Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S.
Item Details
No.

Whether it is a violation case and application is being


submitted under Notification No. S.O.804(E) dated No
14.03.2017 ?
Details of Project:
1. (a)Name of the project(s) M/s Aliens Developers Pvt. Ltd. Construction of Residential apartments
(b)Name of the Company / Organisation M/S ALIENS DEVLOPERS PRIVATE LIMITED
Sy no 384 and 385 (P) Tellapur Village RC Puram Mandal Snagareddy
(c)Registered Address
district,,Sangareddy,Telangana-502032
(d)Legal Status of the Company Private

Address for the correspondence:


(a)Name of the Applicant Challa Hari C
(b)Designation (Owner/ Partner/ CEO) Director
Alienes devlopers pvt ltd plot no 56 and 57 vital rao nagar madhapur
(c)Address
hyderabad,,Kandukur,Rangareddi,Telangana-500081
(d)Pin code 502032
2. (e)E-mail aliensdeveloperspvtltd@gmail.com
(f)Telephone No. 0-
(g)Fax No.
(h)Copy of documents in support of the
competence/authority of the person making this
Annexure-Uploaded Copy of documents in support of the competence/authority
application to make application on behalf of the User
Agency .

Category of the Project/Activity as per Schedule of EIA Notification,2006:


(a)Major Project/Activity 8(b) Townships and Area Development projects.
(b)Minor Project/Activity 8(b) Townships and Area Development projects.
(c)Category B1
3.
(d)Proposal Number SIA/TG/MIS/63840/2021
(e)Master Proposal Number(Single Window) SW/218632/2021
(f)EAC concerned (for category A Projects only) INFRA-2
(g)Project Type Fresh EC

4. Location of the Project:


(a)Plot/Survey/Khasra No. 384 and 385 (P)
(b)Pincode 502032
(c)Bounded Latitudes (North)
From
Degree 17
Minutes 27
Second 37.49
From
Degree 17
Minutes 27
Second 48.70
(d)Bounded Longitudes (East)
From
Degree 78
Minutes 17
Second 02.77
From
Degree 78
Minutes 17
Second 10.76
(e)Survey of India Topo Sheet No. 563
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 563
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary
0.016
within the study area

environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 1/9
8/12/2021 Report Part 1
(j)Seismic Zone 2

(a)Number of States in which Project will be Executed 1


5.
(b)Main State of the project Telangana

Details of State(s) of the project

S.
State Name District Name Tehsil Name Village Name
No.

(1.) Telangana Sangareddy Ramachandrapuram Tellapur

Details of Terms of Reference (ToR):


(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number SIA/TG/MIS/63840/2021
6.
(c)Date of Apply of TOR 11 Jun 2021
(d)Date of Issue of TOR / Standard ToR 03 Jul 2021
(e)Previous TOR Letter Copy of Previous TOR letter

Details of Public Consultation:


(a)Whether the Project Exempted from Public Hearing? Yes
7.
(b)Reason As the proposed project falls under Sector 8(b) -
(c)Supporting Document Copy of Supporting Document

8. Details of Project Configuration/Product:

     8.1.       Project Configuration

S.
Plant/Equipment/Facility Configuration Remarks
No.

Total Plot area – 7.55 Ha out of that about, 0.4919 Ha of area is affected in road
(1.) Total Area 7.05 Ha widening, Further an area of 0.9374 Ha is earmarked for future development.
Hence, the net area of the plot is 6.12 Ha

     8.2.       Product

Other Mode of
S. Product/Activity Mode of Transport / Transport /
Quantity Unit Other Unit
No. (Capacity/Area) Transmission of Product Transmission of
Product

(1.) Built-up area 544190.21 Others SQM Others na

In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) /
Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
9.
Details Not Applicable

Details of Consent to Operate


(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since
NA
inception
9.1. (iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA

Project Cost:
(a)Total Cost of the Project at current price level (in
950
crores)
(b) Funds Allocated for Environment Management
14
(Capital) (in crores)
10. (c) Funds Allocated Towards ESC (Entrepreneur Social
9.5
Responsibility) (in crores)
(d) Funds Allocated for Environment Management Plan
1.5
(EMP) (Recurring per Annum) (in crores)
(e) Funds Allocated for Environment Management
1.47
Capital(%)

Whether project attracts the General Condition


11. No
specified in the Schedule of EIA Notification ?

environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 2/9
8/12/2021 Report Part 1
12. Whether project attract the Specific Condition
No
specified in the Schedule of EIA Notification ?

