You are on page 1of 4

PROJECT NAME:……………………………………………………………………………

ELEMENT 5.19.3
JOB SAFETY PRACTICES

DEPARTMENT/DIVISION EHVPD / COA DATE 29 September 2019


EMPLOYEE JOB TITLE 9019 to 9089 A & B and 9050 to 9089 A & B LOCATION RIYADH-BANBAN
380 KV OHTL Shutdown / Modification Works in Existing safety helmets, gloves, eye protection, high-
Personal Protective
JOB/ TASK TITLE Temporary Ckt 9019 to 9050 A & B to Establish 9019 to 9089 A & visibility clothing, safety footwear and safety
B and 9050 to 9089 A & B
Equipment
harnesses.
STEPS HAZARDS
IN EACH STEP, WHAT COULD CAUSE CONTROL REQUIRED TO MINIMIZE/ ELIMINATE HAZARD COMMENTS OF JOB OBSERVATION
LIST ALL STEPS IN
STEPS # INJURY, LOSS DAMAGE, INTRRUPTION, OR
PERFORMING THIS TASK
POLUTION?
a) Obtain permit from concerned external authority
before starting the activity.
b) Ensure ground level is even and good condition to
placed vehicle/trailer.
c) Ensure sufficient clearance is available to move near
Mobilization of Equipment / vehicle / Trailer Moving / energized lines. (More than 10 meter)
STEPS #1 materials tools and Placed near energized line, Un even d) Ensure proper grounding provided.
equipment’s. ground level. e) Ensure all safety documents, calibration certificate
and TUV of equipment’s must be available and valid.
f) Ensure proper operation and good condition of the
equipment before usage.
g) Provide work at height training for all linemen.
Conduct daily tool box talk before start the activity.
a) Obtain permit to work before starting the activity.
b) Provide manual and mechanical handling training to
all.
Manual and mechanical c) All PPEs (hand gloves, safety shoes, helmet, high
STEPS #2 handling of material Slip, Trip, fall from the same level. visibility jacket, goggles and overall) and tools must
tools and equipment’s. be inspected before use on daily basis.
d) Conduct daily TBT before start the activity.
Ensure the availability of first aid box and certified first
aider.

Page 1 of 4 Rev.2 [08-April-2019] Projects Business Unit


PROJECT NAME:……………………………………………………………………………
ELEMENT 5.19.3
JOB SAFETY PRACTICES

a) Tool box talk must be done by the team supervisor


before starting the work.
b) Avoid working if lightning threat is suspected.
Induction Voltage c) Work area shall be clearly identified before start of work.
Electrocution (Fatality/injury) d) Ensure Competent Supervision.
Fire /Explosion e) Use proper PPE (Safety Helmet, Safety Shoe, Gloves,
Working near
STEPS #3 Flashes Reflective vest & Goggle).
Live lines
Station tripping f) Work shall not be carried out within 10 M of the over
Damage to the equipment and headlines when the line is live with power.
properties g) Work with proper safety clearance & certificates.
h) Voltage detector and adequate portable grounding
equipment's should be provided to eliminate the risk of
induced voltage by other neighboring live circuits.
a) Ensure proper grounding on both sides identified
adjacent tower’s circuit/s.
b) Presence of competent person (Permit/ LOA holder)
must require while installing or removing the grounding.
c) Competent person must ensure the voltage absence
before installing the grounding.
d) Adequate equipment (VAV) shall be used to ensure the
voltage absence before installing the grounding.
e) Use Safety harness with double lanyard with properly
Fall of men or material from Height,
hooked while working above 1.8 MTR height.
STEPS #4 Climbing the tower Heat Stress or Slippery Condition
f) Ensure always three point of contact while climbing to
the tower & as well as while moving horizontally on
tower.
g) Ensure adequate supervision while working at height.
h) Use vertical life line with fall arrestor.
i) Waist pouch for carrying nut & bolt must be use.
j) Ensure availability of Emergency vehicle @ Site.
k) Work must be stopped during severe weather condition.
Necessary refreshments, cold drinks, ORS etc. to be
provided at the site.

