Question 1
Answer saved

Marked out of 1.00

Which of the following is another name of event?

a. Network
b. Arrow
c. Nodes
d. None of These

CLEAR MY CHOICE

Question 2
Answer saved

Marked out of 1.00

An activity which does not have any duration?

a. Critical
b. Non-critical
c. Dummy
d. None of these

CLEAR MY CHOICE

Question 3
Answer saved

Marked out of 1.00

Critical Path is the path having the.....duration in the project?

a. Lowest
b. Highest
c. Equal
d. All of the above

CLEAR MY CHOICE
Question 4
Answer saved

Marked out of 1.00

The Latest times of every activity is calculated by........pass calculation?

a. Backward
b. Forward
c. Ordinary
d. None of These

CLEAR MY CHOICE

Question 5
Answer saved

Marked out of 1.00

Henry Gantt was........Engineer and social scientist who developed Gantt chart?

a. German
b. American
c. French
d. None of these

CLEAR MY CHOICE

← UNIT 5 PART B

Jump to...

QUIZ 2 →

Integral Learning Initiative: A Collaborative Blended Learning Platform

Quick Links

IU site

Gallery

Library

YouTube

Instagram

Disclaimer

Follow Us
 

Contact
Integral University, Kursi Road, Lucknow(india)

 Phone: (000) 123-456

 E-mail: ili@iul.ac.in, sdc@iul.ac.in

Copyright © 2020 - Developed by SDC, Integral University.

Data retention summary


Switch to the standard theme

You might also like