WORK SCHEDULE FOR Mrs JAYANTHI & FAMILY ( 05-03-2021 ) -MERAKI ARCHITECTS

S.NO WORK START FINISH REMARKS


1 PCC Work in bedroom 08-03-2021 09-03-2021
2 Ceiling rework 08-03-2021 09-03-2021
3 Ceiling Plastering 11-03-2021 13-03-2021 Electrical piping has to be done before .
4 Kitchen table top 15-03-2021 16-03-2021
5 Electrical khardy plastering 13-03-2021 13-03-2021
6 Steps ( Entrance steps construction ) 15-03-2021 15-03-2021
7 Corner & Lintel plastering ( inner ) 17-03-2021 20-03-2021 Door and window frame has to be done before .
8 Parapet wall construction 22-03-2021 23-03-2021 Design and quote has to be finalised
9 Suruki pouring work 25-03-2021 25-03-2021
10 Corner plastering ( Exterior ) 29-03-2021 31-03-2021
11 Tiles laying 01-04-2021 03-04-2021
12 Interlock brick finishing ( inner ) 05-04-2021 07-04-2021
13 Interlock brick finishing ( outer ) 08-04-2021 10-04-2021
14 Sunshades & Sitout erecting 12-04-2021 15-04-2021 Design and quote has to be finalised

Mode of Payment

Percentage of
S.NO Type amount
1 Advance 15%
After the completion of PCC , ceiling
2 rework & Ceiling plastering . 20%
After the completion of Kitchen table top ,
Electrical khardy plastering , Steps (
Entrance steps construction ) Corner &
3 Lintel plastering ( inner ) . 20%
After the completion of parapet wall
construction , Suruki pouring work , Corner
plastering ( Exterior ) , After the completion
4 of Tiles laying . 30%

After the completion of Interlock brick


finishing ( inner ) , Interlock brick finishing (
5 outer ) , Sunshades & Sitout erection 15%