You are on page 1of 9

64th R.A.

Bill (Measured), Lumpsum portion


Name of Work :- Civil Package For CW System and Make up water System,stage-II
Name of Agency :- M/S NCC Limited
LOA No. & Date :- CS-9560-318A-9-C-LOA-5478 Dated-22.03.2010
Bill Period :- 01/03/2016 To 31/03/2016 64th R.A Bill
Date of measurement :- 31/03/2016 (Lumpsum)
Date of start :- 1/7/2010
Scheduule Date Of Completion :- 22/08/2012
Time extension up to :- 30.06.2016
Abstract of Costs
Quantity Amount
Revised
BOQ Up to Date as
Sl.no Description of Items Unit Amount since this RA Up to since per Revised
Item No. This RA Bill
(Rs.) previous bill Date previous approved
BBU

Area filling(to the extent shown in tender


125(b)(ii)
1 drg.,internal roads in the make up water No 36000000 0.9775 0 0.9775 35190000 0 35190000
(A)(ii)
facilities area……..(ii) Make up Corridor
2 125(b)(ii)Ai 125(b)(ii)Ai,AR FILL-upto46.2m-pumphouse No 18000000 1.0000 0 1.0000 18000000 0 18000000
3 125(b)(ii)G 125(b)(ii)G,ARFILL-bondrywall inacq.area No 4500000 0.7898 0 0.7898 3554100 0 3554100
4 125(b)(iii) (A) Desilting basin (02 no in scope)EXCAVATION No 6000000 1.0000 0 1.0000 6000000 0 6000000
5 125(b)(iii) (B) Desilting basin (02 no in scope )PCC No 3000000 1.0000 0 1.0000 3000000 0 3000000
6 125(b)(iii) (C) Desilting basin (02 no in scope -Raft for Basin No 15000000 1.0000 0 1.0000 15000000 0 15000000
7 125(b)(iii)F D.B(02)-wall concr.Upto 43m No 6000000 1.0000 0 1.0000 6000000 0 6000000
8 125(b)(iii)G 125(b)(iii)F,D.B02-wall concr.Upto 46.4m No 6000000 1.0000 0 1.0000 6000000 0 6000000
9 125(b)(iii)D 125(b)(iii)D,D.B(02)-PCCof haunch portion No 6000000 1.0000 0 1.0000 6000000 0 6000000
10 125(b)(iii)I 125(b)(iii)I,D.B(02)fix of rail,pipe laying No 6000000 1.0000 0 1.0000 6000000 0 6000000
11 125(b)(iii) (h) Procurement of materials steel etc. No 12000000 1.0000 0 1.0000 12000000 0 12000000
12 125(b)(i)A Switch gear building excavation No 2250000 1.0000 0 1.0000 2250000 0 2250000
13 125(b)(i)B Switch gear building PCC all RAFT No 1050000 1.0000 0 1.0000 1050000 0 1050000
14 125(b)(i)C 125(b)(i)C,SGCRbulding-Founda.cast No 3000000 1.0000 0 1.0000 3000000 0 3000000
15 125(b)(i)D 125(b)(i)D,SwitchGRbuld-Colm&beam upto GL No 1500000 1.0000 0 1.0000 1500000 0 1500000
16 125(b)(i)E 125(b)(i)E,SGCR-Colm & beamuptoRf level No 1500000 1.0000 0 1.0000 1500000 0 1500000
17 125(b)(i)I 125(b)(i)I,SGCRbul-Transformer found No 450000 1.0000 0 1.0000 450000 0 450000
18 125(b)(i)F 125(b)(i)F,SGCRbulding-roof slab No 750000 1.0000 0 1.0000 750000 0 750000
125(b)(i)H,SwitchGRbuldi-mat.proc. steel/
19 125(b)(i)H No 2250000 1.0000 0 1.0000 2250000 0 2250000
cement
20 125(b)(i)G 125(b)(i)G,SGCRbulding-masonary work No 600000 1.0000 0 1.0000 600000 0 600000
21 125(b)(i)K SGCR BUILD-DOOR,WINDOW FIXING No 450000 0.9328 0 0.9328 419760 0 419760
22 125(b)(i)J 125(b)(i)J,SGCRbulding-battery room No 450000 1.0000 0 1.0000 450000 0 450000
23 125(b)(i)L 125(b)(i)L,SGCRbuld-Misc.workviz.pl.prot No 750000 1.0000 0 1.0000 750000 0 750000
MWPH (02) n0.-Excavation & Preparation of
24 125(b)(iv)( a) No 4000000 1.0000 0 1.0000 4000000 0 4000000
PCC
25 125(b)(iv)c 125(b)(iv)c,MWPH02-PCC of all raft No 2000000 1.0000 0 1.0000 2000000 0 2000000
26 125(b)(iv)d 125(b)(iv)d,MWPH02-raft casting No 4000000 1.0000 0 1.0000 4000000 0 4000000
27 125(b)(iv)b 125(b)(iv)b,MWPH02-mat.procu.stl.Stru.st No 6000000 1.0000 0 1.0000 6000000 0 6000000
125(b)(iv)eMWPH-02 wall and column upto GL
28 125(b)(iv)e No 4000000 1.0000 0 1.0000 4000000 0 4000000
and 0m level
29 125(b)(iv)f 125(b)(iv)f,MWPH02-ere.ofstll stru&side No 8000000 1.0000 0 1.0000 8000000 0 8000000
