1. PR
Must be free from erasures especially the price
Make sure the items to be procured do not fall under the irregular, unnecessary, excessive,
unconscionable and extravagant
For PR with amount above 50k, philgeps registration number should be indicated in the
quotation
2. Abstract of Canvass
Names of the BAC signatory in the Abstract of Canvass must be indicated.
If the BAC signatory is on leave/absence, it should be written in the name
Should indicate the unit cost and total for each supplier
3. BAC Resolution
Must be free from erasures
Mode of procurement indicated should be the same with the mode of procurement in the
PHILGEPs posting
If the BAC signatory is on leave/absence, it should be written in the name
4. Notice of Award
Must be free from erasures
Should indicate the complete business name with address of the supplier
Amount in figures must be the same with the amount in words
5. Purchase Order
Must be free from erasures especially the price
For catering/labor services, PO date should be before the date of activity
For catering, indicate date of activity
For labor services, indicate period covered
Brand name should be indicated per item
Prices per unit and quantity in the PO should not exceed the PR per unit and quantity
Prices per unit should be the same with the prices per unit in the quotation
Check prices if not overpriced based on the current market price (10% mark up based on the
current price is acceptable)
As per COA Guidelines, prices in excess of the current and prevailing market price by more than
10% are considered overpriced.
Check the computation of the PO per item and total.
Indicate delivery term - no. of days
Indicate payment term- complete or staggered basis
Supplier must enter into contract within 10 days from receipt of NOA
Delivery of the items must fall within the delivery term indicated in the PO
PO should be stamped received by COA within 5 CD from completion of the contract
10. RIS/RSMI
Should be completely filled up as to date and RIS/RSMI number
No need to be attached if ICS and PAR was attached
11. Date of each document should be in proper order based on the procurement process flow.
12. Generally, all documents attached must be original. If photocopy, it should be indicated where the
original document was attached.
13. As much as possible, all documents must be free from erasures or other forms of
alteration; otherwise, it will be countersigned by the proper authority.