Professional Documents
Culture Documents
The Sulawesi Programme for Earthquake and Tsunami Infrastructure Reconstruction Assistance (PETRA)
Construction Supervision For 2 (Two) Publik Market Omu - Sigi District and Sibado - Donggala District
RECAPITULATION
Location : Omu, Sigi District and Period : 29 November - 31 December 2021
: Sibado, Donggala District
Contractor : PT. Insan Cita Karya
Actual Progress
Contract Up To This
No. Work Description Previous This Week Remarks
Week
Contain (%) Contain (%) Contain (%) Contain (%)
1 MARKET -1 (DRY AREA)
A PREPARATION WORK 4.59 4.33 0.13 4.46
B ARCHITECTURAL WORKS 45.48 45.16 - 45.16
C STRUCTURAL WORK 26.91 26.91 - 26.91
D ELECTRICAL WORKS 1.15 0.31 0.21 0.51
Sub Total 1 78.13 76.72 0.33 77.05
2 TOILET
A PREPARATION WORK 0.11 0.11 - 0.11
B ARCHITECTURAL WORKS 3.32 2.89 0.05 2.94
C STRUCTURAL WORK 1.62 1.62 - 1.62
D MECHANICAL AND ELECTRICAL WORKS 1.33 0.38 0.25 0.64
Sub Total 2 6.38 5.01 0.30 5.31
3 SEPTICKTANK Sub Total 3 3.49 3.49 - 3.49
4 SITE PLAN
A SITEPLAN PLUMBING WORKS 0.85 0.85 - 0.85
B SITE PLAN ELECTRICAL WORKS 2.58 0.92 - 0.92
C SITE WORK, PAVING AND FENCE WORKS 6.07 5.51 0.56 6.07
D GARBAGE BOX AND SLAB 0.83 0.72 - 0.72
E DRAINAGE 1.68 1.68 - 1.68
Sub Total 4 12.01 9.68 0.56 10.24
TOTAL 100.00 94.89 1.19 96.08
Main Item W orks : Market-1 (Dry Area) Period : 29 November - 31 December 2021
Location : Omu, Sigi District
Contractor : PT. Insan Cita Karya
2 Soil backfill m3 20.67 0.035 20.67 0.035 0.00 0.000 20.67 0.035 100.00%
3 Beam 25/35
- Concrete K-250 m3 19.54 0.661 19.54 0.661 0.00 0.000 19.54 0.661 100.00%
- Reinforcement kg 3,881.16 2.060 3881.16 2.060 0.00 0.000 3881.16 2.060 100.00%
- Formwork sloof m2 106.02 1.028 106.02 1.028 0.00 0.000 106.02 1.028 100.00%
4 Floor Slab
- Soil fill for floor elevation m3 144.91 1.102 144.91 1.102 0.00 0.000 144.91 1.102 100.00%
- Sand layer t=10cm m3 82.81 0.478 82.81 0.478 0.00 0.000 82.81 0.478 100.00%
- Base concrete t=5 cm K-100 m3 46.11 1.260 46.11 1.260 0.00 0.000 46.11 1.260 100.00%
- Concrete K-250 m3 66.20 2.241 66.20 2.241 0.00 0.000 66.20 2.241 100.00%
- Reinforcement kg 1,833.91 0.973 1833.91 0.973 0.00 0.000 1833.91 0.973 100.00%
- Formwork m2 13.30 0.134 13.30 0.134 0.00 0.000 13.30 0.134 100.00%
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
5 Drainage and steel grating
- Foundation cutting m3 19.62 0.463 19.62 0.463 0.00 0.000 19.62 0.463 100.00%
- Brick W all 1:5 H=0,3 m m2 78.48 1.220 78.48 1.220 0.00 0.000 78.48 1.220 100.00%
- Mortar plaster work m2 130.80 0.292 130.80 0.292 0.00 0.000 130.80 0.292 100.00%
