66 0.855 0.00 0.000 971.66 0.855 100.00%

III. Other Works


Disability Ramp Work
1 Disability Handrail Ramp work m 11.40 0.269 6.33 0.150 5.07 0.120 11.40 0.269 100.00%
2 Lean concrete ramp fc'= 7.4 MPa (K 100) m3 0.80 0.018 0.80 0.018 0.00 0.000 0.80 0.018 100.00%
3 Ram difabel W ork m3 1.60 0.036 1.60 0.036 0.00 0.000 1.60 0.036 100.00%

B.2 ROOF WORKS


I. Roof Covering Works
1
Truss WF 150 x 75 x 5 x 7, complete kg 5,924.80 6.679 5924.80 6.679 0.00 0.000 5924.80 6.679 100.00%
2
Roof battens CNP 100.50.20.2,3 kg 6,602.64 8.005 6602.64 8.005 0.00 0.000 6602.64 8.005 100.00%
3
Sagrod dia 12 mm kg 181.94 0.205 181.94 0.205 0.00 0.000 181.94 0.205 100.00%
4
W ind tie rod dia. 14 mm, inc clam kg 449.14 0.506 449.14 0.506 0.00 0.000 449.14 0.506 100.00%
5
Span screw Tie rod ea 48.00 0.036 48.00 0.036 0.00 0.000 48.00 0.036 100.00%
6
Hollow steel truss for second skin kg 1,447.26 1.823 1447.26 1.823 0.00 0.000 1447.26 1.823 100.00%
7
W elding steel truss, all inc. rafter, battens and accessories cm 25,263.20 5.966 25263.20 5.966 0.00 0.000 25263.20 5.966 100.00%
8
Anchor bolt trus ɸ 3/4 " - 20 cm ea 128.00 0.504 128.00 0.504 0.00 0.000 128.00 0.504 100.00%
9
Zincalume spandex thk. 0,4 mm Installation m2 1,202.04 3.821 1202.04 3.821 0.00 0.000 1202.04 3.821 100.00%
10
Polycarbonat Roof installation m2 206.06 1.488 206.06 1.488 0.00 0.000 206.06 1.488 100.00%
11
Second skin, perforated plat 2.0 mm thk., d12 mm hole m2 138.40 3.595 138.40 3.595 0.00 0.000 138.40 3.595 100.00%
12
Zincalume spandex ridge m' 63.00 0.204 63.00 0.204 0.00 0.000 63.00 0.204 100.00%
13
Polycarbonat roof ridges m' 10.80 0.031 10.80 0.031 0.00 0.000 10.80 0.031 100.00%
14
Kalsiplank, finish Paint m' 380.56 1.162 380.56 1.162 0.00 0.000 380.56 1.162 100.00%
SUB TOTAL (B) 39.248 38.337 0.869 39.206
C. STRUCTURAL WORK
C.1. FOUNDATION WORK
1 Concrete foundation
- Foundation cutting m3 62.00 1.255 62.00 1.255 0.00 0.000 62.00 1.255 100.00%
- Sand layer t=10cm m3 4.00 0.015 4.00 0.015 0.00 0.000 4.00 0.015 100.00%
- Base concrete t=5 cm K-100 m3 2.00 0.045 2.00 0.045 0.00 0.000 2.00 0.045 100.00%
- Concrete K-250 m3 16.39 0.461 16.39 0.461 0.00 0.000 16.39 0.461 100.00%
- Reinforcement kg 2,342.10 1.165 2342.10 1.165 0.00 0.000 2342.10 1.165 100.00%
- Formwork m2 54.12 0.284 54.12 0.284 0.00 0.000 54.12 0.284 100.00%

2 Soil backfill m3 20.67 0.030 20.67 0.030 0.00 0.000 20.67 0.030 100.01%

C.2. 1ST LEVEL


1 K1 25/35 column
- Concrete K-250 m3 18.78 0.529 18.78 0.529 0.00 0.000 18.78 0.529 100.00%
- Reinforcement kg 5,200.51 2.586 5200.51 2.586 0.00 0.000 5200.51 2.586 100.00%
- Formwork column m2 125.20 1.100 125.20 1.100 0.00 0.000 125.20 1.100 100.00%

2 Sloof / Tie Beam 20/30


- Concrete K-250 m3 20.67 0.582 20.67 0.582 0.00 0.000 20.67 0.582 100.00%
- Reinforcement kg 4,117.94 2.048 4117.93 2.048 0.00 0.000 4117.93 2.048 100.00%
- Formwork sloof m2 112.20 0.626 112.20 0.626 0.00 0.000 112.20 0.626 100.00%

3 Beam 25/35
- Concrete K-250 m3 19.54 0.550 19.54 0.550 0.00 0.000 19.54 0.550 100.00%
- Reinforcement kg 3,881.16 1.930 3881.16 1.930 0.00 0.000 3881.16 1.930 100.00%
- Formwork sloof m2 106.02 0.954 106.02 0.954 0.00 0.000 106.02 0.954 100.00%

