Professional Documents
Culture Documents
GENERAL NOTES
TO UPRIGHTS WITH CHECK BASIS OF DESIGN
LEDGERS AT ALL TIMES DEBRIS NETTING TO BE This drawing has been prepared from information supplied to us by, or on behalf of the
ALL COUPLERS TO BE TYPE
SECURED TO OUTSIDE OF contractor, who should check that his requirements have been correctly interpreted and that all
EN74 CLASS A WITH MIN 6.1kN
UPRIGHTS AT ALL TIMES. loadings, dimensions, lift heights, bay sizes, erection/striking sequences etc. are as required and
SLIP CAPACITY
practicable.
BEAMS TO BE LACED AND PLAN IMPOSED LOADS
BRACED VIA LOAD BEARING The contractor is to ensure that the existing structure, it's fabric and/or the ground will safely
COUPLERS AT ALL TIMES. support the extra imposed loads; or supply new.
TIE TIE TIE Maximum calculated tie load: See notes
TIE
Maximum calculated leg load: See notes
LOADINGS ALLOWED
ALL TIES ARE TO BE INSTALLED The contractor must ensure that all loading(s) allowed for is sufficient.
USING LOAD BEARING Structural transoms to be Live loads: See notes
COUPLERS AT ALL TIMES. Loading bays to be fully braced in installed every alternate
Structural lift to be plan braced as Access scaffold to be tied to See notes
both directions to full height as frame longitudinally via
indicated via load bearing underside of existing concrete Windloading: As BSEN1991-1-4
indicated load bearing couplers on
couplers floor slabs every alternate frame Maximum number of boarded levels:
longitudinally debris netted access
scaffold SHORING WORK
TIE TIE TIE We can not and will not pass comment on the structure being shored, as this involves matters
TIE beyond our control and knowledge. It is the contractors responsibility to ensure that the existing
structure will safely span between our supports, and can be safely shored in the way indicated.
Indicates adapted scaffold lift FOUNDATIONS
installed with progression of STRUCTURAL TRANSOM The contractor must prepare all foundations prior to erection.
brickwork NOT TO SCALE
TEMPORARY ROOFS
Bricklayers access scaffold to be No temporary roof can be made watertight.
installed as indicated on existing Loading: Snow loading assessed using BSEN1991-1-3 2003, unless the contractor adopts a snow
balconies - Balconies to be management system.
TIE TIE propped by others TIE
MATERIALS
TIE
All scaffolding materials forming this structure are to comply, and be constructed in accordance
Ladderbeams bridging between Ladderbeams bridging between with BS1139, BSEN12811 and TG20:13 (current editions).
scaffold supports forming loading scaffold supports forming loading
Ledger bracing to be installed MODIFICATION
gantry gantry
every alternate frame No alteration is to be made to the structure detailed on this drawing without prior written
Plan bracing to be installed longitudinally in structural lift as permission from Prime Scaffold and Structural Designs Ltd.
Gantry to consist of through bridge beams as indicated Gantry to consist of 225x38mm
225x38mm timber timber scaffold boards with layer indicated PROPERTY
scaffold boards with of polythene between This drawing is confidential and the exclusive property of THE SCAFFOLD CONTRACTOR.
layer of polythene TIE TIE TIE TIE No unauthorised use, copy or disclosure is to be made, and is to be returned on request.
between TIE
DIMENSIONS
Uprights based onto 225 x 450mm timber Written dimensions shall take precedence over scaled dimensions. The contractor must verify all
steel base plates sole boards installed site dimensions and notify of any discrepancies prior to erection.
Inside puncheon of access to all uprights
40 No. continuous
scaffold to be supported by PERMITS AND PERMISSIONS
scaffold tubes to be The contractor must obtain all permits and permissions prior to erection.
cantilevered gantry beams
installed as indicated to 150 x 150mm
full extend of support steel base plate CONSTRUCTION NOTES
tower TIE 1) All ladder beams and/or unit beams are to be tied together at 1200 centres on top chord and
TIE 2400 centres on bottom chord, with the top chord plan braced, unless stated otherwise.
2) Unless otherwise noted all lifts other than boarded platform levels are to be constructed using
load bearing couplers.
3) All general construction is to be in accordance with TG20:13 unless noted otherwise.
SECTION A - A 4) Main contractor to undertake all making good where necessary.
SCALE 1 : 75
SECTION B - B SECTION C - C SECTION D - D SOLE BOARD DETAIL 5) Main contractors to provide and maintain adequate tie positions.
SCALE 1 : 75 SCALE 1 : 75 SCALE 1 : 75 NOT TO SCALE 6) No additional sheeting, wind protection or fans to be added to this structure without prior written
permission from Prime Scaffold and Structural Designs Ltd.
3 Board wide access scaffold to Twin transoms to be installed
be raised progressively with either side of upright at every
progression of brick work upright location ISSUED AS WORKING DRAWING
ALL TIES ARE TO BE INSTALLED BAY LAYOUT HAS BEEN SHOWN, WHERE
USING LOAD BEARING NECESSARY BAY SIZES CAN BE ALTERED TO
COUPLERS AT ALL TIMES. ANCHORS TO BE TESTED IN ACCORDANCE SUIT SITE CONDITIONS AND OBSTACLES -
WITH N.A.S.C DOCUMENT TG4
Revisions:
TIE TIE TIE
MAX BAY LENGTH NOT TO EXCEED 2.2m
Imposed loading on
! DESIGN BASED RESIDUAL HAZARD ! Proposed Scaffold Layout for
protection deck not to exceed
Access Scaffold @ 392-394
Design based hazards actively eliminated where
0.75kN/m² at any time possible in the design process. Where hazards
cannot be eliminated, this symbol on the drawing