- Mortar Neat Plaster W ork m2 130.80 0.158 130.80 0.158 0.00 0.000 130.80 0.158 100.00%
- Concrete t=5 cm K-100 m3 13.08 0.357 13.08 0.357 0.00 0.000 13.08 0.357 100.00%
- Steel Grating m' 130.80 2.401 130.80 2.401 0.00 0.000 130.80 2.401 100.00%
SUB TOTAL (C) 26.910 26.910 0.000 26.910
D. ELECTRICAL WORKS
D.1. LOW VOLTAGE PANEL WORKS
Procurement and installation of a complete panel
1 MCB-Box of Los Type-A Market unit 2.00 0.020 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
2 Foundation 2 (terrace)
- Foundation Cutting m3 0.32 0.008 0.32 0.008 0.00 0.000 0.32 0.008 100.00%
- Concrete K-175 m3 0.87 0.027 0.87 0.027 0.00 0.000 0.87 0.027 100.00%
3 Sloof 13/20
- Concrete K-250 m3 0.94 0.032 0.94 0.032 0.00 0.000 0.94 0.032 100.00%
- Reinforcement kg 421.35 0.224 421.35 0.224 0.00 0.000 421.35 0.224 100.00%
- Foundation formwork m2 3.20 0.020 3.20 0.020 0.00 0.000 3.20 0.020 100.00%
2 13/20 Beam B1
- Concrete K-250 m3 0.94 0.032 0.94 0.032 0.00 0.000 0.94 0.032 100.00%
- Reinforcement kg 230.28 0.122 230.28 0.122 0.00 0.000 230.28 0.122 100.00%
- Beam Formwork m2 9.54 0.093 9.54 0.093 0.00 0.000 9.54 0.093 100.00%
SUB TOTAL (C) 1.623 1.623 0.000 1.623
D MECHANICAL AND ELECTRICAL WORKS
I. TOILET PLUMBING WORKS
b. Junction Box
Size : dia. of 600 mm x depth adjusted to inlet level of the unit 2.00 0.073 2.00 0.073 0.00 0.000 2.00 0.073 100.00%
1 Ground W ork
- STP Foundation Cutting m3 19.15 0.452 19.15 0.452 0.00 0.000 19.15 0.452 100.00%
- Backfill m3 6.38 0.011 6.38 0.011 0.00 0.000 6.38 0.011 100.00%
2 W all SPT
- Sand layer t=10cm m3 1.14 0.007 1.14 0.007 0.00 0.000 1.14 0.007 100.00%
- Brick wall 1:5 m3 39.32 0.219 39.32 0.219 0.00 0.000 39.32 0.219 100.00%
- Mortar Plaster W ork m2 39.32 0.088 39.32 0.088 0.00 0.000 39.32 0.088 100.00%
- Mortar Neat Plaster W ork m2 39.32 0.047 39.32 0.047 0.00 0.000 39.32 0.047 100.00%
- K-100 Concrete LC m3 1.44 0.039 1.44 0.039 0.00 0.000 1.44 0.039 100.00%
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
3 Concrete Column
- K-250 Concrete m3 1.79 0.061 1.79 0.061 0.00 0.000 1.79 0.061 100.00%
- Reinforcement kg 76.03 0.040 76.03 0.040 0.00 0.000 76.03 0.040 100.00%
- Column Formwork m2 19.80 0.185 19.80 0.185 0.00 0.000 19.80 0.185 100.00%
4 Concrete Slab
- K-250 Concrete m3 1.13 0.038 1.13 0.038 0.00 0.000 1.13 0.038 100.00%
- Reinforcement kg 93.58 0.050 93.58 0.050 0.00 0.000 93.58 0.050 100.00%
- Sloof Formwork m2 11.38 0.110 11.38 0.110 0.00 0.000 11.38 0.110 100.00%
5 Install PVC 2" Pipe m 4.00 0.061 4.00 0.061 0.00 0.000 4.00 0.061 100.00%
