A Water Treatment & others Nos.

10

B Daily Output Nos. 5

C A/B Duration, Days (8 Hrs/Day) Day 2.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1

E2

F Sum "E" Total Man -

G F*D/B Manhour - 8 - Mday

H G*A Total Manhours - 8 - Mday

OD 3

Manpower/day -

I Equipment: @ Hrs

11

J Sum "I" Total Equip -

K J*D/B EquipHour - 8 - Eday

L K*A Total Equiphours - 8 - Eday

OD 3.00

Equipment/day -
A A H U & Return Fanes Installation Nos. 10

B Daily Output Nos. 2

C A/B Duration, Days (8 Hrs/Day) Day 5.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 1.000 8 0.63 Mday

E2 Labor 1.000 8 0.63 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 4.00 8 32.00 Mday

H G*A Total Manhours 40.00 8 5.00 Mday

OD 3

Manpower/day 1.67

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.63 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 4.000 8 32.00 Eday

L K*A Total Equiphours 40.00 8 5.00 Eday

OD 3.00

Equipment/day 1.67
A Roof Drain Nos. 10

B Daily Output Nos. 4

C A/B Duration, Days (8 Hrs/Day) Day 2.50

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 1.000 8 0.31 Mday

E2 Labor 1.000 8 0.31 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 2.00 8 16.00 Mday

H G*A Total Manhours 20.00 8 2.50 Mday

OD 3

Manpower/day 0.83

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.31 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 2.000 8 16.00 Eday

L K*A Total Equiphours 20.00 8 2.50 Eday

OD 3.00

Equipment/day 0.83
A Insulation Lm 100

B Daily Output Lm 25

C A/B Duration, Days (8 Hrs/Day) Day 4.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 1.000 8 0.50 Mday

E2 Labor 1.000 8 0.50 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 0.32 8 2.56 Mday

H G*A Total Manhours 32.00 8 4.00 Mday

OD 3

Manpower/day 1.33

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.50 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.320 8 2.56 Eday

L K*A Total Equiphours 32.00 8 4.00 Eday

OD 3.00

Equipment/day 1.33
A Hot & Cold Water Piping Lm 100

B Daily Output Lm 12

C A/B Duration, Days (8 Hrs/Day) Day 8.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 1.000 8 1.04 Mday

E2 Labor 1.000 8 1.04 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 0.67 8 5.33 Mday

H G*A Total Manhours 66.67 8 8.33 Mday

OD 3

Manpower/day 2.78

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 1.04 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.667 8 5.33 Eday

L K*A Total Equiphours 66.67 8 8.33 Eday

OD 3.00

Equipment/day 2.78
A Chilled Water Piping Lm 10

B Daily Output Lm 10.6

C A/B Duration, Days (8 Hrs/Day) Day 0.94

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 1.000 8 0.12 Mday

E2 Labor 1.000 8 0.12 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 0.75 8 6.04 Mday

H G*A Total Manhours 7.55 8 0.94 Mday

OD 3

Manpower/day 0.31

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.12 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.755 8 6.04 Eday

L K*A Total Equiphours 7.55 8 0.94 Eday

OD 3.00

Equipment/day 0.31
A Air Cooled Chilled Unit Nos. 10

B Daily Output Nos. 0.2

C A/B Duration, Days (8 Hrs/Day) Day 50.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 1.000 8 6.25 Mday

E2 Labor 1.000 8 6.25 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 80.00 8 640.00 Mday

H G*A Total Manhours 800.00 8 100.00 Mday

OD 3

Manpower/day 33.33

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 6.25 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 40.000 8 320.00 Eday

L K*A Total Equiphours 400.00 8 50.00 Eday

OD 3.00

Equipment/day 16.67
A Chilled water pump Nos. 10

B Daily Output Nos. 0.5

C A/B Duration, Days (8 Hrs/Day) Day 20.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 1.000 8 2.50 Mday

E2 Labor 1.000 8 2.50 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 32.00 8 256.00 Mday

H G*A Total Manhours 320.00 8 40.00 Mday

OD 3

Manpower/day 13.33

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 2.50 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 16.000 8 128.00 Eday

L K*A Total Equiphours 160.00 8 20.00 Eday

OD 3.00

Equipment/day 6.67
A AHU Installation Nos. 10

B Daily Output Nos. 0.5

C A/B Duration, Days (8 Hrs/Day) Day 20.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 1.000 8 2.50 Mday

E2 Labor 1.000 8 2.50 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 32.00 8 256.00 Mday

H G*A Total Manhours 320.00 8 40.00 Mday

OD 3

Manpower/day 13.33

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 2.50 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 16.000 8 128.00 Eday

L K*A Total Equiphours 160.00 8 20.00 Eday

OD 3.00

Equipment/day 6.67
A Domestic Pump Nos. 50

B Daily Output Nos. 0.55

C A/B Duration, Days (8 Hrs/Day) Day 90.91

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 2.000 8 22.73 Mday

E2 Labor 2.000 8 22.73 Mday

F Sum "E" Total Man 4.000

G F*D/B Manhour 58.18 8 465.45 Mday

H G*A Total Manhours 2,909.09 8 363.64 Mday

OD 3

Manpower/day 121.21

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 11.36 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 14.545 8 116.36 Eday

L K*A Total Equiphours 727.27 8 90.91 Eday

OD 3.00

Equipment/day 30.30
A Water Circular Pumps Nos. 50

B Daily Output Nos. 0.55

C A/B Duration, Days (8 Hrs/Day) Day 90.91

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 1.000 8 11.36 Mday

E2 Labor 2.000 8 22.73 Mday

F Sum "E" Total Man 3.000

G F*D/B Manhour 43.64 8 349.09 Mday

H G*A Total Manhours 2,181.82 8 272.73 Mday

OD 3

Manpower/day 90.91

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 11.36 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 14.545 8 116.36 Eday

L K*A Total Equiphours 727.27 8 90.91 Eday

OD 3.00

Equipment/day 30.30
A Interface Between FACP Points 50

B Daily Output Points 12

C A/B Duration, Days (8 Hrs/Day) Day 4.17

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Electrician 1.000 8 0.52 Mday

E2 Labor 1.000 8 0.52 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 1.33 8 10.67 Mday

H G*A Total Manhours 66.67 8 8.33 Mday

OD 3

Manpower/day 2.78

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.52 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.667 8 5.33 Eday

L K*A Total Equiphours 33.33 8 4.17 Eday

OD 3.00

Equipment/day 1.39
A disconnected Switch Install'n Nos. 50

B Daily Output Nos. 0.5

C A/B Duration, Days (8 Hrs/Day) Day 100.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Electrician 1.000 8 12.50 Mday

E3 Labor 1.000 8 12.50 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 32.00 8 256.00 Mday

H G*A Total Manhours 1,600.00 8 200.00 Mday

OD 3

Manpower/day 66.67

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 12.50 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 16.000 8 128.00 Eday

L K*A Total Equiphours 800.00 8 100.00 Eday

OD 3.00

Equipment/day 33.33
A Protection lightning kg. 500

B Daily Output kg. 140

C A/B Duration, Days (8 Hrs/Day) Day 3.57

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Electrician 1.000 8 0.45 Mday

E2 Labor 1.000 8 0.45 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.11 8 0.91 Mday

H G*A Total Manhours 57.14 8 7.14 Mday

OD 3

Manpower/day 2.38

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.45 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.057 8 0.46 Eday

L K*A Total Equiphours 28.57 8 3.57 Eday

OD 3.00

Equipment/day 1.19
A lighting fixture Nos. 200

B Daily Output Nos. 15

C A/B Duration, Days (8 Hrs/Day) Day 13.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrical Foreman 0.125 8 0.21 Mday

E2 Electrician 1.000 8 1.67 Mday

E3 Labor 1.000 8 1.67 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 1.13 8 9.07 Mday

H G*A Total Manhours 226.67 8 28.33 Mday

OD 3

Manpower/day 9.44

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 1.67 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.533 8 4.27 Eday

L K*A Total Equiphours 106.67 8 13.33 Eday

OD 3.00

Equipment/day 4.44
A U/G Conduits Lm 200

B Daily Output Lm 120

C A/B Duration, Days (8 Hrs/Day) Day 1.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrical Foreman 0.125 8 0.03 Mday

E2 Electrician 1.000 8 0.21 Mday

E3 Labor 1.000 8 0.21 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 0.14 8 1.13 Mday

H G*A Total Manhours 28.33 8 3.54 Mday

OD 3

Manpower/day 1.18

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.21 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.067 8 0.53 Eday

L K*A Total Equiphours 13.33 8 1.67 Eday

OD 3.00

Equipment/day 0.56
A Cable Tray Lm 200

B Daily Output Lm 12.65

C A/B Duration, Days (8 Hrs/Day) Day 15.81

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrical Foreman 0.125 8 0.25 Mday

E2 Electrician 1.000 8 1.98 Mday

E3 Labor 1.000 8 1.98 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 1.34 8 10.75 Mday

H G*A Total Manhours 268.77 8 33.60 Mday

OD 3

Manpower/day 11.20

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 1.98 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.632 8 5.06 Eday

L K*A Total Equiphours 126.48 8 15.81 Eday

OD 3.00

Equipment/day 5.27
A Aluminum Shutter(Roofing) M2 200

B Daily Output M2 100

C A/B Duration, Days (8 Hrs/Day) Day 2.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.125 8 0.03 Mday

E2 Metal Worker 2.000 8 0.50 Mday

E3 Building Laborer 3.000 8 0.75 Mday

F Sum "E" Total Man 5.125

G F*D/B Manhour 0.41 8 3.28 Mday

H G*A Total Manhours 82.00 8 10.25 Mday

OD 3

Manpower/day 3.42

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.25 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.080 8 0.64 Eday

L K*A Total Equiphours 16.00 8 2.00 Eday

OD 3.00

Equipment/day 0.67
A Foam Concrete Screed M2 100

B Daily Output M2 60

C A/B Duration, Days (8 Hrs/Day) Day 1.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.125 8 0.03 Mday

E2 Cement Finisher 2.000 8 0.42 Mday

E3 Equip.Operator 1.000 8 0.21 Mday

E4 Labor 3.000 8 0.63 Mday

F Sum "E" Total Man 6.125

G F*D/B Manhour 0.82 8 6.53 Mday

H G*A Total Manhours 81.67 8 10.21 Mday

OD 3

Manpower/day 3.40

I Equipment: @ Hrs

11 Concrete Pump Small 1.000 8 0.21 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.133 8 1.07 Eday

L K*A Total Equiphours 13.33 8 1.67 Eday

OD 3.00

Equipment/day 0.56
A Water Proofing Membrane M2 100

B Daily Output M2 55

C A/B Duration, Days (8 Hrs/Day) Day 1.82

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.125 8 0.03 Mday

E2 Skilled Labor 1.000 8 0.23 Mday

E3 Helper 1.000 8 0.23 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 0.31 8 2.47 Mday

H G*A Total Manhours 30.91 8 3.86 Mday

OD 3

Manpower/day 1.29

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.23 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.145 8 1.16 Eday

L K*A Total Equiphours 14.55 8 1.82 Eday

OD 3.00

Equipment/day 0.61
A Pvc Conduiting & Accessories Lm. 100

B Daily Output Lm. 25

C A/B Duration, Days (8 Hrs/Day) Day 4.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrical Foreman 0.125 8 0.06 Mday

E2 Electrician 1.000 8 0.50 Mday

E3 Helper 1.000 8 0.50 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 0.68 8 5.44 Mday

H G*A Total Manhours 68.00 8 8.50 Mday

OD 3

Manpower/day 2.83

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.50 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.320 8 2.56 Eday

L K*A Total Equiphours 32.00 8 4.00 Eday

OD 3.00

Equipment/day 1.33
A Data & Rj45/Rj45 Other Accessories Nos. 100

B Daily Output Nos. 15

C A/B Duration, Days (8 Hrs/Day) Day 6.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Painter 2.000 8 1.67 Mday

E2 Helper 2.000 8 1.67 Mday

F Sum "E" Total Man 4.000

G F*D/B Manhour 2.13 8 17.07 Mday

H G*A Total Manhours 213.33 8 26.67 Mday

OD 3

Manpower/day 8.89

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.83 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.533 8 4.27 Eday

L K*A Total Equiphours 53.33 8 6.67 Eday

OD 3.00

Equipment/day 2.22
A Telephone,Data, Tv Outlets Nos. 100

B Daily Output Nos. 14

C A/B Duration, Days (8 Hrs/Day) Day 7.14

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrician 1.000 8 0.89 Mday

E2 Helper 1.000 8 0.89 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 1.14 8 9.14 Mday

H G*A Total Manhours 114.29 8 14.29 Mday

OD 3

Manpower/day 4.76

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.89 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.571 8 4.57 Eday

