Professional Documents
Culture Documents
Protection General
Protection General
Handbook
© ABB Group - 1 -
28-Sep-21
Protection General
Electric Power Systems
M
G
© ABB Group - 2 -
Protection System
CT Circuit Breaker
Circuit
Protection Breaker
VT Trip
Equipment Mecha-
Coil
nism
TE
DC-System
© ABB Group - 4 -
28-Sep-21
Protection General
The main task for Relay Protection
K
Protection General
Different fault types in a power system
© ABB Group - 6 -
28-Sep-21
Protection General
Primary and backup protection zones
Redundant system costs more but can give big savings in the
© ABB Group - 11 -
◼ Alarm system
◼ DC system for alarm independent of distribution
◼ Supervision of alarm voltage
8
Protection General
What is Substation Automation ?
A combination of:
◼Protection
◼Monitoring
◼Control
◼Communication
© ABB Group - 17 -
28-Sep-21
Protection General
The conventional way
Control Board
MARSHALING RACK
ABB
GW
LON
.....
REC 561 RE. 5XX REC 561 RE. 5XX
C C C C
E E E E
© ABB Group - 19 -
28-Sep-21
Protection General
The goal of the IEC 61850 standard
Long Term Stability The standard shall be future proof, i.e. it must be able
to follow the progress in communication technology as
well as evolving system requirements.
© ABB Group - 20 -
28-Sep-21
Protection General
TRENDS
Protection System
CT Circuit Breaker
Circuit
Protection Breaker
VT Trip
Equipment Mecha-
Coil
nism
TE
DC-System
© ABB Group - 23 -
28-Sep-21
Protection General
Remote Back-up Protection
A B C
5 1 2 F 6
7 3 4 8
D E
© ABB Group - 24 -
28-Sep-21
Protection General
Remote Back-up Protection
Time Step 3
Step 2
Step 1
Distance
Zone 3
Zone 2
Zone 1
B
A C
© ABB Group - 25 -
28-Sep-21
Protection General
Substation Local Back-up Protection
Substation Local Back-up Protection
P2 B
T P1 P3 C
A P4 D
© ABB Group - 26 -
28-Sep-21
Protection General
Circuit Local Back-up Protection
Circuit Local Back-up Protection
P2 P2
P1 P1
A B
© ABB Group - 27 -
28-Sep-21
Protection General
Duplicated Main Protections
1 3 5 5 3 1
2 4 6 6 4 2
© ABB Group - 28 -
28-Sep-21
Protection General
Circuit Breaker Failure Protection
Has No Reset
Protection Normal Breaker
Operated? Operation Failure
Protection
Yes
Start
Breaker Wait for Fault
Fault Cleared?
Failure
Protection Clearance
Yes
No
Trip Trip
Main Back-up
Breaker(s) Breaker(s)
© ABB Group - 29 -
28-Sep-21
Protection General
Single failure Criterion
◼ Failure of any one component in a fault clearance
system should not result in a complete failure to
clear a power system fault or abnormality.
© ABB Group - 30 -
28-Sep-21
Protection General
Applying single failure criterion
◼ Assume that the power system is either in its normal
switching state or that one line is out of service.
◼ Consider the following types of faults
◼ Three phase fault
◼ Phase to phase fault
◼ Phase to earth fault
◼ Open conductor or broken conductor fault
© ABB Group - 31 -
28-Sep-21
Protection General
Applying single failure criterion
◼ Consider one of the following failures
◼ Loss of input from a voltage transformer,
◼ Loss of input from a current transformer,
◼ A failure to operate of a protection relay,
◼ A blown DC fuse
◼ An interruption of a tripping circuit
◼ A failure of remote end communication (especially line
differential protection)
◼ A failure to operate of a switching device.
© ABB Group - 32 -
28-Sep-21
Protection General
Applying single failure criterion
◼ Check if the fault clearance system clears the faults
at pre-defined locations considering the following
◼ A line fault
◼ A bus bar fault
◼ A fault in power transformer
◼ A fault in the shunt reactor
A B C A B C
L1
L R
L2
© ABB Group - 38 -
28-Sep-21
Protection General
Economic Benefit of Perfect Phase Selection in
Connection With Single Pole Reclosing
© ABB Group - 39 -
28-Sep-21
Protection General
Fault current withstand capability
Rated breaking current capability of switch gear
765 kV 40 kA 1 Sec
© ABB Group - 40 -
28-Sep-21
Protection General
Fault clearance time - Transient stability
Three-phase Reclosing
© ABB Group - 41 -