Ser Key Plan Responsibility Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
ST-01 Stair Finishing and Railing Works BEL, FGM Order Order
GF - Ground Floor Anti-slip Tiles (Kota Stone) Work BEL, FGM TN TN TN TN Tiles
FF, FFM, SF - Floor Tiles Works (Granite and Red Mandana) BPL, DRL, Aevitas Evaluation Evaluation Order TN TN TN TN TN TN TN TN Tiles Tiles
Glass Curtain Wall and Louver Fittings BEL, FGM Selection Order TN TN TN Glass - Ph 1 Glass - Ph 2
FF, FFM, SF - Construction of Remaining Walls with Window Fitting and Plastering after Machine Entry BEL, FGM
RF - Ceramic Tiles Works in all Roofs (RF, ST-01, 02, 03 Roof). BEL, FGM
Face Lifting Structure BEL, FGM Design Design Design Design Offer Selection Order
Face Lifting Fencing and Perforated Metal Sheet Fixing Works BEL, FGM Offer Selection Order
Footpath with Ceramic Tiles Work BEL, FGM
Bone Deck Sheet Painting Works FGM Painting
All Floors - Internal Painting Works BEL, FGM Painting Painting
All Floors - External Painting Works (Weather Coat) BEL, FGM Painting Painting
4.2 SF1 (130 °C) & SF2 (+40 °C) Skid Polmon, BPL, DRL Email Order Order LT LT FAT TN TN INSTL
4.4 SF4 Brine Chiller Voltas, BPL, DRL Offer Selection Selection Selection Order & LC Order & LC LT LT LC LT LT LT LT TN TN INSTL
4.5 Raw Water Supply (5000 L/day) Aevitas, BPL, DRL INSTL INSTL INSTL INSTL INSTL
4.6 Purified Water (PW) with Pre-treatment System Aevitas, BPL, DRL Offer Selection Selection Selection Selection Selection Order & LC LC LC LC LT LT LT TN TN INSTL INSTL COMM VAL
4.7 Smaller Equipment (ETPT, CRT, ET, Air & N2 Receiver, and DT) Aevitas, BPL, DRL URS Offer Selection LC LT LT TN TN TN INSTL COMM VAL
4.8 Nitrogen (Liquid and Gaseous) Distribution 3 N-m3/hour Aevitas, BPL, DRL BOQ Offer Selection Selection Order Order & LC LT LT TN TN TN INSTL INSTL COMM VAL
4.9 Compressed Air (CA) Distribution 90 ft3/minute Aevitas, BPL, DRL BOQ Offer Selection Selection Order Order & LC LT LT TN TN TN INSTL INSTL COMM VAL
4.10 Steam Distribution 650 kg/hour Aevitas, BPL, DRL BOQ Offer Selection Selection Order Order & LC LT LT TN TN TN INSTL INSTL COMM VAL
4.11 Fire Hydrant System Distribution Aevitas, BPL, DRL BOQ Offer Selection Order LT LT LT INSTL INSTL INSTL
4.12 Fire Extinguishers Aevitas, BPL, DRL BOQ Offer Selection Order LT LT LT INSTL INSTL INSTL
Serial Equipment Name Quantity Vendor(s) Lead Time Email LOI LC Opening Date Advance GAD Approval QA Plan Project Schedule DQ Approval IQ Approval OQ Approval Electrical Foundation FAT Schedule FAT Protocol FAT Report Vendor's Dispatch Confirmation Shipping As Built Photos Arrival at Site Remarks
No (Nos) (LOI to Shipment) Confirmation Drawings Drawings Shipment By Documents Drawings
(in Weeks) On
1 Vibro Sifter (SIF) 1 Oleya Equipments 12 12 Jun 2017 Issued 18 Jul 2017 Approved Received Approved Approved On Wheel FAT by Oleya Internally Approved 20 Oct 2017 Dispatched Received Received Received 20 Nov 2017
2 Multimill (MM) 1 Oleya Equipments 12 12 Jun 2017 Issued 18 Jul 2017 Approved Received Approved Approved On Wheel FAT by Oleya Internally Approved 20 Oct 2017 Dispatched Received Received Received 20 Nov 2017
3 Air Jet Mill (AJM) 1 Microtech Engineering Company 14 22 Jun 2017 Issued 07 Aug 2017 Approved Received Approved Approved On Wheel FAT by Microtech Internally Approved 10 Oct 2017 Dispatched Received Received Received 30 Nov 2017
4 Sparkler Filter (SF) 1 Sawant Filtech Pvt. Ltd. 10 19 Jun 2017 Issued 07 Aug 2017 Approved Approved NA Approved On Wheel FAT by Sawant Received 10 Oct 2017 Dispatched Received Received Received 30 Nov 2017
5 Vacuum Nitrogen Sealing (VNS) 1 Cybernetik Technologies Pvt. Ltd. 10 13 Jul 2017 Issued 07 Aug 2017 Approved Received Approved Approved On Wheel FAT by Cybernetik Approved 10 Oct 2017 Dispatched Received Received Received 07 Dec 2017
6 Co Mill (CM) 1 Cybernetik Technologies Pvt. Ltd. 10 13 Jul 2017 Issued 07 Aug 2017 Approved Received Approved Approved On Wheel FAT by Cybernetik Approved 10 Oct 2017 Dispatched Received Received Received 07 Dec 2017
7 SF1 (130 °C) & SF2 (+40 °C) Skid 2 Polmon Vesnfer Pvt. Ltd. 14 13 Jul 2017 Issued 10 Sep 2017 Approved Received Approved Approved Approved Approved Fix, No Base FAT by Aevitas Received Received 10 Dec 2017 Dispatched Received Received Received 28 Dec 2017
8 Vacuum Tray Dryer (VTD) 2 Perfect Engineering 6 20 Aug 2017 Issued 21 Sep 2017 Approved Approved Approved Received Not Needed Above FF FAT by Perfect Received 10 Dec 2017 Dispatched Received Received Received 11 Jan 2018
9 Heat Exchanger (06 Nos HCHE) 6 HRS Process Systems Ltd. 14 13 Jul 2017 Issued 07 Aug 2017 Approved Approved Received Approved NA Hanging FAT by HRS NA Internally Approved 10 Oct 2017 Dispatched Received Received 22 Jan 2018
10 Vacuum Pump (VP) 6 Toshniwall Instruments 8 20 Aug 2017 Issued 05 Nov 2017 Approved Not Needed Not Needed Base FAT by Toshniwal Comments Sent 10 Jan 2018 Dispatched Received Received 23 Jan 2018
