Professional Documents
Culture Documents
HUBBALLI 580031
BACHELOR OF ENGINEERING
In
CIVIL ENGINEERING
Submitted By
Name USN
Avinash Aneppanavar 01FE17BCV013
Chandrashekhar Allikatti 01FE17BCV021
Chinmay Kubihal 01FE16BCV028
Shreyas Shetty 01FE17BCV094
We hereby acknowledge our deep sense of gratitude and indebtedness to our guide
Dr. M. V. Chitawadagi, Professor, School of Civil and environmental Engineering
KLE Technological University, Hubballi, for suggesting this problem and for his valuable
guidance and keen interest throughout my research work. Their direction, supervision and
constructive criticism were indeed a source of inspiration for the success of the project.
We wish to express our sincere thanks to Prof. Vithal.H. Jadhav Adjunct Professor
Co-Ordinator industry internship training, School of Civil and environmental Engineering, KLE
Technological University, Hubballi, for his kind co-guidance and encouragement throughout the
dissertation work.
We wish to express our sincere thanks to company head, mentor and associate staff for
providing us this internship opportunity and giving their valuable guidance and support.
We sincerely thank Dr. V. B. Patil, Professor, Head of the department, School of Civil and
environmental Engineering, KLE Technological University, Hubballi, for his constant support and
valuable guidance in completion of work.
We are highly indebted to Dr. Ashok S Shettar, Vice Chancellor, KLE Technological
University, Hubballi for his counsel and providing necessary facility during the development of the
project.
We express our sincere thanks to all the teaching and non-teaching staff of Civil
Engineering Department and also who have extended their invaluable help and cooperation directly
or indirectly during the course of the project and thereby ensuring successful completion.
DECLARATION
Batch No. 9
Ⅷ Semester,
CONTENTS
1 INTRODUCTION ....................................................................................................................................................... 6
1.1 ABOUT THE COMPANY ................................................................................................................................. 6
1.2 VISION AND MISSION OF THE COMPANY ................................................................................................ 6
1.3 INNOVATION OF B. G. SHIRKE CONSTRUCTION TECHNOLOGY PVT. LTD. ...................................... 6
1.4 ORGANISATIONAL STRUCTURE ................................................................................................................. 7
1.5 SOME OF THE SUCCESSFUL MAJOR PROJECTS OF B.G. SHIRKE CONSTRUCTION TECH.
PVT.LTD ......................................................................................................................................................................... 8
1.6 SOME OF THE ACHIEVEMENTS OF B.G. SHIRKE CONSTRUCTION TECH. PVT.LTD ........................ 8
1.7 SALIENT FEATURES OF THE PROJECT ...................................................................................................... 8
1.8 LIST OF THE BUILDINGS IN THE CAMPUS ................................................................................................ 9
1.9 PLAN LAYOUT [MASTER PLAN] ................................................................................................................ 10
1.10 LOCATION ...................................................................................................................................................... 11
2 DRAWINGS .............................................................................................................................................................. 11
2.1 ARCHITECTURAL DRAWING ..................................................................................................................... 11
2.2 STRUCTURAL DRAWING ............................................................................................................................ 11
2.3 ELECTRICAL DRAWING .............................................................................................................................. 12
2.4 PLUMBING DRAWING .................................................................................................................................. 12
2.5 FINISHING DRAWINGS ................................................................................................................................ 12
3 EXCAVATION ......................................................................................................................................................... 13
4 FOUNDATION ......................................................................................................................................................... 13
4.1 COMPACTING THE GROUND...................................................................................................................... 13
4.2 PCC ................................................................................................................................................................... 15
4.3 FOOTING ......................................................................................................................................................... 15
4.4 REINFORCEMENT FOR FOOTING .............................................................................................................. 16
4.4.1 SHUTTERING OF FOOTING ................................................................................................................ 16
4.4.2 CONCRETING OF FOOTING ................................................................................................................ 17
4.4.3 DE-SHUTTERING AND CURING ........................................................................................................ 18
4.5 COLUMN ......................................................................................................................................................... 18
4.5.1 REINFORCEMENT FOR COLUMN...................................................................................................... 18
4.5.2 SHUTTERING FOR COLUMNS ............................................................................................................ 20
4.5.3 CONCRETING IN COLUMNS ............................................................................................................... 22
4.5.4 DE SHUTTERING AND CURING ......................................................................................................... 23
4.6 BACK FILLING ............................................................................................................................................... 23
4.7 PLINTH BEAM ................................................................................................................................................ 24
4.7.1 REINFORCEMENT OF PLINTH BEAM ............................................................................................... 24
4.7.2 SHUTTERING OF PLINTH BEAM ....................................................................................................... 24
4.7.3 CONCRETING IN PLINTH BEAMS ..................................................................................................... 25
4.7.4 DE-SHUTTERING AND CURING ........................................................................................................ 25
LIST OF FIGURES
FIGURE 1:-PLAN LAYOUT OF IIT, DHARWAD .......................................................................................................... 10
FIGURE 2:- COLUMN LAYOUT ..................................................................................................................................... 12
FIGURE 3:-FOUNDATION DRAWING .......................................................................................................................... 13
FIGURE 4 :- PLATE COMPACTOR ............................................................................................................................... 14
FIGURE 5:- ROLLER COMPACTOR (DOUBLE DRUM ROLLER) ............................................................................ 14
FIGURE 6:-CHECKING THE LEVEL OF PCC USING AUTO LEVEL ........................................................................ 15
FIGURE 7:-REINFORCEMENT FOR RAFT FOOTING ................................................................................................. 16
FIGURE 8:-SHUTTERING FOR FOOTING .................................................................................................................... 17
FIGURE 9:-CONCRETING FOR FOOTING.................................................................................................................... 17
FIGURE 10:- CURING OF COMBINED FOOTING ....................................................................................................... 18
FIGURE 11:-REINFORCEMENT OF COLUMN ............................................................................................................. 19
FIGURE 12:-STIRRUPS FOR COLUMNS ....................................................................................................................... 20
FIGURE 13:- SHUTTERING OF COLUMN .................................................................................................................... 22
FIGURE 14:-CONCRETING OF COLUMN .................................................................................................................... 22
FIGURE 15:-CURING OF COLUMN ............................................................................................................................... 23
FIGURE 16:- BACKFILLING ........................................................................................................................................... 23
FIGURE 17:-REINFORCEMENT OF PLINTH BEAM ................................................................................................... 24
FIGURE 18:-RMC PLANT ................................................................................................................................................ 25
FIGURE 19:-CONCRETE CONTROL SYSTEM ............................................................................................................. 26
FIGURE 20:-CONCRETE REQUISITION SLIP .............................................................................................................. 27
FIGURE 21:-FOSROC AURAMIX 200 ............................................................................................................................ 27
FIGURE 22:-FOSROC CONPLAST SP430 ...................................................................................................................... 28
FIGURE 23:-FOSROC AURACAST405 .......................................................................................................................... 29
FIGURE 24:FOSROC AURAMIX 300PLUS ................................................................................................................... 29
FIGURE 25:-FOSROC AURACAST 270M ...................................................................................................................... 30
FIGURE 26:- TRANSIT MIXER OF 6M3 CAPACITY .................................................................................................... 31
FIGURE 27:-AUTOCLAVE AERATED BLOCKS .......................................................................................................... 31
FIGURE 28:-CHICKEN MESH FOR PLASTERING ....................................................................................................... 33
FIGURE 29:- AAC BLOCK WALL WITH BAND BEAMS ............................................................................................ 33
FIGURE 30:-BRICK MASONRY USING AAC BLOCKS .............................................................................................. 33
FIGURE 31:- QUALITY CONTROL LAB ....................................................................................................................... 34
FIGURE 32:-FORMAT USED FOR TABULATION OF PARTICLE SIZE DISTRIBUTION OF COARSE
AGGREGATE .................................................................................................................................................................... 36
FIGURE 33:- FORMAT FOR TABULATION OF RESULTS OF TESTS ON CEMENT .............................................. 39
FIGURE 34:-FORMAT FOR TABULATION OF COMPRESSIVE TEST RESULTS ................................................... 41
FIGURE 35:-ULTRASONIC PULSE VELOCITY TEST APPARATUS......................................................................... 42
FIGURE 36:-REBOUND HAMMER TEST FOR PRECAST PLINTH BEAM ............................................................... 43
FIGURE 37:-GRAPH USED FOR CALCULATING COMPRESSIVE STRENGTH USING REBOUND NUMBER .. 44
FIGURE 38:- REFERENCE TABLE FOR CLASSIFYING RESULTS OBTAINED ...................................................... 44
FIGURE 39:-STEEL YARD .............................................................................................................................................. 44
FIGURE 40:-BAR BENDING MACHINE ........................................................................................................................ 45
FIGURE 41:-20MM DIAMETER COUPLER ................................................................................................................... 46
FIGURE 42:-REINFORCEMENT FOR PRECAST BEAM AND MOULD FOR PRECAST BEAM ............................. 46
FIGURE 43:-PRECAST COLUMN ................................................................................................................................... 47
FIGURE 44:-CURING OF PRECAST STAIRS ................................................................................................................ 47
FIGURE 45:- INSTALLATION OF PRECAST PLINTH BEAMS .................................................................................. 48
FIGURE 46:- PRECAST SLAB AND BEAM INSTALLATION .................................................................................... 49
FIGURE 47:-TOWER CRANE .......................................................................................................................................... 50
FIGURE 48:-EOT CRANE IN PRECAST YARD ............................................................................................................ 50
FIGURE 49:-HYDRA ........................................................................................................................................................ 51
FIGURE 50:-PROPPING FOR SLAB ............................................................................................................................... 52
FIGURE 51:-SAFETY PARK ............................................................................................................................................ 53
FIGURE 52:-SAFETY SUIT AND SHOES PROVIDED FOR WORKERS .................................................................... 53
FIGURE 53:- CALENDAR FOR PRIMAVERA ............................................................................................................... 96
FIGURE 54:- ACTIVITIES IN SUBSTRUCTURE .......................................................................................................... 97
School of Civil Engineering, KLETU Hubballi -580031 4
INDUSTRY INTERNSHIP TRAINING REPORT 2020-2021
1 Introduction
1.1 About the company
B. G. Shirke Construction Technology Private Limited (BGSCTPL), formerly known as B. G. Shirke
& Company, was established over 74 years ago by its Founder Chairman, Mr. Baburao Govindrao
Shirke. BGSCTPL is a multi-disciplinary civil, mechanical and electrical engineering organization
having international technology tie-ups and over 12,000 workforces. It is a vibrant, dynamic and
integral part of modern India, significantly contributing to industrial, economic and social progress.