30 125(b)(iv)g 125(b)(iv)g,MWPH02-brick work No 2000000 1.0000 0 1.0000 2000000 0 2000000
31 125(b)(iv)i 125(b)(iv)i,MWPH02-External Plaster No 2000000 1.0000 0 1.0000 2000000 0 2000000
32 125(b)(iv)h 125(b)(iv)h,MWPH02-door,window fixing No 2000000 1.0000 0 1.0000 2000000 0 2000000
33 125(b)(iv)j 125(b)(iv)j,MWPH02-external finish No 2000000 1.0000 0 1.0000 2000000 0 2000000
34 125(b)(iv)k 125(b)(iv)k,MWPH02-misc.work No 4000000 0.9000 0 0.9000 3600000 0.0 3600000
125(b)(v)a Stop log,Trash Rack, Lifting Beam
35 125(b)(v)a No 5525000 1.0000 0 1.0000 5525000 0 5525000
for Supply of -MWPH Stage-II
36 125(b)(v)b 125(b)(v)b,S.L,T.R,LBforMWPH-Erect. No 1275000 1.0000 0 1.0000 1275000 0 1275000
37 125(b)(v)c, 125(b)(v)c,S.L,T.R,L.BforMWPHComi.&Test. No 1700000 1.0000 0 1.0000 1700000 0 1700000
125(b)(vi)a Stop log,Trash Rack, Lifting Beam
38 125(b)(vi)a No 5525000 1.0000 0 1.0000 5525000 0 5525000
for Supply of -MWPH Stage-I
39 125(b)(vi)b 125(b)(vi)b,S.L,T.R,L.BforMWPH-Erection No 1275000 1.0000 0 1.0000 1275000 0 1275000
40 125(b)(vi)c, 125(b)(vi)c,S.L,T.R,L.BforMWPHComi.&Test. No 1700000 1.0000 0 1.0000 1700000 0 1700000
Silt Flushing Pump House -02 (Procurement of
41 125( c)(i) k No 4000000 1.0000 0 1.0000 4000000 0 4000000
material)
42 125( c)(i) a Silt Flushing Pump House -02 (Excavation) No 3000000 1.0000 0 1.0000 3000000 0 3000000
43 125( c)(i) b 125( c)(i)c,SFPH02-all raft casting No 3000000 1.0000 0 1.0000 3000000 0 3000000
44 125( c)(i) d 125( c)(i)d,SFPH02-const.of pump foundn. No 2000000 1.0000 0 1.0000 2000000 0 2000000
45 125( c)(i) e 125( c)(i)e,SFPH02-Col&wall uptoroofbeam No 2000000 1.0000 0 1.0000 2000000 0 2000000
46 125( c)(i) f 125( c)(i)f,SFPH02-B/Wuptorooflevl&slab No 800000 1.0000 0 1.0000 800000 0 800000
47 125( c)(i) c 125( c)(i)c,SFPH02-Colum&wall upto GL No 2000000 1.0000 0 1.0000 2000000 0 2000000
48 125( c)(i) h 125( c)(i)h,SFPH02-external finish. No 800000 1.0000 0 1.0000 800000 0 800000
49 125( c)(i) g 125( c)(i)g,SFPH02-int.finish No 800000 1.0000 0 1.0000 800000 0 800000
50 125( c)(i) I 125( c)(i) (I),SFPH02-D,W,*Shutter fixing No 800000 1.0000 0 1.0000 800000 0 800000
51 125( c)(i) j 125( c)(i)k,SFPH02-Misc.civilwork No 800000 1.0000 0 1.0000 800000 0 800000
52 127(a)( c) Geo Technical Investigation No 3450000 1.0000 0 1.0000 3450000 0 3450000
53 127(a)( d) Supply of Cutting edge material No 4140000 1.0000 0 1.0000 4140000 0 4140000
54 127(a)( e) Fabrication of Cutting edge No 3450000 1.0000 0 1.0000 3450000 0 3450000
55 127(a)( f) erection/grounding of cutting edge No 2760000 1.0000 0 1.0000 2760000 0 2760000
56 127(b)(i)(1) Enabling work for gronding cutting edge No 22500000 1.0000 0 1.0000 22500000 0 22500000
57 129( 1) Supply of material at site No 1400000 1.0000 0 1.0000 1400000 0 1400000
58 129 (2) 129 (2)lowering and jointing of pipe No 840000 1.0000 0 1.0000 840000 0 840000
59 129(3) 129 (3) Pcc incasing of pipes No 420000 1.0000 0 1.0000 420000 0 420000
60 129 (4) 129 (4) balance misc work No 140000 0.6667 0 0.6667 93338 0 93338
127(a)(g)wellcurb inner & outershuttere bar,
61 127(a)(g) No 10350000 1.0000 0 1.0000 10350000 0 10350000
concr
62 127(a)(h) 127(a)(h)concr& sten abRL29.Mto RL36.M No 3450000 1.0000 0 1.0000 3450000 0 3450000
63 127(a)(i) 127(a)(i)frmRL (+)36.0M to RL(+)42.0M No 3450000 1.0000 0 1.0000 3450000 0 3450000
64 127(a)(j) 127(a)(j)frm RL42.0Mto oper flr of IWPH No 3450000 1.0000 0 1.0000 3450000 0 3450000
65 127(b)(i)(7) 127(b)(i)(7)iner/outer shRebar(8) 0to3m No 6300000 1.0000 0 1.0000 6300000 0 6300000
66 127(b)(i)(7) 127(b)(i)(7)iner/outer shRebar(9) 3to6m No 6300000 1.0000 0 1.0000 6300000 0 6300000

