You are on page 1of 104

FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA

ETHIOPIAN ELECTRIC POWER CORPORATION (EEPCo)

Gibe III-Sodo 400 kV Power Transmission Lines Project

RESETTLEMENT ACTION PLAN

EEPCo, Environmental Monitoring Unit (EMU)


E-mail emu.eepco@yahoo.com

January 2009
Table of Contents
Page
EXECUTIVE SUMMARY i
1. INTRODUCTION ............................................................................................................ 1
1.1 Back Ground of the Project ........................................................................................ 1
1.2 Objectives of the Resettlement Plan........................................................................... 1
1.3 Methodology .............................................................................................................. 2
1.3.1 Review Literature................................................................................................ 2
1.3.2 Census and Socio-Economic Survey .................................................................. 2
1.3.3 Public Consultation ............................................................................................. 2
1.4 Assessment Team ....................................................................................................... 2
2. OVERVIEW OF THE PROJECT .................................................................................... 3
2.1 Description of the Project Components ..................................................................... 3
2.1.1 Towers................................................................................................................. 3
2.1.2 Right of Way /ROW/ .......................................................................................... 3
2.1.3 Foundation .......................................................................................................... 4
2.1.4 Stringing.............................................................................................................. 4
2.1.5 Access Roads ...................................................................................................... 4
2.1.6 Substation............................................................................................................ 4
2.2 Project cost ................................................................................................................. 4
2.3 Route Selection .......................................................................................................... 4
3. POLICY AND LEGAL FRAMEWORK FOR LAND ACQUISITION,
ACTIVITY AND USE .................................................................................................... 5
3.1 Policy framework ....................................................................................................... 5
3.2 Constitution of FDRE................................................................................................. 5
3.3 National Policy of Women ......................................................................................... 6
3.4 Environmental Policies .............................................................................................. 6
3.5 Review of Laws and Regulation ................................................................................ 7
3.5.1 The Rural Land Administration and Utilization Proclamation ........................... 7
3.5.2 Expropriation and Compensation of Property .................................................... 7
3.5.2.1 Land Tenure................................................................................................................ 7
3.5.2.2 Expropriation of Land Holding for Public Purpose .................................................... 7
3.5.2.3 Compensation ............................................................................................................. 8
3.6 World Bank Policies and Procedure for Involuntary Resettlement ......................... 9
3.7 The African Development Bank Involuntary Resettlement Policy ............................ 9
3.8 EEPCo’s Strategies for Expropriation and Compensation....................................... 10
3.9 The Federal Democratic Republic of Ethiopia and Administration Regions........... 10
4. EXISTING SITUATION OF THE PROJECT AREA ................................................... 11
4.1 Location and Administration Setup.......................................................................... 11
4.2 Population and Demographic Characteristics .......................................................... 11
4.3 Religion, Ethnicity and Language ............................................................................ 11
4.4 Economic Conditions and Livelihood Activities ..................................................... 11
4.5 Land Use and Land Cover ........................................................................................ 12
4.6 Access to Social Services ......................................................................................... 12
4.6.1 Access to Medical Facilities ............................................................................. 12
4.6.2 Access to Education .......................................................................................... 13
4.6.3 Access to Water Supply .................................................................................... 13
4.6.4 NGOs Working In and Around the Project....................................................... 14
4.6.5 Access to Agricultural Support Services .......................................................... 14
5. SOCIO- ECONOMIC CONDITIONS OF THE PAPS .................................................. 15
5.1 Age-wise Distribution of Members of Affected Families ........................................ 15
5.2 Distribution of the Affected Families by Religion ................................................... 16
5.3 Educational Status of the PAPs ................................................................................ 16
5.4 Housing Conditions of the PAPs.............................................................................. 16
5.5 Livestock .................................................................................................................. 16
5.6 Average Land Holding Size ..................................................................................... 16
5.7 Crop Production ....................................................................................................... 17
5.8 Source of Livelihood of the Affected Families ........................................................ 17
5.9 Summary of the Findings of the Socio-Economic Survey ....................................... 18
6. SOCIO - ECONOMIC IMPACT OF THE PROJECT ................................................... 19
6.1 Impact on Household Assets .................................................................................... 19
6.1.1 Impact on Farmland .......................................................................................... 19
6.2 Impact on Housing Structures .................................................................................. 20
6.2.1 Impact on public and community institutions................................................... 20
6.2.2 Impact on Perennial Crops and Trees ............................................................... 20
6.3 The Extent of Impact on the Land Use .................................................................... 21
6.4 Impact on Vulnerable Groups .................................................................................. 22
7. PUBLIC CONSULTATION .......................................................................................... 22
8. ENTITLEMENT MATRIX AND ELIGIBILITY OF PROJECT AFFECTED
PERSONS ...................................................................................................................... 23
8.1 Basis for Valuation of Losses................................................................................... 23
8.2 Compensation for Loses of Crops ............................................................................ 28
8.3 Compensation for Loss of Perennial Crops and Trees ............................................. 28
8.4 Compensation for housing structures ....................................................................... 30
9. INSTITUTION FOR IMPLEMENTATION OF RESETTLEMENT PLAN ................ 31
9.1 Implementation Schedule ......................................................................................... 32
10. GRIEVANCE REDRESS MECHANISM ..................................................................... 33
10.1 Grievances Redress Procedure ............................................................................. 33
11. MONITORING AND REPORTING PLAN .................................................................. 34
11.1 Internal Monitoring............................................................................................... 34
11.2 External Monitoring ............................................................................................. 34
12. IMPLEMENTATION BUDGET.................................................................................... 35
List of Tables

Table 1: Number of People around the Project Affected Woredas


Table 2: Climatic and Temperature Condition of the Project Affected Woredas
Table 3: Health Institutions and Personals
Table 4 Number of Schools in Project Affected Woredas
Table 5 Age Distribution of the Project Affected Woredas
Table 6: Average Yield per Hectare
Table 7: Average Income of the Affected Families
Table 8: Affected land In Ha by Crop Category.
Table 9: Type and Number of Affected Residential Houses
Table 10: Impact on Perennial Crops and Trees
Table 11: Summary of Impacts on House Holds Assets
Table 12: Summary of principles and method used for Valuation of Affected Assets
for Compensation Purpose.
Table 13: Average Yield and Current Market Price of Crops
Table 14: Proposed Compensation for Trees
Table 15: Proposed Compensation for Perennial Crops
Table 16: Proposed Compensation for Losses for Residential Houses
Table 17: Schedule for Implementation of Resettlement Action Plan
Table 18 Members of Grievance Redress Committee
Table 19: Budget Cost Summary

List of Annexes

Annex -1 Detail Number of Affected House Holds and Their Lost Assets
Annex -2 Consultation Minutes of Meeting
Annex -3 Relevant Proclamations
Annex -4 Lists of Consulted Officials
Annex -5 Photos
ACRONYMS

AfDB African Development Bank


EEPCo Ethiopian Electric Power Corporation
EMU Environmental Monitoring Unit
FEPA Federal Environmental Protection Authority
EPE Environmental Policy of Ethiopia
ETB Ethiopian Birr
FDRE Federal Democratic Republic of Ethiopia
FHH Female Headed Households
GRC Grievance Redress Committee
HVTL High Voltage Transmission Line
IC Implementation Committee
IPM Internal Performance Monitoring
Kv Kilo Volt
MW Mega Watt
NGO Non Governmental Organization
OP Operational Policy
OD Operational Directives
PAP’s Project Affected Persons
PIU Project Implementation Unit
RAP Resettlement Action Plan
WB World Bank
Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

EXECUTIVE SUMMARY

Ethiopian economy has grown quickly. Along with the speedy development of economy, the
power demand also greatly increased.

The Power demand in the future can be supported with reliable and quality supply of
electricity. EEPCo has a mandate to satisfy the future need of the customers by keeping the
balance between satisfying the power need of the society and the remaining with in the
capability of the Environment.

In order to achieve this objectives /responsibilities, EEPCo has to develop a new power
projects and re enforce the existing transmission systems on going base.

Accordingly EEPCO planned additional transmissions for new power developments which
are under construction. One of the planned transmissions line is, Gibe III – Addis Ababa 400
kV Power Transmission Project which link the generated energy from Gibe III Hydro Power
Project to Ethiopian’s National Grid.

GibeIII -Sodo 400 kV transmission line is one section of the Gibe III-Addis Ababa power
transmission project.

The construction of the proposed Gibe III –Sodo 400 kV power line project can create
various potential adverse environmental and social effects such as involuntary displacement,
disruption of livelihoods and impoverishment. To mitigate these adverse impacts, appropriate
mitigation measures required to be applied. RAP is one of the major means of addressing
these impacts in a planned and coordinated manner.

a. Objective of the Resettlement Plan

The objective of the resettlement plan is to provide a plan for resettlement and rehabilitation
of the PAPs so that their losses will be compensated and their standard of living will be
improved or at least restore to the pre project levels. To achieve these objectives the plan
provides the rehabilitation measures so that the income earnings potential of individuals is
restored and sustains their livelihoods.

b. Methodology

Various methods, tools and techniques were adopted to collect data and information required
to prepare the resettlement plan. Both primary and secondary data collected using different
methods.

Public consultation also conducted with the project affected people and communities to
create awareness about the project possible impact and how mitigation measures will be
implemented including compensation payments.

The Field survey conducted by the study team comprises sociologists, engineer, and
surveyor.

EEPCo Environmental Monitoring Unit (EMU) i


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

A. Brief overview of the Project.

Power is one of the most essential amenities required for acceleration the economic
development .The Ethiopian economy growth for 5 consecutive years. Along with this
economic growth the demand for power also increases. In order to ensure the load in the
future can be supported with reliable and quality supply of electricity, EEPCO has a long
term strategy to support the government in promoting social and economical progress by
promotes the development of electric power generation and transmission.

As part of the strengthening of the national grid, EEPCO has developed serious of high
voltage direct inter regional links. With the growth in installed capacities and power demand,
the existing transmission facilities are required to be strengthened by establishment of 400
kV.

Accordingly EEPCo planned additional transmissions facilities to transmit the generated


power from newly developed hydro powers. One of the planned transmissions is the Gibe III
400kV –Addis Ababa power line transmission line which links the generated energy from
Gibe III hydro power project to Ethiopian National Grid.

The Gibe III-Sodo transmission line is one section of the Gibe III-Addis Ababa. The line will
have two lines of double circuit tower configuration on one of these lines the two circuits will
be stranded while on the other only one circuit will be stranded when Gibe IV is realized.

Project Location and Description

The Gibe III – Sodo 400 kV transmission line project located in Southern Nation
Nationalities Reginal States/SNNRS/ of Wolita Sodo Zone. The line cross three Woredas
namely Sodo zuria , Damote Sore and Kindo Koiysha .

Description of the Project Components

The proposed 400 kV transmission line is to be constructed between the Gibe III hydro
power project and the newly built Sodo Substation. A distance of 65 km. 50 meter wide
Right of Way is required.

Towers

Transmission line conductors are strung on in line suspension tower and bend (strain) towers.
For the proposed 400 kV transmission line between Gibe III hydro power and Sodo
substation, compact cross –rope suspension structure and self supporting towers might be
used. The towers are generally 30-40 meter in height and a total footprint area
Approximately 12 m x 12 m is required the average span between two towers will be 350
m. Approximately about 186 Towers are required for erection.

EEPCo Environmental Monitoring Unit (EMU) ii


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

Right of Way /ROW/.

The ROW width for a 400 kV transmission line is 50 m i.e. 25 m either side of the center
line .The ROW is required to ensure the safe construction , maintenance and operation of the
power line .

Any farming activities except commercial trees such as Mango, Avocado tree can be
practiced underneath the power line.

No vegetation will be grown above 8 m under the conductor and also no building will be
constructed under the power line.

The minimum distance of 400 kV transmission line from public road is 95 m from the center
line of the structure to the center of the road.

Foundation

The foundation is influenced by the type of terrain encountered as well as the underlying
geotechnical condition. The actual size and type of foundation to be installed will be
depending on the soil bearing capacity. The area required for construction of the foundation
will be 12 m x12 m. Foundation will be excavated manually and using machines such as
compressor and excavator. All foundation will back filled, stabilized through compaction,
and capped with concrete at ground level.

Stringing

Stringing can be under taken mechanically or by hand - A pilot cable conductor is used
between towers.

Access Roads

Access road is required to allow access along the entire length during construction and
operation /maintenance phase of the transmission line power life cycle. During survey, route
line was designed along the existing road in order to reduce the potential impact associated
with the construction of new road .Existing roads will be used as far as possible where
available. About 6 meters x 0 .456 KM new access road will be constructed where the
existing roads can not be used.

The construction of access roads should be in the manner of avoiding permanent removal of
the existing vegetation. All access point and roads will be negotiated with land owners.

Substation

The project will occupy the construction of a new substation at Sodo Zuria Woreda Warza
Lasho Kebele occupies an area of 25 ha.. The total cost of the construction of substation is
estimated about 9.6 Million Birr.

EEPCo Environmental Monitoring Unit (EMU) iii


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

Project Cost

The total cost is estimated for the construction of the project is about 412 Million Birr.

B. Review of Policies, Legal and Institutional Frame Works.

Various policies and legal documents that are relevant with resettlement planning is
reviewed. Some of these documents deal with issues related to land ownership,
expropriation, entitlement, compensation and resettlement issue include;

The Constitution Of The Federal Ethiopia ,Civil code of Ethiopia Environmental Policy of
Ethiopia, Proclamation No 455/2005 on land expropriation of landholdings for public
purpose and payment of compensation and regulation No. 135/ 2007 council of ministers
regulations on the payment of compensation for property situated on land holdings
expropriated for public purposes.

Review of relevant policies and legal frameworks revealed a number of points pertinent to
involuntary resettlement. These legal and institutional frameworks provides a detail
principles and procedures regarding resettlement such as expropriation of land for public
purpose, property valuation, computing compensation rate, compensation payment and
mechanisms for grievance redress.

In addition, there are both national and secotral policies developed to be applicable for all
development projects which entail involuntary displacement. The objective of the policies are
avoid dislocation of people as far as possible, when displacement of people becomes an
avoidable, then the policy principles, institutions, and structure of the government of Ethiopia
provide for the adoption of a wider developmental approach which seek to share the benefit
of the development project with project affected people and local communities. The principle
is that development project at least should not impoverish people by degrading the physical
environment.

In general the national policies, legislation and regulations are all consistent with the World
Banks Operational Policies (OP 4.12) and bank procedure (BP 4.12) on involuntary
resettlement. More over, the national frameworks are also consistent with international
convections, treaties and frameworks which Ethiopia is ratified.

C. Socio Economic Condition of the Project Affected Area

The proposed Gibe III- Sodo 400kV transmission line cross three Woredas namely Sodo
zuria ,Damote Soreand Kindo Koiysha.