4 Floor Slab
- Soil fill for floor elevation m3 144.91 0.863 144.91 0.863 0.00 0.000 144.91 0.863 100.00%
- Sand layer t=10cm m3 82.81 0.300 82.81 0.300 0.00 0.000 82.81 0.300 100.00%
- Base concrete t=5 cm K-100 m3 46.11 1.039 46.11 1.039 0.00 0.000 46.11 1.039 100.00%
- Concrete K-250 m3 66.20 1.864 66.20 1.864 0.00 0.000 66.20 1.864 100.00%
- Reinforcement kg 1,833.91 0.912 1833.91 0.912 0.00 0.000 1833.91 0.912 100.00%
- Formwork m2 13.30 0.070 13.30 0.070 0.00 0.000 13.30 0.070 100.00%
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
5 Drainage and steel grating
- Foundation cutting m3 19.62 0.397 19.62 0.397 0.00 0.000 19.62 0.397 100.00%
- Brick W all 1:5 H=0,3 m m2 78.48 1.004 78.48 1.004 0.00 0.000 78.48 1.004 100.00%
- Mortar plaster work m2 130.80 0.250 130.80 0.250 0.00 0.000 130.80 0.250 100.00%
- Mortar Neat Plaster W ork m2 130.80 0.135 130.80 0.135 0.00 0.000 130.80 0.135 100.00%
- Concrete t=5 cm K-100 m3 13.08 0.295 13.08 0.295 0.00 0.000 13.08 0.295 100.00%
- Steel Grating m' 130.80 2.059 59.73 0.940 22.95 0.361 82.67 1.302 63.21%
SUB TOTAL (C) 23.347 22.228 0.361 22.590
D. ELECTRICAL WORKS
D.1. LOW VOLTAGE PANEL WORKS
Procurement and installation of a complete panel
1 MCB-Box of Los Type-A Market unit 2.00 0.005 0.00 0.000 0.00 0.000 0.00 0.000 0.00%

D.2. LIGHTING WORKS


Procurement, installation of lighting and sockets
1 TL Led 19 W Type unit 16.00 0.058 0.00 0.000 16.00 0.058 16.00 0.058 100.00%
2 Single Electrical Switch unit 2.00 0.004 0.00 0.000 2.00 0.004 2.00 0.004 100.00%
3 Double Electrical Switch unit 8.00 0.016 0.00 0.000 8.00 0.016 8.00 0.016 100.00%
4 100 W W all Electric Socket unit 4.00 0.007 0.00 0.000 4.00 0.007 4.00 0.007 100.00%
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pi point 16.00 0.258 0.00 0.000 16.00 0.258 16.00 0.258 100.00%
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of c point 14.00 0.182 0.00 0.000 14.00 0.182 14.00 0.182 100.00%

D.3. Lightning Rod Installation


Procurement, installation of a complete lightning rod
1 Ø 3/4 30cm Air Terminal , Completed W ith Ø 3/4 70cm GIP set 2.00 0.535 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
2 BC 25 mm² Cable Installation m 60.00 0.028 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
3 600mm² x 600mm² c/w Junction Box with Grounding Syste set 2.00 0.057 2.00 0.057 0.00 0.000 2.00 0.057 100.00%
4 Auxiliary Materials lot 2.00 0.031 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
SUB TOTAL (D) 1.182 0.057 0.525 0.582
TOTAL 67.208 63.836 1.756 65.592

Main Item W orks : Market-2 (Wet Area) Period : 29 November - 31 December 2021
Location : Sibado, Donggala District
Contractor : PT. Insan Cita Karya

Contract Actual Progress


No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
A PREPARATION WORK
1 Site Measurement and Bowplank Intallation m' 76.10 0.120 76.10 0.120 0.00 0.000 76.10 0.120 100.00%
2 Cleaning of field and leveling m2 172.20 0.077 172.20 0.077 0.00 0.000 172.20 0.077 100.00%
SUB TOTAL (A) 0.197 0.197 0.000 0.197
B ARCHITECTURAL WORKS
B.1 1ST LEVEL
I. Wallwork
1 Brick 1:5 (1,5) m2 7.08 0.091 7.08 0.091 0.00 0.000 7.08 0.091 100.00%
2 Mortar plaster work m2 52.20 0.100 52.20 0.100 0.00 0.000 52.20 0.100 100.00%
3 Mortar neat plaster work m2 52.20 0.054 52.20 0.054 0.00 0.000 52.20 0.054 100.00%

II. Painting Works


1 W all painting ; Exterior m2 39.00 0.038 0.00 0.000 39.00 0.038 39.00 0.038 100.00%
2 Listplank painting m2 16.21 0.050 16.21 0.050 0.00 0.000 16.21 0.050 100.00%
3 Steel Painting m2 141.33 0.124 141.33 0.124 0.00 0.000 141.33 0.124 100.00%

