You are on page 1of 12

Jacobs Engineering Singapore

Page:
Health, Safety, & Environment Manual 1 of 12
Procedure No.: First Issue date: Rev.:
(Safe Work Procedures)
HSEM(SWP) 01-10-03 C
– 3.0 Piling Works
Issuing Department: Approval: Previous Rev. Date: Current Revision
Singapore Operations Japa Rusdi 10 May 07 Date: 10 May 07
19 Apr 12

Table of Contents

1.0 PURPOSE........................................................................................................................................................................... 2
2.0 SCOPE................................................................................................................................................................................ 2
3.0 DEFINITIONS................................................................................................................................................................... 2
4.0 RESPONSIBILITIES.........................................................................................................................................................3
5.0 PROCEDURE..................................................................................................................................................................... 3
5.1. Technology Application.............................................................................................................................. 3
5.2. Subcontractor Selection............................................................................................................................. 3
5.3. Initial Inspection......................................................................................................................................... 3

5.4. Pile/Drill Rig Safety................................................................................................................................... 4


5.5. Pile/Drill Rig Set-up Procedures................................................................................................................5
5.6. Pile/Drill Rig Work Near Overhead Electric Lines.....................................................................................6
5.7. Equipment Operation – Angle Borings.......................................................................................................6
5.8. Maintenance and Repairs.......................................................................................................................... 7
5.9. Personal Protective Equipment.................................................................................................................. 7
5.10. Inclement Weather..................................................................................................................................... 8
5.11. Well Construction Materials.......................................................................................................................8
6.0 TRAINING & LICENSES.................................................................................................................................................8
7.0 REFERENCES AND RELATED DOCUMENTS...........................................................................................................8
8.0 figures.................................................................................................................................................................................. 9

Copyright 2012 by Jacobs Engineering Group Inc.


All rights reserved. The contents of this document are proprietary and produced for the exclusive benefit of Jacobs Engineering
Group Inc. No part of this document may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means,
electronic, mechanical, photocopying, recording, or otherwise, without the prior written approval of Jacobs Engineering Group Inc.

The current applicable version of this publication resides on Jacobs’ Intranet. All copies are considered to be uncontrolled.
HSEM(SWP) – 3.0 Page 2 of 12
Piling Works Rev. C, 19 Apr 12

1.0 PURPOSE
The purpose of this work instruction is to ensure the health and safety of all personnel involved
with, and working around, drill rig and other pile driving/extracting operations.
This Procedure sets forth the minimum procedures to be followed for drill rig and other pile driving/
extracting operations.

2.0 SCOPE
This Procedure applies to employees and on-site contractors engaged in operations covered by
the Company HSE program.
One or more of the subjects listed in the References section of this Procedure may also apply to
piling operations. Ensure that appropriate topics from the pertinent Procedures are reviewed and
followed.

3.0 DEFINITIONS
Cable Tool Rig method of drilling is an old technique. The technique is also known as percussion,
churn-drilling, or spudding. Cable tool rigs operate by repeatedly lifting and dropping a string of
down-hole tools.
Rotary Drilling utilizes a technique in which the drill pipe and attached bit are continuously turned
against the face of the hole. A fluid in the form of air, water, mud (bentonite and water), polymer,
or a combination of these is used to lift the cuttings to the surface, to cool and lubricate the bit, and
to keep the hole open. As the rotary bit is advanced, the fluid is forced down the center of the drill
rods and out of the bit.
Reverse Circulation Drilling is essentially the same as rotary drilling, although, as the name
implies, the fluid is forced down through an outer casing and back up to the surface through the
drill stem to a cyclone.
Hollow-Stem Augers (HSA) are essentially a form of continuous flight augers in which the helices
(flights) are welded around a hollow, tubular steel center. A cutting bit is on the lead auger. The
auger is a conveyor that lifts cuttings to the surface by rotation of the auger.
Casing Hammer Drilling uses the principles of rotary drilling in combination with a hammer
system that drives a welded casing to maintain an open bore hole.
Sonic Drilling is a relatively new technology. An extensive hydraulic system causes a counter-
balanced device to articulate rapidly at the rate of typically 20,000 to 30,000 cycles per second.
This oscillating energy is transferred to a drill stem forcing the rods into the ground.
Direct Push Technology is a hydraulic or pneumatic ram that forces the drill rod into the ground.
The weight of the vehicle serves as the counter-weight for the ram system.
Hydraulic Vibratory Driver/Extractor is used to drive or extract pipes, sheet piles and various
piles profiles unto or out of ground. As the pile is vibrated, the surrounding soil vibrates, reducing
resistance between the pile and the surrounding soil. Mounted on top of the gearbox are sets of
rubber suppressors that prevent the vibration from reaching the crane line. Mounted on the bottom
of the gearbox is the clamp attachment, which grips the pile and allows the vibro to drive or extract
the pile. A smaller vibro unit can be attached to an excavator to drive in or extract smaller piles.
Air/Steam Pile Hammers – The cycle begins at impact, the valve is rotated in such a way as to
admit steam or air into the cylinder and below the piston. This accelerates the ram upward. This
continues until the exhaust wedge on the slide bar actuates the trip and rotates the valve to close
off the steam or air inlet and opens the area of the cylinder below the piston to the atmosphere