Raw Material / Fuel Requirement:


(a)Proposed quantity of raw material/fuel 0
13.
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0

    13.1.        Raw Material / Fuel Profile

Source
Distance of
(incase
Source
of
from
Import.
Project Site
please
(in
specify
Kilometres)
country
(In case of
Raw and Other Other Uploaded
S. Other Mode of import, Type of
Material Quantity Unit Name of Mode of Type of Copy of
No. Unit Transport distance Linkage
/ Fuel the port Transport Linkage Linkage
from the
from
port from
which
which the
Raw
raw
Material
material /
/ Fuel is
fuel is
received
received)
)

Tons per LOACL Copy of


(1.) Steel 0 Road 5 Others na
Annum MARKET Linkage

Baseline Data :
14. (a)Period of Base Line Data Collection FROM 01 Mar 2021 To 10 May 2021
(b)Season Summer

    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 6

98
S. Maximum Minimum Prescribed
Criteria Pollutants Other Criteria Pollutants Unit Percentile
No. Value Value Standard
Value

Micro Gram
(1.) SO2 per Meter 17.6 15.8 17.6 80
Cube

Micro Gram
(2.) NOx per Meter 19.3 18.4 19.3 80
Cube

Micro Gram
(3.) PM10 per Meter 61.7 56.6 61.7 100
Cube

Micro Gram
(4.) PM2.5 per Meter 23.4 21.5 23.4 60
Cube

    14.2.     No. of Ground Water Monitoring Locations : 6

Other Maximum
S. Criteria Heavy Maximum Minimum Desirable
Criteria Unit Other Unit Permissible
No. Pollutants Metal Value Value Limit
Pollutants Limit

(1.) pH NA 7.6 7.2 6.5 8.5

(2.) Chlorides mg/l 100.68 50.34 250 1000

(3.) Fluoride mg/l 0.5 0.5 1 1.5

(4.) TSS mg/l 1015 505 0 0

Heavy
(5.) iRON mg/l 0.3 0.3 0.3 0.3
Metals

(6.) TDS mg/l 1010 500 500 2000

Total
(7.) mg/l 400 280 200 600
Hardness

    14.3.     No. of Surface Water Monitoring Locations : 3

S. Criteria Pollutants Other Criteria Pollutants Unit Other Unit Maximum Minimum Classification
No. Value Value of inland

environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 3/9
8/12/2021 Report Part 1
water body

(1.) COD mg/l 20 12 E

(2.) BOD mg/l 6 4 E

(3.) DO mg/l 4.2 4 C

(4.) pH NA 7.85 7.2 A

    14.4.     No. of Ambient Noise Monitoring Locations : 6

S. Prescribed
Parameter Unit Maximum Value Minimum Value
No. Standard

(1.) Leq(Day) A-weighted decibels(dB(A)) 44.8 42.2 45

(2.) Leq(Night) A-weighted decibels(dB(A)) 54.6 51.9 55

    14.5.     No. of Soil Sample Monitored Locations : 6

S.
Parameter Unit Other Unit Maximum Value Minimum Value
No.

(1.) pH 7.89 7.41

(2.) N(Nitrogen) Kilogram per hectare 46.88 26.6

(3.) P(Phosphorus) Kilogram per hectare 38.05 25.74

(4.) K(Potassium) Kilogram per hectare 36.95 26.87

(5.) Electric Conductivity Kilogram per hectare 0 0

Details of Ground Water Table:


(a)Range of Water Table Pre-Monsoon Season (Meters
From 20 To 45
Below Ground Level (m bgl))
14.6.
(b)Range of Water Table Post-Monsoon Season (Meters
From 18 To 35
Below Ground Level (m bgl))
(c)Whether Ground Water Intersection will be there ? No

     15.      Details of Water Requirement (During Operation)

Copy of
Other
Distance Permission Other Method of Date
S. Source Required Mode of Method of Letter Permitted
Source from from Mode of Water of
No. Other Quantity Transport Water No. Quantity
Source Competent Transport Withdrawal Issue
Withdrawal
Authority

Copy of 04
Pipe line
(1.) Others HMWSSB 1740 1 Permission Pipeline Others 825631 Feb 1740
conection
Letter 2011

15.1. (a)Whether Desalination is proposed No

    16.       Waste Water Management(During Operation)

Quantity of
Quantity of
Waste Treatment Quantity of
Treated Water
S. Water Capacity Treatment Mode of Other Mode of Discharged
Type/Source Used in
No. Generated (Kilolitre Method Disposal Disposal Water (Kilolitre
Recycling/Reuse
(Kilolitre per Day) per Day)
(Kilolitre per Day)
per Day)

