Professional Documents
Culture Documents
OMV-Nabors
………………………………..
..……………………………..
.………………………………
Document Revisions
NDIL QHSE
8,9
Superintendent
Yemen Emergency Hard Copy
10
Response Room
Nabors Emergency Hard Copy
11
Response Room
Rig 98 Drilling Hard Copy
12
Supervisor
Rig 98 Rig Manager Hard Copy 13
Rig 98 HSE Advisor Hard Copy 14
Table of Contents
2
HSSE Bridging document
OMV-Nabors
Acronyms................................................................................................................................................ 5
1.0 Introduction...................................................................................................................................... 6
4.0 Operations...................................................................................................................................... 10
4.1 Operational Support:..................................................................................................................... 10
4.2 Permit to Work / Lock Out Tag Out Procedures:...........................................................................10
4.3 Job Safety Analysis....................................................................................................................... 14
4.4 Activities with Elevated Risks........................................................................................................ 14
4.4.1 Confined Space Entry............................................................................................................ 14
4.4.2 Electrical................................................................................................................................ 15
4.4.3 Hot Work............................................................................................................................... 15
4.4.4 Lifting & Rigging.................................................................................................................... 15
4.4.5 Working at Height.................................................................................................................. 16
4.4.6 Simultaneous Operations...................................................................................................... 16
5.0 Communications............................................................................................................................ 16
5.1 HSSE Communications with Statutory and Regulatory Authorities...............................................16
5.2Field and Rig Site Orientation and Induction..................................................................................17
5.3 Safety Meeting.............................................................................................................................. 17
5.4 Pre-Tour Meetings......................................................................................................................... 17
5.5 Daily Operational Meeting............................................................................................................. 18
5.7 Behavioural Base Safety Observation Program............................................................................18
5.8 Management of Change (MOC).................................................................................................... 18
5.9 HSSE Training............................................................................................................................... 18
5.10 Short Service Employees............................................................................................................ 18
3
HSSE Bridging document
OMV-Nabors
4
HSSE Bridging document
OMV-Nabors
Acronyms
5
HSSE Bridging document
OMV-Nabors
1.0 Introduction
The purpose of this OMV Yemen / Nabors Drilling International Limited (NDIL) Bridging Document is to
provide a common baseline for the project in terms of policies & procedures, especially for certain safety
related areas. The objective is:
1. To reconcile the different standards, practices and/or procedures between OMV & NDIL, in order to
obtain consistency.
OMV has contracted NDIL to provide drilling services for the OMV Habban field development phase 2 project
in Yemen. In order to plan, manage and control drilling operations and fulfill those responsibilities this
document serves as a formal bridging between OMV and NDIL HSE Management System.
NDIL have a set of Health, Safety, and Environment (HSE) beliefs and values which have been combined into
OMV Drilling Project HSSE Values, Beliefs and Basic Strategies.
6
HSSE Bridging document
OMV-Nabors
This policy applies to all OMV, NDIL and Service Company personnel.
Personnel will be briefed on the OMV and NDIL Drug and Alcohol policy requirements at the rig site
induction.
Smoking is strictly prohibited in all offices and cabins.
The workers on location who are suffering from a medical condition and are taking prescribed medication
from a physician are required to report to the Rig Medic upon arrival.
Reference to NDIL HUR-021, Drugs, Alcohol and Contraband Policy and OMV HSSE-XX-XX-XX
7
HSSE Bridging document
OMV-Nabors
PIC PIC
Nabors Area OMV Drilling Office Level
Manager Manager
OMV Head of
Nabors Regional Operations And
HSE Manager Maintenance
OMV HSSE
Manager
Nabors
Operations
Manager
PIC PIC
Nabors Rig
PIC PIC Rig Level
Nabors Rig OMV Drilling OMV Drilling
Manager 221 Manager 98 Supervisor Rig supervisor Rig
221 98
8
HSSE Bridging document
OMV-Nabors
He is accountable for meeting the OMV HSSE requirements for all activities and associated drilling support
utility services within the Drill Site geographical area.
