Professional Documents
Culture Documents
Productivity Rate (Building Works)
Productivity Rate (Building Works)
10
E1
E2
OD 3
Manpower/day -
I Equipment: @ Hrs
11
OD 3.00
Equipment/day -
A A H U & Return Fanes Installation Nos. 10
OD 3
Manpower/day 1.67
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.67
A Roof Drain Nos. 10
OD 3
Manpower/day 0.83
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.83
A Insulation Lm 100
B Daily Output Lm 25
OD 3
Manpower/day 1.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.33
A Hot & Cold Water Piping Lm 100
B Daily Output Lm 12
OD 3
Manpower/day 2.78
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.78
A Chilled Water Piping Lm 10
OD 3
Manpower/day 0.31
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.31
A Air Cooled Chilled Unit Nos. 10
OD 3
Manpower/day 33.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 16.67
A Chilled water pump Nos. 10
OD 3
Manpower/day 13.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 6.67
A AHU Installation Nos. 10
OD 3
Manpower/day 13.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 6.67
A Domestic Pump Nos. 50
OD 3
Manpower/day 121.21
I Equipment: @ Hrs
OD 3.00
Equipment/day 30.30
A Water Circular Pumps Nos. 50
OD 3
Manpower/day 90.91
I Equipment: @ Hrs
OD 3.00
Equipment/day 30.30
A Interface Between FACP Points 50
OD 3
Manpower/day 2.78
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.39
A disconnected Switch Install'n Nos. 50
OD 3
Manpower/day 66.67
I Equipment: @ Hrs
OD 3.00
Equipment/day 33.33
A Protection lightning kg. 500
OD 3
Manpower/day 2.38
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.19
A lighting fixture Nos. 200
OD 3
Manpower/day 9.44
I Equipment: @ Hrs
OD 3.00
Equipment/day 4.44
A U/G Conduits Lm 200
OD 3
Manpower/day 1.18
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.56
A Cable Tray Lm 200
OD 3
Manpower/day 11.20
I Equipment: @ Hrs
OD 3.00
Equipment/day 5.27
A Aluminum Shutter(Roofing) M2 200
OD 3
Manpower/day 3.42
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.67
A Foam Concrete Screed M2 100
B Daily Output M2 60
OD 3
Manpower/day 3.40
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.56
A Water Proofing Membrane M2 100
B Daily Output M2 55
OD 3
Manpower/day 1.29
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.61
A Pvc Conduiting & Accessories Lm. 100
OD 3
Manpower/day 2.83
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.33
A Data & Rj45/Rj45 Other Accessories Nos. 100
OD 3
Manpower/day 8.89
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.22
A Telephone,Data, Tv Outlets Nos. 100
OD 3
Manpower/day 4.76
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.38
A Fire Alarm Devices Points. 100
OD 3
Manpower/day 5.90
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.78
A Clock System Nos. 100
OD 3
Manpower/day 20.24
I Equipment: @ Hrs
OD 3.00
Equipment/day 9.52
A Lightning Protection kg. 200
OD 3
Manpower/day 0.95
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.48
A Antenna Installation Lm 10
B Daily Output Lm 6
OD 3
Manpower/day 1.11
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.56
A External Cables Lm 10
B Daily Output Lm 39
OD 3
Manpower/day 0.18
I Equipment: @ Hrs
OD 3.00
Equipment/day -
A Lighting Pole Each 10
OD 3
Manpower/day 0.95
I Equipment: @ Hrs
11 8 - Mday
12 8 - Mday
OD 3.00
Equipment/day -
A Transformer 13.8Kv.,127/220 1000Kva Nos. 10
OD 3
Manpower/day 29.76
I Equipment: @ Hrs
OD 3.00
Equipment/day 9.52
A Switches & Outlets Nos. 100
OD 3
Manpower/day 5.21
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.67
A Lighting Fixtures installation. Nos. 100
OD 3
Manpower/day 4.72
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.22
A Panel boards & Accessories Nos. 100
OD 3
Manpower/day 73.78
I Equipment: @ Hrs
OD 3.00
Equipment/day 34.72
A Wire & Cables M. 100
B Daily Output M. 90
OD 3
Manpower/day 0.79
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.37
A Sanitary Fixture Unit 100
OD 3
Manpower/day 33.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 16.67
A Fire Fighting Final Fixture & Cabinet Unit 100
OD 3
Manpower/day 22.22
I Equipment: @ Hrs
OD 3.00
Equipment/day 11.11
A Grilles & Diffusers Installation each 100
OD 3
Manpower/day 6.67
I Equipment: @ Hrs
OD 3.00