BGSCTPL also plays an active role in protecting and preserving the country’s eco-systems – its forests
and waterways. Company is well established in the civil engineering field for over 70 years.
Today, the Shirke Group is at an enviable position in India’s Civil and Industrial engineering realm,
offering world class engineering and construction capabilities to indigenous and overseas clientele,
carrying forward Shri B. G. Shrike’s single-minded passion for civil engineering and operational
excellence.
• Performance evaluation of the system / actual load test / reverse cyclic load test etc. to evaluate
performance under seismic Zone-IV has been carried out at reputed national institutions like CBRI
Roorkee, IIT Mumbai, TOR Steel Research Foundation of India, Bangalore etc. who have
concluded that 3-S Precast System satisfies all the technical parameters and codal requirements.
• 3-S Precast System has gained wide acceptance across India with large housing, institutional and
other types of projects at New Delhi, Maharashtra, Karnataka, Tamil Nadu, Andhra Pradesh etc.
• Asia’s largest pre-casting facility with State-of-Art automated manufacturing process running at
Delhi since 2013.
1.5 Some of the Successful Major Projects of B.G. Shirke Construction Tech.
Pvt.Ltd
Sl no Name of the project Cost of the
project
1 Suvarnanasoudha, Belgaum. 400cr.
2 Indian Institute of Information Technology (IIIT), Sattur colony 114cr.
Dharwad.
3 Dr.B.R. Ambedkar school of economics (BASE), Bengaluru 170cr.
5 Institute of Medical Science, Chamarajanagar 200cr.
6 DC office complex, Mysore 80cr.
7 Haj Bhavan, Banglore 87cr.
20. GRIHA 5 For administrative Block, Central Lecture Theatre & Academic
Block-1
1.10 Location
It is situated in kelageri,chikkamalligewad village,pune-bangaluru road,opposite to Dharwad high
coart, dharwad, karnataka – 580011
2 Drawings
Drawings plays an important role in the construction field to convey the ideologies and perspective of
the designer to the layman at site.
Types of Construction Drawings
1) Architectural Drawing
2) Structural Drawing
3) Electrical Drawing
4) Plumbing Drawing
5) Finishing Drawings
1) Site Plan
This is primary drawing used for marking out the plan on the ground. It represents the location,
orientation and information about the site’s topography, landscaping utilities, and site work.
2) Working Plan
This drawing gives the information of horizontal dimensions of the building, thickness of walls,
clear spaces inside the building and column locations. It also shows the openings required in
the building such as doors, windows and ventilators.
3) Section Drawings
Section drawings represents the material of construction to be used, heights and measurement
of the different components of buildings, type of structural components such as type of slab,
etc. It represents the drawing when the building is cut through a vertical plane
4) Elevation Drawing
Elevation drawing represents the information of openings, size and shape of external surface,
height of building and finish of the building after completion. These drawings are made by
having an aesthetic view of the building
It contains many types of drawing with very minute details and description.
1) General Note
This is more of codes and by- laws of the buildings. No drawing is found in this, but the details
of all the structural drawings are mention in this such as concrete mix, lapping length, curing
time, abbreviation, codes and other work procedures.
2) Excavation Drawing
This drawing represents the footing excavation dimension, column position, footing plan and
grid lines of column.
3) Column Layout
This drawing represents the position and orientation of columns and column reinforcement
details.
3 Excavation
Excavation is carried out for the construction of foundations. Excavation is carried out as per the
drawings defined lengths & widths. Quantity of excavation was calculated assuming the depth of
excavation as 4m and 1m working space was given and it was included in the excavated quantity.
Quantity of excavation is calculated in m3 (length(m) x width(m) x depth(m)). Cost of excavation
varied for different soil strata depending on depth of excavation. Crawler excavator and wheel
excavator were used for excavation. Excavated soil is preserved nearby to the site for backfilling.
4 Foundation
4.1 Compacting the ground
The excavated pits are trimmed and dressed as per the requirement and the bottom is compacted using
hand compactors (plate compactor) and roller compactors. The compaction is done in such way that
uniform level is to be maintained throughout the excavated area where PCC is to be laid. The levels
are continuously checked using auto level. Hand compactors are usually used to for compaction around
columns or around any other concrete structure where there is no space for roller compactor to
function.
Specifications of roller
Capacity of the compactor= 4.36 ton per drum
Weight of the compactor=3225 kg
Width of drum =1250mm
4.2 PCC
PCC is a solid base on which the reinforcement can be tied and footing can be placed. PCC is laid to
have levelled surface. Shuttering for PCC is calculated by taking perimeter of the portion where PCC
is to be laid. Grade of concrete used for PCC is M15. The ratio of the concrete mix is 1:3:5. Thickness
of PCC is 100mm and it is maintained throughout the PCC bed. The concrete arrived in the transit
mixer is poured on the site and is spread over the compacted earth soil. The levels are checked using
auto level. Curing period for PCC is 14 days. Surface of PCC is covered with hessian cloth and flooded
with water and left for curing.
4.3 Footing
A footing is a part of the foundation that helps support the foundation so that the structure does not
settle.
Purpose of Footings
1) In order to transfer forces from superstructure to firm soil below.
2) To distribute stresses evenly on foundation soil such that foundation soil neither fails nor
experiences excessive settlement.
3) In order to develop an anchor for stability against overturning.
4) In order to provide an even surface for smooth construction of superstructure.
2) Combined footing: - When a footing is provided under a few columns standing close together
it is called a combined column footing. These are used when the columns are too close together
to provide separate footings and if the footings are heavily loaded.
3) Raft Foundation: - Raft foundation is a combined footing that covers the entire area beneath a
structure and supports all the walls and columns.
4.5 Column
A column or pillar is a structural element that transmits, through compression, the weight of the
structure above to other structural elements below.
Different shapes of column observed on the site
1. Circular columns
2. Rectangle columns
3. Square shaped columns
Size of the columns as observed on the site
1. 500x1750
2. 500x1200
3. 500x1050
4. 500x850
5. 500x500
4.5.1.1 Stirrups
The main purpose of stirrup is to hold the primary reinforcement bars. They also prevent columns and
beams from buckling. The stirrups get placed diagonally when there is tension and compression caused
by vertical and transverse section. Two legged stirrups are adequate for typical beams with short widths
while multiple -legged stirrups will be required for beams with longer web width
Different types of stirrups observed on the site.
1) Single legged stirrups.
2) Two-legged stirrups.
3) Four-legged stirrups.
4) Six legged stirrups.