11 Cooling Tower 1 Paharpur 14 14 Jun 2017 Issued 07 Aug 2017 Approved Asked For Not Needed Base FAT by Paharpur Received 15 Nov 2017 At Benapole on 08/01/18 Received 03 Feb 2018
12 SF3 Chilled Brine Chiller 1 Trane, BD (Confidence Trade) 12 13 Sep 2017 Issued 27 Sep 2017 Approved Received Base NA 30 Nov 2017 At Site by 31/01/18 - PCT 03 Feb 2018
13 Centrifuge (CF) 2 Nima Engineering (De Parikh) 14 19 Jun 2017 Issued 24 Aug 2017 Approved NA Approved DRL to Provide Approved Base FAT by NIMA Received 31 Dec 2017 At Site by 07/02/18 Received Received 07 Feb 2018
14 Cold room (2-8 deg C)(CR) 1 Thermolab 10 19 Sep 2017 Issued 03 Oct 2017 Approved Above FF 15 Jan 2018 Dispatched on 15/01/18 22 Feb 2018
15 Centrifugal Pump 46 Leak Proof Pumps 14 10 Jul 2017 Issued 03 Oct 2017 Approved Approved Not Needed Base FAT by LP Pumps Received 31 Dec 2017 At Port by 15/01/18 Received 06 Mar 2018
16 Scrubber 1 Yenplas 6 24 Aug 2017 Issued 11 Oct 2017 Approved Base NA Received 15 Mar 2018 Dispatched on 10/01/18 Received Received Received 06 Mar 2018
17 Glass Lined Reactors (GLR) 6 GMM Pfaudler 16 11 Jun 2017 Issued 19 Jul 2017 Approved Received Approved Received Received On Steel Structure FAT by BPL, Aevitas Received Received 10 Dec 2017 At Port in Jan 2018. Asked For Received 15 Mar 2018
18 Agitated Thin Film Dryer (ATFD) 1 Technoforce 16 13 Jul 2017 Issued 20 Aug 2017 40% Approved Approved Approved Received NA On SS FAT by BPL, Aevitas Received Received 28 Feb 2018 At Port by 24/02/18 Received Asked For 19 Mar 2018
19 Agitated Nutche Filter Dryer (ANFD) 2 BEW Engineering (Bifriends) 18 22 Jun 2017 Issued 07 Aug 2017 40% Approved Received Comments Sent Comments Sent Received Received Fix, No Base FAT by BPL, Aevitas Received Approved 31 Jan 2018 At Port by 10/01/18 Received Received 04 Apr 2018
20 Rotocone Vacuum Dryer (RCVD) 2 BEW Engineering (Bifriends) 16 22 Jun 2017 Issued 07 Aug 2017 Approved Received Comments Sent Comments Sent Received Received Fix, No Base FAT by BPL, Aevitas Received Approved 31 Jan 2018 At Port by 10/01/18 Received Received 04 Apr 2018
21 SS Reactor (SSR) 4 Vinayaka Metal Fab (VMF) 14 19 Jun 2017 Issued 10 Sep 2017 30% Approved Asked For Comments Sent Received NA On SS Received Received 06 Nov 2017 Dispatched on 10 Feb 2018. 05 Apr 2018
22 Heat Exchanger (05 Nos SSHE) 5 Vinayaka Metal Fab (VMF) 14 19 Jun 2017 Issued 10 Sep 2017 Approved Asked For Comments Sent NA Hanging Received Received 06 Nov 2017 05 Apr 2018
23 Receiver (RC) VT/CO 6 Vinayaka Metal Fab (VMF) 14 19 Jun 2017 Issued 10 Sep 2017 Approved Asked For Asked For NA Above FF Received Received 06 Nov 2017 05 Apr 2018
24 Pressure Nutche Filter (PNF) 1 Vinayaka Metal Fab (VMF) 14 19 Jun 2017 Issued 10 Sep 2017 Approved Asked For Comments Sent NA Above FF Received Received 06 Nov 2017 05 Apr 2018
25 Receiver (RC) VMF Engineers 14 19 Jun 2017 Issued 10 Sep 2017 Approved Asked For Received NA Above FF Received Received 06 Nov 2017 11 Apr 2018
21 Dispatched on 10 Feb 2018.
26 Laminar Air Flow (LAF) 1 ESCO 15 18 Oct 2017 NA 15 Nov 2017 Approved Asked For Not Needed Above FF 28 Feb 2018 Needed 13 Apr 2018
28 Floor Finish Works 1 Atharva Marbles & Granites Pvt. Ltd. 10 18 Sep 2017 Issued 06 Nov 2017 NA 15 Jan 2018 ETA 15.03.18 Received 21 Apr 2018
27 Dish End Tank (DT) 10 DV Polymer 10 19 Jun 2017 Issued 10 Sep 2017 Approved Received NA Above FF FAT by DRL Comments Sent 31 Oct 2017 Needed Received Received Not yet at Site
29 Fire Hydrant & Fire Extinguisher 1 MPEL 12 21 Nov 2017 NA NA Approved
30 SF4 Chiller 1 Voltas 14 21 Dec 2017 Issued 01 Apr 2018 Approved Base NA
31 Electrical Substation 1 Energypac 6 20 Dec 2017 NA NA Approved
32 Electrical LT Panels 13 Sanjay Technical Services Pvt. Ltd. 8 31 Dec 2017 Issued 08 Mar 2018 Approved
33 Piping and Mechanical Package 1 Indana Systems 16 04 Feb 2018 29 Mar 2018
34 Instrumentation Package 1 Indana Systems 16 04 Feb 2018 29 Mar 2018
35 PW Systems with Pretreatment 1 CN Water Systems 28 26 Feb 2018 Issued
36 HVAC and Modular Partition Package 1 Hemair Systems India Limited 24 26 Feb 2018 Issued
37 Electrical Package 1 System Engineering 16
38 HT Cable for Substation 1 BRB Cables 4
39 Expansion Tanks for SF3 and SF4 Chillers MS 2 VMF Engineers 10 16 Apr 2018 Received
40 Condensate Receiving Tank 500 Ltr SS 1 VMF Engineers 10 16 Apr 2018 Received
41 Air Receiver (1000 L) MS 1 VMF Engineers 10 16 Apr 2018 Received
42 Nitrogen Receiver (100 L) SS 304 1 VMF Engineers 10 16 Apr 2018 Received
43 MEG Tank (500 L) CS 1 VMF Engineers 10 16 Apr 2018 Received
44 Dump Tank (1500 L) CS 1 VMF Engineers 10 16 Apr 2018 Received
45 ETP Tank (5000 L) CS 2 VMF Engineers 10 16 Apr 2018 Received
Legend:
Technical comments sent to vendor
Received from vendor and yet to finalize
At PMBD
At PCT
Order Placement List of AMF PROJECT (Remaining Equipment)
15.11.2017
Serial TAG. NO CAPACITY EQUIPMENT FUNCTION WEIGHT ELEVATION TYPE Kw MOC MOTOR SPECIFICATION QUANTITY REMARK Decision of 17.11.2017
PROCESS
1 AMF-I-MLT-17-001 1000L HDPE Tank Filtrate / ML Tank 300 Kgs GF - HDPE / LDPE / PP For ANFD-001, Required BPL, If not DRL.