About 406,283 people living in the three Woredas .The average family size for all affected
Woreda is 7 which is more than the national averages 4.8. The average population density is
501.93 persons per km squared with regard gender proportion of current population
constitute 51% female and 49% male. The population growth rate estimated about 2.9 %.

The project area is characterized by a great deal of ethnic and religious diversity. About three
ethnic groups live in the project Woredas .The major ethnic group in the project affected

EEPCo Environmental Monitoring Unit (EMU) iv


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

woreda is Wolita. (95%) and others 5%. The major religious group exist in the area are
Christianity which is 75% the rest are 25%. Regarding language all of them speak Wolita.
There is no ethnic minority or tribal people in and around the project area.

As far as education status concerned about 70% of the head of household has no formal
education of any sort. Only 30% can read and write.

a. Economic Condition and Lively Hood Activity

The primary economic activity and source of income for the majority of the population in the
project affected area is agriculture. Their livelihood depends on crop production. The
common annual crop produced in the project area are Teff ,wheat ,Barely and Maize etc. and
perennial crop such as Enset, Avocado ,Mango ,Sweet Potato ,Potato ,Yam ,Coffee, Banana
,Cassava and Ginger are predominantly grown in the area. Next to crop production live stock
raring is also the source of livelihood in and around the project area. Livestock raring is very
minimal because of shortage of grazing land.

b. Socio Economic Impact of the Project

The major socio economic impact that can be created due to the project is loss of farm land
and loss of income of household they can get from it and demolishing of residential houses.

The project will affect a total of 177 house holds; totally about 335 ha of land will be affected
Due to ROW, access road, tower pad foundation and substation, out of which about 27.67 ha
and 307.33 ha of land will be affected permanently and temporarily, respectively.

The project will not affect cultural historical and religious structures and community and
public infrastructures or institutions.

c. Public Consultation

During census and socio economic survey, a number of consultations were carried out with
PAPs and communities group and selected communities at different location.

The objective of consultation is to fully share the information about the project and its
components and obtain information about the needs of the affected people and the reaction to
the proposed project and to ensure transparent in all activities related to land acquisition and
compensation payment.

During discussions, important points were raised and discussed. The major issues raised
during discussions were the positive and negative impact of the project, compensation option
and income restoration.

D. Institutional Arrangement for the Implementation of RAP

Institutional and organizational arrangement is essential for successful implementation of the


RAP. The over all activities and responsibilities for the implementation of RAP is EEPCO.
For this purpose the main responsible unit with in EEPCo, namely the Gibe III –Sodo 400kV

EEPCo Environmental Monitoring Unit (EMU) v


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

transmission line project office will establish RAP implementing unit for direct and day to
day execution of the activities of the RAP will take place.

Under the resettlement implementation unit valuation committee will be established and
valuation of assets and payment of compensation will be carried out at local level.

The RAP will be implemented along with relevant organization, and grievance redress
committee will be established to address the problem of PAPs during implementation of RAP

The implementation of the RAP will be carried out with the active participation of PAPs and
the local kebele administration and consultation would continue every stage of
implementation process to assess the effectiveness of implementation.

E. Monitoring

Monitoring is the essential activities for the resettlement plan .The main type of monitoring
to be adopted for the purpose of resettlement are internal and external monitoring.

The Environmental monitoring unit of EEPCO will made an internal monitoring of the
proper compensation and implementation of the RAP.

The external monitoring will undertake by environmental protection authority /EPA/. EPA
will undertake all basic supervision on the impact of the project on PAPs and income
restoration, degree of satisfaction of PAPs during implementation of resettlement include
payment of compensation.

F. Implementation Budget and Schedule

The total resettlement implementation cost will be 23,939,240.60 Birr (2,242,278.75 USD).

Table 1: Summary of RAP Implementation Cost

No Items Cost in Birr Cost USD


1 Compensation for permanent land loss due to 162,122.00 15,185.22
tower pad
2. Compensation for Temporary loss of crops Due 709,769.00 66,480.00
to ROW and Access roads
3 Compensation for loss of eucalyptus tree 226,550.00 21,219.90
4 Compensation for losses of perennial crops 15,154,505.00 1,419,452.90
5 Compensation for residential houses 5,000,000.00 468,327.84
Sub total 21,252,946.00 1,990,665.87
Monitoring and valuation
1 Monitoring and evaluation 500,000.00 46,832.70
2 Valuation committee per diem 10,000.00 936.65
Sub Total 510,000.00 47,769.36
Total 21,762,946.00 2,038,435.23
Contingency 10% 2,176,294.60 203,843.52

EEPCo Environmental Monitoring Unit (EMU) vi


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

Grand Total 23,939,240.60 2,242,278.75


Exchange rate dated January 14, 2009
Exchange rate 1 USD =10.6763

G. Implementation Schedule

The following table shows the detail schedule for implementation of resettlement plan for the
Gibe III- Sodo 400 kV HVTL project activities.

Task Months
1 2 3 4 5 6 7
Establish project level resettlement
implementation unit and
Valuation committee formulation
Grievance redress committee formation
Final Inventory of PAPs and
affected assets
Notification on the property rights and
agreement b/n PAPs and the compensation
committee
Consultation with PAPs
Determining compensation rate
PIU finalize budget for compensation and
agreed on mechanism of payment
Compensation payment
Construction of new residential houses

EEPCo Environmental Monitoring Unit (EMU) vii


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

1. INTRODUCTION

1.1 Back Ground of the Project

Ethiopian economy has grown quickly .Along with the speedy development of economy, the
power demand also greatly increased.

The Power demand in the future can be supported with reliable and quality supply of
electricity. EEPCo has a mandate to satisfy the future need of the customers by keeping the
balance between satisfying the power need of the society and the remaining with in the
capability of the Environment.

In order to achieve this objectives /responsibilities, EEPCo has to develop a new power
projects and re- enforce the existing transmission systems ongoing base.

Accordingly EEPCO planned additional transmissions for new power developments which
are under construction. One of the planned transmissions line is, Gibe III – Addis Ababa 400
kV power transmission project which link the generated energy from Gibe III hydro power
project to Ethiopian’s National Grid.

Gibe III -Sodo 400 kV transmission line is one section of the Gibe III-Addis Ababa power
transmission project.

The construction of the proposed Gibe III –Sodo 400 kV power line project can create
various potential adverse environmental and social effects such as involuntary displacement,
disruption of livelihoods and impoverishment. To mitigate these adverse impacts, appropriate
mitigation measures required to be applied. RAP is one of the major means of addressing
these impacts in a planned and coordinated manner.

1.2 Objectives of the Resettlement Plan

The objective of the Resettlement Plan is to provide a plan for resettlement and rehabilitation
of the PAPs so that their losses will be compensated and their standard of living will be
improved or at least restore to the pre- project levels. To achieve these objectives the plan
provides the compensation and rehabilitation measures so that the income earnings potential
of individuals is restored and sustains their livelihoods.

The Resettlement Action Plan (RAP) is also provide details on:-


• the likely impacts resulting from land acquisition for the construction of transmission
line project activities and the mitigatory measures that will be put in place to address
these adverse impacts;
• the policies governing land expropriation, the range of adverse impacts and
entitlements;
• Present strategy for achieving the objectives of the resettlement/ land acquisition
policy;

EEPCo Environmental Monitoring Unit (EMU) 1


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

• a framework for implementation of the stated strategies to ensure timely acquisition


of assets, payment of compensation and delivery of other benefits to project affected
persons (PAP);
• the public information, consultation and participation, and grievance redress
mechanisms in project planning, design and implementation;
• provide identified sources and estimates of required resources for implementation of
the RAP; and
• a framework for supervision, monitoring and evaluation of resettlement
implementation.

1.3 Methodology

The following methodologies were used to prepare the Resettlement Action Plan.
1.3.1 Review Literature

Relevant document and published regulations, guidelines and national policies have been
reviewed.
1.3.2 Census and Socio-Economic Survey

Census and inventory have been conducted to get information required to identify the owner
of the lands and the loss of affected assets with in the proposed project area.

Socio-economic survey also conducted to solicit the opinion of the project affected peoples
about the project impacts and compensation payments.

During the census and inventory, the assessment team was assisted by surveyors and local
daily laborers. The daily laborers can help the team to consult local people with their
language.
1.3.3 Public Consultation

During resettlement action plan process, meaning full consultation has been carried out with
relevant stakeholders including the community members to be affected and kebele
representatives and village elders to fully share the information about the needs of the
affected people and the reactions to the proposed project.

During the discussion, the affected individuals raised questions and provided comments
concerning compensation option and types of compensation they can get.

1.4 Assessment Team

The resettlement action plan study team includes two sociologists( Fikirte kebede and
Alemayehu Desta ) and two Environmentalists (Yohannes Yosef and Kidane Gizaw) from
EEPCo.

EEPCo Environmental Monitoring Unit (EMU) 2


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

2. OVERVIEW OF THE PROJECT

Power is one of the most essential amenities required for the acceleration of Ethiopian
economic development .The Ethiopian economy grows for 5 consecutive years. Along with
this economic growth, the demand for power also increases. In order to meet the need for
power the load in the future can be supported with reliable and quality supply of electricity.
To this effect, EEPCO has a long term strategy to support the government in promoting
social and economic progress through the development of electric power generation and
transmission.

As part of the strengthening of the National Grid, EEPCO has developed serious of high
voltage direct inter - regional links. With the growth of installed capacities and power
demand, the existing transmission facilities are required to be strengthened with additional
400 kV.

Accordingly EEPCo has planned additional transmissions facilities to transmit the generated
power from newly developed hydro powers. One of the planned transmissions is the Gibe III
400 kV –Addis Ababa power transmission line which links the generated energy from Gibe
III hydro power project to Ethiopian National Grid.

The Gibe III-Sodo transmission line is one section of the Gibe III-Addis Ababa. The line will
have two lines of double circuit tower configuration. On one of these lines circuits will be
stranded while on the other only one circuit will be stranded when Gibe IV is realized.

2.1 Description of the Project Components

The proposed 400 kV transmission line is to be constructed between the Gibe III hydro
power project and the newly built Sodo substation. A distance of 65 km with 50 meter wide
Right of Way is required.
2.1.1 Towers

Transmission line conductors are strung on in line suspension tower and bend (strain) towers.
For the proposed 400 kV transmission line between Gibe III hydro power and Sodo
substation, compact cross –rope suspension structure and self supporting towers might be
used. The towers are generally 30-40 meter in height and a total footprint area and
approximately 15 m x 15 m is required. The average span between two towers will be 350 m.
Approximately about 186 towers are required for the power transmission line of 400 kV.
2.1.2 Right of Way /ROW/

The ROW width for a 400 kV transmission line is 50 m i.e. 25 m either side of the center
line .The ROW is required to ensure the safe construction , maintenance and operation of the
power line .

Any farming activities except commercial trees such as Mango, Avocado tree can be
practiced underneath the power line.

EEPCo Environmental Monitoring Unit (EMU) 3


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

No vegetation will be grown above 8 m under the conductor and also no building will be
constructed under the power line.

The minimum distance of 400 kV transmission line from public road is 95 m from the center
line of the structure to the center of the road.
2.1.3 Foundation

The foundation is influenced by the type of terrain encountered as well as the underlying
geotechnical condition .The actual size and type of foundation to be installed will be depend
on the soil bearing capacity . The area required for construction of the foundation will be 12
m X12 m. Foundation will be excavated manually and using machines such as compressor
and excavator. All foundation will back filled, stabilized through compaction, and capped
with concrete at ground level.
2.1.4 Stringing

Stringing can be undertaken mechanically or manually. A pilot cable conductor is used


between towers.
2.1.5 Access Roads

Access road is required to allow access along the entire length during construction and
operation /maintenance phase of the power transmission line. During survey, route line was
designed along the existing road in order to reduce the potential impact associated with the
construction of the new road .Existing roads will be used as far as possible where available.
About 4.5 km (6 m X 4 KM) new access road will be constructed where the existing roads
cannot be used.

The construction of access roads should be in the manner of avoiding permanent removal of
the existing vegetation. All access point and roads will be negotiated with land owners.
2.1.6 Substation

The project will involve the construction of a new substation at Sodo Zuria Woreda Warza
Lasho Kebele which occupies 25 ha of land .The total estimated cost of the construction of
substation is estimated about 9.6 million Birr.

2.2 Project cost

The total cost is estimated for the construction of the project is about 412 Milion Birr

2.3 Route Selection

The final route line is selected after explore different options by EEPCO surveyors keeping
in mind the three basic principles i.e. avoidance, minimization and mitigation. The final route
line has been selected following various factors and comprehensive analysis was carried out
and due consideration was given to agricultural land, social impact number of families
getting affected, and cost of compensation and extent of resettlement.

EEPCo Environmental Monitoring Unit (EMU) 4


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

3. POLICY AND LEGAL FRAMEWORK FOR LAND ACQUISITION,


ACTIVITY AND USE

3.1 Policy framework

The constitution to the Federal Democratic Republic of Ethiopia, National Policies, Laws,
Regulations and Institutional Frameworks regarding expropriation of land for the
development project has been reviewed.

Land required for the construction, operation and maintenance of the project shall be
allocated to the project by the government.

3.2 Constitution of FDRE

Constitution of the Federal Democratic Ethiopia Proclamation 1/1995 contains several


relevant policy legal and institutional frame works that have direct relevant with the
expropriation procedures for those people who might be affected by the proposed project.

The Constitution addresses the land owner ship and holding right. Article 40.3 of the
constitution provides the right to ownership of both rural and urban land as well as natural
resources to government and the people of Ethiopia.

It further states that land is the common property of Ethiopian people and can not be subject
to sale or to other means of exchange .In addition; article 4015 of the constitution guarantees
the right of farmers to obtained land with out payment and protection against eviction from
their possession. The detail implementation of this provision is to be specified by subsequent
laws.

The ownership of land is vested in the state and this people of Ethiopia. The rural and urban
dwelling have only usufruct right over land this right gives to the people, the right to use the
land and benefit from the fruits of his /her labor, which may be crops, trees ,etc found on the
land or any permanent works such as buildings etc, any interference on the use fractural
rights such as expropriation shall entail compensation, this is clearly provided in Article 40.7
of the constitution which says that every Ethiopian shall have the right to the immovable
property the buildings and to the permanent improvement are bring s about on the land by his
labor or capital the owner of that right is entitled to compensation and the detail
implementation shall be determined by law.

Article 40.8 of the constitution strengthens this by providing for expropriation of private
property for public purpose requires advance payment of compensation. The detail
implementation of this provision is also left to be determined by subsequent law.