Different shapes of stirrups observed on the site
1) Triangle shaped
2) Circular shaped
3) Rectangle shaped
4) Diamond shaped
5) Trapezoidal shaped
5 RMC Plant
Ready-mix concrete (RMC) is concrete that is manufactured in a batch plant, according to a set
engineered mix design. Ready-mix concrete is often used instead of other materials due to the cost and
wide range of uses in building, particularly in large projects like high-rise buildings and bridges.
The site engineers place the order for the concrete through concrete requisition slip. The RMC plant
on the site works on a software. Name of the software is SANY. The software controls the whole
concrete system. Electronic weigh batching is used in the RMC plant. The size of coarse aggregates
used in the site are 20mm downsize and 12mm downsize. Aggregates are stored near the RMC plant.
Cement and GGBS is stored in silos of capacity 100ton.The aggregates are loaded to the RMC plant
using wheel loader. The aggregates are transferred to the weighing bin through conveyor belt system.
The aggregates are weighed and transferred to the mixing bin. The cement and GGBS is added to the
mixing bin through the pipes. The required quantity of water and admixture is also transferred to the
bin where mixing takes place for around two mins. The ratio of cement to ggbs is 75:25. After mixing
the concrete is transferred to the transit mixer and is sent to the required location. The mix design is
choose depending on the grade of concrete ordered by site engineer. The moisture content of the
aggregate is regularly monitored to maintain the water content specified for particular mix design.
Moisture content test is regularly conducted in the quality control lab and the results are updated to the
RMC plant. The plant operator modifies the mix design according to the present moisture content of
the aggregates. While modifying any mix design care is taken such that density of the concrete mix
design remains same. If the moisture content is high in the aggregates water content is reduced and
quantity of aggregates and cement is increased to maintain the density of the concrete.
Advantages
• Low viscosity admixture suitable for pumping different grades of concrete to greater
heights.
• Suitable for concrete having cement replacements and low water cement ratio.
• Provides higher strength without increase in cement content or reduction in workability.
Ideal for precast concrete production.
• Reduce rate of workability loss normally associated with super plasticiser. Reduces
shrinkage cracking because of lower water cement ratio. Makes the concrete
water impermeable.
• Better resistance to Carbonation.
• Reduce Shrinkage and Creep.
• Increase Durability.
5.1.1.1 Advantages
• Major increases in strength at early ages without increased cement contents are of
particular benefit in precast concrete, allowing earlier stripping times.
• Makes possible major reductions in water: cement ratio which allow the production of
high strength concrete without excessive cement contents.
• Use in production of flowing concrete permits easier construction with quicker placing
and compaction and reduced labour costs without increasing water content.
• Increased workability levels are maintained for longer than with ordinary sulphonated
melamine admixtures.
• Improved cohesion and particle dispersion minimises segregation and bleeding and
improves pumpability.
• Chloride free, safe for use in pre-stressed and reinforced concrete.
• In screed material, the lower water content leads to quicker drying times
5.1.1.2 Advantages
• Low viscosity admixture suitable for precast industry
• Suitable for concrete having cement replacements and low water cement ratio
• Provides high early strength without increase in cement content or reduction in workability
• Reduce rate of workability loss normally associated with super plasticiser.
• Reduces shrinkage cracking because of lower water cement ratio. Makes the concrete
water impermeable
• Better resistance to Carbonation
Advantages
5.FOSROCAuracast 270M
Auracast 270M is a high-performance super plasticizer suitable for precast concrete industry to
obtain high early strength and moderate workability retentions are required.
Advantages
• AAC Block Autoclaved aerated concrete. It is lightweight, precast, foam concrete building
material suitable for concrete masonry unit.
• Different size of AAC Block is available in market are
1) 600mm × 200mm × 100mm
2) 600mm × 200mm × 150mm,
3) 600mm × 200mm × 200mm
4) 600mm × 200mm × 225mm.
• Water absorbing capacity of AAC Block are about 10% of their weight
1) Dry density of first class AAC blocks are 651 – 750 kg/m3
• AAC Block is Non load bearing material; it can be used only in wall partitions.
• AAC block is brittle in nature that means it can break easily. Presence of voids makes it brittle
in nature.
• Their water absorption is very high. With this their expansion on absorbing water and
• AAC blocks sides are smooth in nature so plastering will not withstand in smooth surface to
• Ferrous -1188 is polymer modified adhesive used to fix AAC blocks, hollow blocks and
• Rapid setting, fast installation and no curing required are the advantages.
• Band beams are provided for every 1.2m as the walls constructed using AAC blocks are not
load bearing.
Quality control can be defined as part of quality management focused on fulfilling quality
requirements. Each and every material used in construction were tested in the QC lab. Test were
conducted on every 50m3 of material after arriving on the site. Materials like steel, cement, AAC blocks
required material testing certificate from the company.
Non-destructive tests:
• Ultrasonic Pulse Velocity (UPV)
• Rebound Hammer Test
• Sieve analysis of aggregates were done before procuring the material to know whether
aggregate is single size aggregate or well graded aggregate.
• The size of coarse aggregate used on the site were 12 mm down size and 20 mm down size.
• Sieve analysis was conducted for every 50 m3 of material.
• If the test results satisfied the specifications of particular material, it was accepted otherwise
the material is rejected.
Procedure
1. The sample shall be brought to an air-dry condition before weighing and sieving.
This may be achieved either by drying at room temperature or by heating at a
temperature of 100‖ to 110°C.
2. The air-dry sample shall be weighed and sieved successively on the appropriate
sieves starting with the largest. Care shall be taken to ensure that the sieves are clean
before use.
3. Each sieve shall be shaken separately over a clean tray until not more than a trace passes
case for a period of not less than two minutes.
4. The shaking shall be done with a varied motion, backward sand forwards, left to right,
circular clockwise and anti-clockwise, and with frequent jarring, so that the material is kept
moving over the sieve surface in frequently changing directions.
5. Material shall not be forced through the sieve by hand pressure Lumps fine material if
present may be broken by gentle pressure with fingers against the side of the sieve.
6. On completion of sieving, the material retained on each sieve together with any
material cleaned from the mesh shall be weighed.
7. The obtained results are tabulated in the format shown below in figure and the
calculations are done.
2. Immediately. after immersion the entrapped air shall be removed from the sample by lifting
the basket containing it 25 mm above the base of the tank and allowing it to drop 25 times
at the rate of about one drop per second. The basket and aggregate shall remain completely
immersed during the operation and for a period of 24 ± l/2 hours afterwards.
3. The basket and the sample shall then be jolted and weighed in water at a temperature of 22°C
to 32°C (weightA1).
4. The basket and the aggregate shall then be removed from the water and allowed to drain for
a few minutes, after which the, aggregate shall be gently emptied from the basket on to one
of the dry clothes, and the empty basket shall be returned to the water and weighed in water
(weight A2).
5. The aggregate placed on the dry cloth shall be gently surface dried with the cloth, transferring
it to the second dry cloth when the first will remove no further moisture. The aggregate shall
then be weighed (weight B).
6. The aggregate shall then be placed in the oven in the shallow tray, at a temperature of 100 to
110°C and maintained at this temperature for 24 ± l/2 hours. It shall then be removed from
the oven, cooled in the airtight container and weighed (weight).
7. Calculations—Specific gravity, apparent specific gravity and water & absorption shall be
calculated as follows-
Specific gravity= C /(A-B)
Water absorption= 100 x(B-C)/C
4. Measure the distance separating the indicator points to the nearest 0.5 mm. Submerge the
mould again in water at the temperature prescribed above.
5. Bring the water to boiling, with the mould kept submerged, in 25 to 30 minutes, and keep it
boiling for three hours. Remove the mould from the water, allow it to cool and measure the
distance between the indicator points.
6. The difference between these two measurements indicates the expansion of the cement. This
must not exceed 10 mm for ordinary, rapid hardening and low heat Portland cements. If in
case the expansion is more than 10 mm as tested above, the cement is said to be unsound.
2. The material for each cube shall be mixed separately and the quantity of cement,
standard sand and water shall be as follows:
Cement 200 g and Standard Sand 600, Water 0.3 percent of combined mass of cement
and sand, where P is the percentage of water required to produce a paste of standard
consistency determined as described in IS: 4031 (Part 4)-1988 or Experiment No.1(a).
3. Place on an on porous plate a mixture of cement and standards and mix it dry with a trowel for one
minute and then with water until the mixture is of uniform color.
4. The quantity of water to be used shall be as specified in step 2. The time of mixing shall in any
event be not less than 3 min and should the time taken to obtain a uniform color exceed 4 min, the
mixture shall be rejected and the operation repeated with a fresh quantity of cement, sand and
water.