L K*A Total Equiphours 57.14 8 7.14 Eday

OD 3.00

Equipment/day 2.38
A Fire Alarm Devices Points. 100

B Daily Output Points. 12

C A/B Duration, Days (8 Hrs/Day) Day 8.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrical Foreman 0.125 8 0.13 Mday

E2 Special Electrician 1.000 8 1.04 Mday

E3 Helper 1.000 8 1.04 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 1.42 8 11.33 Mday

H G*A Total Manhours 141.67 8 17.71 Mday

OD 3

Manpower/day 5.90

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 1.04 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.667 8 5.33 Eday

L K*A Total Equiphours 66.67 8 8.33 Eday

OD 3.00

Equipment/day 2.78
A Clock System Nos. 100

B Daily Output Nos. 3.5

C A/B Duration, Days (8 Hrs/Day) Day 28.57

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrical Foreman 0.125 8 0.45 Mday

E2 Electrician 1.000 8 3.57 Mday

E3 Helper 1.000 8 3.57 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 4.86 8 38.86 Mday

H G*A Total Manhours 485.71 8 60.71 Mday

OD 3

Manpower/day 20.24

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 3.57 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 2.286 8 18.29 Eday

L K*A Total Equiphours 228.57 8 28.57 Eday

OD 3.00

Equipment/day 9.52
A Lightning Protection kg. 200

B Daily Output kg. 140

C A/B Duration, Days (8 Hrs/Day) Day 1.43

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 1.000 8 0.18 Mday

E3 Electrician 1.000 8 0.18 Mday

E3 Helper 1.000 8 0.18 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.11 8 0.91 Mday

H G*A Total Manhours 22.86 8 2.86 Mday

OD 3

Manpower/day 0.95

I Equipment: @ Hrs

11 Power Tool Set 1.000 8 0.18 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.057 8 0.46 Eday

L K*A Total Equiphours 11.43 8 1.43 Eday

OD 3.00

Equipment/day 0.48
A Antenna Installation Lm 10

B Daily Output Lm 6

C A/B Duration, Days (8 Hrs/Day) Day 1.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 1.000 8 0.21 Mday

E3 Helper 1.000 8 0.21 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 2.67 8 21.33 Mday

H G*A Total Manhours 26.67 8 3.33 Mday

OD 3

Manpower/day 1.11

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.21 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.333 8 10.67 Eday

L K*A Total Equiphours 13.33 8 1.67 Eday

OD 3.00

Equipment/day 0.56
A External Cables Lm 10

B Daily Output Lm 39

C A/B Duration, Days (8 Hrs/Day) Day 0.26

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrical Foreman 0.125 8 0.00 Mday

E1 Electrician 1.000 8 0.03 Mday

E3 Helper 1.000 8 0.03 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 0.44 8 3.49 Mday

H G*A Total Manhours 4.36 8 0.54 Mday

OD 3

Manpower/day 0.18

I Equipment: @ Hrs

11 Tool Set 8 - Mday

J Sum "I" Total Equip -

K J*D/B EquipHour - 8 - Eday

L K*A Total Equiphours - 8 - Eday

OD 3.00

Equipment/day -
A Lighting Pole Each 10

B Daily Output Each 7

C A/B Duration, Days (8 Hrs/Day) Day 1.43

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrician 1.000 8 0.18 Mday

E3 Helper 1.000 8 0.18 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 2.29 8 18.29 Mday

H G*A Total Manhours 22.86 8 2.86 Mday

OD 3

Manpower/day 0.95

I Equipment: @ Hrs

11 8 - Mday

12 8 - Mday

J Sum "I" Total Equip -

K J*D/B EquipHour - 8 - Eday

L K*A Total Equiphours - 8 - Eday

OD 3.00

Equipment/day -
A Transformer 13.8Kv.,127/220 1000Kva Nos. 10

B Daily Output Nos. 0.35

C A/B Duration, Days (8 Hrs/Day) Day 28.57

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrical Foreman 0.125 8 0.45 Mday

E2 Electrician 1.000 8 3.57 Mday

E2 Equip Operator 1.000 8 3.57 Mday

E3 Helper 1.000 8 3.57 Mday

F Sum "E" Total Man 3.125

G F*D/B Manhour 71.43 8 571.43 Mday

H G*A Total Manhours 714.29 8 89.29 Mday

OD 3

Manpower/day 29.76

I Equipment: @ Hrs

11 1 Truck crane 1.000 8 3.57 Mday

12 Power/Tool Set 1.000 8 3.57 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 22.857 8 182.86 Eday

L K*A Total Equiphours 228.57 8 28.57 Eday

OD 3.00

Equipment/day 9.52
A Switches & Outlets Nos. 100

B Daily Output Nos. 20

C A/B Duration, Days (8 Hrs/Day) Day 5.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrical Foreman 0.125 8 0.08 Mday

E2 Electrician 1.000 8 0.63 Mday

E2 Equip Operator 1.000 8 0.63 Mday

E3 Helper 1.000 8 0.63 Mday

F Sum "E" Total Man 3.125

G F*D/B Manhour 1.25 8 10.00 Mday

H G*A Total Manhours 125.00 8 15.63 Mday

OD 3

Manpower/day 5.21

I Equipment: @ Hrs

11 1 Truck crane 1.000 8 0.63 Mday

12 Power/Tool Set 1.000 8 0.63 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.400 8 3.20 Eday

L K*A Total Equiphours 40.00 8 5.00 Eday

OD 3.00

Equipment/day 1.67
A Lighting Fixtures installation. Nos. 100

B Daily Output Nos. 15

C A/B Duration, Days (8 Hrs/Day) Day 6.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrical Foreman 0.125 8 0.10 Mday

E2 Electrician 1.000 8 0.83 Mday

E3 Helper 1.000 8 0.83 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 1.13 8 9.07 Mday

H G*A Total Manhours 113.33 8 14.17 Mday

OD 3

Manpower/day 4.72

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.83 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.533 8 4.27 Eday

L K*A Total Equiphours 53.33 8 6.67 Eday

OD 3.00

Equipment/day 2.22
A Panel boards & Accessories Nos. 100

B Daily Output Nos. 0.96

C A/B Duration, Days (8 Hrs/Day) Day 104.17

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrical Foreman 0.125 8 1.63 Mday

E2 Electrician 1.000 8 13.02 Mday

E3 Helper 1.000 8 13.02 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 17.71 8 141.67 Mday

H G*A Total Manhours 1,770.83 8 221.35 Mday

OD 3

Manpower/day 73.78

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 13.02 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 8.333 8 66.67 Eday

L K*A Total Equiphours 833.33 8 104.17 Eday

OD 3.00

Equipment/day 34.72
A Wire & Cables M. 100

B Daily Output M. 90

C A/B Duration, Days (8 Hrs/Day) Day 1.11

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrical Foreman 0.125 8 0.02 Mday

E2 Electrician 1.000 8 0.14 Mday

E3 Helper 1.000 8 0.14 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 0.19 8 1.51 Mday

H G*A Total Manhours 18.89 8 2.36 Mday

OD 3

Manpower/day 0.79

I Equipment: @ Hrs

11 Power/Tool Set 1.000 8 0.14 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.089 8 0.71 Eday

L K*A Total Equiphours 8.89 8 1.11 Eday

OD 3.00

Equipment/day 0.37
A Sanitary Fixture Unit 100

B Daily Output Unit 2

C A/B Duration, Days (8 Hrs/Day) Day 50.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 1.000 8 6.25 Mday

E2 Sheet Metal Worker 1.000 8 6.25 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 8.00 8 64.00 Mday

H G*A Total Manhours 800.00 8 100.00 Mday

OD 3

Manpower/day 33.33

I Equipment: @ Hrs

11 Tool Set 1.000 8 6.25 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 4.000 8 32.00 Eday

L K*A Total Equiphours 400.00 8 50.00 Eday

OD 3.00

Equipment/day 16.67
A Fire Fighting Final Fixture & Cabinet Unit 100

B Daily Output Unit 3

C A/B Duration, Days (8 Hrs/Day) Day 33.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 1.000 8 4.17 Mday

E2 Sheet Metal Worker 1.000 8 4.17 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 5.33 8 42.67 Mday

H G*A Total Manhours 533.33 8 66.67 Mday

OD 3

Manpower/day 22.22

I Equipment: @ Hrs

11 Tool Set 1.000 8 4.17 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 2.667 8 21.33 Eday

L K*A Total Equiphours 266.67 8 33.33 Eday

OD 3.00

Equipment/day 11.11
A Grilles & Diffusers Installation each 100

B Daily Output each 10

C A/B Duration, Days (8 Hrs/Day) Day 10.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 1.000 8 1.25 Mday

E2 Sheet Metal Worker 1.000 8 1.25 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 1.60 8 12.80 Mday

H G*A Total Manhours 160.00 8 20.00 Mday

OD 3

Manpower/day 6.67

I Equipment: @ Hrs

11 Tool Set 1.000 8 1.25 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.800 8 6.40 Eday

L K*A Total Equiphours 80.00 8 10.00 Eday

OD 3.00

Equipment/day 3.33
A Grilles & Diffusers Installation Unit 100

B Daily Output Unit 6

C A/B Duration, Days (8 Hrs/Day) Day 16.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.26 Mday

E2 Sheet Metal Worker 1.000 8 2.08 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 1.50 8 12.00 Mday

H G*A Total Manhours 150.00 8 18.75 Mday

OD 3

Manpower/day 6.25

I Equipment: @ Hrs

11 Tool Set 1.000 8 2.08 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.333 8 10.67 Eday

L K*A Total Equiphours 133.33 8 16.67 Eday

OD 3.00

Equipment/day 5.56
A Bms & Other Accessories Nos. 100

B Daily Output Nos. 7

C A/B Duration, Days (8 Hrs/Day) Day 14.29

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 1.000 8 1.79 Mday

E1 Electrician 1.000 8 1.79 Mday

E2 Helper 1.000 8 1.79 Mday

F Sum "E" Total Man 3.000

G F*D/B Manhour 3.43 8 27.43 Mday

H G*A Total Manhours 342.86 8 42.86 Mday

OD 3

Manpower/day 14.29

I Equipment: @ Hrs

11 Tool Set 1.000 8 1.79 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.143 8 9.14 Eday

L K*A Total Equiphours 114.29 8 14.29 Eday

OD 3.00

Equipment/day 4.76
A Vav Nos. 100

B Daily Output Nos. 4

C A/B Duration, Days (8 Hrs/Day) Day 25.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 2.000 8 6.25 Mday

E2 Helper 2.000 8 6.25 Mday

F Sum "E" Total Man 4.000

G F*D/B Manhour 8.00 8 64.00 Mday

H G*A Total Manhours 800.00 8 100.00 Mday

OD 3

Manpower/day 33.33

I Equipment: @ Hrs

11 Tool Set 1.000 8 3.13 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 2.000 8 16.00 Eday

L K*A Total Equiphours 200.00 8 25.00 Eday

OD 3.00

Equipment/day 8.33
A VavR Nos. 100

B Daily Output Nos. 7

C A/B Duration, Days (8 Hrs/Day) Day 14.29

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 2.000 8 3.57 Mday

E2 Helper 2.000 8 3.57 Mday

F Sum "E" Total Man 4.000

G F*D/B Manhour 4.57 8 36.57 Mday

H G*A Total Manhours 457.14 8 57.14 Mday

OD 3

Manpower/day 19.05

I Equipment: @ Hrs

11 Tool Set 1.000 8 1.79 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.143 8 9.14 Eday

L K*A Total Equiphours 114.29 8 14.29 Eday

OD 3.00

Equipment/day 4.76
A Fan Exhaust (Fans) Nos. 100

B Daily Output Nos. 6

C A/B Duration, Days (8 Hrs/Day) Day 16.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.26 Mday

E2 Sheet Metal Worker 2.000 8 4.17 Mday

E3 Electrician 0.250 8 0.52 Mday

E4 Labor 1.000 8 2.08 Mday

F Sum "E" Total Man 3.375

G F*D/B Manhour 4.50 8 36.00 Mday

H G*A Total Manhours 450.00 8 56.25 Mday

OD 3

Manpower/day 18.75

I Equipment: @ Hrs

11 Tool Set 1.000 8 2.08 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.333 8 10.67 Eday

L K*A Total Equiphours 133.33 8 16.67 Eday

OD 3.00

Equipment/day 5.56
A External Ducts M2 100

B Daily Output M2 15

C A/B Duration, Days (8 Hrs/Day) Day 6.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Unskilled Labor 1.000 8 0.83 Mday

E2 Labor 1.000 8 0.83 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 1.07 8 8.53 Mday