The resettlement /rehabilitation policy framework prepared by EEPCo also expresses


appropriately and recognize these constitutions and they are the basis for the compensation
procedures and the legal framework for the resettlement and rehabilitation policy of EEPCo
(EEPCo 2006, Page 3).

EEPCo Environmental Monitoring Unit (EMU) 5


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

In the course of the preparation of resettlement and rehabilitation action plans as it is stated
clearly in the constitution ( Article 35.6 ; 43.2 and 92.3 ) , all affected stakeholders – special
attentions should be given to project affected women – need to be appropriately consulted to
participate them and identify their needs and interests including determination of the amount
of compensation required .

3.3 National Policy of Women

The Federal Democratic Republic of Ethiopia has declared its unequivocal commitment to
the development of women with announcement of the national policy on women in 1993.
The women’s policy primarily aims to institutionalize the political, economical and social
rights of women by creating an appropriate structure in government offices and institutions
so that the public policies and interventions are gender – sensitive and can ensure equitable
development for all Ethiopian men and women.

Consistent with the above policy, Article 25 of the new constitution guaranties all persons
equality before the law, and prohibit any discrimination on grounds of gender. In addition,
Article 35 reiterates principles of equality of access to economic opportunities, including the
right of equality in employment and land ownership. The democratization process, the new
constitution, the women’s policy and the institutional set up have created conducive
atmosphere for the promotion and the advancement of women and the implementation of the
plan of action.

The policy states that the responsibility of ensuring the implementation of the National
Policy on Women lies mainly with the Government. Besides, various women’s organizations
are formed to promote women issues in different areas.

All development programs at national and regional levels should be able to integrate gender
concerns in their plans and program to see that women participate, contribute, benefit and
their effort is recognized and technologically supported. Thus the mainstreaming of gender in
all development programs should focuses at establishing a system where by each sector
program would use gender as a measuring indicator to quantify project and achievements. To
this effect, the resettlement planners should have referred the Women Policy during the
preparation of this RAP report.

3.4 Environmental Policies

The environmental policy of FDRE was approved by the Council of Minister in 1997. The
policy contains sectoral and cross-sectoral policies including provision required for the
appropriate implementation of the policy it self.

There are relevant elements regarding compensation plan incorporated in cross-sectoral


policies documents. The policy element, which is relevant in the preparation of compensation
plan, is community participation and the management of environment and monitoring and
evaluation during all phases from the project conception to planning and implementation are
undertaken based on the decision of resource users and managers.

EEPCo Environmental Monitoring Unit (EMU) 6


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

3.5 Review of Laws and Regulation

3.5.1 The Rural Land Administration and Utilization Proclamation

The constitution of FDRE leaves the detail implementation of the provisions concerning
tenure rights over rural land to be determined by subsequent specific laws to be issued at both
the federal and regional levels. Accordingly, The Rural Land Administration and Land Use
Proclamation No. 456/2005 was issued in o 2005 to further determine the land use system
and land us e rights in the country or at the federal level. The proclamation provide that land
administration laws to be enacted by regions should be based on the provisions provided
therein and specifies the basic principles of rural land distribution and utilization including
the scope of land use rights with regional laws should grant. Similar to the constitution, the
proclamation provides that peasants and nomads (pastoralists) shall have the right to get rural
land free of charge the size of which shall be determined based up on the specific local
conditions

Accordingly, Southern Nation And Nationality Peoples Regional State /SNNPRS/ has
enacted its own proclamation regarding land administration and utilization to replace
proclamation No.55/ 2001. Since the proposed project is with in the SNNP Regional States
that subject to Resettlement Action plan, the proclamation provides the right of access to
rural land free of charge for those who lives depend on agriculture and who are aged 18 years
or above (Article 5.1). The land holder has the right to use the land for life long for
agricultural purpose or lease the land to the third party or bequeathed it to his /her heirs.

The proclamation in Article 19.1 provides that where the land is required for public use, the
land holder has the right to compensated for their assets on the land or tree, crops cultivated
on land including the right to be compensated similar land. The responsible organ designated
in the proclamation itself, as the land administration and utilization office.
3.5.2 Expropriation and Compensation of Property

3.5.2.1 Land Tenure

According to the Constitution December 1994, Land holding right became under the control
of the people and Government of Ethiopia. Article 40 states that ownership of both urban and
rural land is vested in the state of and the people, and common property, which is not subject
to sale or other means of exchange. Peasants have the right to obtained land with out
payment and are protected against eviction from land in their possession.

3.5.2.2 Expropriation of Land Holding for Public Purpose

According to the Constitution of FDRE, full right to immovable property and permanent
improvement to the land is vested in individuals who have built the property or made the
improvements but government may expropriate such property for public purpose, subject to
the payment in advance of compensation commensurate to the value of the property or
alternative means of compensation including relocation with adequate state assistance.

EEPCo Environmental Monitoring Unit (EMU) 7


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

Thus project plans would include an attractive and sustainable compensation strategy,
offering adequate compensation and incentive to the loss of livelihood.

More relevant for this specific project, the 1960 civil code (article 1446) provides that if land
is owned by the state or other administrative bodies from part of the public area, the
competent authority may, by way of expropriation proceedings obtain the land necessary for
the construction of the project.

The proclamation on Expropriation of Land and Compensation No 455/2005 implied


repealed the outdated provisions of the Ethiopian Civil Code of 1960 regulations land
acquisitions and compensation for the purpose of public project. It is a new legislation
established detail procedures setting the time limits with in which land could be acquired
after a request is received from a proponent, principles for assessment of compensation for
properties on the land as well as for displacement compensation.

It also empowered the Woreda administration to established valuation committees to value


private properties. In the case of public owned infrastructures to be removed the barriers for
planned land acquisition, substantially raised the amount of compensation payable to
expropriated owners of properties and displaced people.

Recently regulation No 135/2007 payment of compensation for property situated on land


holdings expropriated for public purpose is issued for the proper implementation of the
proclamation No. 455/2005 Expropriation of land holdings for public purposes and payment
of compensation .These regulations issued for the purpose of not only paying compensation
but also to assist displaced persons to restore their livelihood.

This regulation set forth details to determine the amount of compensation for different assets
found on land holdings expropriated for public purpose and stipulated the formula to
calculate the amount of compensation payable for different assets.

3.5.2.3 Compensation

Regarding the determination of compensation in part three, article 7 of the proclamation


No.455/2005, the basis and amount of compensation is clearly explained in Article 7(1) a
land holder whose holding has been expropriated shall be entitled to payment of
compensation for his property situated on the land and for permanent improvements he made
such land

Article 7(2) states that the amount of compensation for property situated on the expropriated
land shall be determined on the basis of replacement cost of the property.
Under article 8(1) of this proclamation a survival land holder whose land holding has been
permanently expropriated shall in addition to the compensation payable under article of this
proclamation is paid displacement compensation, which shall be equivalent to ten times the
average annual income he secured to bring the five years preceding the expropriations of the
land.

EEPCo Environmental Monitoring Unit (EMU) 8


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

All PAPs and organization (whether public or private) that loss houses crops or sources of
income will be compensated or rehabilitated according to the type and amount of their losses.
The cut –off date for compensation eligibility will set once all detailed measurements have
been completed; compensation will also not be paid for any structure erected .or crops and
trees planted purely for the purpose of gaining additional compensation. Cultivating land,
constructing settlement in project affected areas after the cut of date will not be eligible for
compensation or subsidies.

3.6 World Bank Policies and Procedure for Involuntary Resettlement

World Bank issued an operational policy on involuntary resettlement 4.12 in 2002, which is
applied to all World Bank financed resettlement 4.12 is 2002, which is applied to all World
Bank financed projects. The World Bank’s O.P 4.12 underlines the need to identify,
understand and mitigate various “impoverishment risk social cultural economic, and
environment that may arise as a result of a development project that entails displacement of
people. The three cores objectives of the O.P 4.12 on involuntary resettlement are the
following.

• Involuntary resettlement should be avoided where feasible , or minimized exploring


all viable alternative project designs.

• where us bit feasible to avoid resettlement ,resettlement activities should be


conceived and executed as sustainable development programs, providing sufficient
investment resources , to enable the persons displaced by the project to share in
project benefits, displaced persons should be meaningfully consulted and should have
opportunities to participate in planning and implementing resettlement programs.

• Displaced persons should be assisted in their effort to improve their livelihoods and
standard of living or at least restore them, in real terms, to pre displacement levels or
to levels higher.

• National policies and legislations are in conformity with the criteria set by the World
Bank there fore, EEPCo also committed to adopt the World Bank policies O.P4.12
and BP4.12 in its power development projects that involve resettlement.

3.7 The African Development Bank Involuntary Resettlement Policy

The AfDB involuntary resettlement policy has been developed to cover involuntary
displacement and resettlement of people caused by a Bank financed project and it applies
when a project results in relocation or loss of shelter of the persons residing in the project
area , or their assets being lost or livelihoods being affected.

The primary goal of the involuntary resettlement policy is to ensure that when people must
be displaced they are treated equitably, and that they share the benefits of the project that
involves their resettlement. The objectives of the policy are to ensure that the disruption of
the livelihood of people in the projects area is minimized; the displaced persons receive
resettlement assistance to improve their living standards and to provide explicit guidance to
Bank staff and to borrowers, and set up a mechanism for monitoring the performance of the

EEPCo Environmental Monitoring Unit (EMU) 9


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

resettlement programs. The policy emphasizes that the resettlement plan should be prepared
and based o n a development approach that addresses issues of the livelihood and living
standard of the displaced person as well as compensation for loss of assets, using a
participatory approach at all stages of project design and implementation.

The policy among others states that compensation at the full resettlement cost for loss of land
and other assets should be paid prior to projects implementation with the view to improve the
former living standards, income earnings capacity and production levels of the affected
population. The borrower will be required to prepare a full resettlement plan for any project
that involve a significant number of people ( 200 or more persons) who would need to be
displaced with a loss of assets , or access or reduction in their livelihood.

3.8 EEPCo’s Strategies for Expropriation and Compensation

It is objective of EEPCo to avoid or reduce the environmental and social impacts of its power
projects to a minimum level. If adverse social impacts to be occurred are unavoidable,
EEPCo will open consultation with PAPs and perform legal compensation for loss of all their
properties. To achieve the social mitigation goal EEPCo will allocate adequate budget for
compensation before the project implementation.

EEPCo in consultation with the administration of regional state governments, zones,


Woredas and Kebele associations shall establish property valuation committee to properly
implement compensation payment for PAPs on time before the start of the project
construction activities.

3.9 The Federal Democratic Republic of Ethiopia and Administration Regions

The federal democratic republic of Ethiopia (FDRE) was formally established on August 21,
1995. The FDRE comprises o f the federal states with 9 Regional state members. The new
government structure takes power from the center to regions and localities. The relative roles
of government at the different level (Federal, Regional and Local) in terms of power and
duties, including on fiscal matters, have been defined by the constitution, proclamation Nos.
33 of 1992 , 41 of 1993 and 4 of 1995. Under these proclamations duties and responsibilities
of regional states include planning, directing and developing social and economic programs,
as well as the administration, development and protection of resources of their respective
regions.

EEPCo Environmental Monitoring Unit (EMU) 10


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

4. EXISTING SITUATION OF THE PROJECT AREA

4.1 Location and Administration Setup

The Gibe III–Sodo 400 kV transmission line project located in Southern Nation
Nationalities Regional States /SNNRS/ of Wolita Sodo Zone. The line cross three Woredas
namely Sodo Zuria, Damote Sore and Kindo koyisha .

4.2 Population and Demographic Characteristics

About 406,283 people live in the three Woredas of Sodo Zuria ,Damot Sore and Kindo
Koyisha.The average family size for all the affected Woreda is 7 which is more than the
national averages 4.8. The average population density is 501.93 Persons per km squared with
regard gender proportion of current population constitutes 51% female and 49% male. The
population growth rate estimated about 2.9 %.

Table -1: Number of people around the project affected woredas

Region Woredas Population Population density


People/ Km2
Sodo Zuria 197,005 418
SNNPRS Damote Sore 122,279 681.0
Kindo koiysha 86,999 243
Total 406,283

Source: Socio –Economic Survey, 2001

4.3 Religion, Ethnicity and Language

The project area is characterized by a great deal of ethnic and religious diversity. About
three ethnic groups live in the project Woredas .The major ethnic group in the project
affected Woreda is Wolita (95%) and the rests 3% are Amhara and 2% Kembata. The major
religious group exist in the area are Christianity which is 75%. The remaining 20 % and 5%
are musilims and other traditional religions respectively. Regarding language all of them
speak Wolita. There is no ethnic minority or tribal people in and around the project area.

4.4 Economic Conditions and Livelihood Activities

Agriculture is the dominant economic activity in the project area. Farming and livestock
raring are the basic livelihood of the people in all project affected Woredas. The farming
system and pattern of agricultural production vary based on the nature of agro ecology. The
project affected area classified traditionally in to three categories Dega (highland),
Woinadega (mid –altitude and Kola (low land). Sodo Zuria and Damote Sore Woreda are
part of the Dega (highland) and Woinadega /mid altitude/ and characterized by the farming
system with combination of enset as a co -stable with cereals and tubers .The Enset based
farming system is found in the highland between 1,600 and 3000 m.a.s.l. where as kindo

EEPCo Environmental Monitoring Unit (EMU) 11


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

koiysh Woreda is belongs to kola /low land and their farming practice is differ from Sodo
Zuria and Damote Sore. They mostly produce maize and sorghums.

The common annual crop produced in the project area are Teff ,Wheat ,Barely and Maize
etc. and perennial crops such as Enset ,Avocado ,Mango ,Sweet Potato ,Potato ,Yam ,Coffee,
Banana ,Cassava and Ginger are predominantly grown in the project area .
Climate and temperature Rain fall Temperature Elevation
Woreda Kola W/Dega Dega Range Min Max m.a.s.l
co co
Kindo Koyisha 54% 39% 7% 400-1400 25 41 620-2680
Damote-Sore 20% 65% 15% 800-1300 25 28 1800-2100
Sodo Zuria - 87% 13% 100-1350 11 28 1500-2980

Table -2: Climate and Temperature Condition of the Project Affected Woreda

Source: Socio –Economic Survey, 2001

4.5 Land Use and Land Cover

The topographic nature of the project area is characterized by undulating hilly with elevation
range from 620-2980 m.a.s.l. The main land use and cover identified in the project area is 88
% farmland, 18 % grazing land and the remaining 6% are forest and un used land.

4.6 Access to Social Services

4.6.1 Access to Medical Facilities

The available health institutions and health personnel of the Woreda is surveyed. The
information obtained from Woreda health bureau shows that about 50 % of the people have
access to medical services.

The available health institution and health personnel of the affected Woredas are presented in
Table 3.