Install PVC 3" Pipe m 18.00 0.299 18.00 0.299 0.00 0.000 18.00 0.299 100.00%
Install Tee 3" unit 12.00 0.140 12.00 0.140 0.00 0.000 12.00 0.140 100.00%
7 Junction Box (0.5x0.5x0.5 m) with manhole cover Lot 2.00 0.073 2.00 0.073 0.00 0.000 2.00 0.073 100.00%
8 Infiltration
- Cutting (2 m depth) m3 6.28 0.148 6.28 0.148 0.00 0.000 6.28 0.148 100.00%
- Install concrete pipa (buis beton) dia. 1 m m' 8.00 0.188 8.00 0.188 0.00 0.000 8.00 0.188 100.00%
- Install pipe PVC 3" (inc. accesories) m 4.00 0.058 4.00 0.058 0.00 0.000 4.00 0.058 100.00%
- Install Manhole cover (inc. handel) m3 0.31 0.011 0.31 0.011 0.00 0.000 0.31 0.011 100.00%
- Reinforecement Manhole (sumur resapan) kg 43.98 1.038 43.98 1.038 0.00 0.000 43.98 1.038 100.00%
- Formwork m2 1.00 0.010 1.00 0.010 0.00 0.000 1.00 0.010 100.00%
- Gravel and sand filter m3 0.79 0.007 0.79 0.007 0.00 0.000 0.79 0.007 100.00%
- Sarang tawon / Bio Media Filter m3 2.40 0.020 2.40 0.020 0.00 0.000 2.40 0.020 100.00%
d. Tower Tank
1 Type : Fibreglass Capacity : 1 m3 unit 2.00 0.129 2.00 0.129 0.00 0.000 2.00 0.129 100.00%
2 Rooftank work c/w W ater Tower 4 meters high unit 1.00 0.275 1.00 0.275 0.00 0.000 1.00 0.275 100.00%
(incl. foundation)
Actual Progress
Contract Up To This
No. Work Description Previous This Week Remarks
Week
Contain (%) Contain (%) Contain (%) Contain (%)
1 MARKET -1 (DRY AREA)
A PREPARATION WORK 3.43 3.21 - 3.21
B ARCHITECTURAL WORKS 39.25 38.34 0.87 39.21
C STRUCTURAL WORK 23.35 22.23 0.36 22.59
D ELECTRICAL WORKS 1.18 0.06 0.53 0.58
Sub Total 1 67.21 63.84 1.76 65.59
2 MARKET -2 (WET AREA)
A PREPARATION WORK 0.20 0.20 - 0.20
B ARCHITECTURAL WORKS 6.92 6.57 0.35 6.92
C STRUCTURAL WORK 4.36 3.98 - 3.98
D ELECTRICAL WORKS 0.23 - 0.23 0.23
Sub Total 2 11.70 10.74 0.57 11.32
3 TOILET
A PREPARATION WORK 0.09 0.09 - 0.09
B ARCHITECTURAL WORKS 3.31 2.78 0.48 3.26
C STRUCTURAL WORK 1.44 1.44 - 1.44
D MECHANICAL AND ELECTRICAL WORKS 1.85 0.74 - 0.74
Sub Total 3 6.69 5.05 0.48 5.53
4 SEPTICKTANK Sub Total 4 2.98 2.98 - 2.98
5 SITE PLAN
A SITEPLAN PLUMBING WORKS 1.06 1.06 - 1.06
B SITE PLAN ELECTRICAL WORKS 2.47 0.31 0.86 1.17
C SITE WORK, PAVING AND FENCE WORKS 7.19 6.67 0.26 6.93
D GARBAGE BOX AND SLAB 0.70 0.55 - 0.55
Sub Total 5 11.42 8.59 1.12 9.71
TOTAL 100.00 91.20 3.93 95.13
Main Item W orks : Market-1 (Dry Area) Period : 29 November - 31 December 2021
Location : Sibado, Donggala District
Contractor : PT. Insan Cita Karya
2 Soil backfill m3 20.67 0.030 20.67 0.030 0.00 0.000 20.67 0.030 100.01%