H G*A Total Manhours 106.67 8 13.33 Mday

OD 3

Manpower/day 4.44

I Equipment: @ Hrs

11 Tool Set 1.000 8 0.83 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.533 8 4.27 Eday

L K*A Total Equiphours 53.33 8 6.67 Eday

OD 3.00

Equipment/day 2.22
A Duct Insulation M2 100

B Daily Output M2 27

C A/B Duration, Days (8 Hrs/Day) Day 3.70

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Unskilled Labor 1.000 8 0.46 Mday

E2 Labor 1.000 8 0.46 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.59 8 4.74 Mday

H G*A Total Manhours 59.26 8 7.41 Mday

OD 3

Manpower/day 2.47

I Equipment: @ Hrs

11 Tool Set 1.000 8 0.46 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.296 8 2.37 Eday

L K*A Total Equiphours 29.63 8 3.70 Eday

OD 3.00

Equipment/day 1.23
A Duct Works M2 100

B Daily Output M2 12

C A/B Duration, Days (8 Hrs/Day) Day 8.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Unskilled Labor 1.000 8 1.04 Mday

E2 Labor 1.000 8 1.04 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 1.33 8 10.67 Mday

H G*A Total Manhours 133.33 8 16.67 Mday

OD 3

Manpower/day 5.56

I Equipment: @ Hrs

11 Tool Set 1.000 8 1.04 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.667 8 5.33 Eday

L K*A Total Equiphours 66.67 8 8.33 Eday

OD 3.00

Equipment/day 2.78
A Ducting Works & Insullation Kg. 500

B Daily Output Kg. 80

C A/B Duration, Days (8 Hrs/Day) Day 6.25

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.125 8 0.10 Mday

E2 Sheet Metal Worker 2.000 8 1.56 Mday

E3 Labor 1.000 8 0.78 Mday

F Sum "E" Total Man 3.125

G F*D/B Manhour 0.31 8 2.50 Mday

H G*A Total Manhours 156.25 8 19.53 Mday

OD 3

Manpower/day 6.51

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.78 Mday

12 Tool Set 1.000 8 0.78 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.100 8 0.80 Eday

L K*A Total Equiphours 50.00 8 6.25 Eday

OD 3.00

Equipment/day 2.08
A Electric Water Heater (EWH) Nos. 50

B Daily Output Nos. 0.65

C A/B Duration, Days (8 Hrs/Day) Day 76.92

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Plumbing Foreman 0.125 8 1.20 Mday

E2 Plumber 1.000 8 9.62 Mday

E3 Plumber Apprentice 1.000 8 9.62 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 26.15 8 209.23 Mday

H G*A Total Manhours 1,307.69 8 163.46 Mday

OD 3

Manpower/day 54.49

I Equipment: @ Hrs

11 Tool Set 1.000 8 9.62 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 12.308 8 98.46 Eday

L K*A Total Equiphours 615.38 8 76.92 Eday

OD 3.00

Equipment/day 25.64
A DX Split Unit Pcs 100

B Daily Output Pcs 4

C A/B Duration, Days (8 Hrs/Day) Day 25.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical 1.000 8 3.13 Mday

E2 Helper 2.000 8 6.25 Mday

F Sum "E" Total Man 3.000

G F*D/B Manhour 6.00 8 48.00 Mday

H G*A Total Manhours 600.00 8 75.00 Mday

OD 3

Manpower/day 25.00

I Equipment: @ Hrs

11 Tool Set 1.000 8 3.13 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 2.000 8 16.00 Eday

L K*A Total Equiphours 200.00 8 25.00 Eday

OD 3.00

Equipment/day 8.33
A Plumbing Fixtures & Accessories Pcs 100

B Daily Output Pcs 10

C A/B Duration, Days (8 Hrs/Day) Day 10.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Plumbing Foreman 0.125 8 0.16 Mday

E2 Plumber 1.000 8 1.25 Mday

E3 Plumber Apprentice 1.000 8 1.25 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 1.70 8 13.60 Mday

H G*A Total Manhours 170.00 8 21.25 Mday

OD 3

Manpower/day 7.08

I Equipment: @ Hrs

11 Tool Set 1.000 8 1.25 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.800 8 6.40 Eday

L K*A Total Equiphours 80.00 8 10.00 Eday

OD 3.00

Equipment/day 3.33
A U.P.V.C. Piping (Drainage First Fix) Unit 100

B Daily Output Unit 8

C A/B Duration, Days (8 Hrs/Day) Day 12.50

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Plumber 1.000 8 1.56 Mday

E2 Plumber Apprentice 1.000 8 1.56 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 2.00 8 16.00 Mday

H G*A Total Manhours 200.00 8 25.00 Mday

OD 3

Manpower/day 8.33

I Equipment: @ Hrs

11 Tool Set 1.000 8 1.56 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.000 8 8.00 Eday

L K*A Total Equiphours 100.00 8 12.50 Eday

OD 3.00

Equipment/day 4.17
A Black Seamless Steel Pipes Lm 100

B Daily Output Lm 18.6

C A/B Duration, Days (8 Hrs/Day) Day 5.38

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.125 8 0.08 Mday

E2 Skilled Labor 1.000 8 0.67 Mday

E3 Plumber Apprentice 1.000 8 0.67 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 0.91 8 7.31 Mday

H G*A Total Manhours 91.40 8 11.42 Mday

OD 3

Manpower/day 3.81

I Equipment: @ Hrs

11 Tool Set 1.000 8 0.67 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.430 8 3.44 Eday

L K*A Total Equiphours 43.01 8 5.38 Eday

OD 3.00

Equipment/day 1.79
A Floor Drains + Floor Clean Out Nos 100

B Daily Output Nos 7

C A/B Duration, Days (8 Hrs/Day) Day 14.29

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.125 8 0.22 Mday

E2 Skilled Foreman 1.000 8 1.79 Mday

E3 Plumber Apprentice 1.000 8 1.79 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 2.43 8 19.43 Mday

H G*A Total Manhours 242.86 8 30.36 Mday

OD 3

Manpower/day 10.12

I Equipment: @ Hrs

11 Tool Set 1.000 8 1.79 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.143 8 9.14 Eday

L K*A Total Equiphours 114.29 8 14.29 Eday

OD 3.00

Equipment/day 4.76
A Drainage Piping System Lm. 100

B Daily Output Lm. 16

C A/B Duration, Days (8 Hrs/Day) Day 6.25

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.125 8 0.10 Mday

E2 Skilled Foreman 1.000 8 0.78 Mday

E3 Plumber Apprentice 1.000 8 0.78 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 1.06 8 8.50 Mday

H G*A Total Manhours 106.25 8 13.28 Mday

OD 3

Manpower/day 4.43

I Equipment: @ Hrs

11 Tool Set 1.000 8 0.78 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.500 8 4.00 Eday

L K*A Total Equiphours 50.00 8 6.25 Eday

OD 3.00

Equipment/day 2.08
A Water Supply Piping Lm. 100

B Daily Output Lm. 10.33

C A/B Duration, Days (8 Hrs/Day) Day 9.68

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.125 8 0.15 Mday

E2 Skilled Foreman 1.000 8 1.21 Mday

E3 Plumber Apprentice 1.000 8 1.21 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 1.65 8 13.17 Mday

H G*A Total Manhours 164.57 8 20.57 Mday

OD 3

Manpower/day 6.86

I Equipment: @ Hrs

11 Tool Set 1.000 8 1.21 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.774 8 6.20 Eday

L K*A Total Equiphours 77.44 8 9.68 Eday

OD 3.00

Equipment/day 3.23
A Venetian Blind M2 100

B Daily Output M2 25

C A/B Duration, Days (8 Hrs/Day) Day 4.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.125 8 0.06 Mday

E2 Carpenter 1.000 8 0.50 Mday

E3 Labor 1.000 8 0.50 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.36 8 2.88 Mday

H G*A Total Manhours 36.00 8 4.50 Mday

OD 3

Manpower/day 1.50

I Equipment: @ Hrs

11 Tool Set 1.000 8 0.50 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.320 8 2.56 Eday

L K*A Total Equiphours 32.00 8 4.00 Eday

OD 3.00

Equipment/day 1.33
A Fire Hose Cabinet Pcs 50

B Daily Output Pcs 2

C A/B Duration, Days (8 Hrs/Day) Day 25.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.125 8 0.39 Mday

E2 Sprinkle Installer 1.000 8 3.13 Mday

E3 Plumber Apprentice 1.000 8 3.13 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 4.50 8 36.00 Mday

H G*A Total Manhours 225.00 8 28.13 Mday

OD 3

Manpower/day 9.38

I Equipment: @ Hrs

11 Tool Set 1.000 8 3.13 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 4.000 8 32.00 Eday

L K*A Total Equiphours 200.00 8 25.00 Eday

OD 3.00

Equipment/day 8.33
A Fire Extiguisher 6kg.Dry Powder + Hydrant
Nos. 100

B Daily Output Nos. 7

C A/B Duration, Days (8 Hrs/Day) Day 14.29

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Plumber Foreman 0.125 8 0.22 Mday

E2 Plumber 1.000 8 1.79 Mday

E3 Plumber Apprentice 1.000 8 1.79 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 1.29 8 10.29 Mday

H G*A Total Manhours 128.57 8 16.07 Mday

OD 3

Manpower/day 5.36

I Equipment: @ Hrs

11 Tool Set 1.000 8 1.79 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.143 8 9.14 Eday

L K*A Total Equiphours 114.29 8 14.29 Eday

OD 3.00

Equipment/day 4.76
A Sprinkle & Accessories Nos. 100

B Daily Output Nos. 11

C A/B Duration, Days (8 Hrs/Day) Day 9.09

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.125 8 0.14 Mday

E2 Sprinkle Installer 1.000 8 1.14 Mday

E3 Sprinkle Apprentice 1.000 8 1.14 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.82 8 6.55 Mday

H G*A Total Manhours 81.82 8 10.23 Mday

OD 3

Manpower/day 3.41

I Equipment: @ Hrs

11 Tool Set 1.000 8 1.14 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.727 8 5.82 Eday

L K*A Total Equiphours 72.73 8 9.09 Eday

OD 3.00

Equipment/day 3.03
A Fire Fighting Piping Lm. 100

B Daily Output Lm. 15.44

C A/B Duration, Days (8 Hrs/Day) Day 6.48

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.10 Mday

E2 Skilled Worker 1.000 8 0.81 Mday

E3 Plumber 1.000 8 0.81 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.58 8 4.66 Mday

H G*A Total Manhours 58.29 8 7.29 Mday

OD 3

Manpower/day 2.43

I Equipment: @ Hrs

11 Tool Set 1.000 8 0.81 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.518 8 4.15 Eday

L K*A Total Equiphours 51.81 8 6.48 Eday

OD 3.00

Equipment/day 2.16
A Toilet Partition Lm. 100

B Daily Output Lm. 3.25

C A/B Duration, Days (8 Hrs/Day) Day 30.77

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.48 Mday

E2 Carpenter 1.000 8 3.85 Mday

E3 Labor 1.000 8 3.85 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 2.77 8 22.15 Mday

H G*A Total Manhours 276.92 8 34.62 Mday

OD 3

Manpower/day 11.54

I Equipment: @ Hrs

11 Tool Set 1.000 8 3.85 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 2.462 8 19.69 Eday

L K*A Total Equiphours 246.15 8 30.77 Eday

OD 3.00

Equipment/day 10.26
A Epoxy Coating m2 100

B Daily Output m2 30

C A/B Duration, Days (8 Hrs/Day) Day 3.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Painter 1.000 8 0.42 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 0.27 8 2.13 Mday

H G*A Total Manhours 26.67 8 3.33 Mday

OD 3

Manpower/day 1.11

I Equipment: @ Hrs

11 Consumable Tool Set 1.000 8 0.42 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.267 8 2.13 Eday

L K*A Total Equiphours 26.67 8 3.33 Eday

OD 3.00

Equipment/day 1.11
A Toilet Bath Accessories Pcs 100

B Daily Output Pcs 14

C A/B Duration, Days (8 Hrs/Day) Day 7.14

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.11 Mday

E2 Carpenter 1.000 8 0.89 Mday

E3 Labor 1.000 8 0.89 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.64 8 5.14 Mday

H G*A Total Manhours 64.29 8 8.04 Mday

OD 3

Manpower/day 2.68

I Equipment: @ Hrs

11 Tool Set 1.000 8 0.89 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.571 8 4.57 Eday

L K*A Total Equiphours 57.14 8 7.14 Eday

OD 3.00

Equipment/day 2.38
A Vinyl Tiles m2 200

B Daily Output m2 25

C A/B Duration, Days (8 Hrs/Day) Day 8.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.13 Mday

E2 Tile Layer 2.000 8 2.00 Mday

E3 Helper 1.000 8 1.00 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 0.68 8 5.44 Mday