EEPCo Environmental Monitoring Unit (EMU) 12


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

Table -3: Health Institutions and Personnel’s

Health institution Sodo Zuria Damote Sore Kindo Total


Koyisha
Hospitals - - - -
Health centers 1 2 3 6
Health posts 28 20 28 76
Total 29 22 31 82
Health personals
Doctor - - - -
Health officer 2 1 1 4
Nurses 35 25 19 79
Health Extension 26 20 31 77
Pharmacy tech. 4 2 1 7
Lab .tech. 3 1 2 7
Sanitarian - - - -
Total 70 49 54 174
Health coverage 53.6% 61% 80%
Source: Socio –Economic survey, 2001

As shown Table 3 above, there are about 76 health post and 6 health centers in different
kebeles including the project affected kebeles. Taking the total population of the Woreda
which is 406,283, the number of people per health station is estimated at 1806. This indicated
that the health coverage is above the national standard which is 10,000 people per health
station.
4.6.2 Access to Education

About 95 primary and secondary and high schools found in the project Woredas and 1039
teachers. The survey result shows that 97% of the people have access to primary and
secondary school.

Table- 4: Number of Schools in Project Affected Woredas

Kebele Type No. of schools No.of Educational


teachers coverage
Sodo Zuria Primary and 34 578 98
Secondary
schools
Damote Sore ” 31 261 110.6
Kindo koiysha ” 30 200 95
Total 95 1039
Source: Socio –Economic Survey, 2001
4.6.3 Access to Water Supply

Protected water supply is available with in project affected kebeles. Most of the people live
in this kebeles use safe water (spring, Pipe water, pond water and hand dug well) for drinking

EEPCo Environmental Monitoring Unit (EMU) 13


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

however the distribution of clean water supply is not adequate. Most of the families travel
long distance to fetch drinking water. The water supply coverage in the Sodo Zuria Woreda
is 57 %, Damote Sore 42.23% and kindo koyisha 21%.
4.6.4 NGOs Working In and Around the Project

Kale Hiwot, Inter Aid, Massy Foot Treatment Association and SOS Sahil Ethiopia are
working in the project affected Woredas on the area of rural water supply, provision of
educational and health services on HIV/AIDS, family planning, soil conservation, rural road
construction, provision of credit facilities etc.

The credit facilities provision mainly focus on supporting female headed households and the
poorest those who have no oxen.
4.6.5 Access to Agricultural Support Services

Farmers have access to get fertilizers and selected seeds from the Woreda Agricultural and
Rural Development Offices. They can get credit facilities for those who couldn’t afford to
buy fertilizers and selected seeds. They also get advice from agricultural experts to improve
the productivity of agricultural products and management of natural resources.

EEPCo Environmental Monitoring Unit (EMU) 14


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

5. SOCIO- ECONOMIC CONDITIONS OF THE PAPS

Socio -Economic survey carried out to assess and evaluate the economic resources base and
socio economic conditions of the PAPs and to understand the socioeconomic characteristics
feature of the affected households, and also their attitude and preference for rehabilitation.
The main objectives of the socio economic survey are:
• to collect baseline demographic and socio economic characteristics of affected
household whose land are being acquired ;
• to categorize the PAPs under different categories for various benefits and
entitlements ;
• to assess the peoples reaction towards the project and ascertain their preference
for resettlement and rehabilitation; and
• to suggest appropriate rehabilitation action plan for improving /restoring the
living standards of affected families.
As per the survey 177 households (1,350 families) are getting affected due to the acquisition
of land for the project. These households are distributed with in three Woredas namely Sodo
Zuria, Demote Sore and Kindo Koiysha. In terms of the geographical distribution of the
project affected households, the majority of the households 96 households (640 families) are
residence of Kindo Koisha.

The majority of the project affected households are male headed 173 (98 %) and only
4 (2 %) are female headed.

5.1 Age-wise Distribution of Members of Affected Families

The distribution of the members of the project affected families (PAFs) based on the age is
presented in Table 5 shown below.

Table -5: Age Distribution of the Project Affected Woredas

No. Age Group No. %


Children and Students less than 18
1 years 1173 87
2 Workers (18-64 years) 172 12
3 Old Persons (More than 65 years) 5 1
4 Total 1350 100
Source: Socio –Economic Survey, 2001

It can be seen from the above table that the majority of the affected persons (87 %) are
children and students who are economically dependent age groups. Considering the fact that
some of these families will lost their land partially and the existing land holding size of each

EEPCo Environmental Monitoring Unit (EMU) 15


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

family will become very small and as a result their livelihood is likely to be severely
affected. Therefore, it is necessary to compensate these families appropriately.

As the socio economic survey identified, only 1% of the affected groups are olds. These
groups could be considered vulnerable as they will be adversely affected by the project.
Members of such groups require a special assistance to restore their income and livelihoods.

5.2 Distribution of the Affected Families by Religion

The families affected due to the acquisition of land in the village are all belongs to Protestant
and Orthodox Christian.

5.3 Educational Status of the PAPs

With respect to educational status of the heads of the households, result of the survey
indicates that almost all (58.8 %) of the head of the households have no formal education of
any sort. Only few of the head of households (22.6 %) reported that they have primary
education, 18% have secondary education and only 0.5% have collage diploma.

5.4 Housing Conditions of the PAPs

Socio- economic assessment has carried out on residential conditions of the PAPs to
understand their living conditions and quality of life. The survey result shows that the
majority of are living in their own houses made from mud and wood wall and grass roofed.
The local name of this type of house is called Wolita. Some of the affected families also live
in houses made from wood and mud wall having corrugated iron sheet roof.

5.5 Livestock

The primary occupation of the PAPs is agriculture. In addition raring of livestock is a


supportive occupation. So that, it is important to consider the livestock owned by PAPs. The
PAPs own a variety of livestock such as oxen, cows, sheep, donkey etc. However due to the
prevalence scarcity of grazing land in the project area, the amount of livestock is relatively
low.

5.6 Average Land Holding Size

Land is one of the most important assets among the PAPs households and land based
economic activities are the major source of livelihoods to the households. Result of the
census survey revealed that in average, about 44 .25 ha of farmland owned by 177 project
affected households.

The overall average land holding size for the project areas is 0.25 ha per household which is
small that of the national average of about 1 ha /household.

EEPCo Environmental Monitoring Unit (EMU) 16


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

5.7 Crop Production

The result of the survey reveals that, the farmlands are used for cultivation of different kinds
of crops; such as, Maize, Wheat Barley, Sorghum, S/potato, etc. Among these s/potato is
dominantly produced followed by potato (26%) and maize (20%).

Table -6: Average Yield per Hectare

No. Type of Annual Crops Yield per hectare in quintal


1 Maize 24
2 Wheat 18
3 Barely 12
4 Teff 7
5 Sorghum 11
6 Potato 69
7 S/Potato 107
8 Boye 105
9 Cassava 90
Average Yield 49
Source: Socio –Economic Survey, 2001

5.8 Source of Livelihood of the Affected Families

Household survey revealed that the primary economic activity of the PAPs is agriculture.
They obtain their income and livelihood from agriculture based economic activities like crop
production. Most of the PAPs use their product for household consumption. They sell only
some amount of crops for purchasing cloths and other consumer goods such as kerosene,
food oil, salt etc. Agricultural product contributes 99 % of annual household income.
Therefore, the loss of income is based on the loss of average land holding.

According to the collected data on the PAFs’ income for the past two – three years, the
average production of crops per the affected families is about 49 Quintals of cereals and root
crops per hectare per year i.e., Birr 23,520.00 (49 Quintals x 480 Birr).

The average land holding size of the project affected families is 0.25 ha. The average income
they can earn from 0.25 ha of land per Annum is Birr 5,880.00 (12.25 Quintals x 480 Birr

Next to crop production live stock raring is also the source of the livelihood in and around
the project area. However, as there is shortage of grazing land in the project area, the share of
annual income that could be collected from livestock raring production is only one percent.

EEPCo Environmental Monitoring Unit (EMU) 17


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

Table- 7: Average Annual Income of the Affected Household

No Source of income Birr


1 Average annual agricultural income 5,880.00
Average annual income from other sources (from selling of
2 3678.00
cash crops, goats and ships etc. )
3 Total average income of household 9,558.00
Source: Household Survey, 2001

Most of the PAPs lose their agricultural land temporary due to ROW and access roads.
Therefore, the agricultural income lost due to these activities expected to be about 13 quintals
/ha /year in a normal rainfall years. The survey has also identified that a number of PAPs
will lose insignificant size of their total land holdings permanently due to the tower
foundation.

5.9 Summary of the Findings of the Socio-Economic Survey

The major observations of the socio-economic survey of the PAFs are summarized below:

About, 335 ha of land will be affected due to ROW, access road, tower pad foundation and
Substation, out of which about 27.67 ha of land will be affected permanently and 307.33 ha
of land temporarily.

Almost all PAFs belong to Wolaita ethnic group

Most of the families live in houses made up mud and wood wall and grass roofed houses.
About 133 Tukuls (grass roofed) and 59 houses (Tin roofed) would be affected due to the
ROW.

Most of the families are predominantly agriculture oriented.

The present landholding size is small to meet their essential needs.

The above factors are given due weight during the preparation of Resettlement
/Rehabilitation Action Plans (RAPs).

EEPCo Environmental Monitoring Unit (EMU) 18


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

6.2 Impact on Housing Structures

A total of 192 housing structure (133 grass roofed and 59 tin roofed houses) will be affected
by the construction of the transmission line.

Table -9: Type and Number of Affected Residential Houses.

Type of houses Sodo Damote Kindo Total


zuria Sore koiysha
Tukuls (hut) 13 41 79 133

Corrugated iron roof Mud 7 26 26 59


and wood wall /houses /
Total 20 67 105 192
Source: Socio –Economic Survey, 2001

Photo-1: Partial View of the Affected Houses and Tukuls

6.2.1 Impact on public and community institutions

The socio economic survey made to the project area and discussion held with affected
Woreda representatives and community elders indicated that the proposed Gibe III –Sodo
transmission line construction will have no impact on social services facilities like public
buildings, schools, health facilities, water supply and religious institutions (churches
mosques). Therefore, no compensation measures will be required.
6.2.2 Impact on Perennial Crops and Trees

Farmers in the project affected areas cultivate a large number of crops on small plots of land
includes cereals, enset and other root and tuber crops, fruits and other trees. One of the major
impacts on PAPs is loss of perennial crops and trees.

A total of 26,892 trees will be affected due to the ROW. Different types of trees to be
affected are Eucalyptus, Juniper /Tid/ and others. Among those types of affected trees, coffee
tree is the largest constitutes about 33.6% of the affected trees.

EEPCo Environmental Monitoring Unit (EMU) 20


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

6. SOCIO - ECONOMIC IMPACT OF THE PROJECT

Construction of the proposed Gibe III –Sodo 400 kV transmission line involved the
demolishing of some houses and loss of annual and perennial crops and trees with in the 50
m wide ROWs.

Socio - economic survey and census and inventory of project affected properties and assets
are conducted within the proposed project affected Woredas to determine the exact number
of affected persons and the extent and nature of impacts.

The findings of the survey revealed that about 177 households are identified to be affected by
the project and most of them will lose their farm land partially. About 192 residential houses
will be affected by the project, and consequently there will be physical displacement.

However, as the project is linear one, the households who lose their houses could be able to
construct their houses at the remaining plot of land with out any resettlement or relocation
.For those who have no enough area to build own houses, there could be a need to relocate
them in short distance from the ROW or (the same location of Wolita Zone) so as to reduce
the social disruption due to resettlement. (See a census of affected persons and their affected
assets in Annex 1)

6.1 Impact on Household Assets

6.1.1 Impact on Farmland

Land is the main asset and source of livelihood for the PAPs. The project affected Woredas
are characterized by acute shortage of farming land, very small and fragmented land holdings
and intensive farming system. The average land holding size of the PAPs is only 0.25 ha. The
existing land use of the project will be affected due to ROW, foundation for towers, access
roads and substation construction which cause temporary and permanent loss of crops and
vegetation clearance.

The number of project affected households and the amount of land they will lose is
summarized in Table -8.
Table- 8: Affected Land in ha by Crop Category
No of HHs Total
Woreda affected Land affected in ha by crop type affected
by project land in ha
Annual Perennial Eucalyptus
crops crops tree
Sodo zuria 20 23.5 5.9 1.5 30.9
Damote sore 67 16.72 9.70 1.1 27.52
Kindokoiysha 105 55.99 13.8 1 70.79
Total 192 96.21 29.40 3.6 129.21
Source: Socio – Economic Survey, 2001

EEPCo Environmental Monitoring Unit (EMU) 19


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

Table- 10: Impact on Perennial Crops and Trees

Perennial crops Woredas total


and trees Sodo Zuria Damote Sore Kindo Koiysha
Euclaptus 727 1749 727 3205
Tid - 677 207 884
coffeee 347 6253 2430 9030
Mango 13 121 51 185
Avocado 56 163 200 419
Banana 9 3719 469 4197
Enset 371 5365 3236 8972
26892
Source: Household Survey, 2001

6.3 The Extent of Impact on the Land Use

Land is the most important source for the PAPs whose livelihood is mainly depend on small
holder farming. In the project affected Woredas, land is scarce and most valuable assets due
to the high population density and the intensive nature of the farming system.

The construction of the transmission line will cause permanent and temporary loss of land.
The permanent loss of land occurred due to tower foundation area and substation which is
about 27.67 ha .On the other hand, 322.65 ha of land would be affected temporarily due to
the creation of ROW and temporary access road construction.

The total number of PAPs affected due to the land acquisition for the project purpose is 177
(1,239 families). On the whole, 0.3 % of the people are affected out of the total population of
the three affected Woredas. Damote Sore is the most affected Woreda in terms of number of
affected households and magnitude of affected assets and properties.

Since the project is linear, most of the households will lose their land partially. The amount
of permanent land loses for each household due to the occupation of tower foundation is less
than 0.01 ha which 4% of the total land holdings .Hence, the significant of the impact is very
minimal.

Table -11: Summary of Impacts on Households Assets by Woreda

No. Woredas No. of affected Affected trees


residential houses
(Tukuls and tin roofed ) Eucalyptus Tid

1 Sodo Zuria 20 727 -


2 Damote Sore 67 1749 574
3 Kindo Koiysha 105 727 197
Total 199 3,205 771
Source: Household Survey, 2001

EEPCo Environmental Monitoring Unit (EMU) 21


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

6.4 Impact on Vulnerable Groups

About 3% of the project affected households are identified as vulnerable groups of which 2%
are female headed households and 1% old age above 65 years old. These groups shall be
considered for additional assistance and need special attentions to ensure that they are
supported to be benefited from compensation entitlement and other mitigation measures.