Reuse within the


(1.) Domestic 1580 1800 STP Plant & Public sewer 1370 210
Recycling,Others

(a)Total Waste Water Generation 1580


16.1. (b)Total Discharged Water 210
(c)Total Reused Water 1370

    17.       Solid Waste Generation/Management

Quantity Distance Other


S. Name of Other Mode of Mode of Other Mode of
Item per Unit from Mode of
No. Waste Item Transport Disposal Disposal
Annum Site(KM) Transport

Converted as
(1.) STP Others Sewage 3.6 Tons 0 Others Reuse Others
manure

Bio Bio Converted as


(2.) Others 1430 Tons 0 Others reuse Others
degradable degradable manure

environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 4/9
8/12/2021 Report Part 1

(3.) used oil Hazardous 204 Tons 0 Road Authorized


Waste (as Recyclers
per
Hazardous
and Other
Waste
Management
rules 2016)

18.

    18.1.     Air Quality Impact Prediction

Other
S. Criteria Baseline Distance Incremental Prescribed
Criteria Unit Total GLC
No. Pollutants Concentration GLC Concentration Standard
Pollutants

(1.) PM10 Microgram per Meter Cube 61.7 1.3 0.07 61.77 100

(2.) SO2 Microgram per Meter Cube 17.6 1.3 0.265 17.865 80

(3.) NOx Microgram per Meter Cube 19.3 1.3 2.19 21.49 80

(4.) PM2.5 Microgram per Meter Cube 0 0 0 0 0

    18.2.     Stack Details

S. Stack
Source Fuel Stack Height(m) Pollutants Other Pollutants Emission (GLS)
No. Diameter(m)

(1.) 14x750 KVA HSD 113 0.332 Others PM 0.05

(2.) 3x630 kvA hsd 113 0.271 Others PM 0.04

Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 9500
(b)Source TSPDCL
19.
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 3X630 KVA and 14 X 750 KVA
(e)Stack Height (in m) 113

Land Ownership Pattern:


(a)Forest Land 0
(b)Private Land 7.05
20. (c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 7.05

Present Land Use Breakup of the Study Area in Ha:


(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
21.
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Construction site 7.05
    Total 7.05

    22.     Land Requirement for Various Activities

S. Description of Activity /
Others Land Requirement Remarks
No. Facility / Plant / Others

(1.) Main Plant 1.53 Plint area

(2.) Township 3.456 Open area

(3.) Green belt 0.742

(4.) Others Roads 1.325

Total 7.053

environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 5/9
8/12/2021 Report Part 1

Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco
23.
Sensitive Areas; ESZs-Eco Sensitive Zones :

    23.1.     Details of Ecological Sensitivity :

S. Details of Ecological
Name Distance from the Project (Km) Remarks
No. Sensitivity

(1.) Corridors None within 10 km Radius 0 0

(2.) Critically Polluted Area None within 10 km Radius 0 0

(3.) WLS None within 10 km Radius 0 0

(4.) NPA None within 10 km Radius 0 0

(5.) ESZs None within 10 km Radius 0 0

(6.) ESAs None within 10 km Radius 0 0

(7.) Wildlife Corridors None within 10 km Radius 0 0

    23.2.     Details of Environmental Sensitivity :

Other Details of
S. Details of Environmental
Environmental Name Distance from the Project (Km) Remarks
No. Sensitivity
Sensitivity

None within 10 km
(1.) Defence Installations 0 0
Radius

None within 10 km
(2.) Archaeological Sites 0 0
Radius

Kondapur Reserved
(3.) Forest 7.5 EAST
forest

(a)Whether Noc / Permission from the competent


No
23.3. authority is required?
(b)Whether NBWL recommendation is required? No

Forest Land:
24.
Whether any Forest Land involved? No

Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not
25. 0
Involved)
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees

Land Acquisition Status:


(a)Acquired Land(Ha) 7.053
26.
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired completed

Rehabilitation and Resettlement (R&R):


(a)No. of Villages 0
(b)No. of Households 0
27. (c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed

Details of Presence of Schedule-I Species:


(a)Whether there is Presence of Schedule-I Species ? No
28. (b)Whether conservation plan for Schedule-I Species has
No
been prepared ?
(c)Whether conservation plan for Schedule-I Species has
No
been approved by competent authority ?

Details of Presence of Water Bodies in Core Area:


(a)Whether there is Presence of Water Bodies in Core
No
Area ?
29.
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent
No
authority ?