5. Molding Specimens-In assembling the mounds ready for use treat the interior faces of the mould
with a thin coating of mould oil.
6. Place the assembled mould on the table of the vibration machine and hold it firmly in position
by means of a suitable clamp. Attach a hopper of suitable size and shape securely at the top of
the mould to facilitate filling and this hopper shall not be removed until the completion of the
vibration period.
7. Immediately after mixing the mortar in accordance with step 1 & 2, place the mortar in the cube
mould and prod with the rod.
8. Place the mortar in the hopper of the cube mould and prod again as specified for the first layer
and then compact the mortar by vibration.
9. The period of vibration shall be two minutes at the specified speed of 12 000 ± 400 vibration per
minute.
10. At the end of vibration, remove the mould together with the base plate from the machine and
finish the top surface of the cube in the mould by smoothing the surface with the blade of a
trowel.
11. Curing Specimens - keep the filled mounds in moist closet or moist room for 24 ± 1 hour after
completion of vibration.
12. At the end of that period, remove them from the mounds and immediately submerge in clean
fresh water and keep there until taken out just prior to breaking.
13. The water in which the cubes are submerged shall be renewed every 7 days and shall be
maintained at a temperature of 27 ± 2°C. After they have been taken out and until they are broken,
the cubes shall not be allowed to become dry.
14. Test three cubes for compressive strength for each period of curing mentioned under the relevant
specifications (i.e., 3 days, 7 days, 28days)
15. The cubes shall be tested on their sides without any packing between the cube and the steel
plattens of the testing machine.
16. One of the plattens shall be carried on a base and shall be self-adjusting, and the load shall
be steadily and uniformly applied starting from zero at a rate of 35 N/mm2/min.
v) Separation of transducer leads: It is advisable to prevent the two transducer leads from coming into
close contact with each other when the transit time measurements are being taken. If this is not done,
the receiver lead might pick-up unwanted signals from the transmitter lead and this would result in an
incorrect display of the transit time.
1. The test thus can be conducted horizontally on vertical surface and vertically upwards or
downwards on horizontal surfaces.
2. For testing, smooth, clean and dry surface is to be selected. If loosely adhering scale is present,
this should be rubbed off with a grinding wheel or stone. Rough surfaces resulting from
incomplete compaction, loss of grout, spalled or tooled surfaces do not give reliable results and
should be avoided.
3. The point of impact should be at least 20 mm away from any edge or shape discontinuity.
4. For taking a measurement, the rebound hammer should be held at right angles to the surface of
the concrete member. The test can -thus be conducted horizontally on vertical surfaces or
vertically upwards or downwards on horizontal surfaces. If the situation demands, the rebound
hammer can be held at intermediate angles also, but in each case, the rebound
5. Rebound hammer test is conducted around all the points of observation on all accessible faces
of the structural element.
8 Steel Yard
All the steel is stored in the steel yard. Cutting bending forging and threading is all done in the steel
yard. Reinforcement for all the structures is prepared according to the structural drawings.
8.3 Couplers
Couplers are used for lapping of bars of size greater than 16mm in the column. couplers are effective
and an economic replacement of lap splice. Size of the couplers used in the site are
20mm,25mm,32mm. Reducers were also used on the site. Couplers are used to avoid congestion of
bars due to lapping. Couplers are cost effective as 1m length of lapping costs more than a coupler as
shown in table 1. For bars less than16 mm diameter cost of lapping is almost equal to the cost of
manufacturing couplers so couplers are used for more than 16mm diameter bars.
9 Precast Construction
Precast concrete is a construction product produced by casting concrete in a reusable mould or form
which is then cured in a controlled environment, transported to the construction site and lifted into
place. There were 4 precast buildings on our site.
FIGURE 42:-REINFORCEMENT FOR PRECAST BEAM AND MOULD FOR PRECAST BEAM
The production of precast concrete elements takes place under controlled conditions in
enclosed factories. This means that tolerances can be accurately controlled, waste can be minimised,
and that a denser, stronger and better quality concrete can be produced.
On the site the adjustable moulds for beams, columns, slabs are stairs were available. The precast
moulds were ordered from the head office. The moulds of precast were adjusted as per the size
required. Reinforcement is done according to the structure drawing. Clear covers were provided as
mentioned in the drawings. The moulds were cleaned and greased before pouring the concrete. Grade
of concrete was depending on the precast structure. The admixtures used in precast construction are
Fosroc Auramix 200 and Fosroc Auramix 450. The mould was placed on a vibrating system which
compacted the concrete coming into the moulds. vibrating needles were also used for compaction
wherever necessary. Demoulding was done after 16hours. Curing was done for 14 days. Concrete is
cast into forms and left to cure. Precast forms are normally made of steel or plywood.
Whereas plywood forms are usually limited to about 20-50 castings.
9.2 Applications
Reinforced concrete is usually used for structural systems due to its strength, durability,
and affordability. Precast concrete is used in the following ways:
▪ To make beams, columns, floor slabs, foundations, and other structural members for buildings.
▪ To make wall or cladding panels for buildings.
▪ To make precast pre-stressed elements for buildings.
▪ To make components for infrastructure projects: elements such as bridge spans, or metro line
viaducts are often precast in a casting yard.
▪ To make products such as precast water tanks, septic
tanks, drainage chambers, railway sleepers, floor beams, boundary walls and water pipes.
▪ As it can be moulded into any shape, it can also be used to create one-off unusual forms such as
boats, sculptures and so on.
9.4 Installation
The on-site installation of precast components can be a high-risk activity involving the use of heavy
plant, cranes and personnel working at height. Consideration should be given therefore
to safeguarding against risks when receiving delivery, moving, and placing units.
10 Cranes
10.1 Tower crane
A tower crane is a fixed crane capable of hauling heavy loads to precarious heights.
Tower cranes were used for the following purposes.
1) Pouring concrete in the columns, foundation.
2) Shifting heavy weight materials from one place and placing them wherever required.
For example, shifting steel reinforcement, shuttering etc.
3) Tower crane is mainly used for installation of precast structures.
4) The radius cover by tower cranes on the site was 50m
An overhead crane also known as a bridge crane is a type of crane where the hook-and-line mechanism
runs along a horizontal beam that itself runs along two widely separated rails. This type of cranes was
used to lift precast slabs.
FIGURE 49:-HYDRA
Hydra generally operate a boom from the end of which a hook is suspended by wire
rope and sheaves. Maximum capacity of the hydra is 15ton.
Hydra was used on the site for following purposes-
1) Pouring concrete in the columns
2) To transport ready steel reinforcement from steel yard to required location
3) Placing or installation of precast structures.
11 Formwork
11.1 Requirements of Good Formwork
1. It should be strong enough to withstand all types of dead and live loads.
2. It should be rigidly constructed and efficiently propped and braced both horizontally and
vertically, to retain its shape.
3. The joints in the formwork should be tight against leakage of cement grout.
4. Construction of formwork should permit removal of various parts in desired sequences without
damage to the concrete.
5. The material of the formwork should be cheap, readily available, and should be suitable for
reuse.
6. The formwork should be set accurately to the desired line, and levels should have a plane
surface.
7. It should be as light as possible.
8. The material of the formwork should not warp or get distorted when exposed to the elements.
9. It should rest on a firm base.
12 Propping
Propping is a system of structural members used temporarily to support loads during construction. The
forces arising from these loads must be fully resolved, using props or columns to provide all the support
needed for the work under construction, such as beams, formwork.
Process of designing a system of props:
• Calculation of all the loads to be supported.
• Then they must consider the characteristics of the support points.
• On the basis of these, they must select appropriate materials.
• Then they calculate all the forces and make a propping design to resolve those forces.
The strutting and wind-bracing of a propping structure is particularly important to prevent sagging and
"buckling". These are the members that resist the deformation of the structure: they consist of diagonal
members forming triangles with the vertical structural members, thus reinforcing and stabilising them.
13 Safety Park
➢There are many methods of training construction workers. One method is coaching construction site
foremen to include safety in their daily verbal exchanges with workers to reduce work-related
accidents.
➢Another method is ensuring that all workers know how to properly use electronics, conveyors, skid-
steer, trucks, aerial lifts, and other equipment on the construction site.