7. PUBLIC CONSULTATION

Information disseminated and consultations with the PAPs were carried out with PAPs and
communities group and selected communities at Shamba and Kuto Surfelo Kebeles in
February 26, 2000.

Besides, meeting was held with local officials and representatives from relevant offices such
as agricultural and rural development, land administration and utilization, and representative
from Kebele officials.

Consultation helps to reduce the potential conflict, minimize the risk of project deliyance and
also enable the project to include resettlement as a comprehensive development program to
suite the needs and priorities of the PAPs.

The main objective of consultation is to fully share the information about the project and its
components and obtain information about the needs of the affected people and the reaction to
proposed project and to ensure transparent in all activities related to land acquisition and
compensation.

During the discussion the important points were raised and discussed. The major issues
raised during discussion were the positive and negative impact of the project, the issue
related to compensation payment, the manner and procedure of compensation payment for
the expropriated land compensation.

The findings of the consultation indicated that the opinion of the peoples about the project is
very encouraging and positive. The consulted people believe that it is one of the development
projects of the government that will definitely improve the existing condition in and around
the project and create employment opportunity for the local people.

Small group meetings and regular interaction with PAPs will be going on and to be continued
during the course of compensation. (See Consultation Minuets of meeting in annex II).

EEPCo Environmental Monitoring Unit (EMU) 22


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

8. ENTITLEMENT MATRIX AND ELIGIBILITY OF PROJECT AFFECTED


PERSONS

This section provides a framework for entitlement for each category of impacts that have
discussed in the previous sections.

To determine the eligible person for compensation EEPCo takes in to account the National
Proclamation and Regulations and the Criteria set by the World Bank contained in op 4.12 of
the WB Operational Manual.

Therefore, the criteria for eligibility for affected persons contained in OD 4.30 and the
National Proclamation No 455/2005 are adopted i.e. those who have formal legal right to
land and lawful possession over the land to be expropriated and owns property situated there
on.

To this effect, census and inventory of lost assets and property is conducted. The date of
census has established for the cut off-date to record the PAPs in a project area.

A person who occupies the land after the completion of inventory of affected households and
assets will not be eligible for compensation for the lost assets and /or resettlement and
rehabilitation.

Entitlement matrix below defines the eligibility for compensation and rehabilitation
assistance for impacts /losses for different types of assets for different category of project
affected persons.

8.1 Basis for Valuation of Losses

The Ethiopian legislation has well developed laws and regulation defining the basis to be
used for valuation of type of loss due to development projects. The principles of the
legislations include;

• Provide equivalent replacement land for long term losses;


• Compensating for any losses in net income; and
• Focus on restoring annual income.
Based on the compensation proclamation, EEPCo will employ the principle of replacement
cost and compensation at market cost for valuation of lost assets.

Replacement cost approach is based on the premise that the costs of replacing productive
assets that have been damaged because of project activities. The approach involves direct

EEPCo Environmental Monitoring Unit (EMU) 23


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

replacement of expropriated assets and covers and amount that is sufficient for asset
replacement.
The process and the necessary action to be taken will be concluded after consultations with
Woreda administration and EEPCo and the entire exercise of valuating the affected assets
will be done by valuation committee.

Compensation for loss of crop calculated on the basis of;

• unit rates of compensation for loss of crops;


• measure the size of land for each type of crop (in square meter or hectare );
• quantify the amount of agricultural production in kilogram ,per hectare or per meter
square ;and
• use current market price for each crop type per kilogram ;and finally
• Calculate the amount of compensation payment based on the type, size and quality of
each type of crop production.

EEPCo Environmental Monitoring Unit (EMU) 24


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

Table -12 Summaries of Principle and Methods Used for Valuation of Assets for Compensation Purpose.

No Type of property Valuation principle Formula For calculation of compensation Remarks


rates

1 For land (displacement A) If vacant land is available, land and cash, by adding Land is provided as replacement of Constitutionally land is
Compensation for land up costs spent for land improvement, has been expropriated land capable of serving a not valued. rather the
on which annual and compensated for the land used to grow crops or similar purpose ,and monetary benefit gained from the
perennial crops are perennial crops. Displacement compensation shall be compensation in equivalent to the annual use of land is evaluated
grown) paid in equivalent to : average income earned from the total land at market price as these
expropriated .this would be generated stated in the principle s.
a)in equivalent to the price of the annual average yield through the following formula thus compensation for
of crops obtained from the land or the loss of annual crops
(area of land in Ha .X productivity of and perennial crops are
b) The price of the annual average yield of crops crops) X price of crops )+cost of used for the valuation of
multiplied by the number of years required to attain the permanent improvement on land the benefit gained from
level of growth of the perennial crops. the expropriated land
Value = ((area of land in Ha. X
B) If there is no vacant land, monetary compensation is productivity of the crops) X Price of the
provided ten times the price of the average yield of crops)) X10 +cost of permanent
crops or perennial crops obtained from the land and improvement on land.
added up the cost spend for land improvement.
Land and cash is paid if vacant land exist ;by applying
the following principles ; Area of land in Ha .X productivity of
2 For annual crops land is provided as replacement of the land lost; crops) X Price of crops) +Cost of
monetary compensation shall be made in equivalent to permanent improvement on land.
the price of the annual average yield of crops obtained
from land
The compensation shall be paid in monetary if there is
no replaced land. Value =((area of land in ha .X productivity
of the crops ) X price of crops ))X10 +cost
Monetary compensation shall be provided ten times of permanent improvement on land
the price of the average yield of crops obtained from
the land ,and added up the cost spent for land
improvement ;

EEPCo Environmental Monitoring Unit (EMU) 25


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

No Type of property Valuation principle Formula For calculation of compensation Remarks


rates
Land and cash is paid if vacant land exist ; by applying For ripe perinial crops
3 For perennial crops the following principles
Value (area of land in Ha X productivity
• Land is provided as replacement of the land lost of the perennial crops) X number of years
• Monetary compensation shall be made in required to ripe) X price of the crops.
equivalent to obtained from land, an the no. of Based on this , the following formulas are
years required to ripe ,plus the cost spend on deducted
permanent improvement on land;
Value, ( ( the annual yield of the perennial
The compensation shall paid in monetary if there is no crops in kilogram )The current price of the
replaced land produced of the perennial crops ))) x 10 +
cost of permanent improvement on land.
Monetary compensation shall be provided on the basis
of The perennial crops has not yet started giving For unripe perennial crop
annual yield, the similarly crops or perennial crops
from a similar area of land in the locality of the last Value ,( number of plant (legs) cost
five years would be used for valuation .if there is no incurred to grow an individual plant )+ cost
vacant land , monetary compensation is provided ten of permanent improvement on land
times the price of the average yield of crops or
perennial crops obtained from the land , and added up
the cost spend for land improvement .

Number of trees at different level of


4 Trees The amount of compensation for trees shall be growth price per trees.
determined on the basis of the level of growth of the
trees and the current local price per square meter or per
unit.

The owner of trees may, in lieu of compensation .cut


and collect the tree within the period fixed pursuant to
article 7 of the proclamation.

EEPCo Environmental Monitoring Unit (EMU) 26


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

No Type of property Valuation principle Formula For calculation of compensation Remarks


rates
Compensation for structures ( housing .etc.) shall paid Cost of per square meter X total size of the
5 For buildings to the amount of replacing the affected house cost of house + cost of permanent improvement on
permanent improvement made on land ,including the land.
amount of refundable monetary for the remaining term
of lease contract .with in the following principles
Replacement cost include to cover the cost of different
construction structure in the constructed houses
The estimated cost for demolishing lifting
reconstruction, and connecting utility line o f the
buildings
The possessor has the right to claim compensation for
the entire buildings surrounding the total land in his
possession where part of the buildings is ordered to be
removed
If compensation shall be paid for the demolished par of
a buildings where the owners prefers to use the un
warranted part of the land ; provided however that such
preferences shall be accepted only where the conditions
of the partly demolished buildings conforms with the
requirements of the appropriate city plan.

EEPCo Environmental Monitoring Unit (EMU) 27


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

8.2 Compensation for Loses of Crops

The following procedure and method are used to set values for crops loss.

• The proportion of area harvested, along with the area covered by each crop will be
taken in to account;
• Yield per hectare;
• Total crop production; and
• Value of crops

Table- 13: Average Yield and Current Market Price of Crops in the Project Affected Woreda

No Crop Type Affected Yield Producti Market Value in


Land in ha (Qt/ha ) on in Qt Price in Birr
Birr
1 Maize 19.35 24 464.3 253 117,468
2 Teff 17.5 7 122.5 462 56,595
3 Wheat 13.61 18 245 420 102,900
4 barely 5.7 12 68.4 350 23,940
5 sorghums 1.44 11 15.84 200 3,180
Root crops
1 S/potato 12.03 107 1287 99 127,413
2 potato 4.93 69 340 425 144,500
3 Boye 3.06 239 731 183 133,773
Total 77.62 - - - 709,769
Source: Socio –Economic Survey, 2001

8.3 Compensation for Loss of Perennial Crops and Trees

Compensation rates for loss of perennial crops and trees will take in to account the
distinction between various types of trees and their economic values.

The compensation rate for eucalyptus tree will take in to account the distinction between
various types of trees and the current local price per unit of the respective sizes of these, i.e.
big, medium, and small seedlings.

Fruit trees will be compensated for the value of lost production until the replacement tree is
at the same stage of productivity.

EEPCo Environmental Monitoring Unit (EMU) 28


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

The compensation for ripe crops is calculated on the basis of the cost required to grow the
plant and the average annual income for each fruit trees is calculated on the basis of tree
characteristics and the ten years benefit.
The compensation for unripe perennial crop calculated on the bases of the amount of cost
expends to grow the plant and the ten years benefit.

Compensation for the loss of eucalyptus tree has been calculated using the following rates:

• Big trees 200 Birr/tree


• Medium 60 Birr /tree
• Small 25 birr /tree
• Seedlings 3 birr/ tree

Table -14: Proposed of Compensation for Affected Trees

Category of No. of tree Unit Total price


Eucalyptus tree price
Big 669 200 133,800
Medium 840 60 50,400
large 1694 25 42,350
Total 3,203 - 226,550
Source: Household Survey .2001

Table-15 Proposed Compensation for Perennial Trees

Perineal Number of Produc- Market Cost Expenditure Annual value for


Crops trees tivity Price For growing comp.
10 years Total
tree Ripe Unripe Per Kg Land Cost to ripe unripe
Comp. compensation
in kg impro- grow
vemen
Banana 2028 2160 10 2.00 4 15 48672 41040 486,720 52,760
Enset 1,172,5
4199 4793 10 2.40 4 15 90,687 11,725,800 11,816,487
80

287 127 50 2.00 3 80 29,581 10,160 295,810 305,970


Avocado
Mango 438,753
194 91 50 3.00 3 80 43,120 7553 431,200

Coffee 7233 1797 1 30.00 5 15 253,155 8985 2,531,550 2,540,535


Total 15,154,505
-- - - -- - -

Source: Household Survey, 2001

EEPCo Environmental Monitoring Unit (EMU) 29


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

8.4 Compensation for housing structures

Buildings/houses are valued on the price of construction material with which they have been
built. The market price remains the most reliable way to evaluate buildings.

Table 16: Compensation for the Loss of Residential Houses

No. Total
Type of housing Total Proposed compensation
1 Corrugated iron sheet roofed rate per m2 cost
houses
1.1 Small (30 m,2 ) 5 30,000 15,000.00
,2
1.2 Medium (40 m ) 6 40,000 240,000.00
1.3 Large (60 m,2 ) 48 60,000 2,880,000.00
Sub total 59 - 3,135,000.00
2 Grass roofed houses
2.1 Small (3 Diameter) 53 10,000 530,000.00
2.2 Medium (4 m Diameter) 53 15,000 795,000.00
2.3 Large (6 Diameter ) 27 20,000 540,000.00
Sub total 133 - 1,865,000.00
Grand total 192 5,000,000.00
Source: Socio –Economic Survey, 2001

EEPCo Environmental Monitoring Unit (EMU) 30


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

9. INSTITUTION FOR IMPLEMENTATION OF RESETTLEMENT PLAN

Implementation of the Resettlement Plan is critical activity. For effective and efficient
implementation of the RAP it is necessary to establish the resettlement organ .The organ has
a responsibility to manage the plan, coordinate, and monitor the resettlement.

The implementation of the Resettlement Plan and all compensation matter such as allocation
of the compensation fee is the responsibility of EEPCo for which the resettlement
implementation unit will establish under the project implementing unit /PIU/ and to be in
charge of implement the Resettlement Plan.

Moreover, the established office will consult and establish valuation committee at Woreda
level as per the proclamation No.455/2005 which comprises 5-7 members from relevant
government offices and representative of the project affected persons from each affected
kebeles.

The members of the committee will consist of Woreda administrator as chair person, and
experts from agriculture and rural development office specially crop management and
protection, land administration and utilization offices and PAPs representatives from each
kebeles. The committee will take up the implementation of the RAP along with the project
implementing office.
The key functions of the committee will be:

• Register the PAPs and affected assets;


• Verify the entitlement right of PAPs with concerned authority;
• Determine the compensation rates with taking in to account the country’s legislation;
and
• Based on the information, implement compensation payments.
The operation of expropriation, compensation and relocation activities shall be under taken
before the commencement of the construction works.

According to the implementation schedule of the project, the tentative commencement of the
work will be starting from September 1st 2009. The Resettlement Plan is based on this
tentative implementation schedule of the project.

The implementation agency should submit report to the donor agency, African Development
Bank (AfDB), which ensure that all the PAPs are fully compensated and resettled before the
start of the construction works.

EEPCo Environmental Monitoring Unit (EMU) 31


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

9.1 Implementation Schedule

All Woredas along Gibe III – Sodo HVTL will finalize the formulation of valuation
committee by February 1st 2009

The committee will finalizes census /inventory of the displaced persons and their assets and
approval of eligibility by March1st 2009

The valuation committee will complete the valuation of assets agreed with PAPs on
modalities of payment /compensation by April 1st 2009

EEPCO ‘s project implementing unit (PIU) will finalize budget for compensation and
agreed on mechanisms of payment to PAPs and payment will be accomplished by August
1st2009.
Woreda and kebele will facilitate construction of new residential houses and the PAPs would
have physically moved by September 1st 2009 and the construction firm takes over the site.
The construction of PAPs residential houses will be finalized during dry season.

The following Table 17 shows the detail schedule for implementation of Resettlement Action
Plan for the Gibe III-Sodo 400 kV HVTL project activities.
Table -17: Implementation Schedule for Resettlement Action Plan.