Page 1 of 9
Quantity Amount

Revised
BOQ Up to Date as
Sl.no Description of Items Unit Amount since this RA Up to since per Revised
Item No. This RA Bill
(Rs.) previous bill Date previous approved
BBU

67 127(b)(i)(7) 127(b)(i)(7)iner/outer shRebar(10) 6to9m No 6300000 1.0000 0 1.0000 6300000 0 6300000


68 127(b)(i)(7) 127(b)(i)(7)iner/outer shRebar(11) 9to12m No 6300000 1.0000 0 1.0000 6300000 0 6300000
69 127(b)(i)(7) 127(b)(i)(7)iner/outer shRebar(12) 12to15m No 6300000 1.0000 0 1.0000 6300000 0 6300000
70 127(b)(ii) 127(b)(ii)More than 15m & upto 20m No 25000000 1.0000 0 1.0000 25000000 0 25000000
71 127(b)(iii) 127(b)(iii)More than 20m & upto 25m No 20000000 1.0000 0 1.0000 20000000 0 20000000
72 127(b)(iv) 127(b)(iv)More than 25m & upto 30m No 15000000 1.0000 0 1.0000 15000000 0 15000000
73 127(b)(v 127(b)(v)More than 30m & upto 35m No 10000000 1.0000 0 1.0000 10000000 0 10000000
74 127(b)(vi) 127(b)(vi)More than 35m & upto 40m No 10000000 1.0000 0 1.0000 10000000 0 10000000
75 127(b)(vii) 127(b)(vii)Beyond 40m No 15000000 0.9347 0 0.9347 14020500 0 14020500
76 127(b)(viii) 127(b)(viii)Ex.ov(182(b)for sink in rock No 500000 1.0000 0 1.0000 500000 0 500000
77 127(b)(i)(2) 127(b)(i)(2)sinking 0to3m level No 5400000 1.0000 0 1.0000 5400000 0 5400000
78 127(b)(i)(3) 127(b)(i)(3)sinking 3 to 6m level No 5400000 1.0000 0 1.0000 5400000 0 5400000
79 127(b)(i)(4) 127(b)(i)(4)sinking 6 to9 m level No 5400000 1.0000 0 1.0000 5400000 0 5400000
80 125(b)(i)(5) 125(b)(i)(5)sinking 9to12m level No 5400000 1.0000 0 1.0000 5400000 0 5400000
81 125(b)(i)(6) 125(b)(i)(6)sinking12to15m level No 5400000 1.0000 0 1.0000 5400000 0 5400000
82 127(b)(i)(7)(16)127(b)(i)(7)(16) HMstudies forIW pumsump No 2700000 1.0000 0 1.0000 2700000 0 2700000
125(b)(7)inner/outer shutter, Rebar(13) bottom
83 125(b)(7) No 1800000 1.0000 0 1.0000 1800000 0 1800000
pluging
84 127(b)(i)(7) 127(b)(i)(7)iner/outershRebar(14)sandfil No 1800000 1.0000 0 1.0000 1800000 0 1800000
85 125(a)(ii)B 125(a)(ii)B,S.L,T.RforIWPHsup.of fabrMat No 11050000 1.0000 0 1.0000 11050000 0 11050000
86 125(a)(ii)C 125(a)(ii)C,S.L,T.RforIWPH-Erection No 2550000 0.1481 0.4075 0.5556 377655 1039125 1416780
87 125(a)(i)(b) 125(a)(i)(b)IWPHproq. of str.Steel No 4500000 1.0000 0 1.0000 4500000 0 4500000
88 125(a)(i)(c) 125(a)(i)(c)IWPH fabr.ofstr&paint No 3000000 1.0000 0 1.0000 3000000 0 3000000
89 125(a)(i)(d) 125(a)(i)(d)IWPH erect.of structure No 1750000 1.0000 0 1.0000 1750082.25 0 1750082.25
90 125(a)(i)(e) 125(a)(i)(e)IWPH Deckslab Conc.& parapet No 1750000 0.0000 0.4000 0.4000 0 700000 700000
91 125(a)(i)(f) 125(a)(i)(f)IWPH Brick work No 500000 1.0000 0 1.0000 500000 0 500000
92 125(a)(i)(a 125(a)(i)(a)IWPH Conc.ofO.F&Beamat 48.2m No 1000000 1.0000 0 1.0000 1000000 0 1000000
93 125(a)(i)(g) 125(a)(i)(g)IWPHconcr.ofM.F&beamat52.15m No 1250000 1.0000 0 1.0000 1250000 0 1250000
94 125(a)(i)(h) 125(a)(i)(h)IWPH interfinish plast & Wattank No 2500000 1.0000 0 1.0000 2500000 0 2500000