14 IS CODES USED
Sr. IS CODE YEAR OF DESCRIPTION
NO NO./BOOK NO PUBLICATION/PART
NO
5. IS:1786-2008 2008 High strength deformed steel bars and wires for
concrete reinforcement-Specification
12. IS:6441-1972 1972(Reaffirmed 2005) Methods of test for autoclaved cellular concrete
products
13. IS:6441-1972 1972(Reaffirmed 2005) Methods of test for autoclaved cellular concrete
products
14. IS:6441-1972 1972(Reaffirmed 2005) Methods of test for autoclaved cellular concrete
products
22. IS:2386-1963 1963(Reaffirmed 2005) Methods of tests for strength of concrete: Particle size
and shape
23. IS:2386-1963 1963(Reaffirmed 2005) Methods of tests for strength of concrete: Estimation
of deleterious materials and organic impurities
24. IS:2386-1963 1963(Reaffirmed 2005) Methods of tests for strength of concrete: Specific
gravity, density, voids, absorption and bulking
25. IS:2386-1963 1963(Reaffirmed 2005) Methods of tests for strength of concrete: Measuring
mortar making properties of fine aggregate
32. IS:2202-1999 1999(Reaffirmed 2005) Wooden flush door shutters (solid core type) –
Specification: plywood face panels
34. IS:287-1993 1993(Reaffirmed 2005) Permissible moisture content for timber used for
different purposes - recommendations
36. IS:13630-2006 2006 Ceramic tiles – methods of test, sampling and basis
acceptance
40. IS:3952-1988 1988(Reaffirmed 2005) Specification for burnt clay hollow bricks for walls
and partition
42. IS:432-1982 1982 Sp.for mild steel and medium tensile steel bars and
hard drawn steel wires for concrete Rf: Mild steel and
uniform tensile steel bars
43. IS:2645-2003 2003(Reaffirmed 2005) Integral waterproofing compounds for cement mortar
and concrete - specification
45. IRC:44-2017 2017 Guidelines for cement concrete mix designs for
pavements
50. IS:1498-1970 1970(Reaffirmed 2002) Classification and identification of soil for general
engineering purposes
51. IS:16714-2018 2018 Ground granulated blast furnace slag for use in
cement, mortar and concrete – specification
56. IS:1122-1974 1974(Reaffirmed 2003) Method of test foe determination of true specific
gravity of natural building stones
57. IS:2720(PART- 1973 Rapid determination of water content from the gas
2)-1973 pressure developed by the reaction of calcium carbide
with the free water of the soil.
16 ONLINE INTERNSHIP
Fund Head
:-
Major Head
:-
Minor Head
:-
Departmental Head
:-
Service Head
:-
Estimate prepared by
:-
Administratively approved
:-
Technically approved / sanctioned
:-
Checked By: -
Assistant Engineer Assistant Executive Engineer
Executive Engineer
4 Subtotal 1 16,074,430.6
7 Subtotal 2 18,887,455.94
3 concrete in footing
6 backfilling
KSRB 2.3 : Filling available excavated earth ( excluding
rock ) in sides of foundations upto plinth in layers not
exceeding 20 cms. in depth, compacting each deposited
layer by ramming after watering with lead upto 50 m. and
lift upto 1.5 m. including cost of all labour complete as
per specifications. specification. No. KBS 2.9
for foundation
volume of soil cum 30 2.1 1.8 1.8 192.78
volume of column cum 26 0.23 0.45 1.7 4.575
4 0.23 0.6 1.7 0.938
300mm layer above ground beam cum 1 28.55 27.8 0.3 238.11
column 26 0.23 0.45 0.3 4.575
4 0.23 0.6 0.3 0.938
total backfilling= 419.86
7
Concreting in beams cum
KSRB 4.2.7 : Providing and laying in position
reinforced cement concrete of design mix M25 with
OPC cement @ 340kgs, with 20mm and down size
graded granite metal coarse aggregates @0.70cum
and fine aggregates @ 0.47cum, with superplastisiser
@3lts confirming to IS9103-1999 Reaffirmed-2008,
machine mixed, concrete laid in layers not exceeding
15 cms thick, vibrated for all works in ground floor level
for roof slabs, staircase, lintels and beams retaining
walls, return walls, walls (any thickness) including
attached pilasters, columns, ,pillars, posts, struts,
buttresses, string or lacing courses, parapets, coping,
bed blocks, anchor blocks, plain window cills, fillets
etc., including cost of all materials, labour, HOM of
machinery, curing, complete but excluding cost of
reinforcement as per specifications. Specification No.
KBS 4.1, 4.6
1.ground beam cum 1 207.04 0.23 0.45 21.428 Running Length = 207.04m (centre line method)
2.basement beam cum 1 207.04 0.23 0.45 21.428
3.cantilever beam cum 6 2 0.23 0.45 1.242
5 1.5 0.23 0.45 0.776*2 = 1.55
2.79
cum total= 46.88
8
Shuttering for beams
KSRB 4-6.7 :Providing and removing centering,
shuttering, strutting, propping etc., and removal of form
work for sides and soffits of beams, beam haunchings,
cantilever girders, bressumers and lintels not
exceeding 1m in depth including cost of all materials,
labour complete as per specifications. Specification
No. KBS 4.6.2
1. Ground beam
For sides sqm 2 207.04 0.045 186.336 Running Length = 207.04m (centre line method)
2. Basement beams
For sides sqm 2 207.04 0.45 186.336
For Bottom sqm 1 207.04 0.23 47.61
3. Cantilever beams
For sides sqm 6 2 0.45 5.4*2 = 10.8
For bottom sqm 6 2 0.23 2.76
For sides sqm 10 1.5 0.45 6.75*2 = 13.5
For bottom sqm 10 1.5 0.23 3.45
Deduction
Columns sqm 26 0.23 0.45 2.691(-)
4 0.23 0.6 0.552(-)
Total = 261.213
9
Concreting of column
KSRB 4.2.7 : Providing and laying in position
reinforced cement concrete of design mix M25 with
OPC cement @ 340kgs, with 20mm and down size
graded granite metal coarse aggregates @0.70cum
and fine aggregates @ 0.47cum, with superplastisiser
@3lts confirming to IS9103-1999 Reaffirmed-2008,
machine mixed, concrete laid in layers not exceeding
15 cms thick, vibrated for all works in ground floor level
for roof slabs, staircase, lintels and beams retaining
walls, return walls, walls (any thickness) including
attached pilasters, columns, ,pillars, posts, struts,
buttresses, string or lacing courses, parapets, coping,
bed blocks, anchor blocks, plain window cills, fillets
etc., including cost of all materials, labour, HOM of
machinery, curing, complete but excluding cost of
reinforcement as per specifications. Specification No.
KBS 4.1, 4.6
Below ground level cum 26 0.23 0.45 1.25 3.36 Type 1 column=26(0.23×0.45)
4 0.23 0.6 1.25 0.69 Type 2 column=4(0.23×0.6)
In basement cum 26 0.23 0.45 2.55 6.86 Type 1 column=26(0.23×0.45)
4 0.23 0.6 2.55 1.4 Type 2 column=4(0.23×0.6)
10
Shuttering for column
Basement
For column of 0.23*0.45
along 0.23 side sqm 2 0.23 2.55 1.173
along 0.45 side sqm 2 0.45 2.55 2.295
3.468*26 =90.168
For column of 0.23*0.6
along 0.23 side sqm 2 0.23 2.55 1.173
along 0.6 side sqm 2 0.6 2.55 3.06
4.23*4 = 16.932
For basement 107.1
11
concreting for slab
KSRB 4.2.7 : Providing and laying in position
reinforced cement concrete of design mix M25 with
OPC cement @ 340kgs, with 20mm and down size
graded granite metal coarse aggregates @0.70cum
and fine aggregates @ 0.47cum, with superplastisiser
@3lts confirming to IS9103-1999 Reaffirmed-2008,
machine mixed, concrete laid in layers not exceeding
15 cms thick, vibrated for all works in ground floor level
for roof slabs, staircase, lintels and beams retaining
walls, return walls, walls (any thickness) including
attached pilasters, columns, ,pillars, posts, struts,
buttresses, string or lacing courses, parapets, coping,
bed blocks, anchor blocks, plain window cills, fillets
etc., including cost of all materials, labour, HOM of
machinery, curing, complete but excluding cost of
reinforcement as per specifications. Specification No.