Task Months
1 2 3 4 5 6 7
Establish project level resettlement
implementation unit and
Valuation committee formulation
Grievance redress committee formation
Final Inventory of PAPs and
affected assets
Notification on the property rights and
agreement b/n PAPs and the compensation
committee
Consultation with PAPs
Determining compensation rate
PIU finalize budget for compensation and
agreed on mechanism of payment
Compensation payment
Construction of new residential houses

EEPCo Environmental Monitoring Unit (EMU) 32


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

10. GRIEVANCE REDRESS MECHANISM

Dissatisfactions may arise through the process of compensation for a variety of reasons,
including disagreement on the compensation value during valuation for assets, controversial
issue on property ownership etc. To address the problem of PAPs during implementation of
compensation a grievance redress committee will be established in project affected kebeles.
The composition of grievance redress committee is depicted below.

Table -18: Members of Grievance Redress Committee


1 Representative of Kebele Administration Chair person
2 Representative of Land Administration secretary
3 Respected Elders (three) members(three)

The main function of the committee would be arbitration and negotiation based on
transparent and fair hearing of the cases of the parties in dispute between PAPs and the
implementing agencies for local government. The committee gives solution to grievances
related to compensation amount, delays in compensation payment or provision of different
type of resettlement assistance.

10.1 Grievances Redress Procedure

All PAPs will be informed in case of any grievance regarding compensation can approach to
chair man of the grievance committee or the project implementer. Any PAPs who have
grievance would present his /her cases to the grievance redress committee. The committee
examines the case and responds within a period of 15 days.

If the PAPs are not satisfied with the decision of the Grievance Redress Committee/GRC/,
they can approach the regular court.

EEPCo Environmental Monitoring Unit (EMU) 33


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

11. MONITORING AND REPORTING PLAN

In order to guarantee that the compensation plan be smoothly performed and the benefit of
the affected persons be well treated, the implementation of the compensation plan will be
under monitoring throughout the whole process. Monitoring will be divided into two parts,
i.e. internal and external monitoring.

11.1 Internal Monitoring

The internal monitoring will be performed by resettlement implementation unit. The


concerned local administration will also conduct their own monitoring .The target of internal
monitoring is to ensure that there is overall fairness and transparency while compensation
process takes place and Resettlement Action Plan is performed based on legal rights.

The main monitoring center would be compensation allocation schedule, payment and use of
compensation fee, implementation of the policies and regulation specified in the resettlement
plan and the whole course of implementation of the compensation.

The main source of data for internal monitoring will be the data base generated from the RAP
for e.g. records on compensation for assets as well as the day today observations by
implementing staffs.

The resettlement office will record the progress of land allocation and resettlement. The
office will make a summary report starting from the commencement of the activities and
special events will be reported on continuous base.

The format of the report will be prepared in terms of the requirement of the World Bank and
African Development Bank. The format usually comprises detail description of resettlement
progress and compensation payment, problems and difficulties met in the implementation
process and corresponding resolution methods and measures.

11.2 External Monitoring

External monitoring is the responsibilities of Federal Ethiopia Environmental Protection


Authority /FEPA/. EPA will under take all basic supervision on the impact of the project on
PAPs and income restoration, degree of satisfaction of PAPs during implementation of
resettlement include payment of compensation.

Environmental monitoring unit of EEPCo also undertakes the resettlement monitoring work
of the resettlement implementing office and it is the independent resettlement monitoring of
EEPCo’s power project. The main responsibility of EMU is to assess the performance of the

EEPCo Environmental Monitoring Unit (EMU) 34


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

resettlement implementation office based on the consolidated report and take corrective
measures in case of problems.

The major monitoring areas include;

• The over all fairness and transparency of the compensation process;


• Progress of compensation payment;
• Appropriateness of grievance redress mechanisms; and
• Problems and difficulties encountered.

12. IMPLEMENTATION BUDGET

The total resettlement implementation cost for the construction of Gibe III-Sodo HVTL is
summarized below in Table -19. The total budget required for compensation payment , i.e.
for loss of crops ,trees and residential houses due to ROW, tower foundation, access roads
and substation will be 23,939,240.60 Birr 2,242,278.75 (USD). This Budget includes
compensation cost for environmental monitoring.

Table- 19: Budget Cost Summary

No Items Cost in Birr Cost USD


1 Compensation for permanent land loss due to 162,122.00 15,185.22
tower pad
2. Compensation for temporary loss of crops 709,769.00 66,480.00
Due to ROW and Access roads
3 Compensation for loss of eucalyptus tree 226,550.00 21,219.90
4 Compensation for losses of perennial crops 15,154,505.00 1,419,452.90
5 Compensation for residential houses 5,000,000.00 468,327.84
Sub total 21,252,946.00 1,990,665.87
Monitoring and valuation
1 Monitoring and evaluation 500,000.00 46,832.70
2 Valuation committee per diem 10,000.00 936.65
Sub Total 510,000.00 47,769.36
Total 21,762,946.00 2,038,435.23
Contingency 10% 2,176,294.60 203,843.52
Grand Total 23,939,240.60 2,242,278.75

Exchange rate dated January 14, 2009


Exchange rate 1 USD =10.6763

EEPCo Environmental Monitoring Unit (EMU) 35


Resettlement Action plan for Gibe III –Sodo 400kV Transmission Lines project January, 2009

13. REFERENCES

1. Asian Development Bank (ADB).May 1998. Hand book on resettlement A Guideline


to. Manila, Philippines: ADB
2. Constitution of the Federal Democratic Ethiopia Proclamation No 1/1995
3. Guidelines for the Preparation of a Resettlement Action Plan, June 2003
4. Environmental Impact Assessment for Gibe III Hydro Electric Project, April 2008.
5. Environmental policy of Ethiopia: Environmental Protection Authority, Addis Ababa,
April 1997.
6. International Finance Corporation (IFC). April 2002. Hand book for preparing a
resettlement Plan, first edition .Washington DC, USA: IFC(Environment and social
development )
7. International finance Corporation (IFC). Doing Better Business through Effective
Public Consultation and disclosure

EEPCo Environmental Monitoring Unit (EMU) 36


Annex -1
Detail Number of Affected House Holds
and Their Lost Assets
Project Name Gibe III-Sodo 400kV Transmission Line
Region SNNPRS
Zone Wolita
Woreda Kindo Koiysha

Family size No. and Type of perineial crops Affected housing structure
No. Name of house hold Age Gender Occupation Total Male Femal Education kebele Type of No. of Age of Type of Size of thre Cost of the
Trees Trees Tree Hosing house M2 the hose
1 Altaye Alembo 30 M farmer 5 3 2 Manshera coffee 2 >4 Tukul 4
42 <4
Avocado 8 <7
Mango 6 <7
Banana 40 <4
Enset 56 <4

2 Ayele Alambo 30 M Farmer 10 5 5 Mnara Coffee 6 <4 Tukul 4


Avocado 1 >4 Tukul 3
2 <4
Mango 4 <4
Banana 12 >4
36 <4
Enset 143 <4

3 Dessie Mununa 25 M Farmer 4 2 2 Menara Coffee 4 <4 Tukul 3


Avocado 4 <7
Mango 1 <7
Mango 1 <7
Banana 65 <4
Enset 25 <4

4 Kuldudei Kuma 35 F Farmer 10 5 5 Menara coffee 20 >4 Tukul 6


Coffee 9 <4
Avocado 1 >7
Mango 1 >7
Mango 3 <7
Banana 9 >4
Banana 60 <4
Enset 8 >3
Enset 85 <3

5 Waja Kuma 40 M Farmer 11 5 6 Manara Coffee 73 >4 Tukul 3


Coffee 1 <4 House 60
Avocado 7 <7
Mango 1 >7
Mango 8 <7
Banana 51 >3
Banana 104 <3
Enset 43 >3
Enset 80 <3

6 Alemayehu Kuma 35 M Farmer 6 4 2 Manara Coffee 16 >4 Tukul 3


Cofee 22 <4
Banana 23 >3
Banana 38 <3
Family size No. and Type of perineial crops Affected housing structure
No. Name of house hold Age Gender Occupation Total Male Femal Education kebele Type of No. of Age of Type of Size of thre Cost of the
Trees Trees Tree Hosing house M2 the hose
Enset 14 >3
Enset 17 <3

7 Agona Anjelo 27 M Farmer 6 4 2 Bulete Coffee 2 >4 Tukul 3


Coffee 15 <4
Banana 2 >3
Banana 15 <3
Enset 59 <3

8 Bejo Anjelo 32 M Farmer 4 2 2 Balete Coffee 14 <4 Tukul 3


Avocado 4 <7
Banana 1 >3
Banana 71 <3
Enset 73 <3

9 Janamo Jarsa 40 M Farmer 8 3 5 Cherecha Enset 109 <3 Tukul 3

10 Aleho Abrhame 38 M Farmer 10 5 5 Cherecha Coffee 27 >4 House 60


Mango 2 <7
Banana 20 >3
Banana 64 <3
Enset 12 >3
Enset 10 <3

11 Getachew Geta 24 M Farmer 3 2 1 Cherecha Tukul 3

12 Gezahegn Geta 19 M Farmer 2 1 1 Cherecha Coffee 2 >4 Tukul 3


Avocado 1 >7
Banana 6 >3
Banana 14 <3
Enset 14 >3
Enset 13 <3

13 Abera Geta 15 M Farmer Cherecha Avocado 1 <7 Tukul 3


Mango 4 <7
Banana 3 <3

14 Birega Bisa 28 M Farmer 7 4 3 Cherecha Coffee 2 <4 Tukul 3


Avocado 1 <7
Ensete 5 <3

15 Alemayehu Mena 18 M Farmer 3 1 2 Cherecha Mango 3 <7 Tukul 3


Banana 9 <3
Enset 21 <3

16 Debisa Dosa 35 M Farmer 7 2 5 Cherecha Banana 13 <3 Tukul 3

17 Nadew Fenta 40 M Farmer 14 7 7 Gela Coffee 73 >4 Tukul 3


Enset 14 <3 House 60

18 Kaleb Buluka 20 M Farmer 5 3 2 Gela Coffee 20 <4 Tukul 3


Family size No. and Type of perineial crops Affected housing structure
No. Name of house hold Age Gender Occupation Total Male Femal Education kebele Type of No. of Age of Type of Size of thre Cost of the
Trees Trees Tree Hosing house M2 the hose
Avocado 3 <3
Mango 1 <7
Banana 40 <3
Enset 35 <3

19 Lambebo Dagebo 30 M Farmer 8 2 6 Gela Coffee 54 <4 Tukul 3


Enset 56 <3

20 Denoto Dima 25 M Farmer 8 4 4 Gela Coffee 25 >4 Tukul 3


Banana 14 <3

21 Timaro Dinote 23 M Farmer 7 4 3 Gela Coffee 20 >4 Tukul 4


Mango 1 >7
Mango 1 <7
Banana 7 >3
Banana 2 <3
Enset 37 <3

22 Dejene Dinneto 18 M Farmer 2 1 1 Gela Banana 3 <3 Tukul 3


Enset 27 <3

23 Medehin Edoto 17 M Farmer 2 1 1 5 Gela Coffee 11 <4 Tukul 3


Banana 19 <3
Enset 24 <3

24 Totero Waza 21 M Farmer 4 3 1 illitra. kokole Coffee 41 >4 Tukul 3


coffee 10 <4
Avocado 2 <7
Mango 1 >7
Banana 27 <3
Enset 57 <3

25 Yasin Asale 22 M Farmer 5 3 2 5th grade Gela Coffee 33 >4 Tukul 3


Coffee 27 <4
Banana 25 <3

26 Zeleke Tigro 38 M Farmer 14 6 8 $th grade Gela Coffee 126 >4 Hose 60
Avocado 1 >7
Banana 16 <3
Enset 10 >3
Enset 160 <3

27 Medehin Chumburo 24 M Farmer 3 1 2 4the grade Gela Coffee 106 >4 Tukul 3
Coffee 30 <3
Mango 2 <7
Banana 42 >3
Banana 11 <3
Enset 50 >3
Enset 70 <3

28 Assefa Getachew 30 M Farmer 9 5 4 7th grade Gucho Coffee 304 >4 Tukul 3
Family size No. and Type of perineial crops Affected housing structure
No. Name of house hold Age Gender Occupation Total Male Femal Education kebele Type of No. of Age of Type of Size of thre Cost of the
Trees Trees Tree Hosing house M2 the hose
Coffee 250 <4 House 30
Enset 260 >3
Enset 250 <3

29 Alemayehu W/Eyesus 30 M Farmer 7 5 2 7the grade Guche Coffee 66 >4 Tukul 4


Banana 55 >3
Banana 25 <3
Enset 65 <3

30 Wana Warako 55 M Farmer 18 6 12 ilitarate Gueche coffee 135 >4 Tukul 4


coffee 35 <4 house 60
Avocado 7 >7 house 30
Avocado 2 <7
Mango 1 <7
Banana 164 >3
Banana 27 <3
Enset 18 >3
Enset 80 <3

31 Madebo Meskele 37 M Farmer 5 3 2 2the grade Gela Coffee 300 >4 House 30
Coffee 15 <4
Avocado 1 <7
Banana 60 >3
Banana 40 <3
Enset 10 >3
Enset 40 <3

32 Mada Meskele 40 M Farmer 6 3 3 ilitrate Gela Coffee 150 >4 Tukul 4


Coffee 13 <4 Tukul 4
Banana 46 >3
Banana 30 <3
Enset 20 >3
Enset 60 <3

33 Wolde Choina 32 M Farmer 5 2 3 10the grade Gela Coffee 70 >4 Tukul 4


Coffee 150 <4
Avocado 6 >7
Enset 300 >3
Enset 400 <3

34 Eyasu Dajeta 25 M Farmer 5 1 4 ilitrate Gucho Coffee 40 >4 Tukul 3


Coffee 20 <4
Banana 8 >3
Banana 62 <3
Enset 14 <3

35 Desalegn Dajita 35 M Farmer 7 4 3 4th grade Guche coffee 190 <4


Avocado 2 <7
Mango 1 <7
Banana 100 <3
Enset 71 <3
Family size No. and Type of perineial crops Affected housing structure
No. Name of house hold Age Gender Occupation Total Male Femal Education kebele Type of No. of Age of Type of Size of thre Cost of the
Trees Trees Tree Hosing house M2 the hose