Copyright© 2012, Jacobs Engineering Group Inc.


HSEM(SWP) – 3.0 Page 3 of 12
Piling Works Rev. C, 19 Apr 12

where the compressed air or steam is exhausted. The ram continues its free rise upward,
decelerating with gravity until the top of the piston passes the relief ports and closes in the dashpot
at the top of the cylinder. This trapped air compresses and brings the rising ram to a halt. The ram
then makes a free drop to impact. Shortly before impact the intake wedge rotates the valve to
admit steam or air to the cylinder and the cycle starts once again.

4.0 RESPONSIBILITIES
Specific HSE Program implementation responsibilities are stated in HSEM 1.4. Additional
management, staff, employee, and subcontractor responsibilities are stated in individual
procedures that address responsibilities specific to the HSE topic.

5.0 PROCEDURE
5.1. Technology Application
5.1.1. There are numerous drilling/piling technologies commonly available on the market
today such as, hollow-stem auger, air-rotary casing hammer, dual tube rotary, sonic rotary,
and direct push technology. Each drill rig or piling equipment has specific and various
capabilities depending on the tools applied. For example, the same drill rig that was used
for well installation via HSA can be used to drill structural footings with a bucket auger.
Evaluate the work and apply the most appropriate technology.
5.1.2. Likewise, terminology can vary between manufacturers, consultants, drillers,
geologists, and HSE professionals and regions of the country. Make terms clear and
concise. It is important that the drilling/piling team work from common terms to avoid any
misunderstanding.
5.1.3. Site access must be considered in selecting the drilling technology. Access
restrictions such as terrain, ecologically sensitive areas, utilities, overhead obstructions,
airport flight lines, etc. may influence the strategy for the selection of the type of drill/pile
rig.
5.1.4. Sonic drill rigs should not be used where there is the potential for unexploded
ordnance.
5.2. Subcontractor Selection
5.2.1. In the request for proposal (RFP) process, the Subcontractor Safety Questionnaire
must be included. This document is used as a tool to advise management of historical
safety performance of the prospective bidder.
5.2.2. Once proposals are received, review the safety questionnaire. By using safety
performance, rate the proposals based on the information provided.
5.2.3. To minimize company liability, inclusion of Jacobs’ general terms and conditions
within the subcontract are mandatory.
5.2.4. The client may also have specific requirements, such as those specified relevant
statutory bodies such as JTC, Mindef, LTA or Airport Authority. Ensure such requirements
are included in the piling’s subcontract.
5.2.5. The Jacobs Corporate and Singapore Operation HSE program and the Site-
Specific Health and Safety Plan (HSP) must be referenced and/or included in the
subcontract.
5.2.6. Subcontractors shall be required to follow HSEM 13.1, Subcontractor Safety.

Copyright© 2012, Jacobs Engineering Group Inc.