B.2 ROOF WORKS


I. Roof Covering Works
1
Truss IWF 150.75.5.7 mm, complete inc. connection kg 1,470.70 1.658 1470.70 1.658 0.00 0.000 1470.70 1.658 100.00%
2
Roof battens CNP 75 x 45 x 15 x 2,3 kg 614.89 0.745 614.89 0.745 0.00 0.000 614.89 0.745 100.00%
3
Column WF 250.125.6.9 mm kg 1,065.60 1.201 1065.60 1.201 0.00 0.000 1065.60 1.201 100.00%
4
W ind tie rod dia. 14 mm, inc clam kg 142.04 0.160 142.04 0.160 0.00 0.000 142.04 0.160 100.00%
5
Span screw Tie rod ea 20.00 0.015 20.00 0.015 0.00 0.000 20.00 0.015 100.00%
6
W elding steel truss, all inc. rafter, battens and accessories cm 6,006.00 1.418 6006.00 1.418 0.00 0.000 6006.00 1.418 100.00%
7
Anchor bolt trus ɸ 3/4 " - 20 cm ea 60.00 0.236 60.00 0.236 0.00 0.000 60.00 0.236 100.00%
8
Zincalume spandex thk 0,4 mm Installation m2 245.16 0.779 147.51 0.469 97.65 0.310 245.16 0.779 100.00%
9
Kalsiplank, finish Paint m' 81.06 0.248 81.06 0.248 0.00 0.000 81.06 0.248 100.00%
SUB TOTAL (B) 6.917 6.569 0.348 6.917
C. STRUCTURAL WORK
C.1. FOUNDATION WORK
1 Concrete foundation
- Foundation cutting m3 16.20 0.328 16.20 0.328 0.00 0.000 16.20 0.328 100.00%
- Sand layer t=10cm m3 1.20 0.004 1.20 0.004 0.00 0.000 1.20 0.004 100.00%
- Base concrete t=5 cm K-100 m3 0.60 0.014 0.60 0.014 0.00 0.000 0.60 0.014 100.00%
- Concrete K-250 m3 6.06 0.171 6.06 0.171 0.00 0.000 6.06 0.171 100.00%
- Reinforcement kg 909.10 0.452 909.10 0.452 0.00 0.000 909.10 0.452 100.00%
- Formwork m2 43.50 0.228 43.50 0.228 0.00 0.000 43.50 0.228 100.00%

2 Soil backfill m3 5.40 0.008 5.40 0.008 0.00 0.000 5.40 0.008 100.00%
3 Brick 1:4 (0.5) m2 38.05 0.178 38.05 0.178 0.00 0.000 38.05 0.178 100.00%
4 Brick 1:4 (1) m2 8.28 0.079 8.28 0.079 0.00 0.000 8.28 0.079 100.00%

C.2. 1ST LEVEL


1 Column 15/20
- Concrete K-250 m3 2.27 0.064 2.27 0.064 0.00 0.000 2.27 0.064 100.00%
- Reinforcement kg 321.87 0.160 321.87 0.160 0.00 0.000 321.87 0.160 100.00%
- Formwork column m2 13.75 0.121 13.75 0.121 0.00 0.000 13.75 0.121 100.00%

2 Floor Slab
- Soil fill for floor elevation m3 46.49 0.277 46.49 0.277 0.00 0.000 46.49 0.277 100.00%
- Sand layer t=10cm m3 17.22 0.062 17.22 0.062 0.00 0.000 17.22 0.062 100.00%
- Slab concrete t=8 cm K-250 m3 13.78 0.388 13.78 0.388 0.00 0.000 13.78 0.388 100.00%
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)

3 Fish Table
Beam 8/12
- Concrete K-250 m3 0.56 0.016 0.56 0.016 0.00 0.000 0.56 0.016 100.00%
- Reinforcement m3 328.43 0.163 328.43 0.163 0.00 0.000 328.43 0.163 100.00%
- Formwork sloof m3 8.22 0.074 8.22 0.074 0.00 0.000 8.22 0.074 100.00%

Deck Slab
- Concrete K-250 m3 1.85 0.052 1.85 0.052 0.00 0.000 1.85 0.052 100.00%
- Reinforcement m3 243.90 0.121 243.90 0.121 0.00 0.000 243.90 0.121 100.00%
- Formwork sloof m3 14.49 0.081 14.49 0.081 0.00 0.000 14.49 0.081 100.00%

Column 8/12
- Concrete K-250 m3 0.06 0.002 0.06 0.002 0.00 0.000 0.06 0.002 100.00%
- Reinforcement m3 42.49 0.021 42.49 0.021 0.00 0.000 42.49 0.021 100.00%
- Formwork sloof m3 0.84 0.007 0.84 0.007 0.00 0.000 0.84 0.007 100.00%

4 Drainage and steel grating


- Foundation cutting m3 4.14 0.084 4.14 0.084 0.00 0.000 4.14 0.084 100.00%
- Brick W all 1:5 H=0,3 m m2 26.88 0.344 26.88 0.344 0.00 0.000 26.88 0.344 100.00%
- Mortar plaster work m2 35.84 0.068 35.84 0.068 0.00 0.000 35.84 0.068 100.00%
- Mortar Neat Plaster W ork m2 35.84 0.037 35.84 0.037 0.00 0.000 35.84 0.037 100.00%
- Concrete t=5 cm K-100 m3 2.24 0.050 2.24 0.050 0.00 0.000 2.24 0.050 100.00%
- Steel Grating m' 44.80 0.705 20.46 0.322 0.00 0.000 20.46 0.322 45.66%
SUB TOTAL (C) 4.360 3.976 0.000 3.976
D. ELECTRICAL WORKS
D.1. LOW VOLTAGE PANEL WORKS
Procurement and installation of a complete panel
1 MCB-Box of Los Type-A Market unit 1.00 0.003 0.00 0.000 0.00 0.000 0.00 0.000 0.00%

