VII.

ACTIVATION AND DEACTIVATION

Below is the flowchart illustrating the course of action taken during the activation/deactivation of the
school contingency plan.

EARTHQUAKE

Intelligence SDRRMC performs PDRA


Gathering

SDRRMC School- YES ACTIVATE NO SDRRMC School-


Red Alert Status CP? Red Alert Status

Cluster deploys
Cluster Convene Responders
Incident Command Post
Barangay

C-3/PCDRRMC
DDRRMC
SDS convenes school at the School
EOC Responders Conduct Normal
Operation

SDS mobilizes and deploys IMT NO

YES Situation Normalized

Schools EOC and deploys IMT Responders Demobilized


Enforces CP

NO IATF/IMT recommends SDS directs


Situation deactivation of
YES deactivation of CP to SDS END
Normalized CP

The decision whether or not to activate the Contingency Plan (CP) will be based on the findings of Pre-
Disaster Risk Assessment by the SDRRMC. If CP is activated, all clusters will convene at the Incident
Command Post. The Incident Management Team will be mobilized, together with the clusters, shall
implement the CP.

The Contingency Plan shall be deactivated once the situation has improved and when heightened alert is
no longer required. Upon deactivation, operation will still remain to until a “white alert” status is finally
declared.

Non-Activation

The decision not to activate the Contingency Plan (CP) will be based upon the findings of Pre-Disaster
Risk Assessment by the SDRRMC suplemented with gathered intelligence or information. Such decision
depends upon the perceived impact and risk of the disaster. In the event of Non-Activation, responders
will still be deployed to conduct normal operations to ensure the safety and welfare of Kalawaan