Professional Documents
Culture Documents
HYDRAULICS
E. Shashi Menon
A CRC title, part of the Taylor & Francis imprint, a member of the
Taylor & Francis Group, the academic division of T&F Informa plc.
Q P Z T
u2 = 0.002122 b2 b 2 2 (USCS units) (2.27)
D Tb P2
Q P ZT
u = 0.002122 b2 b (2.28)
D Tb P
Q P ZT
u = 14.7349 b2 b (SI units) (2.29)
D Tb P
where
u = gas velocity, m/s
Qb = gas flow rate, measured at standard conditions, m3/day
D = pipe inside diameter, mm
Pb = base pressure, kPa
Tb = base temperature, K(273 + °C)
P = pressure, kPa
T = average gas flowing temperature, K(273 + °C)
Z = gas compressibility factor at the flowing temperature, dimensionless
Since the right-hand side of Equation 2.29 contains ratios of pressures, any
consistent unit can be used, such as kPa, MPa, or Bar.
We have seen from the preceding section that the gas velocity is directly related to
the flow rate. As flow rate increases, so does the gas velocity. How high can the gas
velocity be in a pipeline? As the velocity increases, vibration and noise are evident.
In addition, higher velocities will cause erosion of the pipe interior over a long
period of time. The upper limit of the gas velocity is usually calculated approximately
from the following equation:
100
umax = (2.30)
ρ
where
umax = maximum or erosional velocity, ft/s
r = gas density at flowing temperature, lb/ft3
Since the gas density r may be expressed in terms of pressure and temperature,
using the gas law Equation 1.8, the maximum velocity Equation 2.30 can be rewritten as
ZRT
umax = 100 (USCS units) (2.31)
29GP
where
Z = compressibility factor of gas, dimensionless
R = gas constant = 10.73 ft3 psia/lb-moleR
T = gas temperature, °R
G= gas gravity (air = 1.00)
P = gas pressure, psia
Example 1
A gas pipeline, NPS 20 with 0.500 in. wall thickness, transports natural gas (specific
gravity = 0.6) at a flow rate of 250 MMSCFD at an inlet temperature of 60°F. Assuming
isothermal flow, calculate the velocity of gas at the inlet and outlet of the pipe if the
inlet pressure is 1000 psig and the outlet pressure is 850 psig. The base pressure and
base temperature are 14.7 psia and 60°F, respectively. Assume compressibility factor
Z = 1.00. What is the erosional velocity for this pipeline based on the above data and
a compressibility factor Z = 0.90?
Solution
If we assume compressibility factor Z = 1.00, then using Equation 2.26, the velocity
of gas at the inlet pressure of 1000 psig is
1014.7
u2 = 21.29 × = 24.98 ft/s
864.7
Example 2
A gas pipeline, DN 500 with 12 mm wall thickness, transports natural gas (specific
gravity = 0.6) at a flow rate of 7.5 Mm3/day at an inlet temperature of 15°C. Assuming
Hydrogen Piping
and Pipelines
ASME Code for Pressure Piping, B31
--```,``,`,`,,,``,```,,`,,,,,`,`-`-`,,`,,`,`,,`---
A N A M E R I C A N N AT I O N A L STA N DA R D
--```,``,`,`,,,``,```,,`,,,,,`,`-`-`,,`,,`,`,,`---
(c) overpressure shutoff valve(s) upstream or down-
stream of the controlling regulator(s) I-3.6 Electrical Facilities and Electronic Equipment
Installation of alarm devices which indicate primary for Pressure/Flow Control and Metering
(controlling) regulator failure are useful and should be Facilities
considered for monitor regulator systems.
I-3.6.1 All electrical equipment and wiring
I-3.4.2 Each regulator supply, control, and sensing
installed in pressure/flow control facilities and metering
line shall have a separate isolation valve for isolation
facilities shall conform to the requirements of NFPA 70
purposes during regulator setup and maintenance, and
or other applicable electrical codes. Additional API and
to prevent a safety device (i.e., monitor, regulator) from
AGA references are listed in Mandatory Appendix II.
becoming unintentionally inoperable due to plugging
or freezing of instrument lines.