D.2. LIGHTING WORKS


Procurement, installation of lighting and sockets
1 Roset Led 19 W Type Bulb unit 6.00 0.022 0.00 0.000 6.00 0.022 6.00 0.022 100.00%
2 Single Electrical Switch unit 2.00 0.004 0.00 0.000 2.00 0.004 2.00 0.004 100.00%
3 Double Electrical Switch unit 2.00 0.004 0.00 0.000 2.00 0.004 2.00 0.004 100.00%
4 100 W W all Electric Socket unit 2.00 0.003 0.00 0.000 2.00 0.003 2.00 0.003 100.00%
5 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pi point 6.00 0.097 0.00 0.000 6.00 0.097 6.00 0.097 100.00%
6 Electrical Socket NYM 3x2,5 mm² Installation in 20 mm of c point 6.00 0.097 0.00 0.000 6.00 0.097 6.00 0.097 100.00%
SUB TOTAL (D) 0.229 0.000 0.226 0.226
TOTAL 11.703 10.742 0.574 11.317

Main Item W orks : Toilet Period : ###########


Location : Sibado, Donggala District
Contractor : PT. Insan Cita Karya

Contract Actual Progress


No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
A PREPARATION WORK
1 Site Measurement and Bowplank Installation m' 49.00 0.077 49.00 0.077 0.00 0.000 49.00 0.077 100.00%
2 Cleaning of field and leveling m2 33.00 0.015 33.00 0.015 0.00 0.000 33.00 0.015 100.00%
SUB TOTAL (A) 0.092 0.092 0.000 0.092
B ARCHITECTURAL WORKS
B.1 1ST FLOOR
I. Wallwork
1 Brick W all 1:3 m2 34.94 0.167 34.94 0.167 0.00 0.000 34.94 0.167 100.00%
2 Brick W all 1:5 m2 48.63 0.224 48.63 0.224 0.00 0.000 48.63 0.224 100.00%
3 Mortar Plaster W ork m2 189.66 0.362 189.66 0.362 0.00 0.000 189.66 0.362 100.00%
4 Mortar Neat Plaster W ork m2 145.76 0.151 145.76 0.151 0.00 0.000 145.76 0.151 100.00%
5 20x20 Tile work m2 43.94 0.229 43.94 0.229 0.00 0.000 43.94 0.229 100.00%
6 Glass wall / Boven Light roster m2 0.96 0.001 0.96 0.001 0.00 0.000 0.96 0.001 100.00%
7 Roster m2 3.84 0.053 3.84 0.053 0.00 0.000 3.84 0.053 100.00%

II. Floor Installation Work


1 40x40 cm of Ceramic Tile m2 11.29 0.057 11.29 0.057 0.00 0.000 11.29 0.057 100.00%
2 20x20 cm of Ceramic Tile m2 17.28 0.090 17.28 0.090 0.00 0.000 17.28 0.090 100.00%
3 W aterproofing Coating + mortar m2 17.28 0.051 17.28 0.051 0.00 0.000 17.28 0.051 100.00%

III. Painting Works


1 W all ; Interior m2 45.26 0.044 0.00 0.000 41.15 0.040 41.15 0.040 90.91%
2 W all Painting; Exterior m2 100.50 0.097 0.00 0.000 100.50 0.097 100.50 0.097 100.00%
3 Ceiling Painting m2 43.81 0.042 0.00 0.000 43.81 0.042 43.81 0.042 100.00%
3 Lisplank Painting m2 8.15 0.025 0.00 0.000 8.15 0.025 8.15 0.025 100.00%

IV. Sanitary Work and Installation


Sanitary work includes procurement & installation
1 Squatting Closet Unit 4.00 0.107 4.00 0.107 0.00 0.000 4.00 0.107 100.00%
2 Sitting Toilet Unit 2.00 0.129 2.00 0.129 0.00 0.000 2.00 0.129 100.00%
3 Shower spray Unit 2.00 0.008 2.00 0.008 0.00 0.000 2.00 0.008 100.00%
4 Handrail Stainless; Diffable Unit 2.00 0.047 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
5 Faucet Unit 6.00 0.024 6.00 0.024 0.00 0.000 6.00 0.024 100.00%
6 Floor Drain Unit 6.00 0.040 6.00 0.040 0.00 0.000 6.00 0.040 100.00%
7 Fibre Basin 0,30 m3 Unit 6.00 0.326 6.00 0.326 0.00 0.000 6.00 0.326 100.00%

V. Door and Window Installation Work (complete w. wooden frame)


1 Door Installation W ork (type P1) Unit 4.00 0.047 4.00 0.047 0.00 0.000 4.00 0.047 100.00%
2 Door Installation W ork (type P2) Unit 2.00 0.024 2.00 0.024 0.00 0.000 2.00 0.024 100.00%

VI. Ceiling Installation Work


1 6 mm of Calcium Board; hollow frame m2 43.81 0.064 43.88 0.064 0.00 0.000 43.88 0.064 100.15%
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
VII. Other Works
Disability Ramp Work
1 Disability Handrail Ramp work m 11.72 0.277 0.00 0.000 11.72 0.277 11.72 0.277 100.00%
2 Ram difabel W ork m3 1.04 0.023 1.04 0.023 0.00 0.000 1.04 0.023 100.00%
3 Lean concrete ramp fc'= 9.8 MPa (K 125) m3 1.04 0.025 1.04 0.025 0.00 0.000 1.04 0.025 100.00%