2 AMF-I-MLT-17-002 1000L HDPE Tank Filtrate / ML Tank 300 Kgs GF - HDPE / LDPE / PP Required for CF-001 BPL, If not DRL.
3 AMF-I-CR-17-002 -20 Deg. C Freezer RM/FG/Intermediate Storage 500 Kgs FF MEZ 2 SS/PPGI Required 500 Litre, BPL to purchase.
AMF-P-P-17-005 1m3/hr, 25mlc Metering Pump Process Pump (ATFD Feed) 80 Kgs FF For Aqueous Layer Transfer 1.5 SS316 1 FLP Motor, IIA/IIB Required for ATFD DRL will provide Specification. BPL will
4 purchase.
AMF-I-P-17-010 1m3/hr, 25mlc Metering Pump/ AODD Pump Process Pump - LAF 80 Kgs GF For Aqueous Layer Transfer 1.5 SS316 1 FLP Motor, IIA/IIB Required for LAF DRL and Aevitas will check whether Metering
Pump is needed or not. AODD Pump or Barrel
Pump is likely to be more suitable. DRL will
share a specification for this pump.
5
AMF-I-MF-17-001 0.22 Micron/10" housing Micron Filter Polishing Filter 15 Kgs FF - SS316 Required DRL will provide Specification. BPL will
6 purchase. 05 Nos Needed.
AMF-I-MF-17-002 0.22 Micron/10" housing Micron Filter Polishing Filter 15 Kgs FF - SS316 Required DRL will provide Specification. BPL will
7 purchase. 05 Nos Needed.
AMF-I-RC-17-025 100L Receiver for ANFD 001 Drying 300 kgs FF - SS316 Required for ANFD-001
8 Will be sharing the RC and SSHE of RCVD 001.
AMF-P-SSHE-17-009 2 m2 Condenser Drying 150 Kgs FF - SS316 Required for ANFD-002
9 Will be sharing the RC and SSHE of RCVD 002.
AMF-P-RC-17-026 100L Receiver for ANFD 002 Drying 300 Kgs FF - SS316 Required for ANFD-002
10 Will be sharing the RC and SSHE of RCVD 002.
AMF-P-RC-17-012 150L Dish End Tank (Vertical) Recovered Solvent 300 Kgs FF - SS316 Required for GLR-005 Will be sharing the RC of GLR 003 (RC 011).
11
12 Metering Pump (Spare) Not needed as per DRL.
13 AMF-P-SB-17-001 1.2M x 2M Sampling Booth Liquid/Solid Sampling 400 Kgs FF 1.5 PPGI Required Not needed as per DRL.
Serial TAG. NO CAPACITY EQUIPMENT FUNCTION WEIGHT ELEVATION TYPE Kw MOC MOTOR SPECIFICATION QUANTITY REMARK Decision of 17.11.2017
Utility
14 AMF-U-MEG-17-001 500 L MEG Tank Main Equipment 800 kgs GF Tank - CS Required, On Piping BPL, If not DRL.
15 AMF-U-DUT-17-001 1500 L Dump Tank Main Equipment 2500 Kgs FF Tank - CS/MS URS Required BPL, If not DRL.
16 AMF-U-ETPT-17-01 5000 L ETP Tank Main Equipment 6500 Kgs GF Tank - FRP/HDPE/PP/LDPE URS Required BPL, If not DRL.
17 AMF-U-ETPT-17-02 5000 L ETP Tank Main Equipment 6500 Kgs GF Tank - FRP/HDPE/PP/LDPE URS Required BPL, If not DRL.
AMF-U-RWT-17-001 5000 L Raw water tank 5500 Kgs RF Tank - PVC/HDPE/LDPE Required BPL
18
AMF-U-DF-17-001 1 Micron Disc Filter Filter for Nitrogen gas - RF - SS304 Required DRL will provide Specification. BPL will
19 purchase. 02 Nos (5 Micron and 1 Micron
Cartridge)
AMF-U-DF-17-002 1 Micron Disc Filter Filter for Nitrogen gas - RF - SS304 Required DRL will provide Specification. BPL will
20 purchase. 02 Nos (5 Micron and 1 Micron
Cartridge)
AMF-U-DF-17-003 1 Micron Disc Filter Filter for Nitrogen gas - RF - SS304 Extra added as per N2 P& ID DRL will provide Specification. BPL will
21 purchase. 02 Nos (5 Micron and 1 Micron
Cartridge)
AMF-U-MF-17-003 1 Micron Micron Filter Filter for Breathing Air - RF - SS304 Required DRL will provide Specification. BPL will
22 purchase. (1 Micron Cartridge)
AMF-U-MF-17-004 1 Micron Micron Filter Filter for Instrument Air - RF - SS304 Required DRL will provide Specification. BPL will
23 purchase. (1 Micron Cartridge)
AMF-U-MF-17-005 1 Micron Micron Filter Filter for Compressed Air - RF - SS304 Required DRL will provide Specification. BPL will
24 purchase. (1 Micron Cartridge)
AMF-U-MF-17-004 10 Micron Micron Filter for AJM Filter for AJM DRL will provide Specification. BPL will
25 AMF-U-MF-17-005 1 Micron purchase. Total 03 Nos
AMF-U-MF-17-006 0.2 Micron
26 AMF-U-RC-17-002 100 L Nitrogen Receiver (GAS) Main Equipment 300 Kgs RF Tank - CS URS Required BPL, If not DRL.
27 AMF-U-RC-17-001 1000 L Air Receiver Secondary Equipment 800 kgs RF - MS URS Required BPL, If not DRL.
AMF-U-CRS-17-001 Condensate Recovery System For Steam Condensate Recovery Single fluid system for steam (SF-1) 150 Kgs SF - CS Required CRS will not be used. Instead, 01 No of 500
Litres MS tank with centrifugal pump operated
through level switch will be used to transfer
condensate to boiler. Insulation for tank and
pipeline will be needed for that. BPL will
provide information whether boiler can take
28 hot steam or not and a length and route.
Accordingly, Aevitas will provide the design
for this transfer system.
AMF-U-CRS-17-002 Condensate Recovery System For Steam Condensate Recovery Dehumidifiers 150 Kgs FF MEZ - CS Required CRS will not be used. Instead, 01 No of 500
Litres MS tank with centrifugal pump operated
through level switch will be used to transfer
condensate to boiler. Insulation for tank and
pipeline will be needed for that. BPL will
provide information whether boiler can take
29 hot steam or not and a length and route.
Accordingly, Aevitas will provide the design
for this transfer system.
Additional Requirement:
1. Not required.
2 Discussed
3 Caustic Lye, NaOH
Equipment List (AMF PROJECT)
7 AMF-I-MLT-17-001 HDPE Tank BPL will purchase. If not available, DRL will source.
8 AMF-I-MLT-17-002 HDPE Tank BPL will purchase. If not available, DRL will source.
9 AMF-I-P-17-010 Metering Pump DRL and Aevitas will check whether Metering Pump
is needed or not. AODD Pump or Barrel Pump is likely
to be more suitable. DRL will share a specification for
this pump.