KBS 4.1, 4.6
basement cum 1 23.55 20.8 0.15 73.476
deduction of staircase cum 1 3.227 4.5 1.5 21.78
total concreteing for basement slab=51.69
12
form work for slab
KSRB 4-6.9 :Providing and removing centering,
shuttering, strutting, propping etc., for edges of slabs
and breaks in floor including cost of all materials,
labour complete as per specifications. Specification
No. KBS 4.6.2
for basement
for sides
along 23.55 sqm 2 23.55 0.15 7.065
along 20.8 sqm 2 20.88 0.15 6.24
13
concreteing in staircase
steps inside buillding
KSRB 4.2.7 : Providing and laying in position
reinforced cement concrete of design mix M25 with
OPC cement @ 340kgs, with 20mm and down size
graded granite metal coarse aggregates @0.70cum
and fine aggregates @ 0.47cum, with superplastisiser
@3lts confirming to IS9103-1999 Reaffirmed-2008,
machine mixed, concrete laid in layers not exceeding
15 cms thick, vibrated for all works in ground floor level
for roof slabs, staircase, lintels and beams retaining
walls, return walls, walls (any thickness) including
attached pilasters, columns, ,pillars, posts, struts,
buttresses, string or lacing courses, parapets, coping,
bed blocks, anchor blocks, plain window cills, fillets
etc., including cost of all materials, labour, HOM of
machinery, curing, complete but excluding cost of
reinforcement as per specifications. Specification No.
KBS 4.1, 4.6
for waist slab cum 2 3.49 0.15 0.15 1.57
for each step cum 18 1/2*0.19*0.3*0.15 0.77
14
shuttering of staircase
KSRB 4-6.11 :Providing and removing centering,
shuttering, strutting, propping etc., and removal of form
work for Stairs (excluding landing) except spiral
staircase including cost of all materials, labour
complete as per specificaiton. Specification No. KBS
4.6.2
waist slab shuttering area sq.m
waist slab area sq.m 2 3.49 0.15 1.05
sides area sq.m 2 1.5 0.15 0.45
bottom area sq.m 1 3.49 1.5 5.24
6.73 2 number of waist slab
total area= 13.46
15
Plastering
KSRB15-3.8 : Providing 18mm thick cement plaster in
single coat with cement mortar 1:4, to brick masonry
including rounding off corners wherever required
smooth rendering, : Providing and removing
scaffolding, including cost of materials, labour, curing
complete as per specifications.
1.Column Vertical sq.m 2 0.45 3 2.7 FOR ONE COLUMN THE SURFACE AREA FOR PLASTERING
THERE ARE 26 COLUMNS OF SIZE 1.45X0.23
Horizontal sq.m 2 0.23 3 1.38
4.08
total surface area 106.08
2.COLUMN GRID A sq.m 2 0.6 3 3.6
beams of basements
along depth 10 1.5 0.45 13.5 6.75*2=13.5
along breadth 10 1.5 0.23 3.45
30.81
below shop 6
along breadth sq.m 2 4 0.23 1.84
along depth sq.m 2 4 0.45 7.2
along breadth sq.m 2 4.25 0.23 1.955
along depth sq.m 2 4.25 0.45 7.65 same for below wc
37.29
below shop 5
along breadth sq.m 4 3.8 0.23 3.5
along depth sq.m 4 3.8 0.45 13.68
along breadth sq.m 2 4.25 0.23 2.93
along depth 3 4.25 0.45 11.475
31.585
below shop 1
along breadth sq.m 4 3.8 0.23 3.5
along depth sq.m 4 3.8 0.45 13.68 same below shop2,3,4
along breadth sq.m 3 5.9 0.23 4.071
along depth sq.m 4 5.9 0.45 21.24
169.964
at main corridor
along breadth sq.m 3 3.227 0.23 2.23
along depth sq.m 3 3.227 0.45 4.36
6.59
at rear end sq.m 6 1.6 0.23 2.21
sq.m 6 1.6 0.45 4.32
6.53
4.Slab sq.m 1 23.55 20.08 466.67 substract beam area from slab
Staircase
Total surface area of staircase insde building=
Total surface area of waist slab
at side sq.m 2 3.49 0.15 1.047
at bottom sq.m 2 3.49 1.5 10.47
for each step
tread surface sq.m 1 1.5 0.3 0.45
riser surface sq.m 1 1.5 0.19 0.285
triangular surface sq.m 1 1/2*0.19*1.5 0.142
sq.m total 0.877
for 18 steps 15.79 0.877*18
landing surface area 1 3.227 3 9.68
sq.m plastering for steps= 36.983 15.789+1.047+10.47+9.68
17
steel work
KSRB 4.9.2 : Providing T.M.T steel reinforcement for
R.C.C work including straightening, cutting, bending,
hooking, placing in position, lapping and / or welding
wherever required, tying with binding wire and anchoring to
the adjoining members wherever necessary complete as per
design (laps, hooks and wastage shall not be measured and
paid) cost of materials, labour, HOM of machinery complete
as per specifications. Specification No. KBS 4.6.3 - TMT
bars Fe 500
basement
Footing(0.5%) quintal 1 0.17 78.5 13.35 Density of steel=78.5 q/m³
ground beams(1%) quintal 1 0.22 78.5 17.27
roof beams(1%) quintal 1 0.22 78.5 17.27
columns(1.5%) quintal 1 0.18 78.5 14.13
slabs(0.8%) quintal 1 0.41 78.5 32.19
Staircase(0.8%) quintal 1 0.02 78.5 1.57
total 95.77
18 Ramp Concrete(M25)
KSRB 4.2.7 : Providing and laying in position reinforced
cement concrete of design mix M25 with OPC cement @
340kgs, with 20mm and down size graded granite metal
coarse aggregates @0.70cum and fine aggregates @
0.47cum, with superplastisiser @3lts confirming to IS9103-
1999 Reaffirmed-2008, machine mixed, concrete laid in
layers not exceeding 15 cms thick, vibrated for all works
in ground floor level for roof slabs, staircase, lintels and
cum 1 9.5 4.5 1.8 38.475 Area=1/2×9.5×1.8
beams retaining walls, return walls, walls (any thickness)
including attached pilasters, columns, ,pillars, posts,
struts, buttresses, string or lacing courses, parapets,
coping, bed blocks, anchor blocks, plain window cills,
fillets etc., including cost of all materials, labour, HOM of
machinery, curing, complete but excluding cost of
reinforcement as per specifications. Specification No.
KBS 4.1, 4.6
19 FLOORING Sqm
KSRB 14.6-2 :Providing and laying heavy duty cobble
stones 75mm thick interlock pavers, using cement and
course sand for manufacture of blocks of approved size,
shape and colour with a minimum compressive strength
of 281 kg per sqm over 50mm thick sand bed (average
thickness ) and compacting with plate vibrator having 3
tons compaction force thereby forcing part of sand
underneath to come up in between joints, final
compaction of paver surface joints into its final level,
including cost of materials, labour and HOM of
machineries complete as per specifications. Specification
No. KBS
area Sqm 1 23.55 20.80 489.84
deductions 0
column Sqm 26 0.45 0.23 2.691
Sqm 4 0.23 0.6 0.552
Sqm total 486.597
2
shuttering of beams
KSRB 4-6.7 :Providing and removing
centering, shuttering, strutting, propping etc.,
and removal of form work for sides and soffits
of beams, beam haunchings, cantilever
girders, bressumers and lintels not exceeding
1m in depth including cost of all materials,
labour complete as per specifications.