B.2 ROOF WORKS


I. Roof Covering Works
1 Zincalume spandex thk. 0,40 mm installation m2 48.64 0.155 48.64 0.155 0.00 0.000 48.64 0.155 100.00%
2 Light steel frame; including rafter and accessoris m2 48.64 0.299 48.64 0.299 0.00 0.000 48.64 0.299 100.00%
3 Calsiplank list m 40.80 0.125 40.80 0.125 0.00 0.000 40.80 0.125 100.00%
SUB TOTAL (B) 3.313 2.781 0.481 3.262
C STRUCTURAL WORK
I. FOUNDATION WORK
1 Foundation 1
- Foundation Cutting m3 27.22 0.551 27.22 0.551 0.00 0.000 27.22 0.551 100.00%
- Sand layer t=10cm m3 3.02 0.011 3.02 0.011 0.00 0.000 3.02 0.011 100.00%
- Anstamping Stone H=15cm m3 4.54 0.043 4.54 0.043 0.00 0.000 4.54 0.043 100.00%
- Masonry 1:4 m3 11.21 0.052 11.21 0.052 0.00 0.000 11.21 0.052 100.00%
- Backfill m3 9.07 0.013 9.07 0.013 0.00 0.000 9.07 0.013 100.00%

2 Foundation 2 (terrace)
- Foundation Cutting m3 0.32 0.007 0.32 0.007 0.00 0.000 0.32 0.007 100.00%
- Concrete K-175 m3 0.87 0.022 0.87 0.022 0.00 0.000 0.87 0.022 100.00%

3 Sloof 13/20
- Concrete K-250 m3 0.94 0.026 0.94 0.026 0.00 0.000 0.94 0.026 100.00%
- Reinforcement kg 421.35 0.210 421.35 0.210 0.00 0.000 421.35 0.210 100.00%
- Foundation formwork m2 3.20 0.018 3.20 0.018 0.00 0.000 3.20 0.018 100.00%

II. 1ST LEVEL


1 130x130 Column K1
- K-250 Concrete m3 0.76 0.022 0.76 0.022 0.00 0.000 0.76 0.022 100.00%
- Reinforcement kg 268.93 0.134 268.93 0.134 0.00 0.000 268.93 0.134 100.00%
- Column Formwork m2 11.75 0.103 11.75 0.103 0.00 0.000 11.75 0.103 100.00%

2 13/20 Beam B1
- Concrete K-250 m3 0.94 0.026 0.94 0.026 0.00 0.000 0.94 0.026 100.00%
- Reinforcement kg 230.28 0.115 230.28 0.115 0.00 0.000 230.28 0.115 100.00%
- Beam Formwork m2 9.54 0.086 9.54 0.086 0.00 0.000 9.54 0.086 100.00%
SUB TOTAL (C) 1.439 1.439 0.000 1.439
D MECHANICAL AND ELECTRICAL WORKS
I. TOILET PLUMBING WORKS

1.1 CLEAN WATER SYSTEM


Procurement and installation of PPR-PN 10 Pipes
a. Toilet 1 Clean Water Piping and Its Completeness
1 PPR PN-10 Ø 25 mm m 23.50 0.014 23.50 0.014 0.00 0.000 23.50 0.014 100.00%
2 Fitting ls 2.00 0.003 2.00 0.003 0.00 0.000 2.00 0.003 100.00%
3 Gate Valve Ø 32mm unit 2.00 0.001 2.00 0.001 0.00 0.000 2.00 0.001 100.00%

1.2 VENT AND GREY WATER SYSTEM


Procurement and installation of PVC Pipes
Grey Water Piping and Its completeness in toilet to Sepictank
1 PVC-AW Ø 100 mm; SW (Sewage W ater) m 27.50 0.087 27.50 0.087 0.00 0.000 27.50 0.087 100.00%
2 PVC-AW Ø 80 mm; WW (W aste W ater) m 26.00 0.051 26.00 0.051 0.00 0.000 26.00 0.051 100.00%
3 PVC-D Ø 40 mm; VT (Vent) m 4.00 0.002 4.00 0.002 0.00 0.000 4.00 0.002 100.00%
4 Floor Clean Out Ø 80 mm, WW (W aste W ater) unit 6.00 0.012 6.00 0.012 0.00 0.000 6.00 0.012 100.00%
5 Floor Clean Out Ø 100 mm, SW (Sewage W ater) unit 6.00 0.019 6.00 0.019 0.00 0.000 6.00 0.019 100.00%
6 Fitting ls 2.00 0.007 2.00 0.007 0.00 0.000 2.00 0.007 100.00%

1.3 DRAINAGE PIPE SYSTEM TO INFILTRATION WELL


Procurement and installation of PVC Pipes
a. PVC-AW Ø 80 mm; PAH m 8.00 0.070 8.00 0.070 0.00 0.000 8.00 0.070 100.00%

b. Junction Box
Size : dia. of 600 mm x depth adjusted to inlet level of the unit 2.00 0.472 2.00 0.472 0.00 0.000 2.00 0.472 100.00%

2 TOILET ELECTRICAL WORKS


2.1 PANEL WORKS
Procurement & Installation
NYM 3x2,5 mm² Lamp Installation in 20 mmi conduit pipe m 50.00 0.805 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
of MCB-BOX from Market MCB-BOX to Toilet

2.2 LIGHTING WORKS


Procurement, installation of lighting
1 Roset Led 5 W Type Bulb (Toilet) unit 8.00 0.029 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
2 Double Electrical Switch unit 2.00 0.004 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
3 Single Electrical Switch unit 6.00 0.011 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
4 Lighting NYM 3x2,5 mm² Installation in 20 mm of conduit pi point 16.00 0.258 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
SUB TOTAL (D) 1.846 0.739 0.000 0.739
TOTAL 6.690 5.050 0.481 5.531