36 Dergaso Dina 30 M Farmer 6 5 1 ilitrate Daday coffee 60 >4 house 60


Avocado 2 <7
Mango 2 <7
Banana 40 >3
Enset 80 >3
Enset 100 <3

37 Shita Shanka 40 M Farmer 5 3 2 iliitrate Mogisa Coffee 80 >4 Tukul 4


Coffee 20 <4
Mango 1 <7
Banana 30 >3
Banana 30 <3
Enset 100 <3

38 Ofaysa Shata 37 M Farmer 7 2 5 ilitrate Mogisa coffee 60 >4 Tukul 4


coffee 30 <4
Banana 80 <3
Enset 100 <3

39 Gelot Gaga 28 M Famer 6 3 3 4the grade Mogisa Coffee 70 >4 Tukul 4


Coffee 30 <4
Mango 4 <7
Banana 40 <3
Enset 20 <3

40 Gereno Gaga 40 M Farmer 10 1 9 ilitrate Mogesa Coffee 60 <4 house 60


Banana 30 <3
Enset 70 <3

41 Peko Fanta 38 M Farmer 12 6 6 Ilitrate Mogesa Coffee 80 <4 house 40


Mango 1 <7
Banana 30 <3

42 Fanta Mara 40 M Farmer 6 4 2 ilitarate Mogesa Coffee 40 <4 house 60


Avocado 1 <7
Mango 1 <7
Banana 30 <3
Enset 40 <3

43 Goa Geta 45 M Farmer 2 1 1 ilitrate Mogesa coffee 40 <4 House 60


Mango 3 <7
Banana 30 <3
Enset 40 <3

44 Aduen Ashe 30 M Farmer 10 5 5 ilitrate Coffee 6 <4 Tukul 4


Avocado 1 <7 Tukul 3
Mango 2 <7
Banana 12 >3
Banana 36 <3
Enset 108 <3
Family size No. and Type of perineial crops Affected housing structure
No. Name of house hold Age Gender Occupation Total Male Femal Education kebele Type of No. of Age of Type of Size of thre Cost of the
Trees Trees Tree Hosing house M2 the hose

45 Lambbo Lame 30 M Farmer 10 5 5 Ilitrate coffee 20 >4 Tukul 3


Avocado 1 >7
Mango 1 >7
Banana 9 >3
Enset 8 >3
Enset 20 <3
46 Bedru Bute 32 M Farmer 6 4 2 coffee 16 >4 Tukul 3
Coffee 15 <4
Banana 23 >3
Enset 14 >3

47 Gunte Puuche 30 M Farmer 4 2 2 Ilitrate Avocado 4 <7 Tukul 3


Banana 1 >3
Banana 51 <3
Enset 14 <3

48 Mune Kusa 38 M Farmer 10 5 5 illitrate coffee 27 >4 Tukul 3


Mango 2 <7
Banana 20 >3
Banana 46 <3
Enset 12 >3
Enset 10 <3

49 Alyase Enco 19 M Farmer 2 1 1 10th g Coffee 2 >4 Tukul3


Avocado 1 >7
Banana 6 >3
Banana 5 <3
Enset 14 >3

50 Yaya Abale 28 M Farmer 7 4 3 Ilitrate Tukul 3

51 Chokalew Chemerew 35 M Farmer 7 2 5 3rd g Tukul 3

52 Degefe Derche 20 M Farmer 5 3 2 ilitrate Coffee 14 <4 Tukul 3


Banana 30 <3
Enset 25 <3

53 Kitumu Kuale 25 M Farmer 8 4 4 ilitrate coffee 25 >4 Tukul 3


Banana 12 <3

54 Dusha Debuche 18 M Farmer 1 1 10th Tukul 3

55 Shebere Sherco 21 M Farmer 4 3 1 ilitrate Coffee 17 >4 Tukul 3


Coffee 24 <4
Avocado 2 <7
Mango 1 >7
Banana 27 <3
Enset 11 <3

56 Worseso wantago 38 M farmer 14 6 8 4th coffee 126 >4 house 60


Family size No. and Type of perineial crops Affected housing structure
No. Name of house hold Age Gender Occupation Total Male Femal Education kebele Type of No. of Age of Type of Size of thre Cost of the
Trees Trees Tree Hosing house M2 the hose
Avocado 1 >7 Tukul 3
Mango 1 >7
Banana 16 <3
Enset 10 >3

57 Buta burke 30 M Farmer 9 5 4 7th Coffee 304 >4 Tukul 3


enset 260 <3

58 Brhum Alero 48 M Farmer 10 6 4 ilitrate coffee 70 >4 Tukul 4


coffee 65 <4
Avocado 7 >7
banana 120 >5
banana 44 <3
enset 18 >3

59 Asha Allero 40 M farmer 6 3 3 ilitrate Coffee 150 >4 House 60


Banana 46 >3
Enset 20 >3

60 Datch Asshongo 25 M Farmer 5 3 2 ilitrate Coffee 40 >4


Banana 8 >3
Banana 47 <3
Enset 8 <3

61 Isreal Tekero 46 M Farmer 6 5 1 coffee 60 >4 Tukul 4


Banana 40 >3 hose 60
Enset 8 >3
Enset 6 <3

62 Asaare Shanka 30 M Farmer 7 2 5 ilitrate coffee 60 >4 house 60


Banana 50 <3 Tukul 3
Enset 70 <3

63 Laraso Tskaro 28 M Farmer 10 1 9 ilitrate Coffee 60 <4 Tukul 4


Banana 30 <3

64 Fanta mara 40 M Farmer 6 4 2 ilitrate Coffee 40 <4 House 60


Avocado 1 <7
Mango 1 <7
Banana 30 <3
Enset 40 <3

65 Abera Anebo M farmer 7 2 5 5th Coffee 10 <4 Tukul 4


Avocado 1 >7
Mango 4 >7
Enset 10 >3
Enset 70 <3

66 Acha Anebo 18 M Farmer 6 th Coffee 22 <4 Tukul 4


Avocado 5 >7
Mango 7 >7
Family size No. and Type of perineial crops Affected housing structure
No. Name of house hold Age Gender Occupation Total Male Femal Education kebele Type of No. of Age of Type of Size of thre Cost of the
Trees Trees Tree Hosing house M2 the hose
Banana 20 >3

67 Kusa Kuma M Farmer 5 3 2 4th Coffee 105 >4 Tukul 4


Avocado 2 >7
Mango 5 >7
Banana 90 >3

68 Yohannis Abate M Farmer 9 5 4 ilitrate Coffee 90 >4 Tukul 5


Avocado 4 >7
Mango 9 >7
Banana 100

69 Ayneabeba Anegedo 70 F Farmer 9 6 3 ilitrate coffee 2 >4 Tukul 6


coffee 6 <6
Avocado 1 >7
Mango 13 >7
Banana 150 >3
Enset 40 <3

70 Anbesa Negasa M farmer 6 2 4 5th Cofee 64 >4 Tukul 5


Avocado 2 >7
Mango 6 >7
Banana 90 >3
Enset

71 Abebe Chenesho M Farmer 7th Coffee 7 >4


Mango 4 >7
Enset 15 >3

72 Matias Nenebo M Farmer 6 4 2 3th Coffee 15 >4 Tukul 4


Mango 4 >7
Banana 2 >3
Enset 250 >3

73 Aysa Genebo M Farmer 5 3 2 2th Coffee 37 >4 Tukul 4


Mango 4 >7
Banana 10 >3
Banana 4 >3
Enset 10 >3
Enset 40 <3

74 Belete Tegegn M Farmer 5 4 1 4th Coffee 4 <4 Tukul 4


Mango 7 >7
Banana 60 >3

75 Kelicho Jarsa M Farmer 6 3 3 ilitrate coffee 20 >4 Tukul 6


Avocado 2 >7 house 60
Enset 30 <3

76 Selasie Latino M Farmer 9 6 3 6th Avocado 4 >7 Tukul 4


Mango 4 >7 house 40
Family size No. and Type of perineial crops Affected housing structure
No. Name of house hold Age Gender Occupation Total Male Femal Education kebele Type of No. of Age of Type of Size of thre Cost of the
Trees Trees Tree Hosing house M2 the hose
Banana 50 >3
Banana 10 <3

77 Gensa Hantalo M Farmer 9 4 5 ilitrate Avocado 2 >7 Tukul 6


Mango 3 >7

78 Mamo mengesha M Farmer 3 3 ilitrate coffee 120 >4 Tukul 6


Avocado 7 >7
Mango 10 >7
Banana 25 >3
Enset 100 >3
Enset 150 <3

79 Mohamed Meja M Farmer 7 5 2 coffee 102 >4 Tukul 6


Avocado 1 >7
mango 36 >7
Banana 32 >3
Enset 50 >3
Enset 80 <3

80 Matewos Muhamed M Farmer 4 2 2 7th Coffee 16 >4 Tukul 4


Mango 6 >7
Enset 80 <3

81 Megegn Mohamed M Farmer 4 3 1 5th Avocado 1 >4 Tukul 4


Mango 1 >7
Banana 4 >3

82 Bergene Moja M Farmer 9 6 3 4th Coffee 41 >4 Tukul 6


Avocado 2 >7
Mango 4 >7

83 Balta Moja M Farmer 8 3 5 ilitrate coffee 63 >4 Tukul 6


Mango 3 >7
Banana 16 <3

84 Tgiro Tripa M Farmer 8 2 6 ilitrate Coffee 60 >4 house 60


Avocado 8 >7

85 Wadu Geju M Farmer 5 3 2 2th Coffee 96 >4 tukul 6


Avocado 7 >7
Avocado 1 <7
Banana 2 >3

86 Arba Menna M Farmer 10 6 4 ilitrate Coffee 54 >4 House 60


Avocado 2 >7
Mango 1 >7
Banana 30 >3
enset 1 >3
enset 8 <3
Family size No. and Type of perineial crops Affected housing structure
No. Name of house hold Age Gender Occupation Total Male Femal Education kebele Type of No. of Age of Type of Size of thre Cost of the
Trees Trees Tree Hosing house M2 the hose
87 Wageso Dabush M Farmer 9 4 5 ilitrate Coffee 65 >4
Avocado 2 >7
Mango 1 >7

88 Ayelech Shanka F Farmer 7 4 3 ilitrate Coffee 19 >4 House 60


Avocado 1 >7
Mango 1 >7
Enset 30 <3

89 Shanka Altaye M Farmer 7 4 3 7th Coffee 46 Tukul 4


Avocado 1

90 Abera Abate M Farmer 7 3 4 7th Coffee 112 >4 Tukul 6


Avocado 4 >7 House 60
Mango 7 >7
Banana 20 <3
Enset 60 <3

91 Mesfin Abate M Farmer 5 2 3 5th Coffee 662 >4 Tukul 4


Avocado 1 >7
Mango 7 >7
Banana 30 >3
Banana 10 <3

92 Boka Naso M Farmer 5 3 2 ilitrate Coffee 8 >4


Avocado 2 >7
Mango 6 >7

93 Danel Otoro M Farmer 12 9 3 6th Coffee 40 >4 House 60


Avocado 1 >7
Banana 200 >3
Banana 80 <3

94 Daeit Alo M Farmer 7 4 3 8th Coffee 2 >4 Tukul 4


Avocado 3 >7
mango 13 <7
Banana 60 >3

95 Kutaro Kuma M Farmer 9 4 5 8th Coffee 40 >4 House 60


8th Avocado 3 >7
Mango 4 >7
Banana 200 <3
Enset 200 >3

96 Abota Alo M Farmer 7 4 3 Coffee 52 >4 Tukul 6


Coffee 12 <4
Avocado 4 >7
Mango 6 >7
640 327 313
Project Name GibeIII- Sodo 400kV Power Transmission Line
Region SNNPRS
Zone Wolita
Woreda Sodo zuria

Family size No. and Type of perineial crops Affected housing structure
No. Age GenderOccupation Total Male Female Religi. Education kebele Type of No. of Age of Type of Size of thre Cost of the
2
Name of house hold Trees Trees Tree Hosing house M the house
1 Eshetu Annebo M farmer 1 coffee 25 >4 Tukul 4
Avocado 6 <7
Enset 2 <3

2 Amone Anefbo M Farmer 8 5 3 kuto sepelsa Coffee 25 <4 Tukul 4


Avocado 6 >4
Enset 60 <3

3 Alebazo Anebo 25 M Farmer 7 4 3 ilitrate Kuto Coffee 22 <4 House 60


Avocado 2 <7
Mango 2 <7

4 Bancha Bango 35 M Farmer 8 3 5 ilitrate kuto.s coffee 30 >4 House 60


Avocado 10 >7 House 45
Enset 60 <3

5 Belaye Bancha M Farmer 4 2 2 89th Kuto.s Coffee 12 >4 House 60


Avocado 4 <7
Mango 3 <7
Enset 17 <3

6 Zeleke Ataro M Farmer 7 3 4 ilitrate Cofee 14 <4 Tukul 3


Avocado 2 >7

7 Bekele Bekalo M Farmer 8 4 4 ilitrate Kuto.s Coffee 22 >4 Tukul 4


Avocado 6 <7
Mango 2 <7
Enset 30 <3

8 Wakuma Walena 32 M Farmer 9 5 4 3th Kuto.s Coffee 65 <4 House 60


Avocado 5 <7

9 Arja Langano M Farmer 11 7 4 ilitrate Kuto.s Coffee 30 >4 Tukul 4


Avocado 3 >7 Tukul 6
Mango 2 >7
Enset 102 >3

10 Kidane Ganta M trader 6 3 3 Orth. 5th Kuto.s Enset 10 <3 House 40

11 Chude Bade 24 F Farmer 1 Orth. Ilitrate Kuto.s Tukul 3


Family size No. and Type of perineial crops Affected housing structure
No. Age GenderOccupation Total Male Female Religi. Education kebele Type of No. of Age of Type of Size of thre Cost of the
2
Name of house hold Trees Trees Tree Hosing house M the house
12 Zerihun Zeleke 19 M Farmer 8 4 4 Ortho. kut.s Coffee 22 <4 House 60
Avocado 1 <7
Avocado 1 >7
Enset 28 <3

13 Melka Mericho M Farmer 5 2 3 Orth. Ilitrate Kuto.s Coffee 20 <4 Tukul 6


Enset 6 <3

14 Darge Gua M Farmer 4 2 2 Ortho. 6th Kuto.s Coffee 15 <4 Tukul 4


Avocado 5 >7

15 Gujele Goa 18 M Farmer 3 2 1 Ortho. Ilitrate Kuto.s Mango 3 <7 Tukul 3


Banana 9 <3
Enset 21 <3

16 Nuka sherica 35 M Farmer 4 3 1 Ortho. Ilitrate Kuto.s coffee 20 >4 Tukul 4


Avocado 4 >7
Enset 10 >3

17 Gethaneh Getache 40 M Farmer 6 4 2 Ortho. Ilitrate Kutoserfela Coffee 25 >4 Tukul 4


Avocado 1 >7
Mango 1 <7
Enset 25 <3

18 Mena Madebo 20 M Farmer 3 2 1 Ortho. Ilitrate Kuto .s Coffee 11 <4 Tukul 3


Avocado 3 <3
Mango 1 <7
Banana 40 <3
Enset 35 <3
103 55 46
Project Name: GIII-Sodo 400 kV HVTL
Region: SNNPs
Zone Wolita
Woreda Damot Sore