I-3.6.2 Electronic control, monitoring, and hydro-
I-3.4.3 Steps shall be taken to prevent the freezing- gen gas measurement equipment shall be properly
up (internal and external) of regulators, control valves, grounded and isolated from piping to help prevent over-
instrumentation, pilot controls, and valve actuation pressure/accidental shutoff situations caused by equip-
equipment caused by moisture saturated instrument air ment failure due to lightning strikes and electrical
or hydrogen gas, or external ambient conditions. transients and to prevent safety hazards caused by fault
I-3.4.4 Sound pressure levels of 110 dbA and currents. Electrical isolation equipment for corrosion
greater shall be avoided to prevent damage to control control purposes should not be installed in buildings
equipment and piping. unless specifically designed to be used in combustible
atmospheres.
I-3.4.5 Hydrogen gas velocities in piping should
not exceed the erosional velocity at peak conditions.
Lower velocities are recommended. The erosional veloc-
I-3.6.3 Uninterruptible power sources or redun-
dant backup systems shall be considered to help prevent
ity, ue, is calculated by:1
overpressure/unintentional shutoff situations caused by
100 power outages.
ue p
冪 ZRT
29GP
I-3.6.4 A useful reference for electronic hydrogen
1 gas measurements is API Manual of Petroleum
Mohitpour, M., H. Golshan, and A. Murray. Chapter 3 in Pipeline
Design & Construction: A Practical Approach, 3d ed. New York: ASME Measurement Standards, Chapter 21, Section 1 —
Press, 2007. Electronic Gas Measurement.
158
Copyright ASME International
Provided by IHS under license with ASME Licensee=Bogazici University/5964815002, User=ahmadi, rozita
No reproduction or networking permitted without license from IHS Not for Resale, 04/02/2015 11:04:40 MDT
HYDROGEN PIPELINE SYSTEMS
AIGA 033/14
(Re-affirmed AIGA 033/06)
Siting and safety distances should follow established practices and applicable regulations. Typical
arrangements for siting of hydrogen stations in relation to other areas and equipment can be found in
the table of Appendix E.
This chapter describes how the design philosophy presented in Chapter 4 can be applied in practice
to piping, valves, specific piping components and equipment configurations.
Selection of material for pipes, valves, equipment, etc. shall be in accordance with Sections 5.4, 5.5
and 5.6.
Due to the hazardous nature of the gas, above ground pressure containing parts such as piping, valve
bodies, strainer and filter housings, etc. shall be made of metallic materials only. The use of non-
metallic materials shall be limited to services such as valve internals (inserts only), external coatings,
etc. which do not provide primary mechanical strength.
One of the most important criteria is resistance to stress corrosion cracking and hydrogen
embrittlement. The risk of these occurring is increased at higher temperatures and pressures and is
mitigated by low stress levels. Therefore, material selection, fabrication processes, and material
thicknesses should be chosen with a view towards achieving low residual stresses. Typical methods
of lowering stresses once the operating temperature and pressure have been decided are closer pipe
support spacing, thicker pipe walls, thermal relieving residual welding stresses.
There are no special velocity restrictions for piping in hydrogen service other than the underlying
economics. However, the sonic velocity of hydrogen is approximately four times that of most
flammable gases. Therefore, close attention should be paid to possible erosion and abrasion at such
items as control valves and relief valves which usually will have sonic or near sonic velocities.
Because of the high sonic velocity, it is quite possible that problems will arise at differential pressures
which would not have caused a problem with most other gases.
As hydrogen systems may pose a fire or explosion risk, electrical systems shall be in accordance with
the applicable codes. These provide requirements and suggestions for determining the level of hazard
(classification) and mitigating the risks involved. Typically used codes are:
The type of electrical equipment which may be installed and the installation methods depend upon the
level of hazard classification and are described in the prescriptive sections of the codes.
It is worth noting that the equipment and piping should be carefully bonded and grounded to drain
static electricity and to carry electrical fault currents to earth ground, to prevent the release of electric
sparks which could ignite hydrogen leaks in the area.
21
HYDROGEN TRANSPORTATION
PIPELINES
IGC Doc 121/04/E
GLOBALLY HARMONISED DOCUMENT
Due to the hazardous nature of the gas, above ground pressure containing parts such as piping, valve
bodies, strainer and filter housings, etc. shall be made of metallic materials only. The use of non-
metallic materials shall be limited to services such as valve internals (inserts only), external coatings,
etc. which do not provide primary mechanical strength.
One of the most important criteria is resistance to stress corrosion cracking and hydrogen
embrittlement. The risk of these occurring is increased at higher temperatures and pressures and is
mitigated by low stress levels. Therefore, material selection, fabrication processes, and material
thicknesses should be chosen with a view towards achieving low residual stresses. Typical methods
of lowering stresses once the operating temperature and pressure have been decided are closer pipe
support spacing, thicker pipe walls, thermal relieving residual welding stresses.