Main Item W orks : Septicktank Period : ###########


Location : Sibado, Donggala District
Contractor : PT. Insan Cita Karya

Contract Actual Progress


No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)

1 Ground W ork
- STP Foundation Cutting m3 19.15 0.388 19.15 0.388 0.00 0.000 19.15 0.388 100.00%
- Backfill m3 6.38 0.009 6.38 0.009 0.00 0.000 6.38 0.009 100.00%
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)

2 W all SPT
- Sand layer t=10cm m3 1.14 0.004 1.14 0.004 0.00 0.000 1.14 0.004 100.00%
- Brick wall 1:5 m3 39.32 0.181 39.32 0.181 0.00 0.000 39.32 0.181 100.00%
- Mortar Plaster W ork m2 39.32 0.075 39.32 0.075 0.00 0.000 39.32 0.075 100.00%
- Mortar Neat Plaster W ork m2 39.32 0.041 39.32 0.041 0.00 0.000 39.32 0.041 100.00%
- K-100 Concrete LC m3 1.44 0.032 1.44 0.032 0.00 0.000 1.44 0.032 100.00%

3 Concrete Column
- K-250 Concrete m3 1.79 0.051 1.79 0.051 0.00 0.000 1.79 0.051 100.00%
- Reinforcement kg 76.03 0.038 76.03 0.038 0.00 0.000 76.03 0.038 100.00%
- Column Formwork m2 19.80 0.174 19.80 0.174 0.00 0.000 19.80 0.174 100.00%

4 Concrete Slab
- K-250 Concrete m3 1.13 0.032 1.13 0.032 0.00 0.000 1.13 0.032 100.00%
- Reinforcement kg 93.58 0.047 93.58 0.047 0.00 0.000 93.58 0.047 100.00%
- Sloof Formwork m2 11.38 0.102 11.38 0.102 0.00 0.000 11.38 0.102 100.00%

5 Install PVC 2" Pipe m 4.00 0.052 4.00 0.052 0.00 0.000 4.00 0.052 100.00%
Install PVC 3" Pipe m 18.00 0.256 18.00 0.256 0.00 0.000 18.00 0.256 100.00%
Install Tee 3" unit 12.00 0.120 12.00 0.120 0.00 0.000 12.00 0.120 100.00%

6 Install Manhole (Inc. handel)


- K-250 Concrete m3 0.53 0.015 0.53 0.015 0.00 0.000 0.53 0.015 100.00%
- Reinforcement kg 63.50 0.032 63.50 0.032 0.00 0.000 63.50 0.032 100.00%
- Formwork m2 3.84 0.035 3.84 0.035 0.00 0.000 3.84 0.035 100.00%

7 Junction Box (0.5x0.5x0.5 m) with manhole cover Lot 2.00 0.031 2.00 0.031 0.00 0.000 2.00 0.031 100.00%

8 Infiltration
- Cutting (2 m depth) m3 6.28 0.127 6.28 0.127 0.00 0.000 6.28 0.127 100.00%
- Install concrete pipa (buis beton) dia. 1 m m' 8.00 0.161 8.00 0.161 0.00 0.000 8.00 0.161 100.00%
- Install pipe PVC 3" (inc. accesories) m 4.00 0.050 4.00 0.050 0.00 0.000 4.00 0.050 100.00%
- Install Manhole cover (inc. handel) m3 0.31 0.009 0.31 0.009 0.00 0.000 0.31 0.009 100.00%
- Reinforecement Manhole (sumur resapan) kg 43.98 0.890 43.98 0.890 0.00 0.000 43.98 0.890 100.00%
- Formwork m2 1.00 0.009 1.00 0.009 0.00 0.000 1.00 0.009 100.00%
- Gravel and sand filter m3 0.79 0.006 0.79 0.006 0.00 0.000 0.79 0.006 100.00%
- Sarang tawon / Bio Media Filter m3 2.40 0.017 2.40 0.017 0.00 0.000 2.40 0.017 100.00%

TOTAL 2.983 2.983 0.000 2.983

Main Item W orks : Site Plan Period : ###########


Location : Sibado, Donggala District
Contractor : PT. Insan Cita Karya

Contract Actual Progress


No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)

A. SITEPLAN PLUMBING WORKS


1.1 MAIN EQUIPMENTS OF CLEAN WATER SYSTEM
Pipeline procurement and installation include excavation, accessories, and auxiliary equipment
a. Piping and accessories
1 12 m water shalow well Ls 1.00 0.236 1.00 0.236 0.00 0.000 1.00 0.236 100.00%

b. Clean Water Oump


1 Type : Jet Pump, shallow water pump Ls 1.00 0.110 1.00 0.110 0.00 0.000 1.00 0.110 100.00%
Capacity : 20 Lpm -
Suction Head : 10 m
Discharge Head : 31 m
Output Power : 0.125 Kw
Installed complete with W LC (water level control), holder, support etc. according to specifications and drawing

c. Piping from Jet Pump to water tank


1 PPR PN-10 Ø 40 mm m 18.80 0.011 18.80 0.011 0.00 0.000 18.80 0.011 100.00%
2 Gate Valve Ø 40mm unit 1.00 0.002 1.00 0.002 0.00 0.000 1.00 0.002 100.00%
3 Check Valve Ø 40mm unit 1.00 0.002 1.00 0.002 0.00 0.000 1.00 0.002 100.00%
4 Fitting ls 1.00 0.002 1.00 0.002 0.00 0.000 1.00 0.002 100.00%

d. Tower Tank
1 Type : Fibreglass Capacity : 1 m3 unit 2.00 0.158 2.00 0.158 0.00 0.000 2.00 0.158 100.00%
2 Rooftank work c/w W ater Tower 4 meters high unit 1.00 0.472 1.00 0.472 0.00 0.000 1.00 0.472 100.00%
(incl. foundation)