95 125(a)(I)(l) 125(a)(i)(L)IWPH H. Oof frontfor EOT Erect No 1250000 1.0000 0 1.0000 1250000 0 1250000
96 125(a)(i) (I) 125(a)(i)(I)IWPH Hexterfinish-texture paint No 2500000 0.7691 0 0.7691 1922750 0 1922750
97 125(a)(i) (J) 125(a)(i)(J)IWPH D,W RS,V & Deck& Clad sh No 2500000 0.0000 0 0.0000 0 0 0
98 125(a)(l) (k) 125(a)(i)(K)IWPH ironite floring cable duct No 1250000 0.5065 0 0.5065 633125 0 633125
99 125(a)(l) (m) 125(a)(i)(M)IWPH misc. work viz. hand rail No 1250000 0.9619 0.0381 1.0000 1202375 47625 1250000
100 126(a) 126(a)Approach bridge-pile conc No 13500000 1.0000 0 1.0000 13500000 0 13500000
101 126(h) 126(h)Approach bridge-procur.of mat.viz No 13500000 1.0000 0 1.0000 13500000 0 13500000
102 126(d 126(d)Approachbridge-proc.of stru.steel No 18000000 1.0000 0 1.0000 18000000 0 18000000
103 126(e) 126(e)Approach bridge-Fabrication of bridge No 9000000 1.0000 0 1.0000 9000000 0 9000000
104 126(f) 126(f) erection of Bridge No 9000000 0.9901 0 0.9901 8910900 0 8910900
105 126 (g) 126(g) Misc. work (Painting & allied) No 9000000 1.0000 0 1.0000 9000000 0 9000000
106 126(b) 126(b)Approach bridge-pile cap No 9000000 1.0000 0 1.0000 9000000 0 9000000
107 126(c) 126(c)Approach bridge-const.of pier No 9000000 1.0000 0 1.0000 9000000 0 9000000
108 128(d) 128(d) laying of grad I No 4625000 1.0000 0 1.0000 4625000 0 4625000
109 128(c) 128(c)laying of grad II No 4625000 1.0000 0 1.0000 4625000 0 4625000
110 128(b) 128(b)laying of grad III No 3700000 0.8814 0 0.8814 3261180 0 3261180
111 128(e) 128(e)Black top with Seal Coating No 2775000 1.0000 0 1.0000 2775000 0 2775000
112 128(a) 128(a)surface dranege No 1850000 0.5675 0 0.5675 1049875 0 1049875
113 125(b)(ii)B 125(b)(ii)B,AR FILL-sub base-pump house No 4500000 1.0000 0 1.0000 4500000 0 4500000
114 125(b)(ii)C 125(b)(ii)C,AR FILL-grade III pump house No 4500000 0.9147 0 0.9147 4116150 0 4116150
115 125(b)(ii)D 125(b)(ii)D,AR FILL-grade II pump house No 6300000 1.0000 0 1.0000 6300000 0 6300000
116 125(b)(ii)E 125(b)(ii)E,AR FILL-grade I pump house No 4500000 1.0000 0 1.0000 4500000 0 4500000
117 125(b)(ii)H 125(b)(ii)H,AR FILL-internal drain No 4500000 0.9915 0 0.9915 4461750 0 4461750
118 125(a)(iii)A 125(a)(iii)A-RBP Exca upto toe wall No 3623508.76 0.0000 0.00000 0.0000 0 0 0
119 125(a)(iii)B 125(a)(iii)B-RBPDeli of gab&geotexti No 3623508.76 0.4034 0 0.4034 1461723 0 1461723.434
120 125(a (iii)C 125(a (iii)C-RBPdeliv ofboulder forSt.Pi No 2717631.57 0.1301 0.42100 0.5511 353564 1144122.89 1497686.758
121 125(a)(iii)E 125(a)(iii)E-RBP F,C,F46.2to42.5slnt are No 18117543.8 0.5535 0.08100 0.6345 10028060 1467521.05 11495581.54
122 125(a)(iii)F 125(a)(iii)F-RBP F,C,F42.5to39.5slnt are No 18117543.8 0.0000 0.36000 0.3600 0 6522315.77 6522315.768
123 125(a)(iii)H 125(a)(iii)H-RBP S.P with conc 45.5 to 42.5 No 7247017.52 0.5535 0.08100 0.6345 4011224 587008.419 4598232.616
124 125(a)(iii) I 125(a)(iii)I-RBP S.P with conc 42.5 to below No 7247017.52 0.0000 0.36000 0.3600 0 2608926.31 2608926.307
604303112 14116644 618419757