3 Beam 25/35
- Concrete K-250 m3 19.54 0.550 19.54 0.550 0.00 0.000 19.54 0.550 100.00%
- Reinforcement kg 3,881.16 1.930 3881.16 1.930 0.00 0.000 3881.16 1.930 100.00%
- Formwork sloof m2 106.02 0.954 106.02 0.954 0.00 0.000 106.02 0.954 100.00%
4 Floor Slab
- Soil fill for floor elevation m3 144.91 0.863 144.91 0.863 0.00 0.000 144.91 0.863 100.00%
- Sand layer t=10cm m3 82.81 0.300 82.81 0.300 0.00 0.000 82.81 0.300 100.00%
- Base concrete t=5 cm K-100 m3 46.11 1.039 46.11 1.039 0.00 0.000 46.11 1.039 100.00%
- Concrete K-250 m3 66.20 1.864 66.20 1.864 0.00 0.000 66.20 1.864 100.00%
- Reinforcement kg 1,833.91 0.912 1833.91 0.912 0.00 0.000 1833.91 0.912 100.00%
- Formwork m2 13.30 0.070 13.30 0.070 0.00 0.000 13.30 0.070 100.00%
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
5 Drainage and steel grating
- Foundation cutting m3 19.62 0.397 19.62 0.397 0.00 0.000 19.62 0.397 100.00%
- Brick W all 1:5 H=0,3 m m2 78.48 1.004 78.48 1.004 0.00 0.000 78.48 1.004 100.00%
- Mortar plaster work m2 130.80 0.250 130.80 0.250 0.00 0.000 130.80 0.250 100.00%
- Mortar Neat Plaster W ork m2 130.80 0.135 130.80 0.135 0.00 0.000 130.80 0.135 100.00%
- Concrete t=5 cm K-100 m3 13.08 0.295 13.08 0.295 0.00 0.000 13.08 0.295 100.00%
- Steel Grating m' 130.80 2.059 59.73 0.940 22.95 0.361 82.67 1.302 63.21%
SUB TOTAL (C) 23.347 22.228 0.361 22.590
D. ELECTRICAL WORKS
D.1. LOW VOLTAGE PANEL WORKS
Procurement and installation of a complete panel
1 MCB-Box of Los Type-A Market unit 2.00 0.005 0.00 0.000 0.00 0.000 0.00 0.000 0.00%
Main Item W orks : Market-2 (Wet Area) Period : 29 November - 31 December 2021
Location : Sibado, Donggala District
Contractor : PT. Insan Cita Karya
2 Soil backfill m3 5.40 0.008 5.40 0.008 0.00 0.000 5.40 0.008 100.00%
3 Brick 1:4 (0.5) m2 38.05 0.178 38.05 0.178 0.00 0.000 38.05 0.178 100.00%
4 Brick 1:4 (1) m2 8.28 0.079 8.28 0.079 0.00 0.000 8.28 0.079 100.00%
2 Floor Slab
- Soil fill for floor elevation m3 46.49 0.277 46.49 0.277 0.00 0.000 46.49 0.277 100.00%
- Sand layer t=10cm m3 17.22 0.062 17.22 0.062 0.00 0.000 17.22 0.062 100.00%
- Slab concrete t=8 cm K-250 m3 13.78 0.388 13.78 0.388 0.00 0.000 13.78 0.388 100.00%
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
3 Fish Table
Beam 8/12
- Concrete K-250 m3 0.56 0.016 0.56 0.016 0.00 0.000 0.56 0.016 100.00%
- Reinforcement m3 328.43 0.163 328.43 0.163 0.00 0.000 328.43 0.163 100.00%
- Formwork sloof m3 8.22 0.074 8.22 0.074 0.00 0.000 8.22 0.074 100.00%
Deck Slab
- Concrete K-250 m3 1.85 0.052 1.85 0.052 0.00 0.000 1.85 0.052 100.00%
