REALISASI VOLUME PEKERJAAN MINGGU KE-16 ( TGL. 8 S/D TGL.

12 OKTOBER 2021)
URAIAN

AC-BC LEVELING BETON KURUS BETON FS' 45


NO TANGGAL
LEBAR PANJANG VOLUME LEBAR PANJANG VOLUME LEBAR PANJAN VOLUME TIKET
KM KM KM
(M1) (M1) TIKET (TON) (M1) (M1) TIKET (M3) (M1) G (M1) (M3)

1 8 OKTOBER 2021 20+683 - 20+570 (KANAN-1) 4 113 34+300 - 34+365 (KANAN) 4 65


20+683 - 20+450 (KANAN-2) 3,6 233 173,64 34+365 - 34+368 (KANAN) 4 3 83,50
0PRIT AKHIR

2 9 OKTOBER 2021 12+175 - 12+070 (KANAN-1) 3,75 105 122,50


29+591 - 29+686 (KIRI-2) 3,75 95 121,50

3 10 OKTOBER 2021 29+578 - 29+581 (KIRI-2) 3,75 3


OPRIT AWAL
29+581 - 29+591 (KIRI-2) 3,75 10
29+686 - 29+801 (KIRI-2) 3,75 115 156
12-070 - 11+960 (KANAN-1) 3,75 110 128

4 11 OKTOBER 2021 12+195 - 12+175 (KANAN-1) 3,75 20 4 29+801 - 29+926 (KIRI-2) 3,75 125 144,50
11+960 -11+825 (KANAN-1) 3,75 135 157

5 12 OKTOBER 2021 29+926 - 30+056 (KIRI-2) 3,75 130 153


17+075 - 17+150 (KIRI-2) 3,75 75 90
12+195 -12+175 (KANAN-1) 3,75 20
11+825 - 11+710 (KANAN-1) 3,75 115 157,50

6 13 OKTOBER 2021

7 14 OKTOBER 2021

SAMPAI DENGAN MINGGU LALU 12.485 6.879,88 2.393 899,75 7.051 8.380,50
MINGGU INI 346 174 20 4,00 1.106 1.313,50
SAMPAI DENGAN MINGGU INI 12.831 7.053,52 2.413 903,75 8.157 9.694,00
TOTAL VOLUME ADENDUM 8.435,60 1181,00 22.538,48
SISA VOLUME ADENDUM - 1.382,08 - 277,25 - 12.844,48