The equipments shall be installed as per the instructions of the respective manufacturer of equipments
and verification of various process parameters including behavior of equipment in abnormal conditions.
The contractor will have to submit a completion certificate for energizing.
The contractor shall submit required copies of instructions and maintenance manuals of all equipments in
English on operation, preventive and regular maintenance and
repair.
Latest Standards, software versions and classifications to be ensured as per the specifications wherever
applicable and mentioned. The tenderer shall indicate any deviation to given specifications.
Each instrument shall be supplied with Tag and easily visible (after installations) SS complete. The
nameplate shall be as manufacturer standard with following details.
Model No.
Tag No.
Range with its engineering unit.
Serial No.
2.0 Rating
Rating of all items shall be appropriate for the condition on the particular site on which the items will be
used.
The rating of all electrical equipment / components shall match with existing power available nearby.
1.0 Voltage variation + 10%
2.0 Frequency variation + 3%
3.0 Combined variation + 10%
The source of power supply to this scheme will be through SECO (Saudi Electric Company) from the
nearest line available.
The ratings of all equipment shall be as per manufacturer’s printed literatures and drawings.
3.0 Regulations and Standards
All material and equipment shall conform to the relevant Aramco Standards. The material of
construction of all components, which are in direct with liquid, shall be non – corrosive. The contractor
shall be responsible for the safe custody of all the materials and shall insure them against theft, damage
by fire, earthquake etc. Any item, which is proposed as a substitute, shall be accompanied by all
technical detail giving sizes, particulars of materials and the manufacturer. In the event, the
substitution is approval all changes and substitutions shall be requested in writing and approvals obtained
from CRCC.
All materials of the same kind of service shall be identical and made by the same manufactures. Any
deviation to this rule shall be approved. Top priority shall be given to the products that have a
permanent agent providing spare parts and maintenance facilities in the same city where the project is
situated.
The installation shall conform in all respects to Aramco Standard Code of Practice for electrical
equipment installations. It shall also be in conformity with the current National Electrical code and
regulations of the local Electrical Supply Authority in so far as these become applicable to the
installation. Wherever these specifications call for a higher standard of material and / or workmanship
than those required by act of the above regulations, then these specifications shall take precedence over
the said regulations and standard. In general, the material, equipment and workmanship not covered by
the above shall conform to the relevant Aramco Standards.
The contractor shall provide all necessary instruments and labor for testing and shall make adequate
records of test procedures and readings and shall repeat any tests requested by the CRCC and shall
provide test certificates signed by a properly authorized person. Such test certificates shall cover all
works.
If tests fail to demonstrate the satisfactory nature of the installation or any part thereof then no
claims for the extra cost of modifications, replacements or retesting will be considered d. The
CRCC decision as to what constitutes a satisfactory test shall be final.
The above general requirements as to testing shall be read in conjunction with any particular
requirements specified elsewhere.
4.5 All materials, components and equipment covered in this specification shall be procured,
manufactured, erected, commissioned and tested at all the stage as per comprehensive quality
assurance.
4.6 No welding shall be carried out on iron component for repair or whatsoever purposes.
5.0 Spare Parts
The Contractor shall indicate and include, in the supply all the necessary commissioning spares and
recommended spares (of OEM). All spares’ parts shall be readily available in the market.