16 AMF-U-RC-17-001 Air Receiver BPL will purchase. If not available, DRL will source.
17 AMF-U-DUT-17-001 Dump Tank BPL will purchase. If not available, DRL will source.
18 AMF-U-ETPT-17-01 ETP Tank BPL will purchase. If not available, DRL will source.
19 AMF-U-ETPT-17-02 ETP Tank BPL will purchase. If not available, DRL will source.
20 AMF-U-RC-17-002 Nitrogen Receiver (GAS) BPL will purchase. If not available, DRL will source.
22 AMF-U-DF-17-001 Disc Filter DRL will provide Specification. BPL will purchase. 02
Nos (5 Micron and 1 Micron Cartridge)
23 AMF-U-DF-17-002 Disc Filter DRL will provide Specification. BPL will purchase. 02
Nos (5 Micron and 1 Micron Cartridge)
24 AMF-U-DF-17-003 Disc Filter DRL will provide Specification. BPL will purchase. 02
Nos (5 Micron and 1 Micron Cartridge)
25 AMF-U-MF-17-003 Micron Filter DRL will provide Specification. BPL will purchase. (1
Micron Cartridge)
26 AMF-U-MF-17-004 Micron Filter DRL will provide Specification. BPL will purchase. (1
Micron Cartridge)
27 AMF-U-MF-17-005 Micron Filter DRL will provide Specification. BPL will purchase. (1
Micron Cartridge)
28 AMF-U-MF-17-004 Micron Filter for AJM DRL will provide Specification. BPL will purchase.
AMF-U-MF-17-005 Total 03 Nos
AMF-U-MF-17-006
29 AMF-U-CRS-17-001 Condensate Recovery System CRS will not be used. Instead, 01 No of 500 Litres MS
tank with centrifugal pump operated through level
switch will be used to transfer condensate to boiler.
Insulation for tank and pipeline will be needed for
that. BPL will provide information whether boiler can
take hot steam or not and a length and route.
Accordingly, Aevitas will provide the design for this
transfer system.
30 AMF-U-CRS-17-002 Condensate Recovery System CRS will not be used. Instead, 01 No of 500 Litres MS
tank with centrifugal pump operated through level
switch will be used to transfer condensate to boiler.
Insulation for tank and pipeline will be needed for
that. BPL will provide information whether boiler can
take hot steam or not and a length and route.
Accordingly, Aevitas will provide the design for this
transfer system.
Process Engineering Head (1) Production Head (1) Analytical Head (0) QA Head (0) Engineering Head (0) R&D Head (1)
Manager/ D. Manager Manager/ D. Manager Manager/ D. Manager Manager/ D. Manager Manager/ D. Manager Manager/ D. Manager
Process Engineers (4) Shift Incharges (4) Analytical Chemists (7) QA Memebers (4) R&D Chemists (6)
1XOfficer 1XSr. Officer 3XOfficer 4X Officer 2XOfficer
3XAsst. Officer 3XOfficer 3XAsst. Officer 4XAsst. Officer
1XOfficer (Microbiologist)
(3Xfor Development &
3X for Analysis)
PW System (4)
1X Officer
3X Asst. Officer
5 23 7 4 13 7
59
Above are critical functions , supporting functions ( ware house , casual labor ) not considered
Phase wise Manpower for API Manufacturing Facility (AMF)
Date: 06 Nov 2017
Manager / Dy Manager 0 0 1 1
Officer 1 1 0 2
1) R&D
Asst. Officer 1 1 2 4
2 2 3 7
Manager / Dy Manager 1 0 0 1
Officer 1 0 0 1
2) Process Engineering
Asst. Officer 1 2 0 3
3 2 0 5
Manager / Dy Manager 1 0 0 1
Sr. Officer 0 1 0 1
Officer 3 4 2 9
3) Production Asst. Officer 3 6 3 12
Contractual Labour 3 5 2 10
Cleaner 0 3 6 9
10 19 13 42
Manager / Dy Manager 0 0 0 0
Officer 2 2 0 4
4) QC Asst. Officer 1 2 0 3
Contractual Labour 0 2 0 2
3 6 0 9
Manager / Dy Manager 0 0 0 0
Officer 2 2 0 4
5) QA
Contractual Labour 0 2 0 2
2 4 0 6
Manager / Dy Manager 0 0 0 0
Officer 2 1 1 4
Asst. Officer 2 2 1 5
6) Engineering Fitter/ Technician 2 2 0 4
Contractual Labour 0 3 0 3
Cleaner 0 3 0 3
6 11 2 19
Total 26 44 18 88
Position wise Manpower for API Manufacturing Facility (AMF)
Date: 06 Nov 2017
Department
Serial Designation Total
R&D Process Engineering Production QC QA Engineering
1 Manager / Dy Manager 1 1 1 0 0 0 3
2 Sr. Officer 0 0 1 0 0 0 1
3 Officer 2 1 9 4 4 4 24
4 Asst. Officer 4 3 12 3 0 5 27
5 Fitter/ Technician 0 0 0 0 0 4 4
HRD Recruitment (A) 7 5 23 7 4 13 59
6 Contractual Labour 0 0 10 2 2 3 17
7 Cleaner 0 0 9 0 0 3 12
Factory Recruitment (B) 0 0 19 2 2 6 29
SAFETY ITEMS
Sl. No. Name of the Items Specification Purpose / Image QTY
1 Emergency Safety Shower with Eye Wash Station (Full SS) 2
2 Emergency Light 5
3 Safety Goggles 3M 10
4 Safety Helmet 3M 30
5 Gas Mask 3M 30
6 Dust Mask 3M 30
7 Safety Shoe 3M Chemical Resistance 30
8 Chest Cover Local 16
9 Head Gear Local 66
11 Earthing Pad
12 Flameproof Mobile 4
LIST OF FURNITURES AND HANDLING ACCESSORRIES FOR AMF PROJECT
ENGINEERING DEPARTMENT
SAFETY ACCESSORIES
Sl. No. Name of the Items Specification Area / Purpose