1.2 CLEAN WATER SYSTEM


Procurement and installation of PPR-PN 10 Pipes including excavation, accessories, and auxiliary equipment
a. Piping and accessories from the Tank to toilet - 1
1 PPR PN-10 Ø 40 mm m 10.00 0.006 10.00 0.006 0.00 0.000 10.00 0.006 100.00%
2 Fitting ls 1.00 0.002 1.00 0.002 0.00 0.000 1.00 0.002 100.00%
3 Gate Valve Ø 32mm unit 1.00 0.000 1.00 0.000 0.00 0.000 1.00 0.000 100.00%

b. Piping and accessories from the Tank to toilet - 2


1 PPR PN-10 Ø 40 mm m 45.00 0.027 45.00 0.027 0.00 0.000 45.00 0.027 100.00%
2 Fitting ls 1.00 0.002 1.00 0.002 0.00 0.000 1.00 0.002 100.00%
3 Gate Valve Ø 32mm unit 1.00 0.000 1.00 0.000 0.00 0.000 1.00 0.000 100.00%

1.3 VENT AND GREY WATER SYSTEM


Procurement and installation of PVC Pipes including excavation, accessories, and auxiliary tool
a. Grey Water Piping and accessories to Sepictank.1
1 PVC-AW Ø 100 mm; SW (Sewage W ater) m 5.00 0.016 5.00 0.016 0.00 0.000 5.00 0.016 100.00%
2 PVC-AW Ø 80 mm; WW (W aste W ater) m 5.00 0.010 5.00 0.010 0.00 0.000 5.00 0.010 100.00%
3 Fitting ls 1.00 0.003 1.00 0.003 0.00 0.000 1.00 0.003 100.00%
SUB TOTAL (A) 1.059 1.059 0.000 1.059
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
B. SITE PLAN ELECTRICAL WORKS
B.1 LOW VOLTAGE PANEL WORK
Procurement and installation of Panel unit 1.00 0.110 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
Market Main Panel

New Installation of PLN


Connecting Fee VA 1.00 0.315 1.00 0.315 0.00 0.000 1.00 0.315 100.00%
Deposit Money VA 1.00 0.079 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
SLO (Certificate of Eligibility for Operation) (adjusted for rat VA 1.00 0.079 0.00 0.000 0.00 0.000 0.00 0.000 0.00%

B.2 CONNECTOR CABLE PROVISION AND INSTALLATION


The work of procurement, installation and testing Low Voltage Cable ;
From Main Panel to MCB-BOX.1, NYY 3 x 6 mm² + BC 6m m 10.00 0.118 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
From Main Panel to MCB-BOX.2, NYY 3 x 4 mm² + BC 6m m 8.00 0.094 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
From Main Panel to MCB-BOX.3, NYY 3 x 4 mm² + BC 6m m 20.00 0.236 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
From Main Panel to MCB-BOX.4, NYY 3 x 4 mm² + BC 6m m 10.00 0.118 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
From Main Panel to MCB-BOX.5, NYY 3 x 4 mm² + BC 6m m 20.00 0.236 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
From MCB-BOX.1 to Jet Pump, NYY 3 x 4 mm² + BC 6mm m 5.00 0.059 0.00 0.000 0.00 0.000 0.00 0.000 0.00%

B.3 LIGHTING POLE


Ligthing pole (solar cell) complete with founfation ea 4.00 0.945 0.00 0.000 3.64 0.859 3.64 0.859 90.91%

B.4 TESTING & COMMISSIONING


A Testing and setting the installation until it functions properly Lot 1.00 0.079 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
SUB TOTAL (B) 2.465 0.315 0.859 1.174
C. SITE, PAVING AND FENCE WORKS
1 Entrance stair
- Foundation Cutting m3 7.65 0.155 7.65 0.155 0.00 0.000 7.65 0.155 100.00%
- Sand layer t=10cm m3 3.06 0.011 3.06 0.011 0.00 0.000 3.06 0.011 100.00%
- Anstamping Stone H=15cm m3 4.59 0.044 4.59 0.044 0.00 0.000 4.59 0.044 100.00%
- Masonry 1:4 m3 24.63 0.115 24.63 0.115 0.00 0.000 24.63 0.115 100.00%
- Backfill m3 2.55 0.004 2.55 0.004 0.00 0.000 2.55 0.004 100.00%
- Mortar Plaster W ork m2 57.60 0.097 57.60 0.097 0.00 0.000 57.60 0.097 100.00%
- Mortar Neat Plaster W ork m2 57.60 0.060 57.60 0.060 0.00 0.000 57.60 0.060 100.00%
- K-125 Concrete m3 31.66 0.751 31.66 0.751 0.00 0.000 31.66 0.751 100.00%