H G*A Total Manhours 136.00 8 17.00 Mday

OD 3

Manpower/day 5.67

I Equipment: @ Hrs

11 Tool Set 1.000 8 1.00 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.320 8 2.56 Eday

L K*A Total Equiphours 64.00 8 8.00 Eday

OD 3.00

Equipment/day 2.67
A Suspended Ceiling m2 500

B Daily Output m2 23

C A/B Duration, Days (8 Hrs/Day) Day 21.74

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.34 Mday

E2 Finishing Carpenter 2.000 8 5.43 Mday

E3 Helper 1.000 8 2.72 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 0.74 8 5.91 Mday

H G*A Total Manhours 369.57 8 46.20 Mday

OD 3

Manpower/day 15.40

I Equipment: @ Hrs

11 Tool Set 1.000 8 2.72 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.348 8 2.78 Eday

L K*A Total Equiphours 173.91 8 21.74 Eday

OD 3.00

Equipment/day 7.25
A hardner flooring m2 100

B Daily Output m2 40

C A/B Duration, Days (8 Hrs/Day) Day 2.50

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.04 Mday

E2 Tile Layer 1.000 8 0.31 Mday

E3 Helper 1.000 8 0.31 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.23 8 1.80 Mday

H G*A Total Manhours 22.50 8 2.81 Mday

OD 3

Manpower/day 0.94

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.31 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.200 8 1.60 Eday

L K*A Total Equiphours 20.00 8 2.50 Eday

OD 3.00

Equipment/day 0.83
A Ceramic wall Tiling m2 100

B Daily Output m2 10

C A/B Duration, Days (8 Hrs/Day) Day 10.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.16 Mday

E2 Tile Layer 1.000 8 1.25 Mday

E3 Helper 1.000 8 1.25 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.90 8 7.20 Mday

H G*A Total Manhours 90.00 8 11.25 Mday

OD 3

Manpower/day 3.75

I Equipment: @ Hrs

11 Power Tool 1.000 8 1.25 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.800 8 6.40 Eday

L K*A Total Equiphours 80.00 8 10.00 Eday

OD 3.00

Equipment/day 3.33
A Marble Circular Columns Tiling m2 100

B Daily Output m2 3

C A/B Duration, Days (8 Hrs/Day) Day 33.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.52 Mday

E2 Tile Layer 1.000 8 4.17 Mday

E3 Helper 1.000 8 4.17 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 3.00 8 24.00 Mday

H G*A Total Manhours 300.00 8 37.50 Mday

OD 3

Manpower/day 12.50

I Equipment: @ Hrs

11 Power Tool 1.000 8 4.17 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 2.667 8 21.33 Eday

L K*A Total Equiphours 266.67 8 33.33 Eday

OD 3.00

Equipment/day 11.11
A Marble Walls Tilling m2 100

B Daily Output m2 7

C A/B Duration, Days (8 Hrs/Day) Day 14.29

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.22 Mday

E2 Tile Layer 1.000 8 1.79 Mday

E3 Helper 1.000 8 1.79 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 1.29 8 10.29 Mday

H G*A Total Manhours 128.57 8 16.07 Mday

OD 3

Manpower/day 5.36

I Equipment: @ Hrs

11 Power Tool 1.000 8 1.79 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.143 8 9.14 Eday

L K*A Total Equiphours 114.29 8 14.29 Eday

OD 3.00

Equipment/day 4.76
A Aluminum Wall Cladding 1220x2440x38mm Thick
m2 100

B Daily Output m2 22

C A/B Duration, Days (8 Hrs/Day) Day 4.55

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.07 Mday

E2 Tile Layer 1.350 8 0.77 Mday

E3 Helper 2.000 8 1.14 Mday

F Sum "E" Total Man 1.475

G F*D/B Manhour 0.54 8 4.29 Mday

H G*A Total Manhours 53.64 8 6.70 Mday

OD 3

Manpower/day 2.23

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.57 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.364 8 2.91 Eday

L K*A Total Equiphours 36.36 8 4.55 Eday

OD 3.00

Equipment/day 1.52
A Interlocking M2 100

B Daily Output M2 16

C A/B Duration, Days (8 Hrs/Day) Day 6.25

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.10 Mday

E2 Tile Layer 1.000 8 0.78 Mday

E3 Helper 1.000 8 0.78 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.56 8 4.50 Mday

H G*A Total Manhours 56.25 8 7.03 Mday

OD 3

Manpower/day 2.34

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.78 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.500 8 4.00 Eday

L K*A Total Equiphours 50.00 8 6.25 Eday

OD 3.00

Equipment/day 2.08
A Interlocking ( 50mmx400mmx400mm ) M2 100

B Daily Output M2 24

C A/B Duration, Days (8 Hrs/Day) Day 4.17

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.07 Mday

E2 Tile Layer 1.000 8 0.52 Mday

E3 Helper 1.000 8 0.52 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.38 8 3.00 Mday

H G*A Total Manhours 37.50 8 4.69 Mday

OD 3

Manpower/day 1.56

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.52 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.333 8 2.67 Eday

L K*A Total Equiphours 33.33 8 4.17 Eday

OD 3.00

Equipment/day 1.39
A Marble stairs Skirting No. 100

B Daily Output No. 30

C A/B Duration, Days (8 Hrs/Day) Day 3.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.05 Mday

E2 Tile Layer 1.000 8 0.42 Mday

E3 Helper 1.000 8 0.42 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.30 8 2.40 Mday

H G*A Total Manhours 30.00 8 3.75 Mday

OD 3

Manpower/day 1.25

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.42 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.267 8 2.13 Eday

L K*A Total Equiphours 26.67 8 3.33 Eday

OD 3.00

Equipment/day 1.11
A Marble Skirting Lm 100

B Daily Output Lm 35

C A/B Duration, Days (8 Hrs/Day) Day 2.86

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.04 Mday

E2 Tile Layer 1.000 8 0.36 Mday

E3 Helper 1.000 8 0.36 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.26 8 2.06 Mday

H G*A Total Manhours 25.71 8 3.21 Mday

OD 3

Manpower/day 1.07

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.36 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.229 8 1.83 Eday

L K*A Total Equiphours 22.86 8 2.86 Eday

OD 3.00

Equipment/day 0.95
A Marble stairs Tilling Lm 100

B Daily Output Lm 25

C A/B Duration, Days (8 Hrs/Day) Day 4.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.06 Mday

E2 Tile Layer 1.000 8 0.50 Mday

E3 Helper 1.000 8 0.50 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.36 8 2.88 Mday

H G*A Total Manhours 36.00 8 4.50 Mday

OD 3

Manpower/day 1.50

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.50 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.320 8 2.56 Eday

L K*A Total Equiphours 32.00 8 4.00 Eday

OD 3.00

Equipment/day 1.33
A Ceramic Floor Tilling 100mmx200mmx13mm
m2 100

B Daily Output m2 9.3

C A/B Duration, Days (8 Hrs/Day) Day 10.75

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.17 Mday

E2 Tile Layer 1.000 8 1.34 Mday

E3 Helper 1.000 8 1.34 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.97 8 7.74 Mday

H G*A Total Manhours 96.77 8 12.10 Mday

OD 3

Manpower/day 4.03

I Equipment: @ Hrs

11 Power Tool 1.000 8 1.34 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.860 8 6.88 Eday

L K*A Total Equiphours 86.02 8 10.75 Eday

OD 3.00

Equipment/day 3.58
A Cement Floor Tilling m2 100

B Daily Output m2 30

C A/B Duration, Days (8 Hrs/Day) Day 3.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.05 Mday

E2 Tile Layer 1.000 8 0.42 Mday

E3 Helper 1.000 8 0.42 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.30 8 2.40 Mday

H G*A Total Manhours 30.00 8 3.75 Mday

OD 3

Manpower/day 1.25

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.42 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.267 8 2.13 Eday

L K*A Total Equiphours 26.67 8 3.33 Eday

OD 3.00

Equipment/day 1.11
A Marble Floor Tilling m2 100

B Daily Output m2 7

C A/B Duration, Days (8 Hrs/Day) Day 14.29

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.22 Mday

E2 Tile Layer 1.000 8 1.79 Mday

E3 Helper 1.000 8 1.79 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 1.29 8 10.29 Mday

H G*A Total Manhours 128.57 8 16.07 Mday

OD 3

Manpower/day 5.36

I Equipment: @ Hrs

11 Power Tool 1.000 8 1.79 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.143 8 9.14 Eday

L K*A Total Equiphours 114.29 8 14.29 Eday

OD 3.00

Equipment/day 4.76
A Terrazo Tiles m2 100

B Daily Output m2 15

C A/B Duration, Days (8 Hrs/Day) Day 6.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.10 Mday

E2 Tile Layer 2.000 8 1.67 Mday

E3 Helper 1.000 8 0.83 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 1.13 8 9.07 Mday

H G*A Total Manhours 113.33 8 14.17 Mday

OD 3

Manpower/day 4.72

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.83 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.533 8 4.27 Eday

L K*A Total Equiphours 53.33 8 6.67 Eday

OD 3.00

Equipment/day 2.22
A Terrazo Skirting Lm 100

B Daily Output Lm 10

C A/B Duration, Days (8 Hrs/Day) Day 10.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.16 Mday

E2 Tile Layer 2.000 8 2.50 Mday

E3 Helper 1.000 8 1.25 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 1.70 8 13.60 Mday

H G*A Total Manhours 170.00 8 21.25 Mday

OD 3

Manpower/day 7.08

I Equipment: @ Hrs

11 Power Tool 1.000 8 1.25 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.800 8 6.40 Eday

L K*A Total Equiphours 80.00 8 10.00 Eday

OD 3.00

Equipment/day 3.33
A Ceramic Wall m2 50

B Daily Output m2 30

C A/B Duration, Days (8 Hrs/Day) Day 1.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.03 Mday

E2 Tile Layer 2.000 8 0.42 Mday

E3 Helper 1.000 8 0.21 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 0.57 8 4.53 Mday

H G*A Total Manhours 28.33 8 3.54 Mday

OD 3

Manpower/day 1.18

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.21 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.267 8 2.13 Eday

L K*A Total Equiphours 13.33 8 1.67 Eday

OD 3.00

Equipment/day 0.56
A Ceramic Floor m2 100

B Daily Output m2 17

C A/B Duration, Days (8 Hrs/Day) Day 5.88

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.09 Mday

E2 Tile Layer 2.000 8 1.47 Mday

E3 Helper 1.000 8 0.74 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 1.00 8 8.00 Mday

H G*A Total Manhours 100.00 8 12.50 Mday

OD 3

Manpower/day 4.17

I Equipment: @ Hrs

I1 Power Tool 1.000 8 0.74 Mday

I2

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.471 8 3.76 Eday

L K*A Total Equiphours 47.06 8 5.88 Eday

OD 3.00

Equipment/day 1.96
A Screeding (by machine) m2 500

B Daily Output m2 70

C A/B Duration, Days (8 Hrs/Day) Day 7.14

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.11 Mday

E2 Tile Layer 2.000 8 1.79 Mday

E3 Helper 1.000 8 0.89 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 0.24 8 1.94 Mday

H G*A Total Manhours 121.43 8 15.18 Mday

OD 3

Manpower/day 5.06

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.89 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.114 8 0.91 Eday

L K*A Total Equiphours 57.14 8 7.14 Eday

OD 3.00

Equipment/day 2.38
A Steel Window Pcs 50

B Daily Output Pcs 9

C A/B Duration, Days (8 Hrs/Day) Day 5.56

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.09 Mday

E2 Carpenter 2.000 8 1.39 Mday

E3 Helper 1.000 8 0.69 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 1.89 8 15.11 Mday

H G*A Total Manhours 94.44 8 11.81 Mday

OD 3

Manpower/day 3.94

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.69 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.889 8 7.11 Eday

L K*A Total Equiphours 44.44 8 5.56 Eday

OD 3.00

Equipment/day 1.85
A Aluminum Window Pcs 50

B Daily Output Pcs 14

C A/B Duration, Days (8 Hrs/Day) Day 3.57

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.06 Mday

E2 Carpenter 2.000 8 0.89 Mday

E3 Helper 1.000 8 0.45 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 1.21 8 9.71 Mday

H G*A Total Manhours 60.71 8 7.59 Mday

OD 3

Manpower/day 2.53

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.45 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.571 8 4.57 Eday

L K*A Total Equiphours 28.57 8 3.57 Eday

OD 3.00

Equipment/day 1.19
A Glass Door Pcs 20

B Daily Output Pcs 3

C A/B Duration, Days (8 Hrs/Day) Day 6.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.10 Mday

E2 Carpenter 2.000 8 1.67 Mday

E3 Helper 1.000 8 0.83 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 5.67 8 45.33 Mday