In the event of an emergency, the OMV Drilling Supervisor is responsible for coordinating all related logistics
and support services from head office.
OMV Drilling Supervisor is responsible for the well integrity and has the final decision regarding any well
control operations, that doesn’t affect the integrity of the rig or the safety of any personnel.
9
HSSE Bridging document
OMV-Nabors
4.0 Operations
10
HSSE Bridging document
OMV-Nabors
As a minimum the list of activities outlined below and in Appendix 10.3 of HSE-15-01 has been agreed as
drilling activities which require a Permit to Work on all NDIL Rig on Yemen:
o Hot Work
o Working in a confined space
o Mud Pump maintenance
o Working at height
o Live circuit access
o Working on equipment which requires energy isolation
o Hoisting personnel with the Man Riding winch
o Handling of radioactive materials
o Handling of explosives
o Acid handling
o Caustic Soda handling
o Sand blasting during any operation
o Scaffold erection
o All pressure testing of equipment on the rig
o Excavation work
o Diesel Transfer
o Flaring Gas
o Extended Well Control situations
o Working in high winds
o Derrick Lay-down operations
o Any other operations with higher than average risk potential
o All non-routine operations included but not limited to wire line logging, slick line logging, cementing,
coring, etc.
11
HSSE Bridging document
OMV-Nabors
* This is only a guide as the situation on-site may require more stringent controls to be in place due to the
nature of the work being performed.
All rig isolations, including 3rd party contractor equipment isolations will be undertaken using the NDIL
Lockout/Tagout procedure as described in NDIL procedure HSE-22-01. This procedure applies to all
personnel when servicing and performing maintenance on machines and equipment, in which the unexpected
energization, start up or the release of stored energy could cause injury / damage to equipment.
The senior on-site NDIL representative is responsible for ensuring that the NDIL PTW system is implemented
for all tasks and is the Approval Authority for all site permits which should bear his signature. The completed
PTW package will be countersigned by the OMV Drilling Supervisor or his delegate before work can be
undertaken at the rig location.
All work undertaken under the NDIL Permit to Work system is required to be supported by a JSA and Toolbox
Talks meeting of minutes. All opened PTW need to be logged onto the PTW log for auditing purposes. The
PTW and associated JSA will be reviewed and signed by the NDIL Rig Manager and the OMV Drilling
Supervisor or their delegated authority. Closeout of PTW should be audited by NDIL Rig Manager and OMV
Drilling Supervisor.
Each permit will be valid for only 12 hours. Each day a permit meeting will be scheduled at 7:00 AM
(Supervisors Meeting) to review planned work activities for the next 24 hours. The meeting will include the
OMV Drilling Supervisor, OMV HSSE Advisor, NDIL Rig Manager, NDIL HSE Advisor and or 3 rd Party
contractor supervisors, as required to accurately describe the planned operations.
12
HSSE Bridging document
OMV-Nabors
Applicant
Holder
Controller
Authority
JSA
PREPARATION
EXECUTION
Holder Controller
Check Progress
Shift YES
Change?
Shift Supervisors
NO
Controller
Handover
Check Progress
Holder Authority
Holder
Work Completed
EXECUTION Controller
CLOSE-OUT Applicant Re-Approve
Signs Off &
Return to Controller
JSA
Controller
Inspects Site
Authority
Filed
13
HSSE Bridging document
OMV-Nabors
Permit Applicant – The person who applies for the permit, often the Supervisor responsible for its execution
or planning or the person who will carry out the job. The Permit Applicant and Permit Holder should be the
same person as they have full understanding of all work to be carried out (isolations required, etc…)
Permit Holder – The person who carries out the job or his immediate supervisor at the job site. (Permit
Applicant and Permit Holder should be the same person).