Page 2 of 9
Quantity Amount

Revised
BOQ Up to Date as
Sl.no Description of Items Unit Amount since this RA Up to since per Revised
Item No. This RA Bill
(Rs.) previous bill Date previous approved
BBU

Please release these following withheld Amount


RA bill
Item Amount Remarks
No.
5
(SUPLIME RETAINTION FOR GEO TECH REPORT 100000 Geotech report submited (complied)
NTARY)

5 FOR NON COMPACTION OF SOIL BY FQA 200000 Verified by FQA OFFICIAL on 11.5.11 ( complied)
11 FOR NON PRODUCTION WATER TEST REPORT BY EIC 15000 Report submitted.
RETENTION FOR NON PRODUCTION OF TEST REPORT OF ROAD METAL (ATTENBORG
13 LIMIT OF BINDING MATERIALS) 50000
20 FOR NON CONDUCTING PILE INTEGRITY TEST 100000 Report submitted.
25 AGAINST NON CALIBRATION OF BATCHING PLANT 20000 Report submitted.
29 AGAINST PAINTING OF ANGEL, CHANNEL IN SURGE GIRDER OF MWPH-II 50000 ALL PENDING WORK COMPLETED

30 Recovery against risk & cost dismantling of temporary wall for unit rate civil portion 66913

AGAINST FQA PENDING POINT (WATER TIGHTNESS TEST ON WATER RETAINING


33 STRUCTURE) 25000

37 AGAINST FQA PENDING POINT 90000 1.FOR UT OF COLUMN- DONE, 2.COMPLETE DOC. OF MECHANICAL SE
AGAINST FQA PENDING POINT ( PAINTING OF STRUCTURAL STEEL IN LAST SPAN
OF APPROACH BRIDGE INTERMEDEIAT & FINAL COAT ) 400000
54&55
Retention for items of SES not to be paid 248655
58&59 Against inadiquet thickness of black topping thickness & seal coat by EIC 700000
Retention by FQA for inadequete black topping thickness & seal coat 30000
60
Retention for items of SES not to be paid, item no. 126(f) 89100
61 Retention by FQA pending points 50000

