Professional Documents
Culture Documents
- PROJECT MANAGEMENT -
PROJECT MANAGEMENT
SEMESTER:
FALL 2021
THEORY SLIDES:
PRJ COST-PROCUREMENT MNG
COORDINATOR :
Pr. Daniel Garcia-Almiñana
Engineering Projects Department
ETSEIAT - TR5 - Office 209
PROJECT MANAGEMENT
COST MANAGEMENT
PROJECT MANAGEMENT
WBS & COST ESTIMATION
1 2 WBS 4 5
Project Activity list - Sequence activities
Scope - Allocate resources
statement
- Estimate durations
3 WBS Dictionary
6 Develop Schedule
Cost management
7 Activity list +
cost estimates
8 Determine the budget 9 Develop Budget 10 Control costs
€
Time
PROJECT MANAGEMENT THE BUDGET – components and terms
Project
budget Cost
Control Work-
baseline
accounts Package
(BAC) Activity cost
cost estimates
estimates (D2, direct &
indirect
costs)
Budget components
PROJECT MANAGEMENT FUNDING REQUIREMENTS
Project budget
Cumulative cost
Management reserve
BAC – Budget at completion
PV – Planned value =
(BCWS – Budgeted Cost Work Scheduled)
Time
PROJECT MANAGEMENT EARNED VALUE MANAGEMENT
PROJECT MANAGEMENT COST BASELINE – PLANNED VALUE
Cumulative cost
Management reserve
BAC
PV
Time
COST BASELINE – PLANNED VALUE
WP1 10 10 10 30
WP2 15 25 10 50
WP3 45 45 90
WP4 60 100 40 200
WP5 10 10 10 30
WP6 5 5 10
CUM (PV) 10 20 45 70 125 170 230 330 380 390 405 410 410
PV ‐ BAC
450
400
350
300
250
200
150
100
50
0
1 2 3 4 5 6 7 8 9 10 11 12
EARNED VALUE – VARIANCE
Graph analysis
PROJECT MANAGEMENT
Schedule
Cumulative cost
Cost variance?
CV=EV-AC
AC – Actual cost
Schedule
indicator
PV
EV – Earned value
SPI=EV/PV
Cost indicator
Time
CPI=EV/AC
FORECAST ANALYSIS Graph analysis
EAC EAC=BAC/CPI
Cumulative cost
EAC=BAC-CV
Management reserve
BAC When is it likely to
finish?
EACt=schedule/SPI
Time
PROJECT MANAGEMENT PROJECT STATUS & FORECAST ANALYSIS
Variances:
Schedule Variance (SV); SV= EV-PV
Cost Variance (CV); CV=EV-AC
Variance at Completion (VAC); VAC=BAC-EAC
Performance Indices
Schedule Performance Index (SPI); SPI=EV/PV
Cost Performance Index (CPI); CPI=EV/AC
To-complete performance index (TCPI);
TCPI=(BAC-EV)/(BAC-AC) or (BAC-EV)/(EAC-AC)
Forecast
Time estimate at completion (EACt); schedule/SPI
Estimate at completion (EAC); EAC=BAC/CPI or BAC-CV
Estimate to complete (ETC); ETC=EAC-AC
PROJECT MANAGEMENT PROJECT STATUS & FORECAST ANALYSIS
Performance Schedule
Measures SV>0 & SPI>1.0 SV=0 & SPI=1.0 SV<0 & SPI<1.0
CV>0 & Ahead of schedule On schedule Behind schedule
CPI>1.0 Under budget Under budget Under budget
Cost CV=0 & Ahead of schedule On schedule Behind schedule
CPI=1.0 On budget On budget On budget
CV<0 & Ahead of schedule On schedule Behind schedule
CPI<1.0 Over budget Over budget Over budget
SUMMARY
- How efficiently we are using our resources? - Cost performance index: CPI
- How efficiently must we use our remaining resources? - To-complete performance index: TCPI
PROCUREMENT MANAGEMENT
PROJECT MANAGEMENT
MAKE OR BUY ANALYSIS
Reasons for purchasing goods or services:
Lack of skilled workers
PROJECT MANAGEMENT
Lack of capacity
Cost considerations
…
Minimize dependence from suppliers Keep multiple sources (qualified vendor list)
Make : Buy:
Incidence in Incidence in
HHRR procurement
Cost-reimbursable contracts :
PROJECT MANAGEMENT
Advantages Disadvantages
Requires less effort by the buyer to manage Scope and quality shall be clearly stated, otherwise some
contracts reductions may arise
Risks may be transferred to the buyer Seller may initially underquote and later try to increase its
margins with Change Requests
Time and costs may become predictable (and Not having a proper SOW may result in seller not
higher) providing some of the deliverables
Cost-reimbursable contracts
Advantages Disadvantages
Less costly than fixed price because seller does not Requires auditing all of the seller invoices and thus
have to account for their risk increases buyer efforts
Simple to draft contracts Seller may have less incentive to control cost
Good for human resource punctual needs Requires monitoring of daily output
Good for small projects
TYPES OF CONTRACT (Risks & Monitoring)
100% 0%
PROJECT MANAGEMENT
Buyer
Firm Fixed Price Contracts (FFP)
Fixed Price with Economic Price Adjustment
Contracts (FP-EPA)
0% 100%