H G*A Total Manhours 113.33 8 14.17 Mday

OD 3

Manpower/day 4.72

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.83 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 2.667 8 21.33 Eday

L K*A Total Equiphours 53.33 8 6.67 Eday

OD 3.00

Equipment/day 2.22
A Wood Doors Pcs 20

B Daily Output Pcs 9

C A/B Duration, Days (8 Hrs/Day) Day 2.22

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.03 Mday

E2 Carpenter 2.000 8 0.56 Mday

E3 Helper 1.000 8 0.28 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 1.89 8 15.11 Mday

H G*A Total Manhours 37.78 8 4.72 Mday

OD 3

Manpower/day 1.57

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.28 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.889 8 7.11 Eday

L K*A Total Equiphours 17.78 8 2.22 Eday

OD 3.00

Equipment/day 0.74
A Access Door Pcs 20

B Daily Output Pcs 7

C A/B Duration, Days (8 Hrs/Day) Day 2.86

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.04 Mday

E2 Carpenter 2.000 8 0.71 Mday

E3 Helper 1.000 8 0.36 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 2.43 8 19.43 Mday

H G*A Total Manhours 48.57 8 6.07 Mday

OD 3

Manpower/day 2.02

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.36 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.143 8 9.14 Eday

L K*A Total Equiphours 22.86 8 2.86 Eday

OD 3.00

Equipment/day 0.95
A Steel Doors Pcs 20

B Daily Output Pcs 5

C A/B Duration, Days (8 Hrs/Day) Day 4.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.06 Mday

E2 Carpenter 2.000 8 1.00 Mday

E3 Helper 1.000 8 0.50 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 3.40 8 27.20 Mday

H G*A Total Manhours 68.00 8 8.50 Mday

OD 3

Manpower/day 2.83

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.50 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.600 8 12.80 Eday

L K*A Total Equiphours 32.00 8 4.00 Eday

OD 3.00

Equipment/day 1.33
A Aluminum Door Pcs 50

B Daily Output Pcs 8

C A/B Duration, Days (8 Hrs/Day) Day 6.25

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.10 Mday

E2 Carpenter 2.000 8 1.56 Mday

E3 Helper 1.000 8 0.78 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 2.13 8 17.00 Mday

H G*A Total Manhours 106.25 8 13.28 Mday

OD 3

Manpower/day 4.43

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.78 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.000 8 8.00 Eday

L K*A Total Equiphours 50.00 8 6.25 Eday

OD 3.00

Equipment/day 2.08
A Wooden Door Pcs 50

B Daily Output Pcs 5

C A/B Duration, Days (8 Hrs/Day) Day 10.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.16 Mday

E2 Carpenter 2.000 8 2.50 Mday

E3 Helper 1.000 8 1.25 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 3.40 8 27.20 Mday

H G*A Total Manhours 170.00 8 21.25 Mday

OD 3

Manpower/day 7.08

I Equipment: @ Hrs

11 Power Tool 1.000 8 1.25 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.600 8 12.80 Eday

L K*A Total Equiphours 80.00 8 10.00 Eday

OD 3.00

Equipment/day 3.33
A Final Paint M2 500

B Daily Output M2 100

C A/B Duration, Days (8 Hrs/Day) Day 5.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Painter, Structural Steel 2.000 8 1.25 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.16 8 1.28 Mday

H G*A Total Manhours 80.00 8 10.00 Mday

OD 3

Manpower/day 3.33

I Equipment: @ Hrs

11 Paint Sprayer 1.000 8 0.63 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.080 8 0.64 Eday

L K*A Total Equiphours 40.00 8 5.00 Eday

OD 3.00

Equipment/day 1.67
A Primer & First Coat paint M2 500

B Daily Output M2 60

C A/B Duration, Days (8 Hrs/Day) Day 8.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Painter, Structural Steel 2.000 8 2.08 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.27 8 2.13 Mday

H G*A Total Manhours 133.33 8 16.67 Mday

OD 3

Manpower/day 5.56

I Equipment: @ Hrs

11 Paint Sprayer 1.000 8 1.04 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.133 8 1.07 Eday

L K*A Total Equiphours 66.67 8 8.33 Eday

OD 3.00

Equipment/day 2.78
A Marble, Granite Floor M2 500

B Daily Output M2 7

C A/B Duration, Days (8 Hrs/Day) Day 71.43

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.375 8 3.35 Mday

E2 Mason 2.000 8 17.86 Mday

E3 Labor 3.000 8 26.79 Mday

E4 Equipment Operator 1.000 8 8.93 Mday

F Sum "E" Total Man 2.375

G F*D/B Manhour 2.71 8 21.71 Mday

H G*A Total Manhours 1,357.14 8 169.64 Mday

OD 3

Manpower/day 56.55

I Equipment: @ Hrs

11 Crane 11 Ton 0.625 8 5.58 Mday

12 Mixer .17 m3 0.500 8 4.46 Mday

13 Power Tool Set 1.000 8 8.93 Mday

J Sum "I" Total Equip 0.625

K J*D/B EquipHour 0.714 8 5.71 Eday

L K*A Total Equiphours 357.14 8 44.64 Eday

OD 3.00

Equipment/day 14.88
A Plastering M2 500

B Daily Output M2 14

C A/B Duration, Days (8 Hrs/Day) Day 35.71

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.56 Mday

E2 Mason 1.000 8 4.46 Mday

E3 Labor 1.000 8 4.46 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.64 8 5.14 Mday

H G*A Total Manhours 321.43 8 40.18 Mday

OD 3

Manpower/day 13.39

I Equipment: @ Hrs

11 Scaffold Set 1.000 8 4.46 Mday

12 Mixer .17 m3 0.500 8 2.23 Mday

13 Tool Set 1.000 8 4.46 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.571 8 4.57 Eday

L K*A Total Equiphours 285.71 8 35.71 Eday

OD 3.00

Equipment/day 11.90
A Handrails LM 100

B Daily Output LM 15

C A/B Duration, Days (8 Hrs/Day) Day 6.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.10 Mday

E2 Carpenter 1.000 8 0.83 Mday

E3 Power Tool 1.000 8 0.83 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.60 8 4.80 Mday

H G*A Total Manhours 60.00 8 7.50 Mday

OD 3

Manpower/day 2.50

I Equipment: @ Hrs

11 Tool Set 1.000 8 0.83 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.533 8 4.27 Eday

L K*A Total Equiphours 53.33 8 6.67 Eday

OD 3.00

Equipment/day 2.22
A Blockworks M2 500

B Daily Output M2 18

C A/B Duration, Days (8 Hrs/Day) Day 27.78

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.250 8 0.87 Mday

E2 Mason 1.000 8 3.47 Mday

E3 Labor 1.000 8 3.47 Mday

E4 Equipment Operator 0.250 8 0.87 Mday

F Sum "E" Total Man 1.250

G F*D/B Manhour 0.56 8 4.44 Mday

H G*A Total Manhours 277.78 8 34.72 Mday

OD 3

Manpower/day 11.57

I Equipment: @ Hrs

11 Mixer .25 m3 0.125 8 0.43 Mday

12 Crane 0.250 8 0.87 Mday

13 Tool Set 1.000 8 3.47 Mday

14 Forklift 0.125 8 0.43 Mday

15 Truck 0.125 8 0.43 Mday

J Sum "I" Total Equip 0.125

K J*D/B EquipHour 0.056 8 0.44 Eday

L K*A Total Equiphours 27.78 8 3.47 Eday

OD 3.00

Equipment/day 1.16
A Slab Pipe & Sleeve) LM 400

B Daily Output LM 33

C A/B Duration, Days (8 Hrs/Day) Day 12.12

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.125 8 0.19 Mday

E2 Skilled Labor 1.000 8 1.52 Mday

E3 Plumber 1.000 8 1.52 Mday

E4 Equipment Operator 1.000 8 1.52 Mday

F Sum "E" Total Man 1.125

G F*D/B Manhour 0.27 8 2.18 Mday

H G*A Total Manhours 109.09 8 13.64 Mday

OD 3

Manpower/day 4.55

I Equipment: @ Hrs

11 Tool Set 1.000 8 1.52 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.242 8 1.94 Eday

L K*A Total Equiphours 96.97 8 12.12 Eday

OD 3.00

Equipment/day 4.04
A Electl. first fix.( Conduiting ) in slabs LM 400

B Daily Output LM 32

C A/B Duration, Days (8 Hrs/Day) Day 12.50

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Structural Foreman 0.125 8 0.20 Mday

E2 Structural Worker 6.000 8 9.38 Mday

E3 Laborer 2.000 8 3.13 Mday

E4 Equipment Operator 1.000 8 1.56 Mday

F Sum "E" Total Man 8.125

G F*D/B Manhour 2.03 8 16.25 Mday

H G*A Total Manhours 812.50 8 101.56 Mday

OD 3

Manpower/day 33.85

I Equipment: @ Hrs

11 Truck Crane 136 Ton 1.000 8 1.56 Mday

12 Hydraulic Jack 4.000 8 6.25 Mday

13 Power Tool 4.000 8 6.25 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.250 8 2.00 Eday

L K*A Total Equiphours 100.00 8 12.50 Eday

OD 3.00

Equipment/day 4.17
A Precast (Hollow Core) m2 1000

B Daily Output m2 350

C A/B Duration, Days (8 Hrs/Day) Day 2.86

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Structural Foreman 0.125 8 0.04 Mday

E2 Structural Worker 6.000 8 2.14 Mday

E3 Laborer 2.000 8 0.71 Mday

E4 Equipment Operator 1.000 8 0.36 Mday

F Sum "E" Total Man 8.125

G F*D/B Manhour 0.19 8 1.49 Mday

H G*A Total Manhours 185.71 8 23.21 Mday

OD 3

Manpower/day 7.74

I Equipment: @ Hrs

11 Truck Crane 136 Ton 1.000 8 0.36 Mday

12 Hydraulic Jack 4.000 8 1.43 Mday

13 Power Tool 4.000 8 1.43 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.023 8 0.18 Eday

L K*A Total Equiphours 22.86 8 2.86 Eday

OD 3.00

Equipment/day 0.95
A Precast Beam M 200

B Daily Output M 30

C A/B Duration, Days (8 Hrs/Day) Day 6.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Structural Foreman 0.125 8 0.10 Mday

E2 Structural Worker 6.000 8 5.00 Mday

E3 Laborer 2.000 8 1.67 Mday

E4 Equipment Operator 1.000 8 0.83 Mday

F Sum "E" Total Man 8.125

G F*D/B Manhour 2.17 8 17.33 Mday

H G*A Total Manhours 433.33 8 54.17 Mday

OD 3

Manpower/day 18.06

I Equipment: @ Hrs

11 Truck Crane 136 Ton 1.000 8 0.83 Mday

12 Hydraulic Jack 4.000 8 3.33 Mday

13 Power Tool 4.000 8 3.33 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.267 8 2.13 Eday

L K*A Total Equiphours 53.33 8 6.67 Eday

OD 3.00

Equipment/day 2.22
A Precast Column M 200

B Daily Output M 30

C A/B Duration, Days (8 Hrs/Day) Day 6.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Structural Foreman 0.125 8 0.10 Mday

E2 Structural Worker 6.000 8 5.00 Mday

E3 Laborer 2.000 8 1.67 Mday

E4 Equipment Operator 1.000 8 0.83 Mday

F Sum "E" Total Man 8.125

G F*D/B Manhour 2.17 8 17.33 Mday

H G*A Total Manhours 433.33 8 54.17 Mday

OD 3

Manpower/day 18.06

I Equipment: @ Hrs

11 Truck Crane 136 Ton 1.000 8 0.83 Mday

12 Hydraulic Jack 4.000 8 3.33 Mday

13 Power Tool 4.000 8 3.33 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.267 8 2.13 Eday

L K*A Total Equiphours 53.33 8 6.67 Eday

OD 3.00

Equipment/day 2.22
A Precast Shear Walls M 200

B Daily Output M 30

C A/B Duration, Days (8 Hrs/Day) Day 6.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Structural Foreman 0.125 8 0.10 Mday

E2 Structural Worker 6.000 8 5.00 Mday

E3 Laborer 2.000 8 1.67 Mday

E4 Equipment Operator 1.000 8 0.83 Mday

F Sum "E" Total Man 8.125

G F*D/B Manhour 2.17 8 17.33 Mday

H G*A Total Manhours 433.33 8 54.17 Mday

OD 3

Manpower/day 18.06

I Equipment: @ Hrs

11 Truck Crane 136 Ton 1.000 8 0.83 Mday

12 Hydraulic Jack 4.000 8 3.33 Mday

13 Power Tool 4.000 8 3.33 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.267 8 2.13 Eday

L K*A Total Equiphours 53.33 8 6.67 Eday

OD 3.00

Equipment/day 2.22
A E M Ser..1st Fix in RC walls LM 200

B Daily Output LM 26

C A/B Duration, Days (8 Hrs/Day) Day 7.69

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Electrical Foreman 0.125 8 0.12 Mday

