UltraTech Cement PVT LTD Risk Assessment form for concrete pouring & Compaction Date 26-10-2021

Client TATA PROJECTS PVT LTD Location


s.no Activity Hazards probability severity Risk Rating Minimize Risk to Acceptable level probability severity Residual Risk Responsibile person
1 Pouring concrete into splashing into 3 3 9 goggles must be worn, hand gloves, 2 2 4 site Engineer
the ramp wall eyes,concrete sleeves, use proper PPE,
burns to hands competence workers involved.
and feet, skin
infection
2 compaction of splashing into 3 4 12 use secured platform, worn hand 2 2 4 site Engineer
concrete by using eyes, fall from gloves and goggles, worn safety
vibrator at 2.5metre height, burns to helmet, safety shoes, competence
height hands. persons involved, Equipment
inspected before use.

RISK MATIX: (Risk rating = Probability x severity)


Severity
Rating Probability
1 2 3 4 5
1 1 2 3 4 5
2 2 4 6 8 10
3 3 6 9 12 15
4 4 8 12 16 20
5 5 10 15 20 25
Green=Low; Yellow= Medium; Red= High