You are on page 1of 2

pavement work tips – No 2 September 2010

INTRODUCTION  All storage


containers should
Key Summary
Emulsions are an effective method of be labelled with
applying bitumen in sprayed sealing and emulsion grade This issue of
maintenance operations. Because of their and date of “pavement work
composition and behaviour, they need to manufacture. tips” gives some
be handled and stored differently to suggested dos and
 Always make a don’ts for safe and
cutback bitumen. trial blend of the proper storage and
newly-delivered
If properly handled and stored, they will handling of
emulsions and bituminous
perform satisfactorily with few, if any, the stored
problems. If badly handled and stored, emulsions
emulsion to
they can create large-scale cleaning check for
problems. compatibility of the materials before
pumping any material into the storage
To obtain the best handling and storage tank. Remember that emulsions with the
results, the following suggestions are same grade designation can be very
offered. different chemically and in performance.
 Do not allow a bituminous emulsion to
GENERAL
either freeze or boil – it will break.
 Use the correct type and grade of Storage temperature should not be
emulsion allowed to fall below 10°C or exceed
 Transport emulsion in full containers 85°C (except for some specialty
fitted with baffle plates to minimise emulsions that may be heated as high as
surging that may cause foaming and 90°C under strictly controlled
breaking. conditions).
 Do not mix anionic and cationic  Store at the temperature recommended
for the particular grade.
bituminous emulsions. This will cause
each emulsion to break and separate into  Some specialty products such as high
water and bitumen, leaving tanks or other bitumen content and polymer modified
equipment partially filled with semi-solid emulsions are designed for use within a
bitumen, and a difficult cleaning job. short period (commonly less than one
week) after manufacture. Manufacturer’s
 Always use clean containers. Bituminous storage recommendations must be
emulsion must not be loaded into storage followed at all times.
tanks, tank cars, tank transports or
distributors containing remains of  Regularly mix tank contents by gentle
agitation or circulation to prevent build-
incompatible materials.
up of sedimented bitumen particles.
 Bituminous emulsions can cause
 In bulk storage, mix the emulsion every
corrosion in non-ferrous metals such as 1–2 weeks (more frequently in cold
brass, copper and aluminium. The use of weather) or as recommended by the
such materials in the components of supplier. Mixing may be by paddle
valves, pumps, pipe work and fittings agitator (slow), loose gear pump, slow
should be avoided. centrifugal pump, or other suitable low
shear pump.
STORAGE
 Do not bubble air through an emulsion
 It is preferable to store emulsions in bulk to agitate it, as this will create excessive
tanks. Vertical tanks that minimise the foam and may cause the emulsion to
surface area of liquid are preferred to break.
horizontal tanks.
continued on reverse

pavement work tips are produced by AUSTROADS in conjunction with AAPA


For more
page 2 information on any
of the construction
practices discussed
Storage (cont.)  place inlet pipes and return lines near the in "pavement work
tips'', please contact
 A thin layer of kerosene or cutter oil (0.5 L/m2) bottom of tanks to prevent foaming and either your local
spread on top of emulsion in storage tanks can minimise contamination from skinning AUSTROADS
prevent scum formation on materials that that may have formed on the surface. representative or
cannot be regularly agitated.  Use pumps that have proper clearances AAPA:
tel (03) 9853 3595;
 Where there is doubt on the effectiveness of for emulsion use. Tight pump clearances
fax (03) 9853 3484;
emulsions that may have been affected by can cause breaking of the emulsion and e-mail:
extended storage or poor handling, its condition pump seizure. Particular care should be info@aapa.asn.au.
can be checked using the setting time test taken when using new pumps that may
A complete list of
(AS/NZS 3241.29). have tight clearances.
“pavement work
 Use slow pump settings and limit the tips” issues is
CLEANING OF TANKS & EQUIPMENT amount of recirculation. Excessive available on
 Clean tanks properly at product changeover. pumping can lead to breaking of the AAPA’s website:
emulsion, especially in cold weather, as www.aapa.asn.au
 Thoroughly wash out equipment with kerosene
or cutter oil when changing emulsion grade or well as a potential for a reduction in Issues may be
type, particularly when changing between viscosity and instability though downloaded using
anionic and cationic emulsion types. entrainment of air bubbles. Adobe Acrobat
Reader. Copies may
 At the end of each day, flush out the pumping HEATING also be obtained
and spraying system on the bitumen distributor from AAPA.
with kerosene or cutter oil. This will avoid  Use gentle heating systems with heating
Material may be
clogging, binding or seizure from breaking of element surface temperatures below freely reproduced
bituminous emulsion left in the system. 85°C. providing the

 Clear lines by blowing them out with air and  Do not heat above the recommended source is
storage temperature as water may be acknowledged.
leave drain plugs open when out of service.
driven off at elevated temperatures, This edition was
 Fill pumps with kerosene or cutter oil to ensure resulting in a skin of bitumen on the prepared by
a free start-up when they are to be out of surface. members of the
service for even a short period of time. Bituminous
 When heating bituminous emulsion, Surfacings
DILUTION agitate it gently to eliminate or reduce Research Reference
skin formation. Group.
 Field dilution of emulsions should be avoided
where possible, particularly rapid setting grades,  Pumps should be heat-traced to prevent
which involve a high risk of breaking when overload at start-up. Warming the pump to about 65°C can
diluted. facilitate start-up.
 Where medium and slow setting grades are to  Heat tracing and warming of pipe lines can prevent emulsion
be diluted, the following procedures must be breaking in the lines and blockages.
observed:  Use mild heat to unblock lines or valves, or to free a seized
o Use only potable water. Check the com- pump. Avoid overheating that may cause hardening of
patibility of the water with the emulsion by deposited bitumen, with particular risk of potential damage to
testing a small quantity before diluting. pumping systems. The use of propane torches should be
avoided.
o When diluting bituminous emulsion, always
add water to the emulsion, not emulsion to
water. REFERENCES
o Use warm water for diluting (if possible), Austroads (2002) Guide to the selection and use of bitumen
and always add water slowly to the emulsions, AP-G73/02.
emulsion. Austroads (2008) Bitumen emulsions, AP-T107/08.
PUMPING AS 1160 Bituminous emulsions for construction and maintenance
of pavements.
 When pumping emulsions, keep the end of the
discharge pipe submerged in emulsion (near AS/NZS 2341.29 Methods of testing bitumen and related
bottom of tank) to avoid entrainment of air and roadmaking products, Method 29: determination of breaking
foaming that can also cause an emulsion to behaviour by setting time.
break.

Austroads and AAPA believe this publication to be correct at the time of printing and do not accept responsibility for any consequences arising from the use of the information herein.
Readers should rely on their own skill and judgement to apply information to particular issues.

You might also like