COMPANY NAME FACILITY:
RISK RATING
WORK ACTIVITY HAZARD(S) CONTROL MEASURE(S)
1-25
Break the activity down into steps. Each step should accomplish Identify the hazards in each step and give them Identify what control measures will be implemented to
some major task and be in a logical sequence. a risk rating using the Hazard ID and Risk eliminate the hazard or minimise the risk.
Assessment Summary.
Required job activity is to remove signage from front
facade. Workers will use supported stairs to remove - - -
signage. Team of 5 persons will perform the job.
Ladder with anti slip rubber base pads will be used to
Clearing the workspace and hoisting the ladder under Slipping of workers, falling of ladder on avoid slippage. Workers will be wearing gloves, eye
3
the signboard workers glasses, anti-slip shoes and equipped with proper PPE.
While working
Injuries / cuts on hands and body during Workers will be wearing gloves, eye glasses, anti-slip
Unscrewing the sign board 3
unscrewing shoes and equipped with proper PPE. While working
Workers will be wearing gloves, eye glasses, anti-slip
Removal of the screws and dis-attaching the sign board Slipping of workers, falling of workers and shoes and equipped with proper PPE. While working at
2
to lower it to the ground items from height height workers will be equipped with fall arrest
harness.
Injuries / cuts on hands and body, slipping of
Workers will be wearing gloves, eye glasses, anti-slip
Filling the pits and paint finishing the surface workers, paint spill and chemical eye contact 8
shoes and equipped with proper PPE.
hazard
What Plant and Equipment will be used to carry out this Activity? (Note: A Plant Checklist will need to be completed)
Screw Drill, Ladder, Paint brush, & Scrappers
Risk Assessment
Ranking Method
Probability
1 2 3 4 5
5 ☐ M (5) ☐M (10) ☐ H (15) ☐ H (20) ☐ H (25)
Consequence