Permit Controller – The person who controls the issue and validation of permits, usually the HSE Officer or
possibly the Rig Manager.
Permit Issuing Authority – The person who authorizes the permit is the Rig Manager. OMV Drilling
Supervisor is responsible to countersign all permits issued on rig site.
OMV will be responsible for ensuring Job Safety Analysis records are available for third party contractors
contracted by OMV.
All activities with high potential risk have been identified in the Risk Register. Risk Register needs to be
reviewed during the 1st quarter of every year.
14
HSSE Bridging document
OMV-Nabors
4.4.2 Electrical
For electrical isolation work NDIL Lockout / Tagout Procedure HSE-22-01 will be implemented. In addition, all
operations involving portable electrical equipment will be carried on in accordance with NDIL work instruction
HSE-WI-10.6.
All third party temporary equipment installed shall comply with the above requirements. Examples of third
party equipment are:
o Workshops, cabins.
o High-pressure equipment e.g. Nitrogen pumping.
o Diesel driven equipment e.g. hydraulic power units.
o Electrical equipment, such as light towers or welding machines but excluding hand tools.
All third party equipment coming into location needs to have a verifiable inspection report.
Prior to any temporary equipment commissioning and use, the temporary equipment installation shall be
inspected by the NDIL Electrician and/or Mechanic, who shall indicate his approval.
The installation of the equipment shall be approved by the OMV Drilling Supervisor. OMV Drilling Supervisor
to ensure that the equipment is inspected, remains certified and is maintained during its use NDIL Rigs.
15
HSSE Bridging document
OMV-Nabors
All lifts need to be carried under supervision of a competent lifting supervisor who has received awareness
training for lifting operations.
4.4.5 Working at Height
Working at Height is any routine or non-routine work on a surface equal to 6 feet (1.8 m) or more.
All working at height operations on NDIL Rigs will comply with NDIL HSE-11-02 Procedure for Fall Protection.
For man lifting and man riding operations NDIL Work Instruction HSE-WI-10.33 will apply.
In addition:
o All NDIL Rigs will maintain a Working at Height equipment register which is to be audited quarterly by
OMV
o Working at Height equipment will be inspected before use, after use, on a monthly basis, and as
required by Original Equipment Manufacturer by a competent person who has received fall protection
awareness level training.
5.0 Communications
16
HSSE Bridging document
OMV-Nabors
Visitors who are not to perform any work at the rig site shall be inducted as a minimum in
Emergency Instructions
NDIL Safety Rules and Policies
Personal Protective Equipment Requirements
Nabors 10 Rules to Live by
Employees that will be performing any work at the rig site shall be inducted as a minimum in:
Current Operations
Emergency Instructions ( Duties & Responsibilities)
General Safety Rules and Policies
Personal Protective Equipment Requirements
Handling of Hazardous Material
Authorization to operate any equipment
Medical Facility
Accident reporting
Nabors 10 Rules to Live by and OMV 8 Golden Rules.
JSA and PTW Requirements
SSE Requirements
No Go Zones
OMV & NDIL Person in Charge
17
HSSE Bridging document
OMV-Nabors
for work planned in the upcoming tour. Attendance at pre-tour meetings will be recorded and actions will be
recorded in the Rig Action Tracking register.
Changes to NDIL procedures, standards, systems or machinery and equipment that require management
approval will be managed under the NDIL Management of Change procedure QMS-012. These changes will
be presented to OMV for review and approval before implementation.
18
HSSE Bridging document
OMV-Nabors
19
HSSE Bridging document
OMV-Nabors
NDIL and all other contractors, sub-contractors must submit to OMV their “Single Point of Contact” phone
numbers to be included in the Site Specific Emergency Response Plan.
20
HSSE Bridging document
OMV-Nabors
Only competent driver who have received formal defensive driver training are allowed to drive company
vehicles.