Specification No. KBS 4.6.2
ground floor beams
For sides sqm 2 207.04 0.45 186.336
For Bottom sqm 1 207.04 0.23 47.61
Cantilever beams
For sides sqm 6 2 0.45 5.4*2 = 10.8
For bottom sqm 6 2 0.23 2.76
For sides sqm 10 1.5 0.45 6.75*2 = 13.5
For bottom sqm 10 1.5 0.23 3.45
Deduction
Columns sqm 26 0.23 0.45 2.691(-)
4 0.23 0.6 0.552(-)
Total = 261.213
Lintels
window sqm
for sides sqm 23 2 1.8 0.18 14.904
for ends sqm 23 2 0.23 0.18 1.9044
Total = 16.8084
shutters
for sides sqm 7 2 3.3 0.33 15.246
for ends sqm 7 2 0.23 0.33 1.0626
Total = 16.3086
33.117
Concreting of column
KSRB 4.2.7 : Providing and laying in position
reinforced cement concrete of design mix M25
with OPC cement @ 340kgs, with 20mm and
down size graded granite metal coarse
aggregates @0.70cum and fine aggregates @
0.47cum, with superplastisiser @3lts
confirming to IS9103-1999 Reaffirmed-2008,
machine mixed, concrete laid in layers not
exceeding 15 cms thick, vibrated for all works
in ground floor level for roof slabs, staircase,
lintels and beams retaining walls, return walls,
walls (any thickness) including attached
pilasters, columns, ,pillars, posts, struts,
buttresses, string or lacing courses, parapets,
coping, bed blocks, anchor blocks, plain
window cills, fillets etc., including cost of all
materials, labour, HOM of machinery, curing,
complete but excluding cost of reinforcement
as per specifications. Specification No. KBS
4.1, 4.6
ground floor cum 26 0.23 0.45 3.05 8.21*2 =16.42 type 1 column(0.23*0.45)
4 0.23 0.6 3.05 1.68*2 = 3.36 type 2 column(0.23*0.6)
4
Shuttering of column
KSRB 4-6.5 : Providing and removing
centering, shuttering, strutting, propping etc.,
for columns, pillars, post and struts, square /
rectangular/ polygon in plan including cost of all
materials, labour complete as per
specifications. Specification No. KBS 4.6.2
Ground Floor
For column of 0.23*0.45
along 0.23 sqm 2 0.23 3.05 1.403
along 0.45 sqm 2 0.45 3.05 2.745
4.148*26 = 107.84
For column of 0.23*0.6
along 0.23 sqm 2 0.23 3.05 1.403
along 0.6 sqm 2 0.6 3.05 3.6
5.063*4 =20.252
For GF 128.1
5
concreting for slab
KSRB 4.2.7 : Providing and laying in position
reinforced cement concrete of design mix M25
with OPC cement @ 340kgs, with 20mm and
down size graded granite metal coarse
aggregates @0.70cum and fine aggregates @
0.47cum, with superplastisiser @3lts
confirming to IS9103-1999 Reaffirmed-2008,
machine mixed, concrete laid in layers not
exceeding 15 cms thick, vibrated for all works
in ground floor level for roof slabs, staircase,
lintels and beams retaining walls, return walls,
walls (any thickness) including attached
pilasters, columns, ,pillars, posts, struts,
buttresses, string or lacing courses, parapets,
coping, bed blocks, anchor blocks, plain
window cills, fillets etc., including cost of all
materials, labour, HOM of machinery, curing,
complete but excluding cost of reinforcement
as per specifications. Specification No. KBS
4.1, 4.6
Ground floor cum 1 23.55 20.8 0.15 73.476
deduction of staircase cum 1 3.227 4.5 1.5 21.78
total concreteing for GF slab= 51.69
6
form work for slab
7
Flooring
8
Brickwork in superstructure
Deductions
Beam over bathroom wall cum 1 4.25 0.2 0.45 0.3825(-)
Columns
0.23*0.45 cum 26 0.23 0.45 3.5-0.45 8.2(-)
0.23*0.60 cum 4 0.23 0.6 3.5-0.45 1.68(-)
9
concreteing in staircase
steps inside buillding
KSRB 4.2.7 : Providing and laying in position
reinforced cement concrete of design mix M25
with OPC cement @ 340kgs, with 20mm and
down size graded granite metal coarse
aggregates @0.70cum and fine aggregates @
0.47cum, with superplastisiser @3lts
confirming to IS9103-1999 Reaffirmed-2008,
machine mixed, concrete laid in layers not
exceeding 15 cms thick, vibrated for all works
in ground floor level for roof slabs, staircase,
lintels and beams retaining walls, return walls,
walls (any thickness) including attached
pilasters, columns, ,pillars, posts, struts,
buttresses, string or lacing courses, parapets,
coping, bed blocks, anchor blocks, plain
window cills, fillets etc., including cost of all
materials, labour, HOM of machinery, curing,
complete but excluding cost of reinforcement
as per specifications. Specification No. KBS
4.1, 4.6
for waist slab cum 2 3.49 1.5 0.15 1.57
for each step cum 18 1/2*0.19*0.3*1.5 0.77
entrance staircase
for waist slab cum 1 3.17 2.1 0.15 0.998
for each step cum 8 1/2*2.1*0.15*0.3 0.3776
10
shuttering of staircase
12 Steel work
11
Plastering
inner plastering
KSRB15-3.3 : Providing 12mm thick cement
plaster in single coat with cement mortar 1:6,
to brick masonry including rounding off corners
wherever required smooth rendering, :
Providing and removing scaffolding, including
cost of materials, labour, curing complete as
per specifications.
1 Vertical wall of shop 1 sq.m 2 5.9 3.45 40.71 inner plastering for shop 1 and 2
Deduction of window sq.m -4 1.5 2 -12
Add jambs sq.m 8 1.5 0.23 2.76
Add soffit sq.m 8 2 0.23 3.68
2 Vertical wall sq.m 2 5.9 3.45 40.71 inner plastering of shops 3,4,7,8,9 and 10
Deduction of window sq.m -2 1.5 2 -6
Add jambs sq.m 4 1.5 0.23 1.38
Add soffit sq.m 4 2 0.23 1.84
Deduction of shutter sq.m -1 3 3.2 -9.6
Add soffit sq.m 1 3.2 0.23 0.736
Add jambs sq.m 2 3 0.23 1.38
Total shop 6 65.046 sq.m similarly for shop 12 and 13, because of same dimensions
Slab sq.m 1 4 2 8
6 Vertical wall sq.m 2 8.2 3.45 56.58 inner plastering for shop 5
Deduction of window sq.m 3 1.5 2 -9
Add jambs sq.m 6 1.5 0.23 2.07
Add soffit sq.m 6 2 0.23 2.76
Deduction of shutter sq.m 1 3 2 -9.6
Add jambs sq.m 2 3 0.23 1.38
Add soffit sq.m 1 3.2 0.23 0.736
Outer plastering
KSRB15-3.8 : Providing 18mm thick cement
plaster in single coat with cement mortar 1:4,
to brick masonry including rounding off corners
wherever required smooth rendering, :
Providing and removing scaffolding, including
cost of materials, labour, curing complete as
per specifications.
1 Vertical wall of shop 1 sq.m 2 6.36 3.45 43.884 outter plastering for shop 1 and 2
Deduction of window sq.m -4 1.5 2 -12
2 Vertical wall sq.m 2 6.13 3.45 42.297 outter plastering of shops 3,4,9 and 10
Deduction of window sq.m 2 -1.5 2 -6
Deduction of shutter sq.m 1 3 3.2 -9.2
Total of shop 3 50.574 sq.m similarly for shop 4, because of same dimensions
Total 50.574+50.574 =101.148 sq.m
4 Vertical wall sq.m 2 8.66 3.45 59.754 outer plastering for shop 5
Deduction of window sq.m 3 1.5 2 -9
Deduction of shutter sq.m 1 3 3.2 -9.6
5 Vertical wall sq.m 1 4.6 3.45 15.387 1st wc 4x2 outer plastering
Deduction of v sq.m 1 1 0.5 -0.5
6 Vertical wall sq.m 1 4.46 3.45 15.387 2st wc 4x2.05 outer plastering
13 wood work
Ground floor
Shutters
KSRB 7.5 : Providing and fixing pull and push type
rolling shutters of approved make out of 18 guage,
75mm wide cold rolled steel laths of convex
corrugation, with side guides and bottom rail, with
interlocking arrangements for steel laths by means of
alternate clips, suspension shaft with High tension coil
type springs two numbers, mounted on specially
designed pipe shaft, with bracket plates, guide
channels, ball bearing arrangements, for inside &
outside locking with push & pull operations complete
including pulling hooks, 4Nos. handles with all fittings
and accessories, painted with a coat of red lead paint
(without top cover) cost of materials, labour, HOM of
machinery complete as per specifications. Shutter size
3mx2.8 m. Specification No. KBS 7.10 / 7.12
sqm 76.8
16 WINDOW GRILL
KSRB 7.9 : Providing and fixing M.S.grill work for
windows and ventilators weighing 21kg/sqm using M.S.
flats, or M.S. square rods, or combination of M.S. flats
and square rods as per approved design, drawing
including cutting steel sections and welding the same
to required pattern with a coat of red lead primer, cost of
materials, fixtures, labour and HOM of machinery
complete as per specifications. Specification No. KBS
7.12
KG 3.2
1
Concreting in beams cum
Cantilever beams
For sides sqm 6 2 0.45 5.4*2 = 10.8
For bottom sqm 6 2 0.23 2.76
For sides sqm 10 1.5 0.45 6.75*2 = 13.5
For bottom sqm 10 1.5 0.23 3.45
Deduction
Columns sqm 26 0.23 0.45 2.691(-)
4 0.23 0.6 0.552(-)
Total = 261.213
lintels
window
for sides Sqm 21 2 1.8 0.18 13.608
for ends Sqm 21 2 0.23 0.18 1.7388
doors
for sides Sqm 2 2 1.3 0.13 0.676
for ends Sqm 2 2 0.23 0.13 0.1196
ventilators
for sides Sqm 1 1.3 0.13 2 0.338
for ends Sqm 1 2 0.2 0.13 0.052
shutters
for sides Sqm 8 2 3.3 0.33 17.424
for ends Sqm 8 2 0.23 0.33 1.2144
Total = 35.1708
Concreting of column
Shuttering of column
KSRB 4-6.5 : Providing and
removing centering, shuttering,
strutting, propping etc., for
columns, pillars, post and struts,
square / rectangular/ polygon in
plan including cost of all materials,
labour complete as per
specifications. Specification No.