E2 Helper 1.000 8 0.96 Mday

E3 Electrician 1.000 8 0.96 Mday

F Sum "E" Total Man 2.125

G F*D/B Manhour 0.65 8 5.23 Mday

H G*A Total Manhours 130.77 8 16.35 Mday

OD 3

Manpower/day 5.45

I Equipment: @ Hrs

11 Power Tool 1.000 8 0.96 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.308 8 2.46 Eday

L K*A Total Equiphours 61.54 8 7.69 Eday

OD 3.00

Equipment/day 2.56
A Vertical Water Proofing m2 200

B Daily Output m2 30

C A/B Duration, Days (8 Hrs/Day) Day 6.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled W.Proof Technician 1.000 8 0.83 Mday

E2 Laborer 1.000 8 0.83 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.53 8 4.27 Mday

H G*A Total Manhours 106.67 8 13.33 Mday

OD 3

Manpower/day 4.44

I Equipment: @ Hrs

11 Tool Set 1.000 8 0.83 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.267 8 2.13 Eday

L K*A Total Equiphours 53.33 8 6.67 Eday

OD 3.00

Equipment/day 2.22
A Horizontal Water Proofing m2 200

B Daily Output m2 55

C A/B Duration, Days (8 Hrs/Day) Day 3.64

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled W.Proof Technician 1.000 8 0.45 Mday

E2 Laborer 1.000 8 0.45 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.29 8 2.33 Mday

H G*A Total Manhours 58.18 8 7.27 Mday

OD 3

Manpower/day 2.42

I Equipment: @ Hrs

11 Tool Set 1.000 8 0.45 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.145 8 1.16 Eday

L K*A Total Equiphours 29.09 8 3.64 Eday

OD 3.00

Equipment/day 1.21
A Retaining Wall M3 200

B Daily Output M3 15

C A/B Duration, Days (8 Hrs/Day) Day 13.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 1.000 8 1.67 Mday

E2 Laborer 5.000 8 8.33 Mday

E3 Carpenter 5.000 8 8.33 Mday

E4 Steel Fixer 5.000 8 8.33 Mday

E5 Cement Finisher 3.000 8 5.00 Mday

E6 Equipment Operator 0.125 8 0.21 Mday

F Sum "E" Total Man 11.000

G F*D/B Manhour 5.87 8 46.93 Mday

H G*A Total Manhours 1,173.33 8 146.67 Mday

OD 3

Manpower/day 48.89

I Equipment: @ Hrs

11 Power Tool 2.000 8 3.33 Mday

12 Concrete Pump 0.375 8 0.63 Mday

13 Gas Engine Viberator 0.375 8 0.63 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 1.067 8 8.53 Eday

L K*A Total Equiphours 213.33 8 26.67 Eday

OD 3.00

Equipment/day 8.89
A Flat Slab M3 200

B Daily Output M3 15

C A/B Duration, Days (8 Hrs/Day) Day 13.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 1.000 8 1.67 Mday

E2 Laborer 2.000 8 3.33 Mday

E3 Carpenter 4.000 8 6.67 Mday

E4 Steel Fixer 3.000 8 5.00 Mday

E5 Cement Finisher 3.000 8 5.00 Mday

E6 Equipment Operator 0.125 8 0.21 Mday

F Sum "E" Total Man 7.000

G F*D/B Manhour 3.73 8 29.87 Mday

H G*A Total Manhours 746.67 8 93.33 Mday

OD 3

Manpower/day 31.11

I Equipment: @ Hrs

11 Power Tool 2.000 8 3.33 Mday

12 Concrete Pump 0.375 8 0.63 Mday

13 Gas Engine Viberator 0.375 8 0.63 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 1.067 8 8.53 Eday

L K*A Total Equiphours 213.33 8 26.67 Eday

OD 3.00

Equipment/day 8.89
A Waffle Slab M3 200

B Daily Output M3 15

C A/B Duration, Days (8 Hrs/Day) Day 13.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 1.000 8 1.67 Mday

E2 Laborer 5.000 8 8.33 Mday

E3 Carpenter 5.000 8 8.33 Mday

E4 Steel Fixer 4.000 8 6.67 Mday

E5 Cement Finisher 3.000 8 5.00 Mday

E6 Equipment Operator 0.125 8 0.21 Mday

F Sum "E" Total Man 11.000

G F*D/B Manhour 5.87 8 46.93 Mday

H G*A Total Manhours 1,173.33 8 146.67 Mday

OD 3

Manpower/day 48.89

I Equipment: @ Hrs

11 Power Tool 2.000 8 3.33 Mday

12 Concrete Pump 0.375 8 0.63 Mday

13 Gas Engine Viberator 0.375 8 0.63 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 1.067 8 8.53 Eday

L K*A Total Equiphours 213.33 8 26.67 Eday

OD 3.00

Equipment/day 8.89
A Hourdy Slab or Ribbes Slab M3 200

B Daily Output M3 53

C A/B Duration, Days (8 Hrs/Day) Day 3.77

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 1.000 8 0.47 Mday

E2 Laborer 2.000 8 0.94 Mday

E3 Carpenter 4.000 8 1.89 Mday

E4 Steel Fixer 3.000 8 1.42 Mday

E5 Cement Finisher 3.000 8 1.42 Mday

E6 Equipment Operator 0.125 8 0.06 Mday

F Sum "E" Total Man 7.000

G F*D/B Manhour 1.06 8 8.45 Mday

H G*A Total Manhours 211.32 8 26.42 Mday

OD 3

Manpower/day 8.81

I Equipment: @ Hrs

11 Power Tool 2.000 8 0.94 Mday

12 Concrete Pump 0.375 8 0.18 Mday

13 Gas Engine Viberator 0.375 8 0.18 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 0.302 8 2.42 Eday

L K*A Total Equiphours 60.38 8 7.55 Eday

OD 3.00

Equipment/day 2.52
A Shuttering Form Works & Steel Fabrication & Pouring
M3 200

B Daily Output M3 50

C A/B Duration, Days (8 Hrs/Day) Day 4.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 1.000 8 0.50 Mday

E2 Laborer 2.000 8 1.00 Mday

E3 Carpenter 4.000 8 2.00 Mday

E4 Steel Fixer 3.000 8 1.50 Mday

E5 Cement Finisher 3.000 8 1.50 Mday

E6 Equipment Operator 0.125 8 0.06 Mday

F Sum "E" Total Man 7.000

G F*D/B Manhour 1.12 8 8.96 Mday

H G*A Total Manhours 224.00 8 28.00 Mday

OD 3

Manpower/day 9.33

I Equipment: @ Hrs

11 Power Tool 2.000 8 1.00 Mday

12 Concrete Pump 0.375 8 0.19 Mday

13 Gas Engine Viberator 0.375 8 0.19 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 0.320 8 2.56 Eday

L K*A Total Equiphours 64.00 8 8.00 Eday

OD 3.00

Equipment/day 2.67
A Slab on grade M3 200

B Daily Output M3 15

C A/B Duration, Days (8 Hrs/Day) Day 13.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 1.000 8 1.67 Mday

E2 Laborer 3.000 8 5.00 Mday

E3 Carpenter 3.000 8 5.00 Mday

E4 Steel Fixer 3.000 8 5.00 Mday

E5 Cement Finisher 3.000 8 5.00 Mday

E6 Equipment Operator 0.125 8 0.21 Mday

F Sum "E" Total Man 7.000

G F*D/B Manhour 3.73 8 29.87 Mday

H G*A Total Manhours 746.67 8 93.33 Mday

OD 3

Manpower/day 31.11

I Equipment: @ Hrs

11 Power Tool 2.000 8 3.33 Mday

12 Concrete Pump 0.375 8 0.63 Mday

13 Gas Engine Viberator 0.375 8 0.63 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 1.067 8 8.53 Eday

L K*A Total Equiphours 213.33 8 26.67 Eday

OD 3.00

Equipment/day 8.89
A H - Stairs M3 100

B Daily Output M3 12

C A/B Duration, Days (8 Hrs/Day) Day 8.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 1.000 8 1.04 Mday

E2 Laborer 5.000 8 5.21 Mday

E3 Carpenter 5.000 8 5.21 Mday

E4 Steel Fixers 4.000 8 4.17 Mday

E5 Equipment Operator 1.000 8 1.04 Mday

F Sum "E" Total Man 11.000

G F*D/B Manhour 7.33 8 58.67 Mday

H G*A Total Manhours 733.33 8 91.67 Mday

OD 3

Manpower/day 30.56

I Equipment: @ Hrs

I1 Gas Engine Vibrator 1.000 8 1.04 Mday

I2 Concrete Pump 1.000 8 1.04 Mday

13 Transit Mixer 1.000 8 1.04 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.667 8 5.33 Eday

L K*A Total Equiphours 66.67 8 8.33 Eday

OD 3.00

Equipment/day 2.78
A Grade Walls M3 100

B Daily Output M3 15

C A/B Duration, Days (8 Hrs/Day) Day 6.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 1.000 8 0.83 Mday

E2 Laborer 5.000 8 4.17 Mday

E3 Carpenter 5.000 8 4.17 Mday

E4 Steel Fixers 4.000 8 3.33 Mday

E5 Equipment Operator 1.000 8 0.83 Mday

F Sum "E" Total Man 11.000

G F*D/B Manhour 5.87 8 46.93 Mday

H G*A Total Manhours 586.67 8 73.33 Mday

OD 3

Manpower/day 24.44

I Equipment: @ Hrs

I1 Gas Engine Vibrator 1.000 8 0.83 Mday

I2 Concrete Pump 1.000 8 0.83 Mday

13 Transit Mixer 1.000 8 0.83 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.533 8 4.27 Eday

L K*A Total Equiphours 53.33 8 6.67 Eday

OD 3.00

Equipment/day 2.22
A Footing M3 200

B Daily Output M3 18

C A/B Duration, Days (8 Hrs/Day) Day 11.11

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Laborer 4.000 8 5.56 Mday

E2 Carpenter 5.000 8 6.94 Mday

E3 Steel Fixer 5.000 8 6.94 Mday

E4 Cement Finisher 0.250 8 0.35 Mday

E5 Equipment Operator 0.250 8 0.35 Mday

E6 Skilled 1.000 8 1.39 Mday

F Sum "E" Total Man 9.000

G F*D/B Manhour 4.00 8 32.00 Mday

H G*A Total Manhours 800.00 8 100.00 Mday

OD 3

Manpower/day 33.33

I Equipment: @ Hrs

11 Gas Engine Vibrator 0.375 8 0.52 Mday

12 Crane 35 Ton 0.250 8 0.35 Mday

13 Truck 0.125 8 0.17 Mday

14 Concrete Pump 0.125 8 0.17 Mday

15 Power Tool 2.000 8 2.78 Mday

J Sum "I" Total Equip 0.625

K J*D/B EquipHour 0.278 8 2.22 Eday

L K*A Total Equiphours 55.56 8 6.94 Eday

OD 3.00

Equipment/day 2.31
A Raft ( Mat ) Foundation M3 100

B Daily Output M3 25

C A/B Duration, Days (8 Hrs/Day) Day 4.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 1.000 8 0.50 Mday