- Reinforcement m3 243.90 0.121 243.90 0.121 0.00 0.000 243.90 0.121 100.00%
- Formwork sloof m3 14.49 0.081 14.49 0.081 0.00 0.000 14.49 0.081 100.00%
Column 8/12
- Concrete K-250 m3 0.06 0.002 0.06 0.002 0.00 0.000 0.06 0.002 100.00%
- Reinforcement m3 42.49 0.021 42.49 0.021 0.00 0.000 42.49 0.021 100.00%
- Formwork sloof m3 0.84 0.007 0.84 0.007 0.00 0.000 0.84 0.007 100.00%
2 Foundation 2 (terrace)
- Foundation Cutting m3 0.32 0.007 0.32 0.007 0.00 0.000 0.32 0.007 100.00%
- Concrete K-175 m3 0.87 0.022 0.87 0.022 0.00 0.000 0.87 0.022 100.00%
3 Sloof 13/20
- Concrete K-250 m3 0.94 0.026 0.94 0.026 0.00 0.000 0.94 0.026 100.00%
- Reinforcement kg 421.35 0.210 421.35 0.210 0.00 0.000 421.35 0.210 100.00%
- Foundation formwork m2 3.20 0.018 3.20 0.018 0.00 0.000 3.20 0.018 100.00%
2 13/20 Beam B1
- Concrete K-250 m3 0.94 0.026 0.94 0.026 0.00 0.000 0.94 0.026 100.00%
- Reinforcement kg 230.28 0.115 230.28 0.115 0.00 0.000 230.28 0.115 100.00%
- Beam Formwork m2 9.54 0.086 9.54 0.086 0.00 0.000 9.54 0.086 100.00%
SUB TOTAL (C) 1.439 1.439 0.000 1.439
D MECHANICAL AND ELECTRICAL WORKS
I. TOILET PLUMBING WORKS
b. Junction Box
Size : dia. of 600 mm x depth adjusted to inlet level of the unit 2.00 0.472 2.00 0.472 0.00 0.000 2.00 0.472 100.00%
1 Ground W ork
- STP Foundation Cutting m3 19.15 0.388 19.15 0.388 0.00 0.000 19.15 0.388 100.00%
- Backfill m3 6.38 0.009 6.38 0.009 0.00 0.000 6.38 0.009 100.00%
Contract Actual Progress
No. W ork Description Unit Total Previous This W eek Up To This W eek Remarks
Contain (%)
Quantity Quantity Contain (%) Quantity Contain (%) Quantity Contain (%)
2 W all SPT
- Sand layer t=10cm m3 1.14 0.004 1.14 0.004 0.00 0.000 1.14 0.004 100.00%
- Brick wall 1:5 m3 39.32 0.181 39.32 0.181 0.00 0.000 39.32 0.181 100.00%
- Mortar Plaster W ork m2 39.32 0.075 39.32 0.075 0.00 0.000 39.32 0.075 100.00%
- Mortar Neat Plaster W ork m2 39.32 0.041 39.32 0.041 0.00 0.000 39.32 0.041 100.00%
- K-100 Concrete LC m3 1.44 0.032 1.44 0.032 0.00 0.000 1.44 0.032 100.00%
3 Concrete Column
- K-250 Concrete m3 1.79 0.051 1.79 0.051 0.00 0.000 1.79 0.051 100.00%
- Reinforcement kg 76.03 0.038 76.03 0.038 0.00 0.000 76.03 0.038 100.00%
- Column Formwork m2 19.80 0.174 19.80 0.174 0.00 0.000 19.80 0.174 100.00%
4 Concrete Slab
- K-250 Concrete m3 1.13 0.032 1.13 0.032 0.00 0.000 1.13 0.032 100.00%
- Reinforcement kg 93.58 0.047 93.58 0.047 0.00 0.000 93.58 0.047 100.00%
- Sloof Formwork m2 11.38 0.102 11.38 0.102 0.00 0.000 11.38 0.102 100.00%