Total = 2234668

Statutory Deduction-

1 Income Tax @ 2% 282332.89

2 WCT Vat @5% 705832.22

3. Building cess@1% 141166.44

Total Deduction 1129331.55

Net Payable Amount for this Bill 12987313

(M/s NCCL) NTPC Astt. Mgr. NTPC Mgr. NTPC (EIC)


CERTIFICATE
1.The quantity mentioned in the measurement taken on actual and not less than actually executed
2.Work has been done as per specification & instruction of Engineer-In-charge.
3.Test check has been done as per norms.
4.Metarial consumption statement is enclosed.
5.Quality certificate is enclosed.

Page 3 of 9
64th R.A. Bill (Measured), Lumpsum portion
Name of Work :- Civil Package For CW System and Make up water System,stage-II
Name of Agency :- M/S NCC Limited
LOA No. & Date :- CS-9560-318A-9-C-LOA-5478 Dated-22.03.2010
Bill Period :- 01/03/2016 To 31/03/2016
Date of measurement:- 31/03/2016
Date of start :- 1/7/2010
Date Of Completion :- 22/08/2012
Time extension up to :- 30.06.2016
P.O.No.-5500005565
SES No.

125(a)(iii)A 125(a)(iii)A-RBP Exca upto toe wall


As per approved Drg.no. 9560-318A-PVC-U-021-07
Excavation
Total length of scope of work = 271 mtr length
Measurement sheet Qty. (M³)
271x0.5x18.6x (46.2-40.0) 15625.86
271x5x (46.2-40.0) 8401.00
271x15x (46.2-35.0) 45528.00
271x5x (46.2-35.0) 15176.00
271x15x (46.2-30.0) 65853.00
271x10x (46.2-28.9) 46883.00
Extra Excavation:
Horizontal beam = 11x271x0.25x0.15 111.79
Vertical beam = 55x58.6x0.25x0.15 120.86
For drain = 18x58.6x (1.3+0.7) / 2 x 0.4 421.92
For Outfall structure = 3x50x3.35x 2.4 1125.60
Total Scope of work qty. 199247.03

Completed upto 31.03.2016


Measurement sheet Qty. (M³)
178x0.5x18.6x (46.2-40.0) 10263.48
178x5x (46.2-40.0) 5518.00
178x15x (46.2-35.0) 29904.00
178x5x (46.2-35.0) 9968.00
Horizontal beam = 7x178x0.25x0.15 46.73
Vertical beam = 35x43x0.25x0.15 56.44
For drain = 11x43x (1.3+0.7) / 2 x 0.4 189.20
For outfall structure = 2x43x3.35x 2.4 645.34
Total complete qty. as on 31.01.2016 56591.19

Qty. in previous =0 0
qty completed as on 31.03.16 is 56591.19x100/199247.03 = 28.403%
28.403
completed %
qty. in this bill= 28.403 %
amount up to previous bill is = 0.00 0.0
Amount in this RA bill is Rs.3623508.76 x 28.403% 1029185.19 1029185.2
Total up to date amount is = 1029185.19 1029185.2

125(a (iii)C 125(a (iii)C-RBPdeliv ofboulder forSt.Pi


Total quantity of Stone Masonry from RL 46.20m to RL. 33.50m
1 From RL 46.20m to RL.40.00M
272*19.6*.450-55*.250*19.6*.45-4*272*.450*.25 2155.365
2 From RL 40.00m to RL.40.00M
272*5*.450-55*.250*5*.45-272*.45*.25 550.4625
3 From RL 40.00m to RL.35.00M
272*15.81*.450-55*.250*15.81*.45-3*272*.450*.250 1745.519625
4 From RL 35.00m to RL.35.00M
272*5*.450-55*.250*5*.45-272*.45*.25 550.4625
5 From RL 35.00m to RL.33.50M
272*4.74*.450-55*.250*4.74*.45-272*.45*.25 520.24725

