INTERIOR PAINTING
By: UNITED PAINTS, INC.
Document Review
Activity Company Name Title Signature Date
Prepared by UPI Aieocellis Tan Technical Representative
Recommended by MDC Nenith Bagayawa Project Superintendent
Approved by MDC Jesus Dela Pena Project In-Charge
Validated by MDC Walter Rosal / Christian Tepace QAQC Officer/ QAQC Supervisor
1.2 Pre-Construction - Shop Drawing Check Contracts 100% IFC/FCD X/R X/R R
1.3 Pre-Construction - Materials
Sanding paper, Brush & Rollers
Skimcoat
- 100%
Visual Inspection Approved Materials - As per required by RFA - Materials X R R
specs
Nalcrete primer
Nalcrete Topcoat
2. WORK IN-PROGRESS
Parklinks North Tower
Inspection & Test Plan FORM NO.: F-PQP-QP02-03
Application of Skimcoat Visual Inspection Approved TDS; As per Each Work WAP/ WIR X W R/I
Specs
Application of Primer Visual Inspection Approved TDS; As per Each Work WAP/ WIR X W R/I
Specs
Application of Top Coat Visual Inspection Approved TDS; As per Each Work WAP/ WIR X W R/I
Specs
2.2 Survey Visual Inspection As per specs Per area WAP/WIR X R/I R