Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S.
Item Details
No.
environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 1/9
8/12/2021 Report Part 1
(j)Seismic Zone 2
S.
State Name District Name Tehsil Name Village Name
No.
S.
Plant/Equipment/Facility Configuration Remarks
No.
Total Plot area – 7.55 Ha out of that about, 0.4919 Ha of area is affected in road
(1.) Total Area 7.05 Ha widening, Further an area of 0.9374 Ha is earmarked for future development.
Hence, the net area of the plot is 6.12 Ha
8.2. Product
Other Mode of
S. Product/Activity Mode of Transport / Transport /
Quantity Unit Other Unit
No. (Capacity/Area) Transmission of Product Transmission of
Product
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) /
Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
9.
Details Not Applicable
Project Cost:
(a)Total Cost of the Project at current price level (in
950
crores)
(b) Funds Allocated for Environment Management
14
(Capital) (in crores)
10. (c) Funds Allocated Towards ESC (Entrepreneur Social
9.5
Responsibility) (in crores)
(d) Funds Allocated for Environment Management Plan
1.5
(EMP) (Recurring per Annum) (in crores)
(e) Funds Allocated for Environment Management
1.47
Capital(%)
environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 2/9
8/12/2021 Report Part 1
12. Whether project attract the Specific Condition
No
specified in the Schedule of EIA Notification ?
Source
Distance of
(incase
Source
of
from
Import.
Project Site
please
(in
specify
Kilometres)
country
(In case of
Raw and Other Other Uploaded
S. Other Mode of import, Type of
Material Quantity Unit Name of Mode of Type of Copy of
No. Unit Transport distance Linkage
/ Fuel the port Transport Linkage Linkage
from the
from
port from
which
which the
Raw
raw
Material
material /
/ Fuel is
fuel is
received
received)
)
Baseline Data :
14. (a)Period of Base Line Data Collection FROM 01 Mar 2021 To 10 May 2021
(b)Season Summer
98
S. Maximum Minimum Prescribed
Criteria Pollutants Other Criteria Pollutants Unit Percentile
No. Value Value Standard
Value
Micro Gram
(1.) SO2 per Meter 17.6 15.8 17.6 80
Cube
Micro Gram
(2.) NOx per Meter 19.3 18.4 19.3 80
Cube
Micro Gram
(3.) PM10 per Meter 61.7 56.6 61.7 100
Cube
Micro Gram
(4.) PM2.5 per Meter 23.4 21.5 23.4 60
Cube
Other Maximum
S. Criteria Heavy Maximum Minimum Desirable
Criteria Unit Other Unit Permissible
No. Pollutants Metal Value Value Limit
Pollutants Limit
Heavy
(5.) iRON mg/l 0.3 0.3 0.3 0.3
Metals
Total
(7.) mg/l 400 280 200 600
Hardness
S. Criteria Pollutants Other Criteria Pollutants Unit Other Unit Maximum Minimum Classification
No. Value Value of inland
environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 3/9
8/12/2021 Report Part 1
water body
S. Prescribed
Parameter Unit Maximum Value Minimum Value
No. Standard
S.
Parameter Unit Other Unit Maximum Value Minimum Value
No.
Copy of
Other
Distance Permission Other Method of Date
S. Source Required Mode of Method of Letter Permitted
Source from from Mode of Water of
No. Other Quantity Transport Water No. Quantity
Source Competent Transport Withdrawal Issue
Withdrawal
Authority
Copy of 04
Pipe line
(1.) Others HMWSSB 1740 1 Permission Pipeline Others 825631 Feb 1740
conection
Letter 2011
Quantity of
Quantity of
Waste Treatment Quantity of
Treated Water
S. Water Capacity Treatment Mode of Other Mode of Discharged
Type/Source Used in
No. Generated (Kilolitre Method Disposal Disposal Water (Kilolitre
Recycling/Reuse
(Kilolitre per Day) per Day)
(Kilolitre per Day)
per Day)
Converted as
(1.) STP Others Sewage 3.6 Tons 0 Others Reuse Others
manure
environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 4/9
8/12/2021 Report Part 1
18.
Other
S. Criteria Baseline Distance Incremental Prescribed
Criteria Unit Total GLC
No. Pollutants Concentration GLC Concentration Standard
Pollutants
(1.) PM10 Microgram per Meter Cube 61.7 1.3 0.07 61.77 100
(2.) SO2 Microgram per Meter Cube 17.6 1.3 0.265 17.865 80
(3.) NOx Microgram per Meter Cube 19.3 1.3 2.19 21.49 80
18.2. Stack Details
S. Stack
Source Fuel Stack Height(m) Pollutants Other Pollutants Emission (GLS)
No. Diameter(m)
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 9500
(b)Source TSPDCL
19.
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 3X630 KVA and 14 X 750 KVA
(e)Stack Height (in m) 113
S. Description of Activity /
Others Land Requirement Remarks
No. Facility / Plant / Others
Total 7.053
environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 5/9
8/12/2021 Report Part 1
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco
23.
Sensitive Areas; ESZs-Eco Sensitive Zones :
S. Details of Ecological
Name Distance from the Project (Km) Remarks
No. Sensitivity
Other Details of
S. Details of Environmental
Environmental Name Distance from the Project (Km) Remarks
No. Sensitivity
Sensitivity
None within 10 km
(1.) Defence Installations 0 0
Radius
None within 10 km
(2.) Archaeological Sites 0 0
Radius
Kondapur Reserved
(3.) Forest 7.5 EAST
forest
Forest Land:
24.
Whether any Forest Land involved? No
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not
25. 0
Involved)
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 203
31. (c)Temporary Employment- During Construction 700
(d)Temporary Employment- During Operation 100
(e)No. of working days 365
(f)Total Manpower 1003
33. Project Benefits
S.
Type of Project Benefits Details of Project Benefits
No.
S.
Item Details
No.
Parking:
4.
(a)Details of 4 Wheeler/ 2 Wheeler Parking 3399
Other details:
(a)Details of impact on Water Bodies and Drainage
NA
patters of catchment area
6. (b)Details of Traffic Density Impact Assessment and
Copy of Details of Traffic Density Impact Assessment and Modelling Study
Modelling Study
(c)In case Underground Tunnel Project below the Forest Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact
Land - Subsidence Impact Study report Study report
environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 7/9
8/12/2021 Report Part 1
7. Type of Industries to be established with Industrial Estate as per their category A/B
S.
Type of Industry No. of Units Category A/B
No.
NIL
S.
Item Details
No.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water
(Prevention & Control of Pollution) Act:
37.
(a)Whether any Direction issued under EPA Act/Air
No
Act/Water Act ?
Documents to be Attached:
(a)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(b)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(c)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project
Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering
Report(DPR) /Detailed Engineering Report /Detailed
Report /Detailed Conceptual Plan /Approved Mining Plan
Conceptual Plan /Approved Mining Plan
39.
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the
competence/authority of the person making this Copy of documents in support of the competence/authority of the person
application to make application on behalf of the User making this application to make application on behalf of the User Agency
Agency
(i)Uploaded Additional File NA
(f)Uploaded Updated Form1 NA
S.
EDS Sought Date EDS Sought Letter
No.
NO Record
Addtional Details Sought
S.
ADS Sought Date ADS Sought Letter
No.
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my
knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage,
the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above,
I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 8/9
8/12/2021 Report Part 1
Name of Applicant Challa Hari C
Designation Director
Name of Company (Applicant Name should not be
M/S ALIENS DEVLOPERS PRIVATE LIMITED
given here)
Address Sy no 384 and 385 (P) Tellapur Village RC Puram Mandal Snagareddy district