* PROPERTIES

At transfer stage At construction stage At final stage cross section

Breadth of bot flange "bbf" 850 mm 850 mm 850 mm


Depth of bot flange "dbf" mm
400 400 mm 400 mm At transfer stage &
Breadth of Web "bw" = 600
mm 600 mm 600 mm At construction stage
Depth of Web "dw" 205
mm 205 mm 325 mm 600
Clear cover to strand dc` 57.40
mm 57.40 mm 57.40 mm 205
span = 9.506
m 9.106 m 10.106 m
400
HCS span - oneside = 7.9
m 7.9 m 7.9 m
HCS span - otherside = 7.7
m 7.7 m 7.7 m 850
2 2
Steel Grade = 500
N/mm Grade of structural topping 30 N/mm
P.Steel Grade = N/mm2
1860
Grade of concrete (fcck) = N/mm2
50
Area of Concrete (Ac) = 463000 mm2 463000 mm2 535000 mm2 At final stage
Center of Gravity (ybottom) 280.36 mm 280.36 mm 332.13 mm
Center of Gravity (ytop) = 324.64 mm 324.64 mm 392.87 mm 600
Eccentricity e ( for bottom strand) = 184.10 mm 184.10 mm 235.87 mm
325
Eccentricity e ( for top strand) = 274.64 mm 274.64 mm 267.87 mm
Moment of Inertia ,Iyy = 13229297738 mm4 13229297738 mm4 22534289825 mm4
3 3 3 400
Section moudulus (Ztop) = 40750671 mm 40750671 mm 57358133 mm
3 3 3
Section moudulus (Zbottom) = 47186823.15 mm 47186823.15 mm 67847800.03 mm 850
Youngs modules Ec = 27386 N/mm2 35355 N/mm2 35355 N/mm2
2
Grade at transfer (fcckj) = 30 N/mm
Mean Compressive strength of Concrete (fccj) = 35 N/mm2
LOADING kN/m kN/m2 kN/m kN/m2 kN/m Initial transfer stage losses:
Hollow core Slab load = 3.5 27.3 3.5 27.3
75 thk topping = 1.875 14.625 1.875 14.625 Slip loss = 1.08
Construction load = 1.5 12.6 Relaxation loss at 7 days = 2.690
Self weight of beam = 11.575 13.38 13.38 Elastic shortening of concrete = 6.613
Total load,w = 11.575 67.90 55.30 Elastic shortening of abutmenets = 0.54
2 2 2
Unfactored moment = wl /8 wl /8 with constrcution load wl /8 10.92
= 11.575*9.506^2/8 130.75 67.9*9.106^2/8 703.78 705.98 %
wl2/8 without constrcution load
55.3*7.7^2/8 573.18 Bottom bending from 336.67
11.58 Kn/m 67.90 Kn/m analytical model 82.87 535.23

Unfactored moment (in kN-m) = 5.115202591


=
9.506 9.106 2 2
Total Unfactored moment (in kN-m) (WL /8)+ (WL /24) = 1042.65
prestress strand

no of Initial Prestress Nomoinal tensile Prestressing forces after intial (elastic loss &
dia area prestressing force after all loss (kN)
strand (%) strength Prestressing forces relaxation loss at transfer stage) loss (kN)
strand position without any loss (kN)
mm mm2 N/mm2 P initial Eccentricity P all losses Eccentricity
Bottom first layer outer strand 8 15.2 140 75 1860 1562.40 1391.74 215.36 996.63 267.13
Bottom first layer inner strand 0 15.2 140 75 1860 0.00 0.00 215.36 0.00 267.13
Bottom second layer outer strand 6 15.2 140 75 1860 1171.80 1043.81 150.36 747.47 202.13
Bottom second layer inner strand 2 12.7 98.7 75 1860 275.37 245.30 150.36 175.66 202.13
Top strand 3 12.7 98.7 60 1860 330.45 311.83 269.64 280.25 217.87

Prestress Loss Coefficients: Stress in concrete at level of steel (fc) for Elastic loss for Creep loss
Stress in Prestressing force at
concrete at level construction stage
of steel
Assuming loss at Eccentricity of each strand prestressing force ,P ( in
Stress in concrete at level (elastic loss
transfer (%) (mm) N)
of steel(no loss considered)
considered) fc fc =P/A+Pe/Z-
Shrinkage strain = 0.000454 =P/A+Pe/Z-M/Z M/Z
Creep coefficent at erection stage = 2.068 2.068 0 215.36 1562400 7.033 0.052 1262.05
Creep coefficent at final stage = 2.068 0 215.36 0 0.000 0.000 0.00
Relaxation loss for 0.75 fpu = 3.5 N/mm2 1 0 150.36 1171800 4.533 4.112 946.54
Modulus of Elasticity (Es) = 200000 N/mm2 0 150.36 275373 1.065 0.739 222.44
Modular ratio = Es/Ec = 7.303 0 269.64 330448 2.530 1.227 300.17
Prestressing Losses:
Relaxation loss at 7days = 2.690 % 0.7667 PERMISSIBLE TENSILE & COMPRESSIVE STRESSES AS PER INDIAN CODE:
Shrinkage loss at final stage = 6.509 %
Shrinkage loss at 73 days stage = 2.151 % Description Transfer stage (N/mm2) Erection stage (N/mm2)
2
Relaxation loss for long term = 10.500 % 3.00 Final stage (N/mm ) Codal Referrence
Elastic loss for bottom strand = 6.613 % Permissible
3.834 7.205 7.205 IS:1343-2012 CL:24.2 Table 10
Elastic loss for top strand = 1.324 % tensile stress
Creep loss at erection stage for bottom strand = 5.340 % Permissible comp
0.80*0.51fck 0.80*0.37fck 0.80*0.37fck IS:1343-1980 CL:22.8.2.2 &
Creep loss at erection stage for top strand = 2.739 % stress
IS:1343-1980 CL:22.8.1.2
Creep loss at final stage for bottom strand = 10.970 % at support 15.00 14.80 14.80
Creep loss at final stage for top strand = 1.328 % Permissible comp
0.51fck 0.37fck 0.37fck IS:1343-1980 CL:22.8.2.1,FIG 8B &
Total loss for bottom strand = 36.21 % stress
IS:1343-1980 CL:22.8.1.1, FIG 7
Total loss for top strand = 15.192 % at span 15.30 18.50 18.50
Loss at construction stage for bottom strand = 19.224 % Transmission length = 30φ IS:1343-1980 CL:18.6.1.1 b

# Sensitivity: LNT Construction Internal Use