HSEM(SWP) – 3.0 Page 4 of 12
Piling Works Rev. C, 19 Apr 12

5.3. Initial Inspection


5.3.1. A Competent Person shall be designated to inspect all machinery and equipment
prior to the initial use on-site and on a weekly basis. All statutory equipment such as the
lifting machine, rig, lifting gears, air receivers shall be inspected by an Authorized
Examiner prior to use. Drill rig operators who have undergone the appropriate training
required by the WSH Commissioner and helpers should perform routine inspections of the
drilling equipment at least daily to ensure that the equipment is in safe operating condition.
Defective equipment will be repaired before use or continuation of use. Refer to HSEM 6.0
and 7.0 on Inspection and Maintenance requirements respectively.
5.3.2. The Authorized Examiner will make a thorough, annual inspection of all hoisting
equipment (the air receiver/compressor shall be inspected once in 24 months). Other
equipment such as the generators shall inspected periodically by an outside, third-party
agency. A record of the date and result of this inspection must be maintained.
5.3.3. Load lines should be checked routinely and thoroughly:
 The running line should be taken out of service if there are six randomly distributed
broken wires on one lay or three broken wires in any one strand in one lay.
 The rope should be taken out of service, if there is wear of one-third of the original
diameter, kinking, crushing, bird-caging, or any other distortion of the rope structure.
5.3.4. After decontamination at the site and before drilling/piling can begin. The pile/drill
rig operator and the rig geologist or engineer must complete an initial inspection and the
attached pile/drill rig inspection form.
5.3.5. During the inspection, examine the number and placement of the “kill switch(es)”
including which equipment is deactivated when the switch is engaged. The pile/drill rig
operator shall test the kill switch as part of the inspection.
5.3.6. All hydraulic, pneumatic, and discharge hoses must have adequate “whip checks”,
safety wiring, and/or clamps, which have been properly applied to prevent injury in the
event a fitting or hose breaks loose.
5.3.7. Inspect the welded attachment plates of the mast’s lifting ram for cracks and
alignment of the rams. Wire rope clips should be matched to the size of the wire rope.
Inspect for proper application of the clips.
5.3.8. Assure that the wire rope is wound about the winch drum without the rope
crossing over itself. Misapplication will cause rapid wear of the rope. Ensure that at least
one and one-half turns of rope remain (the width of the drum) while hoisting. The drum
flange shall, at all times, extend a minimum of 12.5mm over the top layer of rope.
5.3.9. Inspect the drill rig for system leaks. A spill control kit of sufficient size should be
maintained on the rig.
5.3.10. Perform a visual inspection of the rigging, wire ropes, chains, hooks, clevises,
swivels, etc. Use simple and inexpensive measuring gauges to ensure that wear is not
excessive.
5.3.11. Wire rope clips should be matched to the size of the wire rope. Inspect for proper
application of the clips.
5.3.12. All platforms and walkways shall have antiskid surfaces.
5.4. Pile/Drill Rig Safety
5.4.1. Rated load capacity charts, recommended operating speeds, special hazard
warnings, and other essential information must be posted in a conspicuous location on drill

Copyright© 2012, Jacobs Engineering Group Inc.


HSEM(SWP) – 3.0 Page 5 of 12
Piling Works Rev. C, 19 Apr 12

rigs, hoists, and other equipment. Never exceed manufacturer’s recommendations.


Never attempt to lift more than the rated capacity of any machine or its rigging.
5.4.2. Do not perform routine maintenance, fueling, or repairs while the equipment is in
use.
5.4.3. Never allow anyone to ride the hook or the load.
5.4.4. A fire extinguisher, rated at least 21B, must be available at all operator stations or
cabs of drill rigs and at least 70B rated fire extinguisher near the generators.
5.4.5. Safety latches are required on all hooks. Taglines must be used when handling
loads.
5.4.6. Loads must not be swung over the heads of personnel in the area.
5.4.7. Outriggers must be extended fully to ensure the machine’s full capacity.
5.4.8. Never leave a machine with a load suspended.
5.4.9. “Walking” of suspended loads should be avoided. Where necessary to do so, the
following steps must be taken:
 Investigate the route to be followed for solid and level footing.
 Tie load to the frame of drill rigs or use tag lines.
 Follow manufacturer’s recommendations.
5.4.10. Weight of the load must be established prior to lifting and must be within
manufacturer’s capacity charts. Check brakes and machine stability when load is only
inches above the ground.