30. Details of Presence of Water Bodies in Buffer Area:


environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 6/9
8/12/2021 Report Part 1
(a)Whether there is Presence of Water Bodies in Buffer
Yes
Area ?
(i)Details of Water Bodies in Buffer Area Medlachervu Tank
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 0.016

Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 203
31. (c)Temporary Employment- During Construction 700
(d)Temporary Employment- During Operation 100
(e)No. of working days 365
(f)Total Manpower 1003

Green Belt in Ha:


(a)Total Area of Green Belt (in hectare) 0.742
(b)Percentage of Total Project Area 10.52
32.
(c)No. of Plants to be Planted 1855
(d)Funds Allocated for Plantation 352000
(e)Uploaded Green Belt plan Copy of Green Belt Plan

    33.         Project Benefits

S.
Type of Project Benefits Details of Project Benefits
No.

(1.) Social Infrastructure development

   34.   CRZ Specific Details : Not Applicable

   35.   Sector Specific Details For INFRA-2

S.
Item Details
No.

Details of Building Construction:


(a)Maximum Height of the Building (Meters) 90
(b)Total No. of Flats to be Build 2240
1.
(c)No. of Buildings 1
(d)Total plot area (sqm) 70549.13
(e)Total built up area (sqm) 544190.21

Foreshore Facilities and/or Marine Disposal:


2. (a)Whether Project Involves Foreshore Activities and/or
No
marine Disposal?

Rain Water Harvesting:


(a)No. of Storage 0
3.     Capacity 0
(b)No. of Recharge Pits 2.46
    Capacity 65

Parking:
4.
(a)Details of 4 Wheeler/ 2 Wheeler Parking 3399

Energy Saving Measures:


(a)Source/Mode SOLAR LED CFLs in common areas
5.
(b)Percentage 10
(c)Quantity 500

Other details:
(a)Details of impact on Water Bodies and Drainage
NA
patters of catchment area
6. (b)Details of Traffic Density Impact Assessment and
Copy of Details of Traffic Density Impact Assessment and Modelling Study
Modelling Study
(c)In case Underground Tunnel Project below the Forest Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact
Land - Subsidence Impact Study report Study report

environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 7/9
8/12/2021 Report Part 1
     7.       Type of Industries to be established with Industrial Estate as per their category A/B

S.
Type of Industry No. of Units Category A/B
No.

NIL

8. Length of the alignment N/A

Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass


9.
Details Not Applicable

S.
Item Details
No.

Details of Court Cases:


36. (a)Whether there is any Court Cases pending against the
project and/or land in which the project is proposed to be No
set up ?

Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water
(Prevention & Control of Pollution) Act:
37.
(a)Whether any Direction issued under EPA Act/Air
No
Act/Water Act ?

Details of EIA Consultant:


(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1821/SA 0122
(ii)Name of the EIA Consultant Sri Sai Manasa Nature Tech Private Limited
(iii)Address Plot No. 74/A, Flat No.102, Central bank building, Kalyan Nagar, Hyderabad
(iv)Mobile No. 9391116139
38. (v)Landline No. 0404135555
(vi)Email Id suresh.pasali@ssmntech.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 21 Nov 2021
(x)Uploaded Certificate of Accreditation certified by
Copy of Certificate of Accreditation
QCI/NABET

Documents to be Attached:
(a)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(b)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(c)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project
Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering
Report(DPR) /Detailed Engineering Report /Detailed
Report /Detailed Conceptual Plan /Approved Mining Plan
Conceptual Plan /Approved Mining Plan
39.
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the
competence/authority of the person making this Copy of documents in support of the competence/authority of the person
application to make application on behalf of the User making this application to make application on behalf of the User Agency
Agency
(i)Uploaded Additional File NA
(f)Uploaded Updated Form1 NA

           Essential Details Sought

S.
EDS Sought Date EDS Sought Letter
No.

NO Record
           Addtional Details Sought

S.
ADS Sought Date ADS Sought Letter
No.

NO Record

Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my
knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage,
the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above,
I hereby give undertaking that no activity/ construction/ expansion has since been taken up.

environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 8/9
8/12/2021 Report Part 1
Name of Applicant Challa Hari C
Designation Director
Name of Company (Applicant Name should not be
M/S ALIENS DEVLOPERS PRIVATE LIMITED
given here)
Address Sy no 384 and 385 (P) Tellapur Village RC Puram Mandal Snagareddy district

environmentclearance.nic.in/state/FB_ECGeneral_Report.aspx?pid=189053 9/9