Qty
1 Emergency Light LED light Operational Maintenance 1
MAINTENANCE TOOLS/ACCESSORIES
Sl. No. Name of the Items Specification Purpose
Qty
1 Vacuum Cleaner Maintenance 1
2 Storage Trolley tools cabinet 2'x3'x 4' , SS304 Maintenance 1
3 Shifting Trolley 2'x 4' , SS304 Maintenance 2
4 Stainless Steel Tool Box Movable Maintenance 1
5 SS Oil Can 1 ltr Maintenance 2
6 Stainless Steel Foldable Ladder 5' & 10 ' Maintenance 2
7 Ball peen Hammers 1 lb & 5 lb Maintenance 2
8 Teflon Face Hammer 1lb Maintenance 1
9 Flat Screwdrivers (Flat) set 6",8",10,",12" Maintenance 1
10 Philips Screwdriver set 6",8",10,",12" Maintenance 1
11 Adjustable Wrenches 10,",12",18" Maintenance 3
12 Pliers standard Maintenance 2
13 Sockets Wrenches BOX Maintenance 1
14 Rubber Mallet 1lb Maintenance 1
15 Nose Pliers 10" Maintenance 1
16 Ratchet Set BOX Maintenance 1
17 Hand Drill Machine ( D-walt) 1000 w Maintenance 1
18 Hand Grinding machine ( D-walt) 1000 w Maintenance 1
Serial Name Total No TAG NO CAPACITY EQUIPMENT FUNCTION WEIGHT ELEVATION TYPE Kw MOC QUANTITY Motor Spec REMARK
AMF-I-GLR-17-001 630 L/PBT/96 GL Reactor (-20 to -40) Acryloylchloride charging / Reaction / Distillation / Layer Separation 1650 Kgs FF MEZ 3.1HTA / 170JV 2.2 MSGL
AMF-I-GLR-17-002 630 L/PBT/96 GL Reactor Dissolution / Reaction / Distillation / Solution Preparation 1650 Kgs FF MEZ 3.1HTA / 170JV 2.2 MSGL
AMF-P-GLR-17-003 (Cry) 630 L/ANC/48 GL Reactor Crystallizer 1650 Kgs FF MEZ 3.1HTA / 170JV 2.2 MSGL / INS
1 Glass Lined Reactors (GLR) 6
AMF-I-GLR-17-004 100 L/PBT/96 GL Reactor Reaction / Distillation / Layer Separation 600 Kgs FF MEZ 1HTA / 80JV 2.2 MSGL
AMF-P-GLR-17-005 (Cry) 250 L/ANC/96 GL Reactor Crystallizer 800 Kgs FF MEZ 1.66HTA / 90JV 2.2 MSGL
AMF-I-GLR-17-006 250L/PBT GL Reactor Reactor 800 Kgs FF MEZ 1.66HTA / 90JV 2.2 MSGL
2 Agitated Thin Film Dryer (ATFD) 1 AMF-P-ATFD-17-001 1.5 M2 SS ATFD Drying 1400 Kgs FF MEZ 2.2 SS316
AMF-I-ANFD-17-001 0.5 M2 ANFD Filtration & Drying 2500 Kgs FF 7.7 SS316
3 Agitated Nutche Filter Dryer (ANFD) 2
AMF-P-ANFD-17-002 0.5 M2 ANFD Filtration & Drying 2500 Kgs FF 7.7 SS316
AMF-I-RCVD-17-001 100L (W) Rotocone Vacuum Dryer Drying 1000 Kgs FF 5.5 SS316
4 Rotocone Vacuum Dryer (RCVD) 2
AMF-P-RCVD-17-002 100L (W) Rotocone Vacuum Dryer Drying 1000 Kgs FF 5.5 SS316
AMF-I-P-17-002 2m3/hr, 25mlc Centrifugal Pump Process Pump for RC-05 80 Kgs FF For Aqueous Layer Transfer 1.5 PVDF 1 FLP Motor, IIA/IIB
AMF-I-P-17-011 2m3/hr, 25mlc Centrifugal Pump Process Pump for MLT-001 80 Kgs GF For Aqueous Layer Transfer 1.5 PVDF 1 FLP Motor, IIA/IIB
AMF-I-P-17-001 2m3/hr, 25mlc Centrifugal Pump Process Pump for PNF001 80 Kgs FF For Aqueous Layer 1.5 SS316 1 FLP Motor, IIA/IIB
AMF-I-P-17-003 2m3/hr, 25mlc Centrifugal Pump Process Pump 80 Kgs FF For Aqueous Layer Transfer 1.5 PVDF 1 FLP Motor, IIA/IIB
AMF-I-P-17-007 2m3/hr, 25mlc Centrifugal Pump Process Pump 80 Kgs FF For Aqueous Layer Transfer 1.5 PVDF 1 FLP Motor, IIA/IIB
13
AMF-P-P-17-006 2m3/hr, 25mlc Centrifugal Pump Process Pump (ATFD Distilate) 80 Kgs FF For Aqueous Layer Transfer 1.5 SS316 2 FLP Motor, IIA/IIB 1 Spare
AMF-I-P-17-009 2m3/hr, 25mlc Centrifugal Pump Process Pump 80 Kgs FF For Aqueous Layer Transfer 1.5 PVDF 2 FLP Motor, IIA/IIB 1 Spare
AMF-I-P-17-004 2m3/hr, 25mlc Centrifugal Pump Process Pump for RC-010 80 Kgs FF For Aqueous Layer Transfer 1.5 SS316 2 FLP Motor, IIA/IIB 1 Spare
AMF-I-P-17-008 2m3/hr, 25mlc Centrifugal Pump Process Pump for RC-020 80 Kgs FF For Aqueous Layer Transfer 1.5 PVDF 1 FLP Motor, IIA/IIB
AMF-I-P-17-018 2m3/hr, 25mlc Centrifugal Pump Process Pump MLT-02 80 Kgs GF For Aqueous Layer Transfer 1.5 PVDF 1 FLP Motor, IIA/IIB
AMF-U-P-17-038 2 m3/hr, 20 mlc MEG Transfer pump Secondary Equipment GF Centrifugal Pump 1.5 CS FLP Motor, IIA/IIB 2
AMF-U-P-17-039 150 m3/hr, 25 mlc Cooling water transfer Pump Secondary Equipment RF Centrifugal Pump 18 CS Non-FLP 1
AMF-U-P-17-040 150 m3/hr, 25 mlc Cooling water transfer Pump Secondary Equipment RF Centrifugal Pump 18 CS Non-FLP 1 Standby
AMF-U-P-17-041 60 m3/hr, 20 mlc SF-3 Transfer Pump Secondary Equipment SF Centrifugal Pump 11 CS Non-FLP 1
AMF-U-P-17-042 60 m3/hr, 20 mlc SF-3 Transfer Pump Secondary Equipment SF Centrifugal Pump 11 CS Non-FLP 1 Standby
AMF-U-P-17-043 15 m3/hr, 20 mlc SF-4 Transfer Pump Secondary Equipment SF Centrifugal Pump 5.5 CS Non-FLP 1
AMF-U-P-17-044 15 m3/hr, 20 mlc SF-4 Transfer Pump Secondary Equipment SF Centrifugal Pump 5.5 CS Non-FLP 1 Standby