Equipment/day 3.33
A Grilles & Diffusers Installation Unit 100
OD 3
Manpower/day 6.25
I Equipment: @ Hrs
OD 3.00
Equipment/day 5.56
A Bms & Other Accessories Nos. 100
OD 3
Manpower/day 14.29
I Equipment: @ Hrs
OD 3.00
Equipment/day 4.76
A Vav Nos. 100
OD 3
Manpower/day 33.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 8.33
A VavR Nos. 100
OD 3
Manpower/day 19.05
I Equipment: @ Hrs
OD 3.00
Equipment/day 4.76
A Fan Exhaust (Fans) Nos. 100
OD 3
Manpower/day 18.75
I Equipment: @ Hrs
OD 3.00
Equipment/day 5.56
A External Ducts M2 100
B Daily Output M2 15
OD 3
Manpower/day 4.44
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.22
A Duct Insulation M2 100
B Daily Output M2 27
OD 3
Manpower/day 2.47
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.23
A Duct Works M2 100
B Daily Output M2 12
OD 3
Manpower/day 5.56
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.78
A Ducting Works & Insullation Kg. 500
OD 3
Manpower/day 6.51
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.08
A Electric Water Heater (EWH) Nos. 50
OD 3
Manpower/day 54.49
I Equipment: @ Hrs
OD 3.00
Equipment/day 25.64
A DX Split Unit Pcs 100
OD 3
Manpower/day 25.00
I Equipment: @ Hrs
OD 3.00
Equipment/day 8.33
A Plumbing Fixtures & Accessories Pcs 100
OD 3
Manpower/day 7.08
I Equipment: @ Hrs
OD 3.00
Equipment/day 3.33
A U.P.V.C. Piping (Drainage First Fix) Unit 100
OD 3
Manpower/day 8.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 4.17
A Black Seamless Steel Pipes Lm 100
OD 3
Manpower/day 3.81
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.79
A Floor Drains + Floor Clean Out Nos 100
OD 3
Manpower/day 10.12
I Equipment: @ Hrs
OD 3.00
Equipment/day 4.76
A Drainage Piping System Lm. 100
OD 3
Manpower/day 4.43
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.08
A Water Supply Piping Lm. 100
OD 3
Manpower/day 6.86
I Equipment: @ Hrs
OD 3.00
Equipment/day 3.23
A Venetian Blind M2 100
B Daily Output M2 25
OD 3
Manpower/day 1.50
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.33
A Fire Hose Cabinet Pcs 50
OD 3
Manpower/day 9.38
I Equipment: @ Hrs
OD 3.00
Equipment/day 8.33
A Fire Extiguisher 6kg.Dry Powder + Hydrant
Nos. 100
OD 3
Manpower/day 5.36
I Equipment: @ Hrs
OD 3.00
Equipment/day 4.76
A Sprinkle & Accessories Nos. 100
OD 3
Manpower/day 3.41
I Equipment: @ Hrs
OD 3.00
Equipment/day 3.03
A Fire Fighting Piping Lm. 100
OD 3
Manpower/day 2.43
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.16
A Toilet Partition Lm. 100
OD 3
Manpower/day 11.54
I Equipment: @ Hrs
OD 3.00
Equipment/day 10.26
A Epoxy Coating m2 100
B Daily Output m2 30
OD 3
Manpower/day 1.11
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.11
A Toilet Bath Accessories Pcs 100
OD 3
Manpower/day 2.68
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.38
A Vinyl Tiles m2 200
B Daily Output m2 25
OD 3
Manpower/day 5.67
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.67
A Suspended Ceiling m2 500
B Daily Output m2 23
OD 3
Manpower/day 15.40
I Equipment: @ Hrs
OD 3.00
Equipment/day 7.25
A hardner flooring m2 100
B Daily Output m2 40
OD 3
Manpower/day 0.94
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.83
A Ceramic wall Tiling m2 100
B Daily Output m2 10
OD 3
Manpower/day 3.75
I Equipment: @ Hrs
OD 3.00
Equipment/day 3.33
A Marble Circular Columns Tiling m2 100
B Daily Output m2 3
OD 3
Manpower/day 12.50
I Equipment: @ Hrs
OD 3.00
Equipment/day 11.11
A Marble Walls Tilling m2 100
B Daily Output m2 7
OD 3
Manpower/day 5.36
I Equipment: @ Hrs
OD 3.00
Equipment/day 4.76
A Aluminum Wall Cladding 1220x2440x38mm Thick
m2 100
B Daily Output m2 22
OD 3
Manpower/day 2.23
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.52
A Interlocking M2 100
B Daily Output M2 16
OD 3
Manpower/day 2.34
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.08
A Interlocking ( 50mmx400mmx400mm ) M2 100
B Daily Output M2 24
OD 3
Manpower/day 1.56
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.39
A Marble stairs Skirting No. 100
OD 3
Manpower/day 1.25
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.11
A Marble Skirting Lm 100
B Daily Output Lm 35
OD 3
Manpower/day 1.07
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.95
A Marble stairs Tilling Lm 100
B Daily Output Lm 25
OD 3
Manpower/day 1.50
