Professional Documents
Culture Documents
Estimation of Shed
Estimation of Shed
MATERIAL COST
ITEMS MATERIAL DESCRIPTION QTY UNIT
UNIT COST TOTAL COST
I. FOR COLUMN
a. Concrete Post (0.7m x 0.2m x 0.2m)
4" GI Pipe 6 pcs 3467 20802
Portland Cement 2 bags 270 540
Ordinary Plywood 5 pcs 380 1900
2"x2"8' Coco Lumber 148.35 bd. ft 62 9197.7
#2 1/2 CW Nail 1.5 kg 69 103.5
#1 CW Nail 0.50 kg 65 32.50
32,575.70
II. FOR SLAB
a. Slab (8m x 4m x 0.1m)
Portland Cement 20 bags 270 5400
8mm dia. bar @ 6m 24 pcs 140 3360
MATERIAL COST
ITEM MATERIAL DESCRIPTION QTY UNIT
UNIT COST TOTAL COST
I. MASONRY/CONCRETING WORKS
a. 4" Concrete Hollow Blocks 252 pcs 10 2520
Portland Cement 27 bags 270 7290
Gravel 1 cu. m 900 900
Fine Aggregates 3 cu. m 919 2757
13467
II. REBAR WORKS
a. For Column
12mm dia. bar @ 6m 10 pcs 223 2230
8mm dia. bar @ 6m 12 pcs 140 1680
#12 GI Tie Wire 3 kg 72 216
4126
b. For Vertical/Horizontal Bars
10mm dia. bar @ 6m 16 pcs 156 2496
#12 GI Tie Wire 2 kg 72 144
2640
III. MANPOWER
a. Skilled Worker (7 working days) 7 days 700 4900
4900