EPCI OF WELLHEAD PLATFORMS, ASSOCIATED PIPELINES

AND BROWNFIELD MODIFICATION


FOR ZAWTIKA DEVELOPMENT PROJECT PHASE 1D
TECHNICAL BID EVALUATION FOR HELIEMSH SAFETY NET

PREPAR'D BY RFF DOCUMENT NO. : MM-ZTK-1D-ZWP12/13/14/15-STR-TBE-0008 REVISION: A2 DATE: 15-Nov-21

CHECK'D BY EEO / TV BIDDER / NATIONALITY : SG Soutions (Helimesh)

NO. REQUIREMENT TENDER CLARIFICATION EVALUATION REMARKS

1.0 TECHNICAL DOCUMENT


Drawings for approval within 4-5 working days from date of PO
Allow 1 week for any comments and final approval
Due to global supply issues, Helimesh can supply the the Safety Net for all 4 platforms Ex Works Helimesh factory
in 16 weeks from date of drawing approval.
If partial shipment is allowed :
1.1 Project Schedule COMPLY Accept on TC-1 Helimesh can supply the safety netting for 2 helidecks within 8-9 weeks from drawing approval
Helimesh can supply the safety netting for 2 helidecks within 16 weeks from drawing approval
Allow 2 weeks for factory shutdown over Christmas and New Years holidays
All lead times are subject to re-confirmation at time of PO due to to limited availability of raw materials due to
supply chain issues

1.2 Manufacturing Procedure Specification COMPLY Helimesh will manufacture to PTTEP specifications

1.3 Inspection and Test Procedure COMPLY Not included in bid

1.4 Guarantee and Warranty COMPLY Per tender terms

1.5 Drawing Reference COMPLY Drawings created on award of project

1.6 Performance Data COMPLY ABS, DNV, Lloyds certificates submitted

1.7 Material Certificate COMPLY Issued on completion of project

Helimesh Pty Ltd will supply prefabricated Helimesh safety net panels comprising 19mm dia. 316SS tube frame
with diamond mesh fitted. See Helimesh photo P1110289 of a typical Helimesh safety net panel.
Helimesh Pty Ltd will supply all mounting hardware (Heliclips, Helibands, 316SS Banding and 316SS buckles). The
1.8 Complete Scope of Supply COMPLY Accept on TC-2 hardware is specifically designed to isolate the Helimesh 316SS tube from the steel structure to prevent galvanic
corrosion. See Helimesh photo P8310037 showing the Helimesh mounting hardware.
The 60mm dia. safety net support framing is NOT supplied by Helimesh.

2.0 HELIMESH SAFETY NET REQUIREMENT


The Helimesh prefabricated safety net panels are designed to sit on the structural frames (60 OD).
Helimesh Safety net panel (by vendor) shall run on all the safety net frame (60 The Helimesh mounting hardware (Heliclips, Helibands, 316SS Banding and 316SS buckles) are to fix the Helimesh
2.1 YES Accept on TC-3
OD) all along the length for both outer and intermediate members. safety net panels to the structure frames. The hardware is specifically designed to isolate the Helimesh 316SS
tube from the steel structure to prevent galvanic corrosion.
A minimum pull-through energy criterion of a rope netting system is 2.3 kJ as
2.2 YES
per EN 1263

2.3 The interim inspection periods and methodology. YES

Capable of retaining sufficient strength and elasticity to withstand the imposed


2.4 YES
loads

Test methods for wire mesh systems by an approved testing facility using an
2.5 YES
approved test method .

4.0 EXCEPTION / DEVIATION NO DEVIATION

5.0 EVALUATION CONCLUTION QUALIFIED

NOTE:
1. EVALUATION SHOULD BE "ACCEPT", "DEVIATE" OR "NOT ACCEPT"
2. CONCLUSION" SHOULD BE "QUALIFIED" OR "UNQUALIFIED"
3. AS LONG AS ONE KEY TECHNICAL PARAMETER DOES NOT MEET THE REQUIREMENT, THE CONCLUSION SHOULD BE "UNQUALIFIED".
4. WHEN THERE ARE FIVE OR MORE THAN FIVE "NOT ACCEPT" OCCUR ON THE TECHNICAL PARAMETERS, THE CONCLUSION SHOULD BE "UNQUALIFIED".
TECHNICAL CLARIFICATIONS TO VENDOR OFFER
Client : PTTEP International Ltd. Revision : A2
Project Name : EPCI OF WELLHEAD PLATFORMS, ASSOCIATED PIPELINES Date : 15-Nov-21
AND BROWNFIELD MODIFICATION FOR ZAWTIKA DEVELOPMENT PROJECT PHASE 1D Prepared By : RFF
RFQ Title : RFQ Number : Checked By : EEO / TV
Offer Number :
Bidder : SG SOLUTIONS (HELIMESH) Offer Date :
Received Date :

SR. NO. SUBJECT / REFERENCE CLAUSE TECHNICAL CLARIFICATION VENDOR's RESPONSE STATUS REMARKS

Structural Discipline :

1st Clarification; 1st Clarification;


1-Nov-21 by Roficho FF

Drawings for approval within 4-5 working days from date of PO


Allow 1 week for any comments and final approval
Due to global supply issues, Helimesh can supply the the Safety Net for all 4
platforms Ex Works Helimesh factory in 16 weeks from date of drawing
approval.
If partial shipment is allowed :
Helimesh can supply the safety netting for 2 helidecks within 8-9 weeks from
Please estimate the project schedule more detailed from manufactured until delivery time.
drawing approval
TC-1 Project Schedule Helimesh can supply the safety netting for 2 helidecks within 16 weeks from CLOSE
drawing approval
Allow 2 weeks for factory shutdown over Christmas and New Years holidays
All lead times are subject to re-confirmation at time of PO due to to limited
availability of raw materials due to supply chain issues

2nd Clarification; 2nd Clarification;

1st Clarification; 1st Clarification;


1-Nov-21 by Roficho FF

Helimesh Pty Ltd will supply prefabricated Helimesh safety net panels
comprising 19mm dia. 316SS tube frame with diamond mesh fitted. See
Helimesh photo P1110289 of a typical Helimesh safety net panel.

Helimesh Pty Ltd will supply all mounting hardware (Heliclips, Helibands,
Did vendor also apply the tube panels/netting? 316SS Banding and 316SS buckles). The hardware is designed to isolate the
Helimesh 316SS tube from the steel structure to prevent galvanic corrosion.
TC-2 Complete Scope of Supply close
See Helimesh photo P8310037 showing the Helimesh mounting hardware.

The 60mm dia. safety net support framing is NOT supplied by Helimesh.

2nd Clarification; 2nd Clarification;

1st Clarification; 1st Clarification;


1-Nov-21 by Roficho FF

From design drawing, safety net frame with OD 60 will be manufactured by CTR, vendor only
See response above and photos attached in email.
manufactured tube netting/panels, mesh/netting, and fastening materials.
TC-3 Net Frame CLOSE
2nd Clarification; 2nd Clarification;

1st Clarification; 1st Clarification;

2nd Clarification; 2nd Clarification;

Page 1 of 1