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.33
A Ceramic Floor Tilling 100mmx200mmx13mm
m2 100
OD 3
Manpower/day 4.03
I Equipment: @ Hrs
OD 3.00
Equipment/day 3.58
A Cement Floor Tilling m2 100
B Daily Output m2 30
OD 3
Manpower/day 1.25
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.11
A Marble Floor Tilling m2 100
B Daily Output m2 7
OD 3
Manpower/day 5.36
I Equipment: @ Hrs
OD 3.00
Equipment/day 4.76
A Terrazo Tiles m2 100
B Daily Output m2 15
OD 3
Manpower/day 4.72
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.22
A Terrazo Skirting Lm 100
B Daily Output Lm 10
OD 3
Manpower/day 7.08
I Equipment: @ Hrs
OD 3.00
Equipment/day 3.33
A Ceramic Wall m2 50
B Daily Output m2 30
OD 3
Manpower/day 1.18
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.56
A Ceramic Floor m2 100
B Daily Output m2 17
OD 3
Manpower/day 4.17
I Equipment: @ Hrs
I2
OD 3.00
Equipment/day 1.96
A Screeding (by machine) m2 500
B Daily Output m2 70
OD 3
Manpower/day 5.06
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.38
A Steel Window Pcs 50
OD 3
Manpower/day 3.94
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.85
A Aluminum Window Pcs 50
OD 3
Manpower/day 2.53
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.19
A Glass Door Pcs 20
OD 3
Manpower/day 4.72
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.22
A Wood Doors Pcs 20
OD 3
Manpower/day 1.57
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.74
A Access Door Pcs 20
OD 3
Manpower/day 2.02
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.95
A Steel Doors Pcs 20
OD 3
Manpower/day 2.83
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.33
A Aluminum Door Pcs 50
OD 3
Manpower/day 4.43
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.08
A Wooden Door Pcs 50
OD 3
Manpower/day 7.08
I Equipment: @ Hrs
OD 3.00
Equipment/day 3.33
A Final Paint M2 500
OD 3
Manpower/day 3.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.67
A Primer & First Coat paint M2 500
B Daily Output M2 60
OD 3
Manpower/day 5.56
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.78
A Marble, Granite Floor M2 500
B Daily Output M2 7
OD 3
Manpower/day 56.55
I Equipment: @ Hrs
OD 3.00
Equipment/day 14.88
A Plastering M2 500
B Daily Output M2 14
OD 3
Manpower/day 13.39
I Equipment: @ Hrs
OD 3.00
Equipment/day 11.90
A Handrails LM 100
B Daily Output LM 15
OD 3
Manpower/day 2.50
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.22
A Blockworks M2 500
B Daily Output M2 18
OD 3
Manpower/day 11.57
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.16
A Slab Pipe & Sleeve) LM 400
B Daily Output LM 33
OD 3
Manpower/day 4.55
I Equipment: @ Hrs
OD 3.00
Equipment/day 4.04
A Electl. first fix.( Conduiting ) in slabs LM 400
B Daily Output LM 32
OD 3
Manpower/day 33.85
I Equipment: @ Hrs
OD 3.00
Equipment/day 4.17
A Precast (Hollow Core) m2 1000
OD 3
Manpower/day 7.74
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.95
A Precast Beam M 200
B Daily Output M 30
OD 3
Manpower/day 18.06
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.22
A Precast Column M 200
B Daily Output M 30
OD 3
Manpower/day 18.06
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.22
A Precast Shear Walls M 200
B Daily Output M 30
OD 3
Manpower/day 18.06
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.22
A E M Ser..1st Fix in RC walls LM 200
B Daily Output LM 26
OD 3
Manpower/day 5.45
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.56
A Vertical Water Proofing m2 200
B Daily Output m2 30
OD 3
Manpower/day 4.44
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.22
A Horizontal Water Proofing m2 200
B Daily Output m2 55
OD 3
Manpower/day 2.42
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.21
A Retaining Wall M3 200
B Daily Output M3 15
OD 3
Manpower/day 48.89
I Equipment: @ Hrs
OD 3.00
Equipment/day 8.89
A Flat Slab M3 200
B Daily Output M3 15
OD 3
Manpower/day 31.11
I Equipment: @ Hrs
OD 3.00
Equipment/day 8.89
A Waffle Slab M3 200
B Daily Output M3 15
OD 3
Manpower/day 48.89
I Equipment: @ Hrs
OD 3.00
Equipment/day 8.89
A Hourdy Slab or Ribbes Slab M3 200
B Daily Output M3 53
OD 3
Manpower/day 8.81
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.52
A Shuttering Form Works & Steel Fabrication & Pouring
M3 200