Page 2 of 4 Rev.2 [08-April-2019] Projects Business Unit


PROJECT NAME:……………………………………………………………………………
ELEMENT 5.19.3
JOB SAFETY PRACTICES

a) Use Safety harness with double lanyard with properly


hooked while working above 1.8 MTR height.
b) Waist pouch for carrying nuts, bolts and hand tools in ring
available in harness shall be used access the tower.
c) Do not throw up / throw down the materials / tools.
d) Ensure availability of Emergency vehicle @ Site.
e) Mechanical lifting Equipment’s like shovel must be
Removing &
inspected before start of work.
STEPS #5 alternation of Existing Fall of men or material from Height
f) All Lifting Gears like Pulley, Slings, Rope and Insulator
jumper at height
Assembly Should be inspected before Work.
g) Color Coding of T & P Should be Verified
h) Work should be executed by Experienced Foreman.
i) Adequate and damage free guy ropes to be used, tied
properly.
j) Smooth (without jerk) lifting must be ensured.
Competency of the Operator should be verified.
a) Mechanical lifting Equipment’s like shovel must be
inspected before start the work.
b) All Lifting Gears like Pulley, Slings, Rope and Insulator
Failure of rope, slings, pulleys Assembly Should be inspected before Work.
Fall of objects from height c) Color Coding of T & P Should be Verified.
STEPS #6 Insulator Hoisting
Major Injury, Material damage d) Work should be executed by Experienced Foreman.
Using inappropriate tools/equipment e) Adequate and damage free guy ropes to be used & tied
properly.
f) Competency of the Operator should be verified.
Winch should be used for lifting the insulators
STEPS #7 Payout/Stringing of Electric Shock, Induction Voltage, a) Permit should be obtained before the activity.
Conductor & OPGW People being struck by or run over, b) Unauthorized Entry Should Be Prohibited. Prior
Overturning, Asset Damage Permission should be availed from the Client.
c) Competent Person Should Operate Tensioner and Puller.
d) Tensioner and Puller should be provided with grounding.
e) Constant and competent supervision needed for work.
f) Conduct specific tool box talks before starting the activity.
g) Minimum Safe Distance of 10M from energized Lines

Page 3 of 4 Rev.2 [08-April-2019] Projects Business Unit


PROJECT NAME:……………………………………………………………………………
ELEMENT 5.19.3
JOB SAFETY PRACTICES

should be maintained.
h) Only trained personnel to be allowed to work
i) Tools needs to be insulated
j) Safety Net should be installed as per Requirement.
k) Tools need to be insulated.
a) Proper Platform should be used for pressing of conductor.
b) Use of appropriate PPE's like full body harness, fall
arrestor, helmet and shoes.
c) Do not throw up / throw down the materials / tools.
d) All the arrangement should be prepared under skilled
foreman.
e) Proper Housekeeping should be done before start of
Conductor & OPGW Major Injury, fatal, material work.
STEPS #8 Clipping, Spacering Damage, Slip/Trip/Fall f) No Technician should stand under the Tower.
and Jumpering Hazards g) Adequate and damage free guy ropes to be used, tied
properly. a) Aluminum ladder with hooks should use to
enter the clipping area.
h) Use of appropriate PPE's like full body harness,
Retractable fall arrestor, helmet and shoes.
i) Spacer Trolley Load Should within the SWL
j) Retractable fall arrester and safety Harness must be used
by the line man during Jumpering work.
JSP Prepared By: Daya Sankar, Faisal & Sethu Signature: Date:

JSP Accepted By: Signature: Date:

JSP Approved By (SEC Site): Signature: Date:

JSP Approved By (SEC): Signature: Date:

Page 4 of 4 Rev.2 [08-April-2019] Projects Business Unit

You might also like