5 Install PVC 2" Pipe m 4.00 0.052 4.00 0.052 0.00 0.000 4.00 0.052 100.00%
Install PVC 3" Pipe m 18.00 0.256 18.00 0.256 0.00 0.000 18.00 0.256 100.00%
Install Tee 3" unit 12.00 0.120 12.00 0.120 0.00 0.000 12.00 0.120 100.00%
7 Junction Box (0.5x0.5x0.5 m) with manhole cover Lot 2.00 0.031 2.00 0.031 0.00 0.000 2.00 0.031 100.00%
8 Infiltration
- Cutting (2 m depth) m3 6.28 0.127 6.28 0.127 0.00 0.000 6.28 0.127 100.00%
- Install concrete pipa (buis beton) dia. 1 m m' 8.00 0.161 8.00 0.161 0.00 0.000 8.00 0.161 100.00%
- Install pipe PVC 3" (inc. accesories) m 4.00 0.050 4.00 0.050 0.00 0.000 4.00 0.050 100.00%
- Install Manhole cover (inc. handel) m3 0.31 0.009 0.31 0.009 0.00 0.000 0.31 0.009 100.00%
- Reinforecement Manhole (sumur resapan) kg 43.98 0.890 43.98 0.890 0.00 0.000 43.98 0.890 100.00%
- Formwork m2 1.00 0.009 1.00 0.009 0.00 0.000 1.00 0.009 100.00%
- Gravel and sand filter m3 0.79 0.006 0.79 0.006 0.00 0.000 0.79 0.006 100.00%
- Sarang tawon / Bio Media Filter m3 2.40 0.017 2.40 0.017 0.00 0.000 2.40 0.017 100.00%
d. Tower Tank
1 Type : Fibreglass Capacity : 1 m3 unit 2.00 0.158 2.00 0.158 0.00 0.000 2.00 0.158 100.00%
2 Rooftank work c/w W ater Tower 4 meters high unit 1.00 0.472 1.00 0.472 0.00 0.000 1.00 0.472 100.00%
(incl. foundation)
5 Fence:
- Foundation Cutting m3 8.70 0.176 8.70 0.176 0.00 0.000 8.70 0.176 100.00%
- Sand layer t=10cm m3 1.74 0.006 1.74 0.006 0.00 0.000 1.74 0.006 100.00%
- Anstamping Stone H=15cm m3 2.61 0.025 2.61 0.025 0.00 0.000 2.61 0.025 100.00%
- Masonry 1:4 m3 7.61 0.036 7.61 0.036 0.00 0.000 7.61 0.036 100.00%
- Backfill m3 2.90 0.004 2.90 0.004 0.00 0.000 2.90 0.004 100.00%
- Mortar Plaster W ork m2 58.00 0.098 0.00 0.000 58.00 0.098 58.00 0.098 100.00%
- Mortar Neat Plaster W ork m2 58.00 0.060 0.00 0.000 58.00 0.060 58.00 0.060 100.00%
- K-250 Concrete m3 0.65 0.018 0.65 0.018 0.00 0.000 0.65 0.018 100.00%
- Reinforcement kg 116.09 0.058 116.09 0.058 0.00 0.000 116.09 0.058 100.00%
- Column Formwork m2 3.30 0.029 3.30 0.029 0.00 0.000 3.30 0.029 100.00%
- Roster m2 5.00 0.068 5.00 0.068 0.00 0.000 5.00 0.068 100.00%
SUB TOTAL (C) 7.188 6.667 0.264 6.931
D. GARBAGE BOX AND SLAB
1 Concrete slab for garbage truck
- Sand layer t=10cm m3 1.75 0.006 1.75 0.006 0.00 0.000 1.75 0.006 100.00%
- Base concrete t=8 cm K-100 m3 0.88 0.020 0.88 0.020 0.00 0.000 0.88 0.020 100.00%
- K-250 Concrete m3 2.10 0.059 2.10 0.059 0.00 0.000 2.10 0.059 100.00%
- Reinforcement kg 142.10 0.071 142.10 0.071 0.00 0.000 142.10 0.071 100.00%
- Formwork m2 1.02 0.005 1.02 0.005 0.00 0.000 1.02 0.005 100.00%