There are no special velocity restrictions for piping in hydrogen service other than the underlying
economics. However, the sonic velocity of hydrogen is approximately four times that of most
flammable gases. Therefore, close attention should be paid to possible erosion and abrasion at such
items as control valves and relief valves which usually will have sonic or near sonic velocities.
Because of the high sonic velocity, it is quite possible that problems will arise at differential pressures
which would not have caused a problem with most other gases.
As hydrogen systems may pose a fire or explosion risk, electrical systems must be in accordance with
the applicable codes. These provide requirements and suggestions for determining the level of hazard
(classification) and mitigating the risks involved. Typically used codes are:
• National Fire Protection Association (NFPA) 70
• IEC 79
• NFPA 496, 497
• American Petroleum Institute RP 500 A,B,C
• European directive ATEX 94/9
The type of electrical equipment which may be installed and the installation methods depend upon the
level of hazard classification and are described in the prescriptive sections of the codes.
It is worth noting that the equipment and piping should be carefully bonded and grounded to drain
static electricity and to carry electrical fault currents to earth ground, to prevent the release of electric
sparks which could ignite hydrogen leaks in the area.
5.4 Piping
Welded connections are preferred and should be used wherever practical to minimize potential leak
sources. Threaded connections which are seal welded are considered as welded connections for this
purpose. Either seamless or longitudinally welded pipe and wrought or machined fittings shall be used
except in exceptional circumstances e.g. absolute unavailability.
5.4.1 Venting
The flammability and auto ignition potential of hydrogen gas is a significant potential risk factor.
Therefore, care must be taken when venting. The discharge piping from all vent sources such as vent
valves, safety relief valves, compressor packing vents, etc. must be piped to a properly designed and
sited disposal system which may be as simple as a single pipe or as complex as a manifolded
collection header connected to a flare. The back pressure this creates must be properly accounted for
in the design, especially on safety relief valve discharges (API RP 520, 521 are often used reference
documents for this). There are two types of systems which may be used – venting to atmosphere and
destruction in a flare. The same materials as are used elsewhere in the pipe line should also be used
for vent collection and disposal piping with one exception which is discussed below under venting to
atmosphere.
19
NORSOK STANDARD
PROCESS DESIGN
P-001
Rev. 3, November 1997
Process Design P-001
Rev. 3, November 1997
The maximum velocity in carbon steel should not exceed 4 m/s to avoid problems such as
cavitation/erosion on bends and damage to inline equipment/vessels internals.
5.4.1 General
Gas lines shall generally be sized in order to not exceed the acceptable noise level at the platform.
Piping with gas at the dewpoint and/or with some droplets shall be designed as gas lines.
0.43
1
V = 175 ρ or 60 m/s, whichever is lowest
The requirement set by this formula can be omitted by doing more detailed noise calculations
of individual pipes. Where high noise levels are not considered as a problem, the maximum
velocity can be calculated as for gas relief lines.
For sizing and arrangement connected to and adjacent to pressure control valves in order to
avoid excessive dispersion of noise, the valve manufacturer shall be considered.
For antisurge lines the constant 175 in the formula may be replaced with 200 during process upsets,
if the noise level is acceptable. However, during normal recycle, the velocity shall be limited to the
velocity as given by the equation above.
Corrosive service
For carbon steel piping systems the corrosion rate often limits the life time. With increased flow
velocity the corrosion rate tend to increase due to increased shear forces and increased mass
transfer.
The flow velocity shall be restricted to maximum 10 m/s to limit the erosion of the protective layer
of corrosion products and reduce the risk for a corrosion inhibitor film break down.
Nevertheless, the actual back pressure at the PSV outlet and in the block valve shall be checked to
be consistent with back pressure limitations.
The pressure loss shall be so as to not impose any restrictions on the depressurisation objectives.
6.1.1 General
It shall be possible to isolate equipment or process sections during maintenance work to obtain safe
working conditions for the maintenance personnel. Process sections will also be isolated for leak
testing before commissioning, after a maintenance operation, and for pressure testing.
Double block and bleed should only be used on hydrocarbon systems after considering the
following:
• special safety considerations
• the system is critical for the overall regularity
• the equipment is maintained when the rest of the process system is in operation