5.4.11. Always the hammer is lower choked or blocked in the leads or lowered to the
ground whenever piling rig is not in use.
5.4.12. The pile/drill rig operator must not attempt any lift if conditions are inadequate or
hazardous.
5.4.13. Spreader bars, eye pads, personnel baskets, and lifting devices of all kinds will be
evaluated and approved by the Site Manager and inspected by the Authorized Examiner
prior to use.
5.5. Pile/Drill Rig Set-up Procedures
5.5.1. Ensure compliance with the utility clearance process prior to mobilizing the drill
rig. Refer to HSEM (SWP) 2.0.
5.5.2. Adequately prepare pile/drill pad and stabilize rig to prevent rig turnover.
5.5.3. A firm, level foundation capable of supporting the load and drill rig shall be
provided and maintained. Avoid areas where extensive fill is required to level the pad.
Compaction is necessary if significant amounts of fill are needed.
5.5.4. Where there is surface contamination, use clean fill or gravel to cover areas of
contamination and provide a level work area. Cover material may be considered
contaminated at the conclusion of work in the area. The cost of remediation may be
increased due to the increase in the quantity of contaminated materials to be treated. To
minimize cost, rather than placing a material cover over contaminated surface materials,
simply decontaminate the drill rig and associated equipment that may have become
contaminated from contact with the contaminated ground surface before leaving the site.
See HSEP 8.9, Drilling in VOC Contaminated Soil, for additional precautions.

Copyright© 2012, Jacobs Engineering Group Inc.


HSEM(SWP) – 3.0 Page 6 of 12
Piling Works Rev. C, 19 Apr 12

5.5.5. Blocking-materials or mats under outriggers must be adequate to support the


pile/drill rig for the ground condition.
5.5.6. Establish an exclusion zone on all sides of the work area that is at least the height
of the mast.
5.5.7. Have plastic sheeting of sufficient size or drip pan available to provide coverage of
the entire undercarriage of pile/drill rig and support vehicles and equipment in the event of
hydraulic fluid or fuel releases. Keep plastic in place until necessary repairs can be made.
Remove excess sheeting that could pose a slip hazard beyond the pile/drill stand.
5.5.8. Regardless of the weight of the load, all lifts and sets must be performed with all
hydraulic outriggers fully extended in order to level and stabilize the rig prior to drilling.
5.5.9. Pick-and-carry operations are allowed only when a firm level foundation, which will
support the load and drill rig, is provided.

5.6. Pile/Drill Rig Work Near Overhead Electric Lines


5.6.1. Any overhead line must be considered energized unless it is disconnected and
physically grounded or temporarily taken out of service by a lock-out/tag-out method.
5.6.2. No part of motorized equipment, including the load, may be allowed to get closer
to bare live circuits or apparatus than the distances indicated:
Nominal Voltage Minimum Clearance
0 – 50 KV 6m (20 ft.), or one mast length; whichever is
greater
50 KV+ 6m + 100mm (20 ft. + 4 in.) for every 10 KV
over 50 KV or 1.5 mast lengths; whichever is
greater
5.6.3. Warning flags or other suitable devices should be positioned to define the
operating clearance distance to the power line, while adjacent to personnel or equipment.
5.6.4. When it becomes necessary for a mast or any part of the rig or similar equipment
to be swung, worked, or moved (including transit between worksites) within the required
clearances listed above, the work must be stopped immediately. The rigging
superintendent, the site manager, and Site HSE are to be contacted.
5.6.5. The individuals mentioned in 5.6.4, in conjunction with client personnel will decide
which of the following steps must be taken.
 The line must be identified, de-energized, and properly tagged and locked out. The
line must also be visibly grounded at the point of work.
 If the above is not possible, the following precautions must be taken.
 Any motorized equipment must be grounded with #2/0 wire to a permanent
ground or a temporarily installed ground rod.
 An observer must be stationed to warn the operator while the drill rig, boom, or
load is in motion.
 No one can be allowed to come in contact with the motorized equipment or load
while the equipment is in motion. All tag lines must be constructed of non-
conductive material.
 Additional precautions which may be taken to avoid contact with the line include:

Copyright© 2012, Jacobs Engineering Group Inc.