B Daily Output M3 50
OD 3
Manpower/day 9.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.67
A Slab on grade M3 200
B Daily Output M3 15
OD 3
Manpower/day 31.11
I Equipment: @ Hrs
OD 3.00
Equipment/day 8.89
A H - Stairs M3 100
B Daily Output M3 12
OD 3
Manpower/day 30.56
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.78
A Grade Walls M3 100
B Daily Output M3 15
OD 3
Manpower/day 24.44
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.22
A Footing M3 200
B Daily Output M3 18
OD 3
Manpower/day 33.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.31
A Raft ( Mat ) Foundation M3 100
B Daily Output M3 25
OD 3
Manpower/day 12.00
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.33
A Slab On Ground M3 100
B Daily Output M3 40
OD 3
Manpower/day 7.50
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.83
A Slabs Including Drop Beams M3 100
OD 3
Manpower/day 1.96
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.20
A Walls (pouring) M3 200
B Daily Output M3 50
OD 3
Manpower/day 9.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.67
A Neck Column M3 100
B Daily Output M3 10
OD 3
Manpower/day 33.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 3.33
A Grid Beam add to Slab M3 100
B Daily Output M3 20
OD 3
Manpower/day 16.67
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.67
A Stairs & Landing M3 100
B Daily Output M3 30
OD 3
Manpower/day 11.11
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.11
A Beam M3 100
B Daily Output M3 7
OD 3
Manpower/day 47.62
I Equipment: @ Hrs
OD 3.00
Equipment/day 4.76
A Stairs & Landing Bars Ton 2
OD 3
Manpower/day 6.67
I Equipment: @ Hrs
11
12
13
14
OD 3.00
Equipment/day -
A Slabs Bars Ton 2
OD 3
Manpower/day 2.50
I Equipment: @ Hrs
11
12
13
14
OD 3.00
Equipment/day -
A Walls Bars Ton 2
OD 3
Manpower/day 2.22
I Equipment: @ Hrs
11
12
13
14
OD 3.00
Equipment/day -
A Columns Bars Ton 2
OD 3
Manpower/day 3.33
I Equipment: @ Hrs
11
12
13
14
OD 3.00
Equipment/day -
A Footing Including Ground Beams Bars Ton 2
OD 3
Manpower/day 2.86
I Equipment: @ Hrs
11
12
13
14
OD 3.00
Equipment/day -
A Blinding M3 200
B Daily Output M3 34
OD 3
Manpower/day 9.80
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.23
A Wearing Course(Asphalt Conc.Pvmt.) m2 6000
OD 3
Manpower/day 5.86
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.95
A Binder Course(Asphalt Conc.Pvmt.) m2 6000
OD 3
Manpower/day 4.86
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.79
A Compaction m3 5000
OD 3
Manpower/day 3.13
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.08
A MANHOLES & CLEANOUTS EA 10
B Daily Output EA 1
OD 3
Manpower/day 15.42
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.67
A Base Course M2 5000
OD 3
Manpower/day 0.30
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.80
A Base M2 5000
OD 3
Manpower/day 0.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.88
A Fill m3 5000
OD 3
Manpower/day 3.75
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.50
A Hauling m3 5000
OD 3
Manpower/day 73.20
I Equipment: @ Hrs
OD 3.00
Equipment/day 50.68
A Heavy Soil Excavation m3 1000
OD 3
Manpower/day 2.30
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.29
A SHEET PILING M2 100
B Daily Output M2 18
OD 3
Manpower/day 0.93
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.85
A SELECTIVE DEMOLITION m3 100
OD 3
Manpower/day 0.46
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.85
A BUILDING DEMOLITION m3 500
OD 3
Manpower/day 0.13
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.52
A Test Pit,Hand Digging,Light Soil m3 100
OD 3
Manpower/day 9.52
I Equipment: @ Hrs
OD 3.00
Equipment/day 9.52
A Site Clearing(Stripping) m3 5000
OD 3
Manpower/day 4.76
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.38
Item Activity Activity SUB Unit
ID Description ACTIVITY
SITEWORKS
SUBSTRUCTURE
For Disposal M3
Formworks M2
Rebars kg
Deshuttering M2
QTY Prod. Rate Days (H) Tot. Man Crew Tot. Mdays
53,280.00 250 213.12 2.056 1 Steel Fixer, 1 Helper, .056 Operator 438.17
1,184.00 35 33.83 3.056 2 Carpenter, 1 Helper, .056 Operator 103.38
OD (O) Manpower MAN-DAYS
/day
(N/O) Carpenter Mason Steel Fixer Helper Operator Driver Technician Painter
1 42.76
Desc. (H x X)
0 0 0 0 0
EQMT-DAYS
0.08
0.55
1.19
0.19
0 0 0 1.93 0.08 0 0