Stone Rip Rap/Pitching Qty from RL 33.50m up to Toe


Wall
1 Toe Wall
5*272*1.1 1496
2 Slant Portion from RL 33.50 up to Toe Wall
918*0.4*0.45 165.24
Total Qty 7183.296875

Total Quantity of Materials procured at the site is 2352.94cum

% of material supply is = 2352.94*100/7183.29=32.755% 0.3275500

% for this bill = 32.755%-13.01% = 19.745% 0.1974500


as per approved BBU,Total amount for supply of boulder for stone
pitching is Rs.2717631.57/-
Amount up to the previous bill is = 353563.8673 353563.9
Amount in this RA bill is = 536596.353497 536596.4
Upto Date amount = 890160.220797 890160.2

Page 4 of 9
64th R.A. Bill (Measured), Lumpsum portion
Name of Work :- Civil Package For CW System and Make up water System,stage-II
Name of Agency :- M/S NCC Limited
LOA No. & Date :- CS-9560-318A-9-C-LOA-5478 Dated-22.03.2010
Bill Period :- 01/03/2016 To 31/03/2016
Date of measurement:- 31/03/2016
Date of start :- 1/7/2010
Date Of Completion :- 22/08/2012
Time extension up to :- 30.06.2016
P.O.No.-5500005565

Page 5 of 9
64th R.A. Bill (Measured), Lumpsum portion
Name of Work :- Civil Package For CW System and Make up water System,stage-II
Name of Agency :- M/S NCC Limited
LOA No. & Date :- CS-9560-318A-9-C-LOA-5478 Dated-22.03.2010
Bill Period :- 01/03/2016 To 31/03/2016
Date of measurement:- 31/03/2016
Date of start :- 1/7/2010
Date Of Completion :- 22/08/2012
Time extension up to :- 30.06.2016
P.O.No.-5500005565
125(a)(iii)E 125(a)(iii)E-RBP F,C,F46.2to42.5slnt are

As per approved Drg.no. 9560-318A-PVC-U-021-07


Total Length of Bank protection from RL 46.20m to RL 42.50M is 271M
Total Length of work done as on 31.03.16 is 172M
% of Work done is =172/271=63.468% 0.63468 %
Less already paid in previous R.A is 150 m 0.55350 %
This bill Qty 0.08118 %
as per approved BBU,total amount for the 271M length is
Rs.18117543.8
amount up to previous bill is = 10028060.49 10028060.49
Amount in this RA bill is = 1470782.21 1470782.21
Total up to date amount is= 11498842.70 11498842.70

125(a)(iii)F 125(a)(iii)F-RBP F,C,F42.5to39.5slnt are


As per approved Drg.no. 9560-318A-PVC-U-021-07
Total Length of stone pitching is from RL 46.20m to RL 42.50M is 271M
Total Length of work done as on 31.03.16 is 100M
% of Work done is =100/271=36.900% 0.36900 % 36.90036900369

as per approved BBU,total amount for the 271M length is


Rs.18117543.8
amount up to previous bill is = 0.00 0.00
Amount in this RA bill is = 6685373.66 6685373.66
Total up to date amount is = 6685373.66 6685373.66

125(a)(iii)H 125(a)(iii)H-RBP S.Pwith conc45.5to-42.5


As per approved Drg.no. 9560-318A-PVC-U-021-07
Total Length of stone pitching is from RL 46.20m to RL 42.50M is 271M
Total Length of work done as on 31.03.16 is 172M
% of Work done is =172/271=63.468% 0.63468 %
Less already paid in previous R.A is 150 m 0.55350 %
This bill Qty 0.08118 %
as per approved BBU,total amount for the 271M length is
Rs.7247017.52
amount up to previous bill is = 4011224.20 4011224.20
Amount in this RA bill is = 588312.88 588312.88
Total up to date amount is = 4599537.08 4599537.08

125(a)(iii) I 125(a)(iii)I-RBP S.P with conc 42.5 to below

As per approved Drg.no. 9560-318A-PVC-U-021-07


Total Length of stone pitching is from RL 46.20m to RL 42.50M is 271M
Total Length of work done as on 31.03.16 is 100M
% of Work done is =100/271=36.900% 0.36900 %

as per approved BBU,total amount for the 271M length is


Rs.7247017.52
amount up to previous bill is = 0.00 0.00
Amount in this RA bill is = 2674149.46 2674149.46
Total up to date amount is = 2674149.46 2674149.46