AMF-U-P-17-015 2 m3/hr, 20 mlc Centrifugal Pump for ANFD1 Secondary Equipment SF Centrifugal Pump 1.5 CS FLP Motor, IIA/IIB 2 1 Spare
AMF-U-P-17-016 2 m3/hr, 20 mlc Centrifugal Pump for ANFD2 Secondary Equipment SF Centrifugal Pump 1.5 CS FLP Motor, IIA/IIB 1
AMF-U-P-17-017 2 m3/hr, 20 mlc Centrifugal Pump for ATFD Secondary Equipment SF Centrifugal Pump 1.5 CS FLP Motor, IIA/IIB 1
5 Centrifugal Pump (Process 13+ Utility 33) AMF-U-P-17-018 2 m3/hr, 20 mlc Centrifugal Pump for VTD1 Secondary Equipment SF Centrifugal Pump 1.5 CS FLP Motor, IIA/IIB 1
Total=46
AMF-U-P-17-019 2 m3/hr, 20 mlc Centrifugal Pump for VTD2 Secondary Equipment SF Centrifugal Pump 1.5 CS FLP Motor, IIA/IIB 1
AMF-U-P-17-020 2 m3/hr, 20 mlc Centrifugal Pump for RCVD1 Secondary Equipment SF Centrifugal Pump 1.5 CS FLP Motor, IIA/IIB 1
AMF-U-P-17-021 2 m3/hr, 20 mlc Centrifugal Pump for RCVD2 Secondary Equipment SF Centrifugal Pump 1.5 CS FLP Motor, IIA/IIB 1
AMF-U-P-17-022 5 m3/hr, 20 mlc Centrifugal Pump for AMF-I-GLR-17-004 Secondary Equipment SF Centrifugal Pump 2.2 CS FLP Motor, IIA/IIB 2
33 AMF-U-P-17-023 5 m3/hr, 20 mlc Centrifugal Pump for AMF-I-SSR-17-004 Secondary Equipment SF Centrifugal Pump 2.2 CS FLP Motor, IIA/IIB 1
AMF-U-P-17-024 5 m3/hr, 20 mlc Centrifugal Pump for AMF-P-GLR-17-005 Secondary Equipment SF Centrifugal Pump 2.2 CS FLP Motor, IIA/IIB 1
AMF-U-P-17-025 5 m3/hr, 20 mlc Centrifugal Pump for AMF-I-GLR-17-006 Secondary Equipment SF Centrifugal Pump 2.2 CS FLP Motor, IIA/IIB 1
AMF-U-P-17-026 15 m3/hr, 20 mlc Centrifugal Pump for AMF-I-SSR-17-001 Secondary Equipment SF Centrifugal Pump 3.7 CS FLP Motor, IIA/IIB 1
AMF-U-P-17-027 5 m3/hr, 20 mlc Centrifugal Pump for AMF-I-SSR-17-003 Secondary Equipment SF Centrifugal Pump 2.2 CS FLP Motor, IIA/IIB 1
AMF-U-P-17-028 15 m3/hr, 20 mlc Centrifugal Pump for AMF-I-GLR-17-001 Secondary Equipment SF Centrifugal Pump 3.7 CS FLP Motor, IIA/IIB 1
AMF-U-P-17-029 15 m3/hr, 20 mlc Centrifugal Pump for AMF-I-GLR-17-002 SF Centrifugal Pump 3.7 CS FLP Motor, IIA/IIB 1
AMF-U-P-17-030 15 m3/hr, 20 mlc Centrifugal Pump for AMF-I-SSR-17-002 (Cryo) Secondary Equipment SF Centrifugal Pump 3.7 CS FLP Motor, IIA/IIB 1
AMF-U-P-17-031 15 m3/hr, 20 mlc Centrifugal Pump for AMF-P-GLR-17-003 Secondary Equipment SF Centrifugal Pump 3.7 CS FLP Motor, IIA/IIB 1
AMF-U-P-17-045 5 m3/hr, 20 mlc Centrifugal Pump for ETP - Low COD Secondary Equipment GF Centrifugal Pump 3.7 FLP Motor, IIA/IIB 1
AMF-U-P-17-046 5 m3/hr, 20 mlc Centrifugal Pump for ETP - High COD Secondary Equipment GF Centrifugal Pump 3.7 FLP Motor, IIA/IIB 1
AMF-U-P-17-047 Centrifugal Pump for Scrubber Secondary Equipment RF Centrifugal Pump 3.7 Non-FLP 1
AMF-U-P-17-050 Centrifugal Pump for Scrubber Secondary Equipment RF Centrifugal Pump 3.7 Non-FLP 1 Standby
AMF-U-P-17-048 5 m3/hr, 20 mlc Centrifugal Pump for HW Secondary Equipment RF 3.7 Non-FLP 1
AMF-U-P-17-049 5 m3/hr, 20 mlc Centrifugal Pump for HW Secondary Equipment RF 3.7 Non-FLP 1 Standby
6 Air Jet Mill (AJM) 1 AMF-P-AJM-17-001 10 Kg/Hr Micronizer / Air Jet Mill (2") Size Reduction 250 Kgs FF/CR 1.5 SS316
AMF-I-SSR-17-001 630 L/PBT/96 SS Reactor Reaction / Distillation / Solution Preparation (Citric Acid) 1200 Kgs FF MEZ 1.66HTA / 90JV 2.2 SS316
AMF-I-SSR-17-002 (Cryo) 1000 L/PBT/96 SS Reactor Dissolution / Reaction / Distillation / Solution Preparation 1650 Kgs FF MEZ 3.1HTA / 170JV 3.7 SS316
7 SS Reactor (SSR) 4
7 SS Reactor (SSR) 4
AMF-I-SSR-17-003 250 L/PBT/48 SS Reactor Dissolution / Reaction / Distillation / Solution Preparation 800 Kgs FF MEZ 1.66HTA / 90JV 2.2 SS316 / INS
AMF-I-SSR-17-004 100 L/PBT/96 SS Reactor Reaction / Distillation / Solution Preparation (Citric Acid) 600 Kgs FF MEZ 1.2HTA / 60JV 2.2 SS316
AMF-I-SSHE-17-001 2.7 M2 Primary Condensor For Distillation 300 Kgs FF MEZ S&T / Corrugated - SS316
AMF-I-SSHE-17-002 2.7 M2 Primary Condensor For Distillation 300 Kgs FF MEZ S&T / Corrugated - SS316
8 Heat Exchanger (05 Nos SSHE) 5 AMF-I-SSHE-17-003 2 M2 Primary Condensor For Distillation 200 Kgs FF MEZ S&T / Corrugated - SS316
AMF-I-SSHE-17-004 1.5 M2 Primary Condensor For Distillation 100 Kgs FF MEZ S&T / Corrugated - SS316
AMF-P-SSHE-17-005 3 M2 Primary Condensor For Distillation 200 Kgs FF MEZ S&T / Corrugated - SS316
AMF-I-RC-17-001 1000L Dish End Tank (Vertical) Fresh Ethyle Acetate 800 Kgs SF - SS316
AMF-I-RC-17-007 250L Dish End Tank (Horizontal) Filtrate from ANFD001 150 Kgs FF - SS316
AMF-I-RC-17-006 250L Dish End Tank (Horizontal) Filtrate from PNF001 150 Kgs FF - SS316
AMF-I-RC-17-003 1000L Dish End Tank (Vertical) Fresh Acetone 800 Kgs SF - SS316