HSEM(SWP) – 3.0 Page 7 of 12
Piling Works Rev. C, 19 Apr 12

 Temporary insulation sleeves, which may be installed on the power line: (Note
that there is also considerable hazard involved in this procedure, and the use of
temporary sleeves must be evaluated on a case-by-case basis.)
 Angle borings; and
 Warning flags or other suitable devices that may be positioned to define the
allowable operating radius of the equipment, while adjacent to personnel or
equipment.
5.7. Equipment Operation – Angle Borings
5.7.1. Angle borings are typically used when a sample point cannot be accessed from a
vertical position. Examples of these are:
 Under power lines
 Under building foundations,
 Under river channels, or
 Where extremely high levels of contamination pose a health or fire hazard for the
drilling crew.
5.7.2. The approximate vertical depth is calculated based on the cosine of the angle of
the boring and the angled length of the borehole.
5.7.3. An angle of less than 30 degrees (measured between the ground surface and the
mast) is usually not acceptable except for short drilling distances. This is due to the
rotation of the auger causing the drill stem to “walk” away from the desired sample point,
which can endanger personnel or cause equipment damage.
5.7.4. Although angle borings are useful, they can have difficulty in achieving the desired
results, particularly in soils with cobbles or boulders. These obstructions can deflect the
drill stem to an undesired position.
5.7.5. With these restrictions in mind, pay careful attention when drilling or angle boring
under utilities or other known obstructions to prevent inadvertent contact.
5.8. Maintenance and Repairs
5.8.1. To ensure safe operations, the pile/drill rig and ancillary equipment should receive
routine maintenance in accordance with manufacturer’s recommendations.
5.8.2. A lock-out/tag-out process is required prior to any maintenance activity or repair.
When a drive head cannot be completely lowered to the drill table, the drive head should
be properly blocked and supported.
5.8.3. The mast must be lowered when head works repairs are being performed. If this
is impossible, follow fall protection practices.
5.8.4. Welding and cutting repairs on the pile/drill rig pose flammability hazards and may
cause high strength steel to be damaged. There should not be open flames within 15m of
combustible materials such as diesel fuel tanks. If this distance cannot be maintained,
place noncombustible welding mats over tanks or other combustibles to protect from
sparks and hot slag. Protect hydraulic lines as well.
5.8.5. A qualified welder familiar with the weld grades, weld types, and material specified
in the pile/drill rig design should perform all welding on pile/drill rigs or its components.

Copyright© 2012, Jacobs Engineering Group Inc.


HSEM(SWP) – 3.0 Page 8 of 12
Piling Works Rev. C, 19 Apr 12

5.8.6. Machine guards must be utilized and maintained on the drill rig to protect
personnel from belts, gears, shafts, pulleys, sprockets, spindles, drums, flywheels, or
other reciprocating, rotating, or other moving parts or equipment or other hazards.
5.8.7. Always replace guards after servicing the rig or equipment. When a pinch point
cannot be guarded, paint the point bright yellow and post an appropriate warning sign.
Provide a safe distance barrier and allow only authorized personnel to enter the zone.
5.9. Personal Protective Equipment
5.9.1. Personal Protective Equipment (PPE) should be viewed as the last line of defense
against mechanical and chemical hazards. The use of PPE does not guarantee freedom
from injury. In many cases, PPE mitigates, but does not eliminate, forces of impact,
abrasion, etc.
5.9.2. In addition to chemical protective clothing that may be required for the site, all
personnel must wear SS 98 or equivalent type of hardhats, SS 473 standard safety
glasses with side shields or goggles, and SS 513 or equivalent safety footwear. Bump
hats, sport glasses, and tennis shoe style safety shoes are not acceptable.
5.9.3. Because of the noise levels typically associated with operation of a piling
operation, hearing protection is required in the area.
5.10. Inclement Weather
Adverse weather conditions requiring immediate suspension of field activities are:
5.10.1. Thunderstorms and Lightning
A 30-minute stand down period is maintained from the last observed lightning to allow
proper distance for the storm to pass.
 Take shelter in buildings or hard top vehicles with the windows rolled up and away
from trees, power lines, bodies of water, and the drill mast, etc
 If caught outside, place hands over ears and squat down with feet close together and
flat on the ground. Always attempt to be lower than the highest object around but do not
lie on the ground.

