1.1.1. Switching ON
d) The system will perform the initialization, delay 20 seconds and then start transmitting.
b) If the DVOR is currently in the non-standard mode of operation, the user will be
prompted to correct the issues before continuing with the logoff.
1.2.1.3. Coordination
a) Inform the CNSSO shift supervisor/shift members before leaving the station.
b) Call Air Traffic Control to cross runway.
1.2.1.5. PM Procedures
1.2.1.5.1. Check Integral Monitor Data Screen (Refer to SELEX DVOR 1150A Operations
and Maintenance Manual 3.6.8.1.1.1 (Fig. 3-31))
1.2.1.5.2. Check Notch Monitor Data Screen (Refer to SELEX DVOR 1150A Operations and
Maintenance Manual 3.6.8.1.1.2 (Fig. 3-32))
1.2.1.5.3. Check Sideband Antenna VSWR Screen (Refer to SELEX DVOR 1150A Operations
and Maintenance Manual 3.6.8.1.1.3 (Fig. 3-33))
1.2.1.5.4. Check Transmitter Data Screen(Refer to SELEX DVOR 1150A Operations and
Maintenance Manual 3.6.8.3.1 (Fig. 3-46))
1.2.1.5.5. Check transmitter Status screen (Refer to SELEX DVOR 1150A Operations and
Maintenance Manual 3.6.8.3.4 (Fig. 3-49))
1.2.1.6. Post safety precaution/activity
a) Make sure all equipment switches/settings are back to their original position prior to PM
activities.
b) Check for abnormalities in the environment (such as smell, wet floor, debris, sounds,
temperature, etc.).
1.2.1.8. Culmination
a) Check and inventory tools and materials used in the activity.
b) Record your activity on PM logbook.
c) Record your activity on PM ERC.
d) Before leaving, check again for abnormalities in the environment (such as smell,
wet floor, debris, sounds, temperature, etc.).
e) Switch off lighting.
f) Make sure that the station main door is locked.
g) Let the shift supervisor sign the PM form if needed.
1.2.2 Weekly
1.2.2.3 Coordination
a) Inform the CNSSO shift supervisor/shift members before leaving the station.
b) Call Air Traffic Control to cross runway.
b) Check the Radio battery if not low power, if its transmission and reception are ok.
c) Wear proper attire shoes and protective gloves.
d) Open the main door using the specified key.
e) Upon entering the equipment room, switch on the room lightings.
f) Check for abnormalities in the environment (such as smell, wet floor, debris, sounds,
temperature, etc.).
g) Inform of any abnormalities observed, if any.
1.2.2.5. PM Procedures
1.2.2.5.1. Shelter/Equipment General Cleaning
1.2.2.5.2. Check/Clean Air Conditioning Filters
1.2.2.5.3. Transmitter Cabinet Inspection
1.2.3. Monthly
1.2.3.1. Materials Needed
NAV-AIDS Daily Maintenance Checklist.
Toolbox
Keys (Vehicle, Shelter, Road gates)
Pen
Hand-held Radios
Groundcheck Form
b)
1.2.3.3. Coordination
1.2.3.5. PM Procedure
1.2.3.5.1. Check DVOR Ground Check Data Screen (Refer to SELEX DVOR 1150A Operations
and Maintenance Manual 3.6.8.3.2 (Fig. 3-47))
1.2.3.5.2. Established Markers’ Ground Check
1.2.3.5.3. Inside and Outside of Fence Mowing
1.2.3.5.4. Around Field Monitor Mowing
1.2.3.6. Post safety precaution/activity
a) Make sure all equipment switches/settings are back to their original position prior to PM
activities.
b) Check for abnormalities in the environment (such as smell, wet floor, debris, sounds,
temperature, etc.).
1.2.3.8. Culmination
a) Check and inventory tools and materials used in the activity.
b) Record your activity on PM logbook.
c) Record your activity on PM ERC.
d) Before leaving, check again for abnormalities in the environment (such as smell, wet
floor, debris, sounds, temperature, etc.).
e) Switch off lighting.
f) Make sure that the station main door is locked.
g) Let the shift supervisor sign the PM form if needed.
1.2.2 Quarterly
1.2.2.1
1.2.4.1 Materials Needed
NAV-AIDS Daily Maintenance Checklist.
Toolbox
Keys (Vehicle, Shelter, Road gates)
Pen
Hand-held Radios
1.2.4.5. PM Procedure
1.2.4.5.1. Check Auto-Transfer Screen (Refer to SELEX DVOR 1150A Operations and
Maintenance Manual 6.2.7)
1.2.4.5.2. Reassign Main/Standby Transmitters
1.2.4.5.3. RCSU Operation Check Screen (Refer to SELEX DVOR 1150A Operations and
Maintenance Manual 6.2.10)
1.2.4.5.4. Print Data Parameters
1.2.4.8 Culmination
a) Check and inventory tools and materials used in the activity.
b) Record your activity on PM logbook.
c) Record your activity on PM ERC.
d) Before leaving, check again for abnormalities in the environment (such as smell, wet
floor, debris, sounds, temperature, etc.).
e) Switch off lighting.
f) Make sure that the station main door is locked.
g) Let the shift supervisor sign the PM form if needed.
1.2.5. Semi-annual
1.2.5.1. Materials Needed
NAV-AIDS Daily Maintenance Checklist.
Toolbox
Keys (Vehicle, Shelter, Road gates)
Pen
Hand-held Radios
FOM Manual
Continuous Paper
1.2.5.3. Coordination
a) Inform the CNSSO shift supervisor/shift members before leaving the station.
b) Call Air Traffic Control to cross runway.
1.2.6. Annual
1.2.6.1. Materials Needed
NAV-AIDS Daily Maintenance Checklist.
Toolbox
Keys (Vehicle, Shelter, Road gates)
Pen
Hand-held Radios
a) Make sure all equipment switches/settings are back to their original position prior to PM
activities.
b) Check for abnormalities in the environment (such as smell, wet floor, debris, sounds,
temperature, etc.).
1.2.6.7. Post coordination activity
a) Advise supervisor/shift members on duty that the PM activity is already done.
1.2.6.8. Culmination
a) Check and inventory tools and materials used in the activity.
b) Record your activity on PM logbook.
c) Record your activity on PM ERC.
d) Before leaving, check again for abnormalities in the environment (such as smell, wet
floor, debris, sounds, temperature, etc.).
e) Switch off lighting.
f) Make sure that the station main door is locked.
g) Let the shift supervisor sign the PM form if needed.
1.3.2.Equipment/Tools Needed
a) Multitester
b) Oscilloscope
1.3.3.Coordination
a) Inform the CNSSO shift supervisor/shift members before leaving the station.
Call Air Traffic Control to cross runway.
a) Check the Vehicle for Road Worthiness. (Fuel, Brakes, Lights, Oil, water, signal lights
etc.)
b) Check the Radio battery if not low power, if its transmission and reception are ok.
c) Wear proper attire shoes and protective gloves.
d) Open the main door using the specified key.
e) Upon entering the equipment room, switch on the room lightings.
f) Check for abnormalities in the environment (such as smell, wet floor, debris, sounds,
temperature, etc.).
g) Inform of any abnormalities observed, if any.
1.3.5. CM procedure