KBS 4.6.2
first Floor
For column of 0.23*0.45
along 0.23 sqm 2 0.23 3.05 1.403
along 0.45 sqm 2 0.45 3.05 2.745
4.148*26 = 107.84
For column of 0.23*0.6
along 0.23 sqm 2 0.23 3.05 1.403
along 0.6 sqm 2 0.6 3.05 3.6
5.063*4 =20.252
For GF 128.1
5
concreting for slab
6
form work for slab
KSRB 4-6.9 :Providing and
removing centering, shuttering,
strutting, propping etc., for edges
of slabs and breaks in floor
including cost of all materials,
labour complete as per
specifications. Specification No.
KBS 4.6.2
for first floor
for sides
along 23.55 sqm 2 23.55 0.15 7.065
along 20.8 sqm 2 20.88 0.15 6.24
7
Flooring
Providing and fixing Vitrified
glazed tiles of approved make,
quality & colour of size 600 x 600
x 10mm thick fixed on bed of
12mm thick cement mortar for
flooring, skirting and jointed with
neat cement slurry mixed with
pigment to mach shade of tiles,
including providing spacers at
required interval and removing
stains, including cost of all
mateirals, mortar, labour, etc ,
Complete as per specification.
shop 7 sqm 1 8.2 5.9 48.38
shop 8 sqm 1 8.2 5.9 48.38
shop 9 sqm 1 8.2 5.9 48.38
shop 10 sqm 1 8.2 5.9 48.38
shop 11 sqm 1 8.2 4.25 34.85
shop 12 sqm 1 4 4.25 17
shop 13 sqm 1 4 4.25 17
8
Brickwork in superstructure
Deductions
Columns
0.23*0.45 cum 26 0.23 0.45 3.5-0.45 8.2(-)
0.23*0.60 cum 4 0.23 0.6 3.5-0.45 1.68(-)
9
concreteing in staircase
steps inside buillding
Steel work
shuttering of staircase
KSRB 4-6.11 :Providing and
removing centering, shuttering,
strutting, propping etc., and
removal of form work for Stairs
(excluding landing) except spiral
staircase including cost of all
materials, labour complete as per
specificaiton. Specification No.
KBS 4.6.2
waist slab shuttering area sq.m
waist slab area sq.m 2 3.49 0.19 1.33
sides area sq.m 2 1.5 0.19 0.57
bottom area sq.m 1 3.49 1.5 5.24
7.13 2 number of waist slab
total area= 14.26
wood work
Ground floor
KSRB 9.4-3 : Providing Mathi /
Nandi wood frames of doors,
windows, clerestory windows,
ventilators and other frames,
wrought, framed or assembled
including making plaster groves (
excluding cost of cement
concrete and side clamps ), but
including cost of materials, labour,
HOM of machineries complete as
per specifications. Specification
No. KBS 9.33
doors cum 2 0.12 0.08 1.3 0.023 15cm bearing on sides
windows
in horizontal cum 2 1.8 0.09 0.06 0.019
in vertical cum 2 2.3 0.09 0.06 0.024
0.044
for FF 23 1.02
Total 1.043
WINDOW GRILL
11 Plastering
inner plastering
Total of shop 7, 132.626 sq.m similarly for all shops of 8,9 and 10, because of same dimensions
Total of shop 7,8.9 and 10 132.626x4= 530.504 sq,m
2 Vertical wall sq.m 2 8.2 3.45 56.58 inner plastering for shop 11
Deduction of window sq.m 3 1.5 2 -9
Add jambs sq.m 6 1.5 0.23 2.07
Add soffit sq.m 6 2 0.23 2.76
Deduction of shutter sq.m 1 3 2 -9.6
Add jambs sq.m 2 3 0.23 1.38
Add soffit sq.m 1 3.2 0.23 0.736
Total shop 6 65.046 sq.m similarly for shop 13, because of same dimensions
OUTER PLASTERING
Total of shop 9 50.574 sq.m similarly for all shops of 10, because of same dimensions
Total of shop 9 and 10 50.574x2= 101.148 sq.m
2 Vertical wall sq.m 2 6.36 3.45 43.884 outter plastering of shops 7 and 8
Deduction of window sq.m 2 1.5 2 -6
Deduction of shutter sq.m 1 3 3.2 -9.6
Total of shop 7 52.161 sq.m similarly for shop 8, because of same dimensions
Total of shop 7 and 8 52.161x2=104.322 sq.m
3 Vertical wall sq.m 2 8.66 3.45 59.754 outer plastering for shop 11
Deduction of window sq.m 3 1.5 2 -9
Deduction of shutter sq.m 1 3 3.2 -9.6
Total shop 12 34.37 sq.m similarly for shop 13, because of same dimensions
Shutters
ALUMINIUM WINDOWS
KSRB 7.11 : Providing and fixing in
position aluminium windows and
ventilators as per approved drawings
with sliding shutters using three track
window frame of size 92x31.75mm
bottom section 1.3mm thick, weight
1.07kg/m; sides and top sections 1.3
mm, thick, weight 0.933 kg/m.shutter
frame section comprising top and
bottom section of size 40mmx18mm,
wall thickness 1.25mm. weight 0.417
kg./m. shutter side outer 40mmx18mm.
wall thickness 1.25mm. weight 0.417
kg/m, shutter interlock section
40mmx26.7mm wall thickness 1.1 mm.
thick, weight 0.469 kg/m, the shutters
mounted on nylon rollers with approved
quality of fixtures such as aluminium
handles tower bolts etc.; providing and
fixing 5.5mm. thick plain glass for
shutters fitted with rubber beading all
aluminium sections including cutting to
required length, joints mitred subdividing
the frame tenonned and rivetted, in the
assembled frame, stiffened with end sqm 21 2 1.5 63
17 Abstract
17.1.1 Abstract of Basement
PAGE NO/
ITEMCODE DESCRIPTION QUANTITY UNIT RATE UNIT AMOUNT
KSRB 2-2.1 : Earthwork excavation by
manual means for foundation of
buildings, water supply, sanitary lines
and electrical conduits either in pits or in
trenches 1.5m and above in width, in
ordinary soil not exceeding 1.5 m. in
depth including dressing the bottom and
sides of pits and trenches, stacking the
excavated soil clear from edges of
excavation with lead upto 50 m. after
breaking of clods complete as per
specifications. specification. No. KBS
2.1(a) / 2.3.5KSRB 2.14-1: Extra for
additional lift of 1.5m. or part thereof for
excavation In loose / soft or hard soil
including cost of materials, labour
6/2.3 complete as per specifications. 1926.32 CUM 344.520 CUM 663655.7664
PAGE NO/
ITEMCODE DESCRIPTION QUANTITY UNIT RATE UNIT AMOUNT
PAGE NO/
ITEMCODE DESCRIPTION QUANTITY UNIT RATE UNIT AMOUNT
17.2 PRIMAVERA
Primavera P6 Professional Project Management, the recognized standard for high-
performance project management software, is designed to handle large scale, highly
sophisticated and multifaceted projects. It can be used to organize projects up to
100,000 activities, and it provides unlimited resources and an unlimited number of
target plans
17.2.1 CALENDAR
• This calendar defines the available work hours in each calendar day. You can also specify
national holidays, your organizations holiday, project specific work or non-workdays, and
resource vacation days.
• The calendar defines the available work hours in each calendar day.
• Time period is from 9am to 6pm including break of 1 hour from 1pm to 2pm in afternoon.
• Gantt charts illustrate the start and finish dates of the terminal elements and
summary elements of a project. Terminal elements and summary elements
constitute the work breakdown structure of the project. Modern Gantt charts
also show the dependency (i.e., precedence network) relationships between
activities.
Planned Value
Actual Cost
Earned Value
It is calculated as:
It is calculated as:
It is calculated as:
CV % = CV ⁄ BCWP
Schedule Variance (SV) indicates how much ahead or behind the schedule a
• ETC is calculated and applied when the past estimating assumptions become
invalid anda need for fresh estimates arises.
• Reinforcement of beams
• Reinforcement of slab
• Earned value analysis and earned value management is performed using primavera-
P6 software.