5.10.2. Wind Speeds


 Sustained wind speeds of 40 to 64 km/h or wind gusts of 56 to 72 km/h.
 Tornado, hurricane, blizzard

5.10.3. Other Inclement Weather Conditions


 Freezing rain during hoist and cat-head activities
 Moderate rain during hoisting activities
5.11. Well Construction Materials
5.11.1. Common well construction materials are graded sand, bentonite, and Portland
cement. All these material contain varying amounts of crystalline silica. Minimize
exposure by wetting the material, using respiratory protection, and by following the safe
handling procedures in the manufacturer’s instructions and in the material safety data
sheets.
5.11.2. Packages of these materials range from 11.3 to 45.4kg. Use material handling
equipment such as forklifts whenever possible. Practice good lifting techniques.

Copyright© 2012, Jacobs Engineering Group Inc.


HSEM(SWP) – 3.0 Page 9 of 12
Piling Works Rev. C, 19 Apr 12

6.0 TRAINING & LICENSES


6.1.1. Pile/Drill rig operators shall be certified to operate the pile/drill rig. A copy of their
crane operator license and piling rig operator certificates should be on file with the HSE
representative prior to beginning work.
6.1.2. The piling/drilling company should also provide evidence of a current Approved
Crane Contractor certificate.
6.1.3. Assure compliance with regulatory and client license and permit requirements.
6.1.4. Additional documentation may be required, such as employee training and
physician written opinion reports.

7.0 REFERENCES AND RELATED DOCUMENTS


Workplace Safety and Health Act
WSH (Construction) Regulations
WSH (Operation of Cranes) Regulations.
WSH (Noise) Regulations.
HSEM 13.1, Subcontractor Safety
http://IADC.org, Web site for the International Association of Drilling Contractors
HSEM(SWP) 2.0: Utility Clearance
HSEM (SWP) 34.0 Basic Ergonomic
HSEM(SWP) 18.0: Material Handling
HSEM(SWP) 24.0: Hot Work
HSEP 8.9: Drilling in VOC Contaminated Soil
HSEM(SWP) 11.0: Unexploded Ordnance Clearance
HSEM 12.8 series related to Radiation
HSEM 12.0 series related to Health e.g. hearing, respiratory.
HSEM 17.0 series related to Environmental & Industrial Hygiene
HSEM 2.3: Personal Protection Program
HSEM 11.0 series related to Emergency & Contingency Planning
HSEM(SWP) 14.0: Lock-out/Tag-out
HSEM 7.0 series related to Maintenance Regime, Tools & Equipment
HSEM(SWP) 16: Machine Guarding
HSEM(SWP) 21.0: Rigging
HSEM(SWP) 22.1: Lifting Operation
HSEM(SWP) 23.0: Crane Suspended Work Platform
HSEM(SWP)15.0 series related to Electrical Installation/Energization
HSEM 16.1: Transportation of Materials and Personnel

Copyright© 2012, Jacobs Engineering Group Inc.


HSEM(SWP) – 3.0 Page 10 of 12
Piling Works Rev. C, 19 Apr 12

HSEM 16.2: Motor Vehicle Safety


The Site-Specific Health and Safety Plan
SS536 : 2010 Code of Practice on the Safe Use of Mobile Crane
SS532 :2007 Code of Practice for Storage of Flammable and Combustible Liquids.
CP 49 : 1998 Code of Practice for Noise Control on Construction and Demolition Sites.
SS 510 : 2005 Code of Practice for Safety in Welding and Cutting (and Other Operations Involving
The Use of Heat).
29 CFR 1910.120, Hazardous Waste and Emergency Response Operations
29 CFR 1910.180, Crawler, Locomotive and Truck Cranes

8.0 FIGURES
Drill/Pile Rig Inspection Form

Copyright© 2012, Jacobs Engineering Group Inc.