2 Difabel ram work


- Masonry 1:4 m3 24.86 0.116 24.86 0.116 0.00 0.000 24.86 0.116 100.00%
- Disability Handrail Ramp work m 27.00 0.638 22.50 0.531 4.50 0.106 27.00 0.638 100.00%
- Lean concrete ramp fc'= 7.4 MPa (K 100) m3 2.34 0.053 2.34 0.053 0.00 0.000 2.34 0.053 100.00%
- K-150 Concrete m3 2.34 0.058 2.34 0.058 0.00 0.000 2.34 0.058 100.00%

3 Road access and site cleaning


- Selected embankment / road gravel (CBR 75%) 15 cm th m3 329.88 1.541 274.90 1.284 0.00 0.000 274.90 1.284 83.33%
- Masonry 1:4 inc. voeg plaster m3 28.90 0.214 28.90 0.214 0.00 0.000 28.90 0.214 100.00%
- Cut and fill, cleaning & leveling site m2 4,334.80 1.945 4334.80 1.945 0.00 0.000 4334.80 1.945 100.00%

4 Additional area open los (24m x 3 m x 2)


- Sand layer t=10cm m3 14.40 0.052 14.40 0.052 0.00 0.000 14.40 0.052 100.00%
- Lean concrete ramp fc'= 7.4 MPa (K 100) m3 9.60 0.216 9.60 0.216 0.00 0.000 9.60 0.216 100.00%
- K-250 Concrete Slab, t=10cm m3 19.20 0.540 19.20 0.540 0.00 0.000 19.20 0.540 100.00%

5 Fence:
- Foundation Cutting m3 8.70 0.176 8.70 0.176 0.00 0.000 8.70 0.176 100.00%
- Sand layer t=10cm m3 1.74 0.006 1.74 0.006 0.00 0.000 1.74 0.006 100.00%
- Anstamping Stone H=15cm m3 2.61 0.025 2.61 0.025 0.00 0.000 2.61 0.025 100.00%
- Masonry 1:4 m3 7.61 0.036 7.61 0.036 0.00 0.000 7.61 0.036 100.00%
- Backfill m3 2.90 0.004 2.90 0.004 0.00 0.000 2.90 0.004 100.00%
- Mortar Plaster W ork m2 58.00 0.098 0.00 0.000 58.00 0.098 58.00 0.098 100.00%
- Mortar Neat Plaster W ork m2 58.00 0.060 0.00 0.000 58.00 0.060 58.00 0.060 100.00%
- K-250 Concrete m3 0.65 0.018 0.65 0.018 0.00 0.000 0.65 0.018 100.00%
- Reinforcement kg 116.09 0.058 116.09 0.058 0.00 0.000 116.09 0.058 100.00%
- Column Formwork m2 3.30 0.029 3.30 0.029 0.00 0.000 3.30 0.029 100.00%
- Roster m2 5.00 0.068 5.00 0.068 0.00 0.000 5.00 0.068 100.00%
SUB TOTAL (C) 7.188 6.667 0.264 6.931
D. GARBAGE BOX AND SLAB
1 Concrete slab for garbage truck
- Sand layer t=10cm m3 1.75 0.006 1.75 0.006 0.00 0.000 1.75 0.006 100.00%
- Base concrete t=8 cm K-100 m3 0.88 0.020 0.88 0.020 0.00 0.000 0.88 0.020 100.00%
- K-250 Concrete m3 2.10 0.059 2.10 0.059 0.00 0.000 2.10 0.059 100.00%
- Reinforcement kg 142.10 0.071 142.10 0.071 0.00 0.000 142.10 0.071 100.00%
- Formwork m2 1.02 0.005 1.02 0.005 0.00 0.000 1.02 0.005 100.00%

2 Garbage Box / Trush Bin


- Foundation Cutting m3 2.69 0.054 2.69 0.054 0.00 0.000 2.69 0.054 100.00%
- Sand layer t=10cm m3 0.90 0.003 0.90 0.003 0.00 0.000 0.90 0.003 100.00%
- Anstamping Stone H=15cm m3 1.34 0.013 1.34 0.013 0.00 0.000 1.34 0.013 100.00%
- Masonry 1:4 m3 2.08 0.010 2.08 0.010 0.00 0.000 2.08 0.010 100.00%
- Backfill m3 0.90 0.001 0.90 0.001 0.00 0.000 0.90 0.001 100.00%
- Soil fill for floor elevation m3 2.00 0.012 2.00 0.012 0.00 0.000 2.00 0.012 100.00%
- Brick wall 1:5 m2 15.40 0.071 15.40 0.071 0.00 0.000 15.40 0.071 100.00%
- Mortar Plaster W ork m2 30.80 0.052 30.80 0.052 0.00 0.000 30.80 0.052 100.00%
- Mortar Neat Plaster W ork m2 30.80 0.032 30.80 0.032 0.00 0.000 30.80 0.032 100.00%
- K-175 Concrete m3 1.24 0.032 1.24 0.032 0.00 0.000 1.24 0.032 100.00%
- Reinforcement kg 128.55 0.064 128.55 0.064 0.00 0.000 128.55 0.064 100.00%
- Column Formwork m2 4.80 0.042 4.80 0.042 0.00 0.000 4.80 0.042 100.00%
- Cover Ls 1.00 0.157 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
SUB TOTAL (D) 0.705 0.548 0.000 0.548
TOTAL 11.418 8.589 1.123 9.712

You might also like