AMF-P-RC-17-011 250L Dish End Tank (Vertical) Recovered Solvent 300 Kgs FF - SS316
AMF-P-RC-17-032 250L Dish End Tank (Horizontal) Filtrate from ANFD002 150 Kgs FF - SS316
AMF-I-RC-17-018 100L Dish End Tank (Vertical) Recovered Solvent 300 Kgs FF - SS316
AMF-P-DT-17-006 100L Dish End Tank (Vertical) Addition Tank 150 Kgs FF MEZ - SS-PTFE
AMF-P-RC-17-013 250L Dish End Tank (Horizontal) Filtrate from CF002 150 Kgs FF - SS316
AMF-P-RC-17-015 500L Dish End Tank (Vertical) Recovered Solvent 300 Kgs FF - SS316
9 Receiver (RC) 21 AMF-P-RC-17-014 500L Jktd Dish End Tank (Vertical) Feed Vessel for ATFD 350 Kgs FF With Insulation - SS316
AMF-I-DT-17-010 100L Dish End Tank Addition Tank 150 Kgs FF MEZ S&T / Corrugated - SS-PTFE
AMF-I-RC-17-021 150L Dish End Tank (Vertical) Recovered Solvent 150 Kgs FF - SS316
AMF-I-DT-17-002 100L Dish End Tank (Vertical) Addition Tank 250 Kgs FF MEZ - SS316
AMF-I-RC-17-002 1000L Dish End Tank (Vertical) Fresh Methanol 800 Kgs SF - SS316
AMF-I-RC-17-008 150L Dish End Tank (Vertical) Recovered Solvent 300 Kgs FF - SS316
AMF-I-DT-17-004 100L Dish End Tank (Vertical) Addition Tank 250 Kgs FF MEZ - SS316
AMF-I-RC-17-010 250L Dish End Tank (Vertical) Recovered Solvent 300 Kgs FF - SS316
AMF-I-DT-17-008 100L Dish End Tank (Vertical) Addition Tank 250 Kgs FF MEZ - SS316
AMF-I-RC-17-019 100L Dish End Tank (Vertical) Recovered Solvent 300 Kgs FF - SS316
AMF-I-RC-17-016 250L Dish End Tank (Horizontal) Filtrate from CFG001 150 Kgs FF - SS316
AMF-I-VT/CO-17-006 100L Dish End Tank (Vertical) Vacuum Trap 300 Kgs SF - SS316
AMF-P-VT/CO-17-003 100L Dish End Tank (Vertical) Vacuum Trap 300 Kgs SF - SS316
AMF-P-VT/CO-17-004 100L Dish End Tank (Vertical) Vacuum Trap 300 Kgs SF - SS316
10 Receiver (RC) VT/CO 6
AMF-P-VT/CO-17-005 100L Dish End Tank (Vertical) Vacuum Trap 300 Kgs SF - SS316
AMF-I-VT/CO-17-001 100L Dish End Tank (Vertical) Vacuum Trap 300 Kgs SF - SS316
AMF-I-VT/CO-17-002 100L Dish End Tank (Vertical) Vacuum Trap 300 Kgs SF - SS316
11 Pressure Nutche Filter (PNF) 1 AMF-I-PNF-17-001 100L Pressure Nutche Filter Salt Filtration 600 Kgs FF - SS316
13 Cooling Tower 1 AMF-U-CT-17-001 250 TR Cooling Tower Main Equipment 3000 Kgs RF 5.5 PP/FRP
14 Vibro Sifter (SIF) 1 AMF-P-SIF-17-001 20"/20, 40, 80 Mesh Vibro Sifter Sifting 200 Kgs FF 1 SS316
15 Multimill (MM) 1 AMF-P-MM-17-001 10 Kg/Hr Multi Mill Size Reduction 250 Kgs FF 2.2 SS316
AMF-I-DT-17-001 100L Dish End Tank (Vertical) Addition Tank 50 Kgs FF MEZ - SS-PTFE
AMF-I-RC-17-004 250L Dish End Tank (Vertical) Recovered Solvent 300 Kgs FF - SS316
AMF-I-RC-17-005 500L Dish End Tank (Vertical) Recovered Solvent / Hold Tank 300 Kgs FF - MS-PTFE
AMF-I-DT-17-003 100L Dish End Tank (Vertical) Addition Tank 50 Kgs FF MEZ - SS-PTFE
AMF-I-RC-17-009 250L Dish End Tank (Vertical) Recovered Solvent 300 Kgs FF - SS316
16 Dish End Tank (DT) 10
AMF-P-DT-17-005 100L Dish End Tank (Vertical) Addition Tank 50 Kgs FF MEZ - SS-PTFE
AMF-I-DT-17-007 100L Dish End Tank (Vertical) Addition Tank 50 Kgs FF MEZ - SS-PTFE
AMF-I-RC-17-017 100L Dish End Tank (Vertical) Recovered Solvent 300 Kgs FF - MS-PTFE
AMF-I-DT-17-009 100L Dish End Tank (Vertical) Addition Tank 50 Kgs FF MEZ - SS-PTFE
AMF-I-RC-17-020 150L Dish End Tank (Vertical) Recovered Solvent 300 Kgs FF - MS-PTFE
17 Sparkler Filter (SF) 1 AMF-I-SF-17-001 50 L Sparkler Filter Carbon Filtration 100Kgs FF - SS316
AMF-I-HCHE-17-001 2.7 M2 Primary Condensor For Distillation 300 Kgs FF MEZ S&T / Corrugated - Hast. C22
AMF-I-HCHE-17-002 2.7 M2 Primary Condensor For Distillation 300 Kgs FF MEZ S&T / Corrugated - Hast. C22
AMF-P-HCHE-17-003 2.7 M2 Primary Condensor For Distillation 300 Kgs FF MEZ S&T / Corrugated - Hast. C22
18 Heat Exchanger (06 Nos HCHE) 6
AMF-I-HCHE-17-004 1.5 M2 Primary Condensor For Distillation 100 Kgs FF MEZ S&T / Corrugated - Hast. C22
AMF-P-HCHE-17-005 2 M2 Primary Condensor For Distillation 150 Kgs FF MEZ S&T / Corrugated - Hast. C22
AMF-I-HCHE-17-006 2 M2 Primary Condensor For Distillation 300 Kgs FF - Hast. C22
AMF-U-SF1-17-001 120000 Kcal/hr Single fluid system for steam (SF-1) Main Equipment 500 Kgs SF Shell & Tube HE - CS
AMF-U-P-17-034 25 m3/hr, 20 mlc SF-1 Transfer system Secondary Equipment 150 kgs SF Centrifugal Pump 5.5 CS
1
AMF-U-P-17-035 25 m3/hr, 20 mlc SF-1 Transfer system Secondary Equipment 150 kgs SF Centrifugal Pump 5.5 CS Standby
SF1 (130 °C) & SF2 (+40 °C) Skid AMF-U-TA-17-001 100 L Expansion Tank Secondary Equipment 250 kgs RF Tank - CS
19
Total 2 set AMF-U-SF2-17-002 100000 Kcal/hr Single fluid system for Cooling water (SF-2) Main Equipment 500 Kgs SF PHE - CS