E2 Laborer 3.000 8 1.50 Mday

E3 Carpenter 5.000 8 2.50 Mday

E4 Steel Fixers 4.000 8 2.00 Mday

E5 Equipment Operator 1.000 8 0.50 Mday

F Sum "E" Total Man 9.000

G F*D/B Manhour 2.88 8 23.04 Mday

H G*A Total Manhours 288.00 8 36.00 Mday

OD 3

Manpower/day 12.00

I Equipment: @ Hrs

I1 Gas Engine Vibrator 1.000 8 0.50 Mday

I2 Concrete Pump 1.000 8 0.50 Mday

13 Transit Mixer 1.000 8 0.50 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.320 8 2.56 Eday

L K*A Total Equiphours 32.00 8 4.00 Eday

OD 3.00

Equipment/day 1.33
A Slab On Ground M3 100

B Daily Output M3 40

C A/B Duration, Days (8 Hrs/Day) Day 2.50

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 1.000 8 0.31 Mday

E2 Laborer 4.000 8 1.25 Mday

E3 Carpenter 4.000 8 1.25 Mday

E4 Steel Fixers 4.000 8 1.25 Mday

E5 Equipment Operator 1.000 8 0.31 Mday

F Sum "E" Total Man 9.000

G F*D/B Manhour 1.80 8 14.40 Mday

H G*A Total Manhours 180.00 8 22.50 Mday

OD 3

Manpower/day 7.50

I Equipment: @ Hrs

I1 Gas Engine Vibrator 1.000 8 0.31 Mday

I2 Concrete Pump 1.000 8 0.31 Mday

13 Transit Mixer 1.000 8 0.31 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.200 8 1.60 Eday

L K*A Total Equiphours 20.00 8 2.50 Eday

OD 3.00

Equipment/day 0.83
A Slabs Including Drop Beams M3 100

B Daily Output M3 170

C A/B Duration, Days (8 Hrs/Day) Day 0.59

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 1.000 8 0.07 Mday

E2 Laborer 4.000 8 0.29 Mday

E3 Carpenter 5.000 8 0.37 Mday

E4 Steel Fixer 5.000 8 0.37 Mday

E5 Equipment Operator 1.000 8 0.07 Mday

F Sum "E" Total Man 10.000

G F*D/B Manhour 0.47 8 3.76 Mday

H G*A Total Manhours 47.06 8 5.88 Mday

OD 3

Manpower/day 1.96

I Equipment: @ Hrs

11 Gas Engine Vibrator 1.000 8 0.07 Mday

12 Concrete Pump 1.000 8 0.07 Mday

13 Transit Mixer 1.000 8 0.07 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.047 8 0.38 Eday

L K*A Total Equiphours 4.71 8 0.59 Eday

OD 3.00

Equipment/day 0.20
A Walls (pouring) M3 200

B Daily Output M3 50

C A/B Duration, Days (8 Hrs/Day) Day 4.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 1.000 8 0.50 Mday

E2 Laborer 2.000 8 1.00 Mday

E3 Carpenter 4.000 8 2.00 Mday

E4 Steel Fixer 3.000 8 1.50 Mday

E5 Cement Finisher 3.000 8 1.50 Mday

E6 Equipment Operator 0.125 8 0.06 Mday

F Sum "E" Total Man 7.000

G F*D/B Manhour 1.12 8 8.96 Mday

H G*A Total Manhours 224.00 8 28.00 Mday

OD 3

Manpower/day 9.33

I Equipment: @ Hrs

11 Power Tool 2.000 8 1.00 Mday

12 Concrete Pump 0.375 8 0.19 Mday

13 Gas Engine Viberator 0.375 8 0.19 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 0.320 8 2.56 Eday

L K*A Total Equiphours 64.00 8 8.00 Eday

OD 3.00

Equipment/day 2.67
A Neck Column M3 100

B Daily Output M3 10

C A/B Duration, Days (8 Hrs/Day) Day 10.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 1.000 8 1.25 Mday

E2 Laborer 4.000 8 5.00 Mday

E3 Carpenter 5.000 8 6.25 Mday

E4 Steel Fixer 5.000 8 6.25 Mday

E5 Cement Finisher 1.000 8 1.25 Mday

E6 Equipment Operator 1.000 8 1.25 Mday

F Sum "E" Total Man 10.000

G F*D/B Manhour 8.00 8 64.00 Mday

H G*A Total Manhours 800.00 8 100.00 Mday

OD 3

Manpower/day 33.33

I Equipment: @ Hrs

11 Gas Engine Vibrator 1.000 8 1.25 Mday

12 Concrete Pump 1.000 8 1.25 Mday

13 Transit Mixer 1.000 8 1.25 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.800 8 6.40 Eday

L K*A Total Equiphours 80.00 8 10.00 Eday

OD 3.00

Equipment/day 3.33
A Grid Beam add to Slab M3 100

B Daily Output M3 20

C A/B Duration, Days (8 Hrs/Day) Day 5.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 1.000 8 0.63 Mday

E2 Laborer 4.000 8 2.50 Mday

E3 Carpenter 5.000 8 3.13 Mday

E4 Cement Finisher 1.000 8 0.63 Mday

E5 Equipment Operator 1.000 8 0.63 Mday

F Sum "E" Total Man 10.000

G F*D/B Manhour 4.00 8 32.00 Mday

H G*A Total Manhours 400.00 8 50.00 Mday

OD 3

Manpower/day 16.67

I Equipment: @ Hrs

I1 Gas Engine Vibrator 1.000 8 0.63 Mday

I2 Concrete Pump 1.000 8 0.63 Mday

13 Transit Mixer 1.000 8 0.63 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.400 8 3.20 Eday

L K*A Total Equiphours 40.00 8 5.00 Eday

OD 3.00

Equipment/day 1.67
A Stairs & Landing M3 100

B Daily Output M3 30

C A/B Duration, Days (8 Hrs/Day) Day 3.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 1.000 8 0.42 Mday

E2 Laborer 4.000 8 1.67 Mday

E3 Carpenter 5.000 8 2.08 Mday

E4 Steel Fixer 5.000 8 2.08 Mday

E5 Cement Finisher 1.000 8 0.42 Mday

E6 Equipment Operator 1.000 8 0.42 Mday

F Sum "E" Total Man 10.000

G F*D/B Manhour 2.67 8 21.33 Mday

H G*A Total Manhours 266.67 8 33.33 Mday

OD 3

Manpower/day 11.11

I Equipment: @ Hrs

I1 Gas Engine Vibrator 1.000 8 0.42 Mday

I2 Concrete Pump 1.000 8 0.42 Mday

13 Transit Mixer 1.000 8 0.42 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.267 8 2.13 Eday

L K*A Total Equiphours 26.67 8 3.33 Eday

OD 3.00

Equipment/day 1.11
A Beam M3 100

B Daily Output M3 7

C A/B Duration, Days (8 Hrs/Day) Day 14.29

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 1.000 8 1.79 Mday

E2 Laborer 4.000 8 7.14 Mday

E3 Carpenter 5.000 8 8.93 Mday

E4 Steel Fixer 5.000 8 8.93 Mday

E5 Cement Finisher 1.000 8 1.79 Mday

E6 Equipment Operator 1.000 8 1.79 Mday

F Sum "E" Total Man 10.000

G F*D/B Manhour 11.43 8 91.43 Mday

H G*A Total Manhours 1,142.86 8 142.86 Mday

OD 3

Manpower/day 47.62

I Equipment: @ Hrs

I1 Gas Engine Vibrator 1.000 8 1.79 Mday

I2 Concrete Pump 1.000 8 1.79 Mday

13 Transit Mixer 1.000 8 1.79 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.143 8 9.14 Eday

L K*A Total Equiphours 114.29 8 14.29 Eday

OD 3.00

Equipment/day 4.76
A Stairs & Landing Bars Ton 2

B Daily Output Ton 0.6

C A/B Duration, Days (8 Hrs/Day) Day 3.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Steel Fixer 4.000 8 1.67 Mday

E2 Labor 2.000 8 0.83 Mday

F Sum "E" Total Man 6.000

G F*D/B Manhour 80.00 8 640.00 Mday

H G*A Total Manhours 160.00 8 20.00 Mday

OD 3

Manpower/day 6.67

I Equipment: @ Hrs

11

12

13

14

J Sum "I" Total Equip -

K J*D/B EquipHour - 8 - Eday

L K*A Total Equiphours - 8 - Eday

OD 3.00

Equipment/day -
A Slabs Bars Ton 2

B Daily Output Ton 1.6

C A/B Duration, Days (8 Hrs/Day) Day 1.25

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Steel Fixer 4.000 8 0.63 Mday

E2 Labor 2.000 8 0.31 Mday

F Sum "E" Total Man 6.000

G F*D/B Manhour 30.00 8 240.00 Mday

H G*A Total Manhours 60.00 8 7.50 Mday

OD 3

Manpower/day 2.50

I Equipment: @ Hrs

11

12

13

14

J Sum "I" Total Equip -

K J*D/B EquipHour - 8 - Eday

L K*A Total Equiphours - 8 - Eday

OD 3.00

Equipment/day -
A Walls Bars Ton 2

B Daily Output Ton 1.8

C A/B Duration, Days (8 Hrs/Day) Day 1.11

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Steel Fixer 4.000 8 0.56 Mday

E2 Labor 2.000 8 0.28 Mday

F Sum "E" Total Man 6.000

G F*D/B Manhour 26.67 8 213.33 Mday

H G*A Total Manhours 53.33 8 6.67 Mday

OD 3

Manpower/day 2.22

I Equipment: @ Hrs

11

12

13

14

J Sum "I" Total Equip -

K J*D/B EquipHour - 8 - Eday

L K*A Total Equiphours - 8 - Eday

OD 3.00

Equipment/day -
A Columns Bars Ton 2

B Daily Output Ton 1.2

C A/B Duration, Days (8 Hrs/Day) Day 1.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Steel Fixer 4.000 8 0.83 Mday

E2 Labor 2.000 8 0.42 Mday

F Sum "E" Total Man 6.000

G F*D/B Manhour 40.00 8 320.00 Mday

H G*A Total Manhours 80.00 8 10.00 Mday

OD 3

Manpower/day 3.33

I Equipment: @ Hrs

11

12

13

14

J Sum "I" Total Equip -

K J*D/B EquipHour - 8 - Eday

L K*A Total Equiphours - 8 - Eday

OD 3.00

Equipment/day -
A Footing Including Ground Beams Bars Ton 2

B Daily Output Ton 1.4

C A/B Duration, Days (8 Hrs/Day) Day 1.43

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Steel Fixer 4.000 8 0.71 Mday

E2 Labor 2.000 8 0.36 Mday

F Sum "E" Total Man 6.000

G F*D/B Manhour 34.29 8 274.29 Mday

H G*A Total Manhours 68.57 8 8.57 Mday

OD 3

Manpower/day 2.86

I Equipment: @ Hrs

11

12

13

14

J Sum "I" Total Equip -

K J*D/B EquipHour - 8 - Eday

L K*A Total Equiphours - 8 - Eday

OD 3.00

Equipment/day -
A Blinding M3 200

B Daily Output M3 34

C A/B Duration, Days (8 Hrs/Day) Day 5.88

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mason 1.000 8 0.74 Mday

E2 Labor 4.000 8 2.94 Mday

F Sum "E" Total Man 5.000

G F*D/B Manhour 1.18 8 9.41 Mday

H G*A Total Manhours 235.29 8 29.41 Mday

OD 3

Manpower/day 9.80

I Equipment: @ Hrs

11 Gas Engine Vibrator 0.375 8 0.28 Mday

12 Crane 35 Ton 0.250 8 0.18 Mday

13 Transit Mixer 1.000 8 0.74 Mday

14 Concrete Pump 1.000 8 0.74 Mday

J Sum "I" Total Equip 0.625

K J*D/B EquipHour 0.147 8 1.18 Eday

L K*A Total Equiphours 29.41 8 3.68 Eday

OD 3.00

Equipment/day 1.23
A Wearing Course(Asphalt Conc.Pvmt.) m2 6000

B Daily Output m2 4220

C A/B Duration, Days (8 Hrs/Day) Day 1.42

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.375 8 0.07 Mday

E2 Surveyor 1.000 8 0.18 Mday

E3 Equip Operator ( Medium ) 3.000 8 0.53 Mday

E4 Laborer 7.000 8 1.24 Mday

E5 Asphalt Paver 1.000 8 0.18 Mday

F Sum "E" Total Man 12.375

G F*D/B Manhour 0.02 8 0.19 Mday

H G*A Total Manhours 140.76 8 17.59 Mday

OD 3

Manpower/day 5.86

I Equipment: @ Hrs

I1 Tandem Roller, 9 Ton 1.000 8 0.18 Mday

I2 Roller, Pneumatic Wheel 1.000 8 0.18 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 0.004 8 0.03 Eday

L K*A Total Equiphours 22.75 8 2.84 Eday

OD 3.00

Equipment/day 0.95
A Binder Course(Asphalt Conc.Pvmt.) m2 6000

B Daily Output m2 5095

C A/B Duration, Days (8 Hrs/Day) Day 1.18

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.375 8 0.06 Mday

E2 Surveyor 1.000 8 0.15 Mday

E3 Equip Operator ( Medium ) 3.000 8 0.44 Mday

E4 Laborer 7.000 8 1.03 Mday

E5 Asphalt Paver 1.000 8 0.15

F Sum "E" Total Man 12.375

G F*D/B Manhour 0.02 8 0.16 Mday

H G*A Total Manhours 116.58 8 14.57 Mday

OD 3

Manpower/day 4.86

I Equipment: @ Hrs

I1 Tandem Roller, 9 Ton 1.000 8 0.15 Mday

I2 Roller, Pneumatic Wheel 1.000 8 0.15 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 0.003 8 0.03 Eday

L K*A Total Equiphours 18.84 8 2.36 Eday

OD 3.00

Equipment/day 0.79
A Compaction m3 5000

B Daily Output cu.m 1600

C A/B Duration, Days (8 Hrs/Day) Day 3.13

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Truck Driver 1.000 8 0.39 Mday