125(a)(ii) 125(a)(ii)C,S.L,T.R for IWPH-Erection


1 as per scope total sets of 1st stage embeded parts
Stop Log set 4
Trash
as per Rack
scope total sets of 2nd stage embeded parts along with stoplog & trash set 4
2 rack gates
Stop Log set 4
Trash Rack set 4
3 Lifting Beam,Trash Rack,Stop Log Gates No 10
4 Monorail Hoist No 1
total amount as per approved BBU for above supply is Rs.11050000 TOTAL- 27

total erectionas on 31.12.15


1 total sets of 1st stage embeded parts
Trash Rack set 4
Stop Log set 4
2 total sets of 2nd stage embeded parts
Stop Log set 4
Trash Rack set 2
3 Lifting Beam,Trash Rack,Stop Log Gates (2+0+2) no 4
4 Monorail Hoist No 1
TOTAL- 19
i.e 100 % erection includes above 27 item, hence for erection of 19 items,%
erection is 19/27*100=70.37% 0,7037
hence amount for 70.37% of supply is Rs.2550000*70.37%= 1794435.000

up to previous bill ,total amount is =.1481 377655.000


Page 6 of 9
64th R.A. Bill (Measured), Lumpsum portion
Name of Work :- Civil Package For CW System and Make up water System,stage-II
Name of Agency :- M/S NCC Limited
LOA No. & Date :- CS-9560-318A-9-C-LOA-5478 Dated-22.03.2010
Bill Period :- 01/03/2016 To 31/03/2016
Date of measurement:- 31/03/2016
Date of start :- 1/7/2010
Date Of Completion :- 22/08/2012
Time extension up to :- 30.06.2016
P.O.No.-5500005565
total amount in this RA bill is =(70.37-14.81) = 55.56% 1416780.000
Total up to date amount is =.7037 1794435.000

Page 7 of 9
Measurement for Texture paint, Hand rail & Deck & Cladding sheet

Item No. Description Qty. L B Total Gross Total


125(a)(i) (I) Total Qty. of Texture paint
Motor Floor 2 22.8 0.9 41.040
Curve part 2 10.994 0.9 19.789
Total qty. 60.829
Work completed as on date
Motor Floor 2 22.8 0.9 41.040
Curve part 2 10.994 0.9 19.789
Total qty. 60.829 100.00 %

125(a)(l) (m) Total Qty. of Handrail


Motor Floor 1 77.418 77.418
Pump Floor 1 69.918 69.918
Total qty. 147.336
Work completed as on date
Motor Floor 1 77.418 77.418
Pump Floor 1 69.918 69.918
Total qty. 147.336 100.00 %
125(a)(i) (J) Total Qty. of IWPH D,W RS,V & Deck& Clad sh
Door 2 1.2 2.1 5.040
Windows 24 1.5 1.2 43.200
Vent. 40 1.8 0.9 64.800
RS 1 3 3 9.000
Deck sheet (Straight part) 1 22.8 11.7 266.760
Deck sheet (Curve part) 2 3.1 11.7 72.540
Cladding upto Crane girder lvl
Curve part 2 9.226 7.31 134.884
Straight part 2 22.8 7.31 333.336
Cladding upto Crane girder to parapet
Curve part 2 13.066 6.065 158.491
Straight part 2 22.8 6.065 276.564

Total qty. 1364.615 m²


Work completed as on date
Door 2 1.2 2.1 5.040
Windows (70% Complete only) 16.8 1.5 1.2 30.240
Vent. (70% Complete only) 28 1.8 0.9 45.360
RS 1 3 3 9.000
Deck sheet (Straight part) 1 22.8 11.7 266.760
Deck sheet (Curve part) 2 3.1 11.7 72.540
Cladding upto Crane girder lvl
Curve part 2 9.226 7.31 134.884
Straight part 2 22.8 7.31 333.336
Cladding upto Crane girder to parapet
Curve part 2 13.066 2.473 64.624
Straight part 2 22.8 2.473 112.769

Total qty. 1074.553 m²


78.74 %

Total Qty. of deck slab & parapet concreeting


Deck slab (Straight part) 1 22.8 11.7 0.085 22.675
Deck slab (Curve part) 2 3.1 11.7 0.085 6.166
Deck Slab Parapet
Curve part 2 13.066 0.1 0.958 2.502
Concrete
Straight part 2 22.8 0.1 0.958 4.366
Deck Slab
Concrete

Total qty. 35.709 m³

You might also like