HSEM(SWP) – 3.0 Page 11 of 12
Piling Works Rev. C, 19 Apr 12

Drill/Pile Rig Inspection


Date__________________________ Inspector_________________________________
Rig # _________________________ Company_________________________________
Rig Type______________________ JE Oversight______________________________
Pile/Drill Rig/Support Equipment Yes No N/A Repaired
1. Are there obvious hose/connection leaks on rig?
2. Are hydraulic system safety shut offs in proper condition?
3. Are hand tools and power tools maintained in good repair?
Is there evidence of wearing or grooving of cathead to a
4. depth greater than 3mm (1/8”), indicating replacement
required?
Are casing hammer cables, shackles, and hammer rails in
5.
safe condition?
Are air and water hoses/connections in good repair; whip
6.
checks installed properly?
7. Is pumping equipment properly secured to rig?
8. Are pump pressure regulators set at approved PSI rating?
9. Is welding equipment properly secured to rig?
10. Are oxygen & acetylene bottles properly stored & labeled?
Are welding torches (gas) equipped with anti-flashback
11.
check valve between bottle regulator & torch manifold?
Are compressed air tanks regularly purged of excess
12.
moisture accumulation (air brakes)?
Are fossil fuels and flammable solvents stored/dispensed
13.
from approved safety cans? Properly labeled?
Are discharge hoses on dual type percussion rig properly
14.
restrained / barricaded against striking personnel?
15. Is Haz Mat spill control kit available/well stocked?
Are proper number and kinds of outrigger pads, blocking,
16.
cribbing on hand?
Are kill switches operating?
17a.
Initials of person who tested switches: ____________
17b. Indicate how to activate kill switch.
Rigging/Material Handling Equipment
Is all material handling equipment used and maintained in
18. accordance with WSH Act, code of practice and/or
manufacturers recommendations?
Has all hoisting equipment been completely inspected for
19.
broken wires, crushing, bird-caging, or other damage?
Do all wire ropes have sufficient rated capacity for the
20.
hoisting equipment used and the lifts being performed?

Copyright© 2012, Jacobs Engineering Group Inc.


HSEM(SWP) – 3.0 Page 12 of 12
Piling Works Rev. C, 19 Apr 12

Pile/Drill Rig/Support Equipment Yes No N/A Repaired


21. Is correct number of wire rope clamps in use & installed?
22. Is a thimble installed in all hoisting eyes?
23. Do hooks have approved safety latch installed?
24. Does hook rating match rated tonnage of winch?
25. List hoisting equipment inspected:
MOM Reg. Number Description

Protective Systems/Equipment
Are all guards, etc. in place around pinch points, moving
26.
machinery etc. and in good repair?
Are mechanical pinch points on drilling rig properly
27.
labeled/color coded?
Is there adequate fall protection equipment available if
28.
climbing the mast is necessary?
If derrick platform is more than 1.2m (4 ft.) above grade, is
29.
it equipped with safety railing and toe boards as required?
Are signs stating caution/danger shock or electrocution
30.
hazard in place on the mast?
Is there a possibility for exhaust fumes from the drilling rig
31.
to accumulate and affect worker’s health?
Is adequate lighting, in accordance with WSH Act and
32.
SS567 installed for night operations?
Are all workers wearing proper hard hats, safety boots,
33.
and safety glasses?
Are there an adequate number of fire extinguishers,
34.
portable eye wash(es), and first aid kit(s) on site?
Programs/Plans
Are assured grounding procedures for equipment and
35.
power tools being followed?
Are drillers following a “code of safe practices” developed
36.
by the contractor?
Is there a safe procedure in place for guiding drill rods or
37.
pipe sections into racks or onto transport vehicle?
38. Is a certified CPR/First Aid trained individual with the rig?

Comments:

Copyright© 2012, Jacobs Engineering Group Inc.

You might also like