6.1.8 Well Control Emergencies
Nabors Well Control Standard (RMS-11) will be the primary document during the drilling operations and it will
be followed for all well control incidents. In case of well control event, the parties have agreed to the use of
“Hard” Shut-in procedure.
During Well Control events:
Nabors Rig Manager is responsible for overall Rig integrity
OMV Drilling Supervisor is responsible for well integrity
The OMV Drilling Supervisor, in the event of a well control incident, will direct the drilling contractor in line with
the agreed well control policies. Initial duties of the on-site OMV Drilling Supervisor are to:
Notify OMV D&C Superintendent, report pertinent information
Evaluate nature of events and determine need to activate relevant Emergency Response Plan (Well
Control / Fire / Medivac / H2S etc)
Initiate communication log for all parties involved with the response
Initiate evacuation, medical response as needed
Initiate fire watch if needed
Consult Well Control Contingency Plan (WCCP) / Oil Spill Response Plan (OSRP)
Verify headcount and POB
The OMV Drilling Manager is the “Single Point of Contact” based at the OMV Camp site for drilling related
incidents. Initial Duties of the off-site OMV D&C Superintendent are to:
Receive and distribute initial information (contact Drilling Manager to initiate Chain of Command
notifications)
Activate support for relevant Emergency Response Plan (Well Control / Fire / Medivac etc)
Initiate communication log for all parties involved with the response
Opens briefing / control room
Assemble and brief Emergency Response Support Team
Establish exclusion zones
Contact and mobilize Well Control Specialists/Equipment
Mobilize Drilling Contractor Representative
As a minimum copies of the Site Specific Emergency Response Plan will be provided to the NDIL Area office,
NDIL Rig Manager’s office, Rig’s clinic, OMV Drilling Supervisor office, OMV HSSE Advisor office, OMV
Drilling Superintendent’s office and OMV Sana’a Emergency Management Center.
21
HSSE Bridging document
OMV-Nabors
Fatality
Lost Time Injuries (LTI).
Restricted Workday Cases (RWDC).
Medical Treatment Cases (MTC).
Non Work Related Incidents (IFO)
First Aid Cases (FAC).
Environmental Spills and Releases.
Near Misses and;
Observation Cards
Man hours
Security Incidents
Training Hours
Preventive/ Corrective Action Register (PCAR)
Emergency Training Drills List
22
HSSE Bridging document
OMV-Nabors
Any supplier of services shall ensure provide MSDS’s to the NDIL medic and OMV Doctor.
*While on rig site, all personnel is required to wear fire resisting long sleeve clothing. Trouser and short sleeve
clothing is strictly prohibited.
In addition to the above PPE NDIL requires additional PPE when performing certain activities particularly
handling hazardous materials, grinding, and welding etc. NDIL will provide specialist PPE to comply with the
requirements associated with certain high risk activities and potential exposures. These include:
The wearing of jewelry such as rings, necklaces, earrings etc. is prohibited while at rig site or when
performing work. This also includes metal and metal band watches.
23
HSSE Bridging document
OMV-Nabors
24
HSSE Bridging document
OMV-Nabors
NDIL shall report all spill or release incidents to the OMV Drilling Supervisor.
Refer to NDIL Environmental Policy, (HSE-1-03) and OMV E & P Environment Standard (HSSE-HQ-06-06-
02).
25
HSSE Bridging document
OMV-Nabors
26
HSSE Bridging document
OMV-Nabors
27
HSSE Bridging document
OMV-Nabors
Medical Evacuation
Site Security
Road Transportation
Well Control Emergencies RMS-11 Well Control
Incident Management
Incident Reporting and NDIL HSE Procedures and Work Instructions
Investigation (HSE-05-01).
HSSE Statistics Accident / NDIL HSE Procedures and Work Instructions
Incident Reporting (HSE-05-01).
Hazardous Materials HSE-WI-10.17, Handling and Storage of
Management Hazardous Materials
Personal Protective Equipment HSE-11-01, Personal Protective Equipment
28