REINFORCED CEMENT CONCRETE COST ANALYSIS

MATERIAL REQUIREMENT ANALYSIS FOR 10M3 VOLUME


WALL+COL TOP SLAB
Reinforced Cement Concrete 48.82 m3 69.68 m3
>Cement CONCRETE PROPORTION
Quantity of Cement = 12.21 m3 17.65 m3 CEMENT 1
Nos of Cement Bag= 341.9 bag 494.5 bag SAND 2
>Sand AGGREGATE 3
Quantity of sand = 24.41 m3 35.31 m3
> Aggregate
Quantity of aggregate = 36.62 m3 52.96 m3
48.8 m3 69.7 m3

10.98880353