AMF-U-P-17-036 20 m3/hr, 20 mlc SF-2 Transfer system Secondary Equipment 140 kgs SF Centrifugal Pump 5.5 CS
1
AMF-U-P-17-037 20 m3/hr, 20 mlc SF-2 Transfer system Secondary Equipment 140 kgs SF Centrifugal Pump 5.5 CS Standby
AMF-U-TA-17-002 100 L Expansion Tank Secondary Equipment 250 kgs RF Tank - CS
20 SF3 Chilled Brine Chiller 1 AMF-U-SF3-17-001 100 TR Chilling water plant@ 7 to 12 0C (SF-3) Secondary Equipment 3000 Kgs SF Screw 75 CS
21 Co Mill (CM) 1 AMF-P-CM-17-001 10 Kg/Hr Co- Mill Size Reduction 250 Kgs FF 2.2 SS316
22 Vacuum Nitrogen Sealing (VNS) 1 AMF-P-VNS-17-001 - Vacuum Nitrogen Sealing Machine For FG Packing 600 Kgs FF 1.5 SS316
AMF-I-VP-17-006 175 m3/Hr Oil Ring Vacuum Pump For Vacuum (For Intermediate Reactors GLR001, GLR002, SSR001 & SSR002) 150 Kgs SF 3.7 CS
AMF-P-VP-17-003 175 m3/Hr Oil Ring Vacuum Pump For Vacuum (For Clean Room Reactors GLR003 & GLR005) 150 Kgs SF 3.7 CS
AMF-P-VP-17-004 175 m3/Hr Oil Ring Vacuum Pump For Vacuum (For Clean Room Dryers ANFD002 & ATFD001) 150 Kgs SF 3.7 CS
23 Vacuum Pump (VP) 6
AMF-P-VP-17-005 175 m3/Hr Oil Ring Vacuum Pump For Vacuum (For Clean Room Dryers VTD002 & RCVD002) 150Kgs SF 3.7 CS
AMF-I-VP-17-001 175 m3/Hr Oil Ring Vacuum Pump For Vacuum ( For Intermediate Reactors GLR004, GLR006 , SSR003 & SSR004) 150 Kgs SF 3.7 CS
AMF-I-VP-17-002 175 m3/Hr Oil Ring Vacuum Pump For Vacuum (For Intermediate Dryers VTD001, RCVD001, & ANFD001) 150 Kgs SF 3.7 CS
26 Cold room (2-8 deg C)(CR) 1 AMF-I-CR-17-001 2 - 8 Deg. C Cold Room / 2M x 3M RM/Intermediate Storage 800 Kgs FF 3.7 SS/PPGI
132
BEXIMCO PHARMACEUTICALS LTD.
Tongi, Gazipur, Bangladesh
No. of
Item Name of the instrument No. of Inst. (DRL QC (T-I) can Instrument Instrument Brand & Source
Requirements) Share to be
Procured
1 Fume chamber 2 1 1 Variolab, UK
2 *Muffle furnace 1 1 0 Nabertherm, Germany
3 Oven/ Incubator for LOD 1 0 1 Memert, Germany
4 *Oven with vacuum pump 1 1 0 Memert, Germany
5 Drying cabinet for Glassware 1 0 1 Taken by locally
6 *Shaking Water bath 1 1 0 Witeg Labortechnik, Germany
7 Tap density Meter (Bulk Density Meter) 1 0 1 Logon, USA
8 Ultrasonic cleaning bath (Sonicator) 1 0 1 Elma, Germany
9 UV - visible spectrophotometer 1 0 1 Shimadzu, Japan
10 Melting point apparatus 1 0 1 Buchi, Swizerland
11 *Potentiometric titrator 1 1 0 Metrohm, Swizerland
12 Karl Fisher Titrator (831 –KF coulometer) 1 0 1 Metrohm, Swizerland
13 *Karl fisher Titrator 1 1 0 Metrohm, Swizerland
14 pH meter 1 0 1 Mettler Toledo, Swizerland
15 *Polari meter 1 1 0 Rudolph, USA
16 Calibration weight set 1 0 1 Mettler Toledo, Swizerland
17 Micro Blance with Table 1 0 1 Mettler Toledo, Swizerland
18 IR Moisture Balance 1 0 1 Mettler Toledo, Swizerland
19 Analytical balance 21 1 1 Mettler Toledo, Swizerland
20 Refrigerator 1 0 1 Berjer, Malaysia
21 Deepfreezerr (300 L - 400 L) 1 0 1 Frimed, Italy
22 FTIR 1 0 1 Shimadzu, Japan
23 **ICP-MS 1 1 1 Agilent Corporation Will be procured from Unit 03
24 Gas chromatography 1 0 1 Agilent Corporation
25 *Particle size analyzer 1 1 0 Malvern, UK
26 HPLC 3 0 3 Waters/Agilent, USA
27 Water Purification system for HPLC 1 0 1 Milli-Q, Germany
28 Degassing pump with filtration unit for HPLC 1 0 1 Waters, USA
29 Stop Watch 1 0 1
30 Digital Thermometer 1 0 1
31 Hygrometer 1 0 1
32 TLC Chamber 1 0 1
33 ** Stability Chamber (6,000 liters) for Real time and Accelerated 2 0 2 Thermolab, India/ Newtonic, India
condition.
34 ** Stability Chamber (1,000 liters) for 2 to 8⁰C 1 0 1 Thermolab, India/ Newtonic, India
35 ** Stability Chamber (1,000 liters) for room temperature condition 1 0 1 Thermolab, India/ Newtonic, India
36 DSC 1 0 1
37 TGA 1 0 1 Not budgeted
38 Ion Chromatography 1 0 1
42 10 34
BEXIMCO PHARMACEUTICALS LTD.
Tongi, Gazipur, Bangladesh Date : 31.10.17
4 Tap density meter (Bulk Density Meter) 1 Yes Done Approved 125/17-18(07.09.17)
8 Karl fisher Titrator (831 -KF coulometer) 1 Yes Done Approved 129/17-18(07.09.17)
20 Degassing Pump with filtration unit for HPLC 1 Yes Done Approved 138/17-18(07.09.17)
21 Stop Watch 1 Yes Done Approved
22 Digital Thermometer 1 Yes Done Approved 139/17-18(07.09.17)
23 Hygrometer 1 Yes Done Approved
24 Yes Done Approved 140/17-18(07.09.17)
TLC Chamber 1
25 Stability Chamber (6,000 Liters) for Real time and Yes Done Approved
Accelerated condition. 2
141/17-18(07.09.17)
Page 17 of 18
BEXIMCO PHARMACEUTICALS LTD.
Tongi, Gazipur, Bangladesh Date : 31.10.17
NB: All equipments should delivery at our site within April 2018
Page 18 of 18