E2 Equip Operator ( Medium ) 1.000 8 0.39 Mday

E3 Laborer 1.000 8 0.39 Mday

F Sum "E" Total Man 3.000

G F*D/B Manhour 0.02 8 0.12 Mday

H G*A Total Manhours 75.00 8 9.38 Mday

OD 3

Manpower/day 3.13

I Equipment: @ Hrs

I1 Water Tanker, 25m3 1.000 8 0.39 Mday

I2 Sheepfoot Roller, 300 HP 1.000 8 0.39 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 0.010 8 0.08 Eday

L K*A Total Equiphours 50.00 8 6.25 Eday

OD 3.00

Equipment/day 2.08
A MANHOLES & CLEANOUTS EA 10

B Daily Output EA 1

C A/B Duration, Days (8 Hrs/Day) Day 10.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.125 8 0.16 Mday

E2 Equip Operator ( Medium ) 0.500 8 0.63 Mday

E3 Laborers 4.000 8 5.00 Mday

F Sum "E" Total Man 4.625

G F*D/B Manhour 37.00 8 296.00 Mday

H G*A Total Manhours 370.00 8 46.25 Mday

OD 3

Manpower/day 15.42

I Equipment: @ Hrs

I1 Crane 23 Tons 0.500 8 0.63 Mday

J Sum "I" Total Equip 0.500

K J*D/B EquipHour 4.000 8 32.00 Eday

L K*A Total Equiphours 40.00 8 5.00 Eday

OD 3.00

Equipment/day 1.67
A Base Course M2 5000

B Daily Output M2 2084

C A/B Duration, Days (8 Hrs/Day) Day 2.40

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.250 8 0.07 Mday

E2 Surveyor 0.125 8 0.04 Mday

E3 Common Laborer 1.000 8 0.30 Mday

E4 Equip Operator ( Light ) 3.000 8 0.90 Mday

F Sum "E" Total Man 0.375

G F*D/B Manhour 0.00 8 0.01 Mday

H G*A Total Manhours 7.20 8 0.90 Mday

OD 3

Manpower/day 0.30

I Equipment: @ Hrs

I1 Water Tanker 1.000 8 0.30 Mday

12 Grader 1.000 8 0.30 Mday

13 Tandem Roller 9 Ton 1.000 8 0.30 Mday

14 Dozer 200HP 1.000 8 0.30 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.004 8 0.03 Eday

L K*A Total Equiphours 19.19 8 2.40 Eday

OD 3.00

Equipment/day 0.80
A Base M2 5000

B Daily Output M2 1886

C A/B Duration, Days (8 Hrs/Day) Day 2.65

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.250 8 0.08 Mday

E2 Surveyor 0.125 8 0.04 Mday

E3 Common Laborer 1.000 8 0.33 Mday

E4 Equip Operator ( Light ) 3.000 8 0.99 Mday

F Sum "E" Total Man 0.375

G F*D/B Manhour 0.00 8 0.01 Mday

H G*A Total Manhours 7.95 8 0.99 Mday

OD 3

Manpower/day 0.33

I Equipment: @ Hrs

I1 Water Tanker 1.000 8 0.33 Mday

12 Grader 1.000 8 0.33 Mday

13 Tandem Roller 9 Ton 1.000 8 0.33 Mday

14 Dozer 200HP 1.000 8 0.33 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.004 8 0.03 Eday

L K*A Total Equiphours 21.21 8 2.65 Eday

OD 3.00

Equipment/day 0.88
A Fill m3 5000

B Daily Output m3 666

C A/B Duration, Days (8 Hrs/Day) Day 7.51

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Equip Operator 1.000 8 0.94 Mday

E2 Laborer 0.500 8 0.47 Mday

F Sum "E" Total Man 1.500

G F*D/B Manhour 0.02 8 0.14 Mday

H G*A Total Manhours 90.09 8 11.26 Mday

OD 3

Manpower/day 3.75

I Equipment: @ Hrs

I1 Dozer 1.000 8 0.94 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.012 8 0.10 Eday

L K*A Total Equiphours 60.06 8 7.51 Eday

OD 3.00

Equipment/day 2.50
A Hauling m3 5000

B Daily Output m3/day 37

C A/B Duration, Days (8 Hrs/Day) Day 135.14

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Truck Driver 1.500 8 25.34 Mday

E2 Equip Operator 0.125 8 2.11 Mday

F Sum "E" Total Man 1.625

G F*D/B Manhour 0.35 8 2.81 Mday

H G*A Total Manhours 1,756.76 8 219.59 Mday

OD 3

Manpower/day 73.20

I Equipment: @ Hrs

I1 Dump Truck 1.000 8 16.89 Mday

I2 Shovel 0.125 8 2.11 Mday

J Sum "I" Total Equip 1.125

K J*D/B EquipHour 0.243 8 1.95 Eday

L K*A Total Equiphours 1,216.22 8 152.03 Eday

OD 3.00

Equipment/day 50.68
A Heavy Soil Excavation m3 1000

B Daily Output m3/day 290

C A/B Duration, Days (8 Hrs/Day) Day 3.45

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Helper 1.000 8 0.43 Mday

E2 Equip Operator 1.000 8 0.43 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.06 8 0.44 Mday

H G*A Total Manhours 55.17 8 6.90 Mday

OD 3

Manpower/day 2.30

I Equipment: @ Hrs

I1 Shovel 0.125 8 0.05 Mday

I2 Hydraulic Excavator 1.000 8 0.43 Mday

J Sum "I" Total Equip 1.125

K J*D/B EquipHour 0.031 8 0.25 Eday

L K*A Total Equiphours 31.03 8 3.88 Eday

OD 3.00

Equipment/day 1.29
A SHEET PILING M2 100

B Daily Output M2 18

C A/B Duration, Days (8 Hrs/Day) Day 5.56

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.500 8 0.35 Mday

E2 Pile Drivers 4.000 8 2.78 Mday

E3 Equipment Operator Light 1.000 8 0.69 Mday

E4 Equipment Operator Heavy 1.000 8 0.69 Mday

F Sum "E" Total Man 0.500

G F*D/B Manhour 0.22 8 1.78 Mday

H G*A Total Manhours 22.22 8 2.78 Mday

OD 3

Manpower/day 0.93

I Equipment: @ Hrs

11 Crane, 36 metric ton 1.000 8 0.69 Mday

12 Vibratory Hammer & Gen. 0.625 8 0.43 Mday

13 Bed Truck 0.500 8 0.35 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.444 8 3.56 Eday

L K*A Total Equiphours 44.44 8 5.56 Eday

OD 3.00

Equipment/day 1.85
A SELECTIVE DEMOLITION m3 100

B Daily Output m3/day 18

C A/B Duration, Days (8 Hrs/Day) Day 5.56

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.250 8 0.17 Mday

E2 Building Laborers 4.000 8 2.78 Mday

E3 Equipment Operator Light 1.000 8 0.69 Mday

E4 Equipment Operator Heavy 1.000 8 0.69 Mday

E5 Mechanic 1.000 8 0.69 Mday

F Sum "E" Total Man 0.250

G F*D/B Manhour 0.11 8 0.89 Mday

H G*A Total Manhours 11.11 8 1.39 Mday

OD 3

Manpower/day 0.46

I Equipment: @ Hrs

11 Air Compressor,250 CFM 1.000 8 0.69 Mday

12 F.E Loader, T.M 1.91 CUM 1.000 8 0.69 Mday

13 F.E Loader, 1.9 M3 1.000 8 0.69 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.444 8 3.56 Eday

L K*A Total Equiphours 44.44 8 5.56 Eday

OD 3.00

Equipment/day 1.85
A BUILDING DEMOLITION m3 500

B Daily Output m3/day 320

C A/B Duration, Days (8 Hrs/Day) Day 1.56

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.250 8 0.05 Mday

E2 Building Laborers 3.000 8 0.59 Mday

E3 Equipment Operator 2.000 8 0.39 Mday

E4 Truck Drivers 2.000 8 0.39 Mday

F Sum "E" Total Man 0.250

G F*D/B Manhour 0.01 8 0.05 Mday

H G*A Total Manhours 3.13 8 0.39 Mday

OD 3

Manpower/day 0.13

I Equipment: @ Hrs

11 Hydraulic Crane 23 Ton 1.000 8 0.20 Mday

12 F.E Loader, T.M 1.91 CUM 1.000 8 0.20 Mday

13 Dump Trucks 10 Ton 2.000 8 0.39 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.025 8 0.20 Eday

L K*A Total Equiphours 12.50 8 1.56 Eday

OD 3.00

Equipment/day 0.52
A Test Pit,Hand Digging,Light Soil m3 100

B Daily Output m3/day 3.5

C A/B Duration, Days (8 Hrs/Day) Day 28.57

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Common Laborer 1.000 8 3.57 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 2.29 8 18.29 Mday

H G*A Total Manhours 228.57 8 28.57 Mday

OD 3

Manpower/day 9.52

I Equipment: @ Hrs

11 Tool Set 1.000 8 3.57 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 2.286 8 18.29 Eday

L K*A Total Equiphours 228.57 8 28.57 Eday

OD 3.00

Equipment/day 9.52
A Site Clearing(Stripping) m3 5000

B Daily Output m3/day 700

C A/B Duration, Days (8 Hrs/Day) Day 7.14

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Building Laborer 1.000 8 0.89 Mday

E2 Equipt.Operator 1.000 8 0.89 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.02 8 0.18 Mday

H G*A Total Manhours 114.29 8 14.29 Mday

OD 3

Manpower/day 4.76

I Equipment: @ Hrs

I2 Dozer 200 HP 1.000 8 0.89 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.011 8 0.09 Eday

L K*A Total Equiphours 57.14 8 7.14 Eday

OD 3.00

Equipment/day 2.38
Item Activity Activity SUB Unit

ID Description ACTIVITY

SITEWORKS

Z2V33-0000 Site Clearing M2

Z2V33-0010 Setting-out / Layout M

SUBSTRUCTURE

Z2V33-0020 Excavation for footings + Disposal of Materials For Excavation M3

For Disposal M3

Z2V33-0030 Formation Level & Compaction M3

Z2V33-0040 Anti-Termite Applications (Under PCC Footings)

Z2V33-0050 Backfill & Compaction upto bot. of PCC Tie-Beam

Z2V33-0060 Anti-Termite Applications (Under PCC Tie-Beam)

Z2V33-0070 Backfill & Compaction up to bot of PCC Grd. Slab

Z2V33-0080 Anti-Termite Applications (Under PCC Grade Slab)

Z2V33-0090 Shutters + 50mm Thk. PCC Under Footings

Z2V33-0100 50mm Protection Screed (Over W.P. Membrane-Ftg.)

Z2V33-0110 RCC For Footings Casting M3

Formworks M2

Rebars kg
Deshuttering M2
QTY Prod. Rate Days (H) Tot. Man Crew Tot. Mdays

(unit/day) (H) (I) Desc. (K)

(F) (G) (F/G) (H x I)

1,597.00 4,200.00 0.38 2 1 Operator, 1 Helper 0.76

163.88 76 2.16 3 2 Carpenter, 1 Helper 6.47

576 409.5 1.41

288 345.6 0.83

194 252 0.77

296 180 1.64 26 1 Carpenter, 18 Helper, 6 Mason, 1 Steel Fixer 42.76

1,184.00 12 98.67 3.056 2 Carpenter, 1 Helper, .056 Operator 301.53

53,280.00 250 213.12 2.056 1 Steel Fixer, 1 Helper, .056 Operator 438.17
1,184.00 35 33.83 3.056 2 Carpenter, 1 Helper, .056 Operator 103.38
OD (O) Manpower MAN-DAYS

/day

(N/O) Carpenter Mason Steel Fixer Helper Operator Driver Technician Painter

1 0.76 0.38 0.38

1 6.47 4.31 2.16

1 42.76

4 75.38 19.73 9.87 0.55

3 146.06 21.31 21.31 1.19


2 51.69 6.77 12.92 3.38 0.19

10 26.5 12.92 21.31 34.56 1.93 0 0 0


Tot. Eqmt. (X) Eqmt Tot. Edays (Z) E

Desc. (H x X)

Alum. Tech Waterproofer Dozer Shovel Dump T.

1 1 Dozer 0.38 0.38

0.5 .5 Vibrator 0.82

0.056 .056 M. Crane 5.53

0.056 .056 M. Crane 11.93


0.056 .056 M. Crane 1.89

0 0 0 0 0
EQMT-DAYS

B. Roller B. Cat S. Roller M. Crane Vibrator Excavator Tower Crane

0.08

0.55

1.19
0.19

0 0 0 1.93 0.08 0 0