Family size No. and Type of perineial crops Affected housing structure
No. Name of house Age Gender Occupation Total Male Female Religion Education kebele Type of No. of Age of Type of Size of the Cost of the
2
hold Trees Trees Tree Housing house M the house
1 Alkas Onkie M farmer 8 5 3 Orth. Illitrate Shamba k coffee 30 >4 Tukul 6
Avocado 2 <7

2 Olisa Onkie M Farmer 8 3 5 Orth. Illitrate Shamba k. Coffee 56 >4 house 60


Avocado 6 >4

3 Birhanu Alkeso M Farmer 6 3 3 Orth. 7th Shamba k. Coffee 4 >4 Tukul 4


Avocado 1 >7
Banana 1 >3

4 Tadese Shonga M Farmer 8 6 2 Ortho. 6th Shamba k. Avocado 2 <7 Tukul 4

5 Tafese Bindesa M Farmer 4 3 1 Ortho. 4th Shamba k. Avocado 2 <7 Tukul 4


Banana 6 <3
Enset 50 >3

6 Ena Elisa M Farmer 4 2 2 Protest. Illitrate Shamba k. Coffee 42 >4 Tukul 4


Avocado 3 >7
Avocado 1 <7
Banana 10 >3
Enset 50 <3

7 Chancha Bija M Farmer 10 6 4 Ortho. Illitrate Shamba K. Coffee 67 >4 House 60


Avocado 5 >7
Enset 20 >3
Enset 50 <3

8 Tamiru Shuda M Farmer 4 2 2 Ortho. 7th Shamba K. Tukul 6

9 Bekele Shuda M Farmer 6 5 1 Ortho. 5th Shamba K. Coffee 30 >4 Tukul 3


Enset 30 >3

10 Keba Chukalo M Farmer 6 4 2 Ortho. Illitrate Shamba K. Coffee 65 >4 Tukul 4


Avocado 1 >7
Family size No. and Type of perineial crops Affected housing structure
No. Name of house Age Gender Occupation Total Male Female Religion Education kebele Type of No. of Age of Type of Size of the Cost of the
2
hold Trees Trees Tree Housing house M the house
Enset 150 >3

11 Mengesha Keba M Farmer 5 1 4 Ortho. Illitrate Shamba K. Coffee 42 >4 House 60


Avocado 1 >7

12 Merchu Chiquala M Farmer 4 2 2 Ortho. Illitrate Shamba K. Coffee 54 >4 Tukul 3

13 W/Mariam Lodiso M Farmer 10 6 4 Ortho. 12th Shamba K. Avocado 5 >7 House 60


Mango 3 >7
Coffee 80 >4
Enset 40 >3
Enset 30 <3

14 Tesema Wada M Farmer 5 3 2 Ortho. 11th Kuto Sorpela Coffee 4 >4 House 40
Ensete 40 <3

15 Geremu Geleso M Farmer 7 4 3 Ortho. 9th Shamba K. Coffee 30 >4 House 60


Avocado 2 >7
Mango 1 >7
Enset 130 >3

16 Birhanu Zeleke M Farmer 6 2 4 Protest. 6th Kuto Sorpela Avocado 2 >7 Tukul 3
Enset 28 >3
Enset 50 <3

17 Wada Walana M Farmer 10 5 5 Ortho. Illitrate Kuto Sorpela Coffee 49 >4 House 30
Enset 6 <3 House 60

18 Bala Sagebo M Farmer 8 3 5 Protest. Illitrate Shamba K. Coffee 40 >4 House 60


Avocado 3 >7
Avocado 6 <7
Banana 40 <3
Enset 415 >3

19 Tegegn Bala M Farmer 7 4 3 Protest. 10th Shamba K. Avocado 2 >7 Tukul 4


Avocado 2 <7
Banana 2 <3
Enset 42 <3
20 Tesfaye Bekele M Farmer 6 2 4 Protest. Diploma Shamba K Coffee 100 >4 House 60
Coffee 50 <4
Family size No. and Type of perineial crops Affected housing structure
No. Name of house Age Gender Occupation Total Male Female Religion Education kebele Type of No. of Age of Type of Size of the Cost of the
2
hold Trees Trees Tree Housing house M the house
Avocado 6 >7
Mango 1 >7
Banana 111 >3
Enset 500 >3

21 Teklie Bekele M Farmer 1 1 0 Protest. 8th Kuto Sorpela Enset 20 <3 House 60

22 Bekele Belachew M Farmer 15 8 7 Protest. Illitrate Shamba K. Coffee 34 >4 House 60


Coffee 12 <4
Banana 12 >3
Enset 25 <3
23 Mola Moja M Farmer 8 3 5 Protest. 7th Shamba K. Coffee 30 >4 Tukul 6
Coffee 15 <4
Avocado 2 >7
Mango 5 >7
Banana 17 <3
Enset 160 >3

24 Kasahun Gebona M Farmer 6 1 5 Protest 7th Shamba k. Coffee 200 >4 Tukul 4
Avocado 7 >7
Mango 5 >7
Banana 55 >3
Enset 260 >3

25 Mahiteme Gibona M Farmer 4 1 3 Protest. 8th Shamba K. Coffee 6 >4 House 60


Avocado 2 >7
Banana 80 <3

26 Dargie Kuate M Farmer 5 3 2 Otho. 4th Shamba K Coffee 50 >4 House 60


Avocado 3 >7
Avocado 2 <7
Banana 30 >3
Enset 300 >3

27 Wadie Kuyitie M Farmer 6 4 2 Ortho. 6th Shamba K. Coffee 104 >4 House 60
Avocado 2 >7
Mango 3 <7
Banana 42 >3
Banana 12 >3
Enset 38 <3
Family size No. and Type of perineial crops Affected housing structure
No. Name of house Age Gender Occupation Total Male Female Religion Education kebele Type of No. of Age of Type of Size of the Cost of the
2
hold Trees Trees Tree Housing house M the house

28 Chelemo Meskelie M Farmer 3 2 1 Ortho. 7th Shamba K. Coffee 50 >4 Tukul 4


Enset 10 >3

29 Tesfaye Meskelie M Farmer 4 2 2 Protest. 7th Shamba K. Coffee 20 >4 Tukul 4


Banana 3 >3

30 Kebede Meskelie M Farmer 5 1 4 Protest. Illitrate Shamba K. coffee 19 >4 Tukul 4


Avocado 1 >7 Tukul 4
Avocado 6 <7
Enset 35 >3
Enset 144 <3

31 Dalga Sheno M Farmer 10 2 8 Ortho. 3rd Shamba K. Coffee 111 >4 Tukul 6
Mango 1 >7
Avocado 2 >7
Banana 3 >3

32 Altaye Ashebo M Farmer 9 3 6 Ortho. Illitrate Shamba K. Coffee 10 >4 Tukul 6


Avocado 9 >7
Enset 13 >3

33 Adilo Altaye M Farmer 1 1 0 Ortho. 2nd Shamba K. Tukul 3

34 Workineh Wedelo M Farmer 6 2 4 Protest. 2nd Shamba K. Coffee 10 >4 Tukul 4


Coffee 21 <4 Tukul 4
Avocado 11 >7
Avocado 15 <7
Mango 12 >7
Mango 6 <7
Enset 10 >3
Enset 12 <3

35 Dejene Mena M Farmer 8 5 3 Ortho. 8th Bolola Chewkeri coffee 56 >4 House 60
Avocado 2 >7
Mango 1 >7

36 Ofayisa Badie M Farmer 6 4 2 Ortho. 5th Bolola Chewkeri coffee 36 >4 house 60
Avocado 3 >7
Mango 2 <7
Family size No. and Type of perineial crops Affected housing structure
No. Name of house Age Gender Occupation Total Male Female Religion Education kebele Type of No. of Age of Type of Size of the Cost of the
2
hold Trees Trees Tree Housing house M the house
Enset 2 >3

37 Semeon Daniel M Farmer 7 2 5 Protest. Illitrate Bolola Chewkeri Coffee 61 >4 Tukul 4
Avocado 9 >7
Enset 3 >3

38 Yishak Dicha M Farmer 3 1 2 Protest. Illitrate Bolola Chewkeri coffee 6 >4 Tukul 4
Avocado 3 >7
Enset 2 >3
Enset 54 <3

39 Bundiro Arba M Famer 8 4 4 Ortho. 4th Bolola Chewkeri Coffee 69 >4 Tukul 4
Avocado 12 >7
Mango 4 <7
Banana 20 >3
Enset 8 >3

40 Dawit Degefa M Farmer 5 1 4 Protest Illitrate Bolola Chewkeri Tukul 4

41 Almaz Arba F Farmer 6 4 2 Ortho. Illitrate Bolola Chewkeri Avocado 1 <7 house 60
Enset 6 >3
Enset 15 <3

42 Merkin Madebo M Farmer 4 1 3 Ortho. Illitrate Bolola Chewkeri Coffee 1 >4 Tukul 3
Coffee 2 <4

43 Madebo Mena M Farmer 12 5 7 Ortho. Illitrate Bolola Chewkeri coffee 135 >4 House 60
Avocado 7 >7
Banana 2 >3

44 Bergana Basa M Farmer 6 3 3 Ortho. Illitrate Bolola Chewkeri Coffee 30 >4 Tukul 6
Avocado 1 <7

45 Kuma Shata M Farmer 6 2 4 Pagan 7th Bolola Chewkeri coffee 24 >4 Tukul 3
Coffee 10 <4
Avocado 8 >7

46 Shata Shanka M Farmer 4 2 2 Ortho. Illitrate Bolola Sorie coffee 6 >4 Tukul 4
Avocado 1 <7
Family size No. and Type of perineial crops Affected housing structure
No. Name of house Age Gender Occupation Total Male Female Religion Education kebele Type of No. of Age of Type of Size of the Cost of the
2
hold Trees Trees Tree Housing house M the house
47 Merken Shata M Farmer 6 3 3 Protest 3rd Bolola Chewkeri Coffee 12 >4 House 40
Avocado 1 >7

48 Kinfe Gunta M Farmer 10 4 6 Protest. 5th Bolola Chewkeri coffee 29 >4 Tukul 6
Mango 2 <7
Banana 11 >3
Banana 12 <3

49 Haile Shonkie M Farmer 11 7 4 Protest 8th Bolola Chewkeri Coffee 135 >4 House 60
Avocado 4 >7
Mango 1 >7
Enset 59 >3

50 Gebre Ganta M Farmer 6 2 4 Protest 5th Bolola Chewkeri Coffee 24 >4 house 60
Avocado 1 <7

51 Abebe Ganta M Farmer 7 2 5 Protest 10th Bolola Chewkeri Avocado1 >7 Tukul 3

52 Asha Derash M Farmer 15 9 6 Protest IllitrateBolola Chewkeri Coffee 63 >4 Tukul 6


Enset 35 >3

53 Admasu Asha M Farmer 9 5 4 Protest 8th Bolola Chewkeri coffee 22 >4 House 60
Avocado 1 >7
Enset 35 >3

54 Abera Asha M Farmer 4 3 1 Protest IllitrateBolola Chewkeri Coffee 13 >4 Tukul 6


Avocado 1 >7
Enset 42 <3

55 Beyene Yota M Farmer 4 2 2 Protest IllitrateDoge Mashido Avocado 2 >7 Tukul 3

56 Markos Mana M farmer 5 2 3 Protest. IllitrateDoge Mashido Avocado 3 >7 Tukul 3

57 Tantu Dando M Farmer 1 0 1 Protest IllitrateDoge Mashido Avocado 1 >7 Tukul 3

58 Nane Oyeto M Farmer 8 4 4 Protest IllitrateDoge Mashido coffee 40 >4 Tukul 4


Avocado 3 >7
Mango 1 >7

59 Abate Anjelo M farmer 7 3 4 Ortho. IllitrateDoge Mashido Coffee 29 >4 Tukul 6


Family size No. and Type of perineial crops Affected housing structure
No. Name of house Age Gender Occupation Total Male Female Religion Education kebele Type of No. of Age of Type of Size of the Cost of the
2
hold Trees Trees Tree Housing house M the house
Avocado 3 >7
Avocado 4 <7
Mango 3 >7
Enset 52 >3
Enset 40 <3

60 Petros Belete M Farmer 8 4 4 Ortho. 10th Doge Mashido Coffee 120 >4 House 60
Avocado 5 >7
Enset 80 >3

61 Abera Asha M Farmer 8 4 4 Protest IllitrateDoge Mashido Enset 19 >3 Tukul 3


Enset 16 <3

62 Tasew Pinta M Farmer 12 8 4 Protest IllitrateDoge Mashido coffee 26 >4 house 60


Avocado 2 >7
Enset 60 >3
Enset 32 <3

63 Zekarias Tasew M Farmer 6 3 3 Protest 7th Doge Mashido Coffee 10 >4 Tukul 6
Enset 6 >3

64 Megegn Melaqu M Farmer 13 7 6 Ortho. IllitrateDoge Mashido Coffee 36 >4 House 60


430 211 219 Enset 12 <3 Tukul 6
1671
Annex -2
Consultation Minutes of Meeting
Annex -3
Relevant Proclamations
Annex -4
Lists of Consulted Officials
List of Contact Persons

No Personal contact Woreda Responsibility


.
1 Ato Bereket Bergana Sodo zuria Woreda administration head

2 Ato Takele Tantu ” Woreda administration head

3 Ato Powlos Nana ” Shamba kebele Administrater

4 Ato Feleke Mena Qutu kebele chair person

5 Ato Shende Derso Disease control l head

6 Ato Danele Wadicho Kindo koysha Wored Administration head

7 Ato Esrael chjo ” Public relation officer

8 Ato Dawit Miga ” Wored Public relation head

9 Ato Matiyos Mena ” Age/Rural Development head

10 Ato Sameson Gelan ” Age/Rural Development vise head

11 Ato Desta Yirga ” ”

12 Ato Tamene Tadesse ”

13 Ato Besu fekad Animal desk head

14 Ato Matiyose ” Natural resource Desk head

15 Ato Eyasu Chema Damote Sore Health bureau head

16 Ato Worku Beluko ” ”

17 Ato Aklilu Lema ” Education Bureau head

18 Ato Abayneh Abate ” ”

19 Ato Asfaw Manado ” ”

20 Ato Tumulo Dana ” ’’


Annex -5
Photos
Affected Avocado Trees Affected Mango trees

Affected Banana Plant Affected Eucalyptus


Inventory of affected Household Asset Consultation with Community Elders

Public consultation at Shamba Kebele Public consultation at Kutosurfela Kebele


Affected Houses One of the affected Tukul

Affected Coffee plants Affected Enset plants

You might also like